About this file

This is a revised specifications exhibit for an Oregon Department of Transportation (ODOT) painting project at the Odell Lake Maintenance Station located at Highway 58, Mile Post 64.3 in Klamath County. The project involves exterior painting, caulking, siding repair, and hand scraping of historical homes and a dormitory at the maintenance station, with work requiring approval from the U.S. Forest Service (USFS) and State Historic Preservation Office (SHPO). Prospective contractors must be lead-certified with current licensure for lead abatement and must conduct a mandatory pre-quote conference on June 16, 2026, at 10:00 a.m. at the project site; failure to attend results in automatic disqualification. Quotes are due June 25, 2026, through the OregonBuys eProcurement system. The contract is structured as a lump-sum agreement with substantial completion required by August 6, 2026, and final completion by September 10, 2026, with contract expiration on September 30, 2026, or upon completion of all contractor obligations and full payment, whichever occurs sooner. Work must be performed on weekdays between 7:00 a.m. and 5:00 p.m., excluding weekends and state holidays unless otherwise approved.

The project requires contractors to hold an active Oregon Construction Contractors Board (CCB) license and current Oregon Health Authority Lead-Based Paint Program (LBPP) certification prior to bidding; these are decision-filters that automatically disqualify non-compliant offers. Contractors must obtain commercial general liability insurance with limits of $1,000,000 per occurrence and $2,000,000 annual aggregate, commercial automobile liability insurance with $1,000,000 combined single limit, and workers' compensation insurance with $500,000 per accident employer's liability coverage. The work is subject to Oregon prevailing wage rates and apprenticeship rates for Klamath County (BOLI Region 11), effective January 5, 2026, as amended April 5, 2026. Liquidated damages are assessed at $300 per calendar day for each day exceeding the substantial completion date. Payment will be made within 30 calendar days of invoice receipt following work acceptance, with ODOT retaining 5 percent from each invoice. Award will be made to the responsible offeror submitting the responsive quote that best serves ODOT's interests, considering price, experience, and expertise. The contractor must provide a one-year installation warranty on all workmanship and applicable equipment warranties, maintain as-built drawings, submit all operations and maintenance information, and instruct ODOT personnel on operation and maintenance of all systems and equipment.

View the file

Other files

File Type Posted
Exhibit 3 - Specifications.doc DOC document
Pre-bid Sign in Sheet~1.pdf PDF
00017098 Addendum 2 Bid Cancellation~1.docx DOCX document
Attachment B - Sample Contract~1.docx DOCX document
00017098_Addendum One.docx DOCX document
00017098_RFCQ.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXHIBIT 1

PROJECT OVERVIEW

DATE 3/10/2026

Oregon Department of Transportation

Project Name Odell Lake Painting Project Project Location:

Odell Lake Maintenance Station Hwy 58 MP. 64.3 Odell Lake ODOT Contact:

The ODOT Project Manager for this project is David Sturges

· E-mail: david.sturges@odot.oregon.gov

· Cell: 503-580-1121

· Address: 885 Airport Rd Se Bldg. X

· Salem, OR. 97301

The ODOT Project Manager may designate an additional ODOT contact person or engineer to support inspections or questions in the field.

Project Background These are historical homes and USFS has authority over all work and must approve prior to any work being done. The homes need siding repair and caulking and paint. The dormitory needs to be hand scraped and primed and 2 coats of exterior paint sprayed and back rolled.

Project Description:

The homes and dormitory need caulking and painting. USFS has given approval along with SHPO and ODOT Environmental has cleared the work to be done. Contractor must be lead certified with a current license for lead abatement.

Detailed Project Specifications:

1. Outline of work:

The houses will need to be hand sanded; all paint materials will need to be captured and disposed of per industry standards. Scraping of large paint chips, caulk around all windows with approved outdoor caulking that is paintable. The dormitory will need to be hand scraped and all loose material placed in bags and disposed of per code for Lead paint. One coat of primer to be sprayed and back rolled and two (2) coats of finish of approved colors per USFS.

General Construction Notes:

· The contractor shall make a site visit and examine existing conditions prior to providing a bid. Any discrepancies shall be brought to the attention of ODOT through a request for clarification as set forth in the bid documents.

· No pressure washing or rinsing of any structures.

· Contractor must provide a portable restroom.

· No cleaning of equipment or paint supplies at the project site.

· Clarifications shall be requested in writing prior to any installation. Incorrect installations shall be corrected at no additional cost to ODOT.

· All work shown is to be by the contractor unless specifically noted as being by ODOT or by others. All materials shown are to be provided by the contractor unless specifically noted as existing or provided by ODOT.

· Drawings are schematic in nature, major components and equipment are shown on the drawings. The contractor shall supply and install all minor components and materials necessary to provide a complete and functional project whether all such components are noted in the drawings and specifications.

· Plans and specifications call out specific makes and models of equipment in some locations. Substitution requests shall be made during the bid process. ODOT shall at its sole discretion determine the acceptability of substitutions. No substitutions shall be installed without prior written approval from the ODOT Construction Project Manager.

· All equipment and materials shall be installed in accordance with the manufacturer’s published installation instructions and recommendations.

· Clean the entire work area at the conclusion of the project to the satisfaction of the ODOT Project Manager.

