REVISED ATTACHMENT B STATEMENT OF WORK MILO MCIVER RESTROOM RESTORATION TILE DEMO AND REPAIRS.pdf
PDF 137 KB Posted
- Solicitation number
- S-63400-00012309
- Issued by
- Clackamas County, Enterprise City, Oregon
About this file
This is a Statement of Work (SOW) from the Oregon Parks and Recreation Department for the Milo McIver Restroom Restoration project involving tile demolition and repairs at Milo McIver State Park. The project involves updating and repairing a 1970's Campground Restroom and Shower facility, including complete removal of existing wall and floor tiles, demolition of interior CMU shower wall dividers, saw cutting and removal of concrete flooring in shower drain relocation areas, and installation of new tile surfaces. The work must be completed by March 13th, 2025, and includes seven specific tasks ranging from demolition to installation of new materials.
The technical specifications require Eleganza Monsoon Glossy 4x16 ceramic wall tile or equivalent, with waterproofing that complies with ANSI A118.10 and ANSI A118.12 standards. All tile must be obtained from the same production run to ensure consistent quality and appearance. The project requires water-cleanable epoxy grout with color verification by the project manager. The owner will provide project schedule, scope, and plan documents, while the contractor is responsible for providing all equipment, labor, materials, and supplies necessary to complete the services in accordance with industry standards and requirements for prudent expenditure of public funds.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT B
STATEMENT OF WORK
MILO MCIVER RESTROOM RESTORATION: TILE DEMO AND REPAIRS
1.0 BACKGROUND
The 1970’s Campground Restroom and Shower facility located at Milo McIver State Park needs updates and repairs to plumbing fixtures and shower stall configuration. Existing tile floor and wall surfaces will be demolished and updated as part of these updates.
2.0 SCOPE
Remove all tile from walls and flooring as well as demo interior CMU shower wall dividers. Saw cut and remove concrete floor in area of shower drain relocation areas and prep walls and floor for installation of new tile on all vertical and horizontal wall surfaces.
3.0 WORK AND DELIVERABLES
3.1 Contractor’s Obligations
Contractor shall perform the tasks and provide the deliverables set forth in this section according to the requirements, standards, and expectations set forth in the Contract and this Statement of Services:
3.1.1 General Requirements
• Perform all Services according to the stated tasks, requirements, delivery schedule, and relevant industry standards;
• Provide all equipment, labor, materials, and supplies necessary to complete the Services and
• Keep a record of Services performed, including sufficient detail to substantiate invoices.
• Contractor shall perform the Services specified in this Contract to obtain the greatest long-term value for the State of Oregon and to result in the prudent expenditure of public funds within the constraints of the Project program, context and budget.
3.1.2 Work Schedule. Contractor shall begin providing the Services upon the Effective Date of the Contract and shall continue to provide all Services required under the Contract until the completion of the Project. All task under this contract must be completed no later than March 13th, 2025, unless approved by project manager.
3.1.3 Product Specifications
• Obtain tile from same production run and of consistent quality in appearance and physical properties for each contiguous area.
• Tile product to be Eleganza Monsoon Glossy 4x16 ceramic wall tile or equivalent
• Waterproofing of shower areas to comply with ANSI A118.10 and ANSI A118.12
• Water-Cleanable Epoxy Grout, color to be verified by project manager
3.1.3 Tasks and Deliverables. The tasks to be performed by Contractor are described below:
Task 1. Demo, remove, and dispose of existing wall and floor tile per plans.
Task 2. Demo, remove, and dispose of interior CMU shower block walls.
Task 3. Saw cut and remove sub-grade concrete from shower rooms to allow removal of old drainpipe.
Task 4. Re-pour concrete with a minimum 1/8” slope grade to new drain locations as shown in Plans and Drawings.
Task 5. Prep and waterproof all areas indicated on plans for the installation of new tile and epoxy floor covering.
Task 6. Provide and install new tile to all interior walls per plans.
Task 7. Provide and install seal coat for all tile grout joints.
4.0 OWNER OBLIGATIONS
Owner will provide the following:
• Project Schedule, Scope, and plan documents.
File details come from the government source that posted it. Updated .