This is Addendum No. 2 to Request for Bid (RFB) No. 26-0023 issued by the City of Columbus, Georgia Finance Department Purchasing Division for Comprehensive Generator Services under an annual contract. The addendum extends the proposal due date to Wednesday, March 4, 2026, at 2:30 PM Eastern Time. Vendors are required to acknowledge receipt of this addendum using the form provided in the original solicitation and include the acknowledgment with their electronic bid response. Failure to acknowledge receipt may result in the proposal being deemed incomplete and ineligible for award consideration.
The addendum addresses a previously submitted vendor question regarding the 4-hour load bank cost, clarifying that this cost should be included with semi-annual inspection and maintenance services rather than billed separately. Additional vendor questions have been received and are under review by the User-Department, with responses to be provided in a forthcoming addendum. All vendors submitting proposals must use the appropriate Addenda Acknowledge form and include it with their bid response to ensure compliance with solicitation requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFB26_0023Add6.pdf | ||
| RFB 26_0023 Add1.pdf | ||
| RFB 26_0023 Add4.pdf | ||
| RFB 26_0023 Add3.pdf | ||
| rfb 26_0023.pdf | ||
| RFB26_0023Add5.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum No. 2 RFB No. 26-001 Page 1 of 2
COMPREHENSIVE GENERATOR SERVICES (Annual Contract)
FINANCE DEPARTMENT
PURCHASING DIVISION 1111 First Avenue, P. O. BOX 1340
COLUMBUS, GEORGIA 31902-1340
706-225-4087 | www.columbusga.gov
February 20, 2026 ADDENDUM No. 2
COMPREHENSIVE GENERATOR SERVICES
(ANNUAL CONTRACT)
RFB No. 26-0023
Use the form provided in the solicitation to acknowledge receipt of this addendum. Failure to do so may result in your submittal being deemed non-responsive and not receiving further consideration for award.
Vendors are informed that the above subject solicitation is hereby modified, corrected, or supplemented as specified, described and set forth in this Addendum:
I. DUE DATE EXTENSION
THE DUE DATE FOR THIS RFP HAS BEEN EXTENDED.
Proposals are due on Wednesday, March 4, 2026, no later than 2:30 PM (Eastern).
II. QUESTION(S)/RESPONSES(S)
Question 1: As far as the 4-hour load bank cost, do I include that with the semi-annual?
Answer: Yes, the 4-hr. load bank will be included in the semi-annual, and the cost should be included in the Inspection and maintenance cost.
III. ADDITIONAL QUESTIONS
The User-Department is in the process of reviewing and preparing responses to previously received questions.
Responses will be provided via a forthcoming addendum.
COLUMBUS CONSOLIDATED GOVERNMENT
Georgia’s First Consolidated Government http://www.columbusga.gov/
Addendum No. 2 RFB No. 26-001 Page 2 of 2
COMPREHENSIVE GENERATOR SERVICES (Annual Contract)
IV. ACKNOWLEDGEMENT
Indicate that your company has received this addendum on the appropriate Addenda Acknowledge form and include your form acknowledgment with your electronic bid response. Failure to acknowledge receipt of this addendum may render your response “Incomplete”.
Andrea J. McCorvey Purchasing Manager
| FINANCE DEPARTMENT |
| February 20, 2026 |
| ADDENDUM No. 2 |