Submittals

The Contractor shall provide the following submittals at a minimum to the ODOT Project Manager. Submittals shall be approved by the ODOT Project Manager prior to the start of on-site construction.

Scheduling of Contract:

· Substantial completion of the Work shall be no later than 8/6/2026. Final completion shall be no later than 9/10/2026.

· After award of contract, the Contractor shall contact the ODOT Project Manager to schedule the Work at least ten (10) business days prior to the start of any work/demolition.

· The Work shall be accomplished on weekdays between the hours of 7 a.m. and 5 p.m. Work hours shall exclude weekends and State Holidays, unless specifically requested by the Contractor and approved by the ODOT Project Managers.

· Any permits required for the Work are the responsibility of the Contractor. The Contractor shall provide copies of permits to the ODOT Project Manager prior to the start of work. The Contractor shall be responsible for posting all permits on site in accordance with local jurisdiction requirements.

· The Contractor shall submit to the ODOT Project Managers a list of the contact information for the Contractor’s project manager and site superintendent, as well as a list of all Subcontractors and their key representatives.

· ODOT shall be responsible for contracting with a special inspections firm based upon the list of inspections required by the Architect/Engineer of Record, manufacturer, or jurisdiction. ODOT shall provide contact info for the approved special inspections firm to the Contractor. The Contractor shall be responsible for scheduling special inspections as to not delay the project schedule. The special inspections firm shall be required by contract to provide copies of the special inspections report to ODOT and the Contractor. The Contractor shall be solely responsible for addressing any deficiencies identified during special inspections. ODOT shall pay for special inspections. Additional inspections required due to Contractor’s failure to reach required standards shall be paid for by Contractor.

· The Contractor shall coordinate the efforts of all Suppliers and Subcontractors and shall maintain orderly progress of the Work, prevent duplication of effort, and ensure proper sequence of operations.

Clean-Up/Conditions of Site:

· The Contractor shall be responsible for keeping the ODOT Project Manager informed of all activity throughout the Work.

· The Contractor shall clean up all worksite debris resulting from construction and remove all excess construction materials and scraps from the premises. The Contractor shall broom-clean their work area at the end of each workday and neatly stack materials and debris in an approved location. The contractor shall clean the entire work area at the conclusion of the project to the satisfaction of the ODOT Project Manager.

· The Contractor shall protect materials subject to damage by temperature or other weather conditions.

· The location for storage of materials, debris, or dumpster on the Premises shall be approved in advance by the ODOT Project Manager. Disposal facilities, bins, or dumpsters shall not be provided by ODOT.

· The Contractor shall notify the ODOT Project Manager at least two (2) days in advance of any major deliveries.

· Contractor shall immediately notify the ODOT Project Manager of any damage done by the Contractor to the Premises, grounds, or adjacent State properties. Damage done by the Contractor to the Premises or surrounding area shall be repaired to existing conditions as found prior to the commencement of the Work.

· ODOT shall not be responsible for the security of the Contractor’s materials, tools, personal belongings, or equipment on the Premises.

· It is the responsibility of the Contractor to ensure the Work is performed in accordance with Oregon OSHA rules and regulations.

· The Contractor shall immediately bring to the attention of the ODOT Project Manager any conflicts or issues between existing utilities and the Work.

Close Out:

· All special inspections must be complete prior to Substantial Completion.

· Inspection of the work by the ODOT Project Manager for establishment of Substantial Completion shall be made within five (5) business days after receipt of the Contractor’s email request. At this time, the ODOT Project Manager and the Contractor shall develop a punch list document of any incomplete or deficient work.

· Prior to Final Completion, the Contractor shall complete all items on the punch list.

· The Contractor shall provide final inspection reports for all permits applicable to this Contract signed by authorities having jurisdiction

· The Contractor shall maintain one set of the approved drawings for recording as-built conditions. Mark (in red) the actual location of all underground utilities and any changes. At the time of Final Completion, the Contractor shall turn over the one marked-up set of record drawings to the ODOT Project Manager.

· Prior to Final Completion, the Contractor shall provide one (1) digital copy via email of all operations, maintenance, and warranty information to the ODOT Project Manager.

· Prior to Final Completion, provide ODOT Project Manager with information for all equipment provided by the project, including but not limited to: Manufacturer, model, serial number, consumables, installation date, purchase date.

· Prior to Final Completion, and as prerequisite for final payment, provide ODOT Project Manager with signed certification that all subcontractors and suppliers have been paid in full and in compliance with all prompt payment requirements. All disputes with property owners have been resolved, all obligations on the project have been satisfied, all monetary claims and indebtedness have been paid, and, to the best of the Contractor's knowledge, there are no claims of any kind outstanding against the project.

· Prior to Final Completion, the Contractor shall fully instruct ODOT’s operating and maintenance personnel in the operation, adjustment, and maintenance of products, equipment, and systems.

· Inspection of the work by the ODOT Project Manager for establishment of Final Completion shall be made within five (5) business days after receipt of the Contractor’s email request.

Warranty:

· Contractor shall provide a 1-year Installation warranty on all workmanship.

· Contractor shall provide all warranties for equipment applicable to this Contract Revision: 5/7/24