Retamal Dam Buoys System DB Specs 5 .pdf

PDF 4 MB Posted

Attached to
Retamal Dam Buoy System
Solicitation number
191BWC26R0006
Issued by

About this file

This is a Design-Build Scope of Work for the Retamal Dam New Waterway Barrier Line project issued by the United States Section of the International Boundary and Water Commission (USIBWC) under Solicitation 191BWC26Rxxxx. The project, located in Hidalgo County, Texas approximately 2.5 miles east of the Donna Point International Port of Entry, requires design and construction of a waterway barrier line system including anchors, alert system, and warning signs at Retamal Dam. The final deliverable must protect public access from hazardous zones upstream and downstream of the dam, deflect debris to reduce intake clogging, provide compliant warning signage and alert systems, include adequate mooring and anchor systems, offer conspicuous marking with retroreflective elements and lighting, enable inspection access, and achieve a minimum 10-15 year service life with defined maintenance and corrosion protection plans.

The work is structured in two phases with separate Notices to Proceed: Phase 1 (Design) includes site investigation, surveying (topographic and bathymetric), hydraulic and hydrology studies, geotechnical investigations, design development, and production of construction documents; Phase 2 (Construction) encompasses site preparation, construction, debris disposal, quality control testing, and commissioning. The Design-Builder is responsible for all labor, materials, equipment, permits, and coordination with utilities and regulatory agencies. Work hours are limited to 7:30 AM to 4:00 PM Monday through Friday, aligned with USIBWC facility operations. Mobilization must commence within 90 days of the Construction Notice to Proceed, contingent upon Government approval of all required pre-mobilization submittals including design documents, quality assurance plans, safety plans, environmental controls, and schedules. The design phases require 30%, 60%, 90%, and 100% submittals with 28-calendar-day Government review periods between each milestone. All designs must be signed and sealed by professional engineers licensed in Texas, and the Design-Builder must comply with Davis-Bacon wage requirements, environmental regulations, Section 404 permitting, stormwater management, and all applicable federal, state, and local requirements.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Front Cover

International Boundary and Water Commission United States and Mexico United States Section

Design-Build Scope of Work Retamal Dam New Waterway Barrier Line with Anchors, Alert System, and Warning Signs Hidalgo County, Texas

Solicitation 191BWC26Rxxxx

March 18, 2026

International Boundary and Water Commission United States Section Construction Management Division El Paso, Texas

This Scope of Work may be reprinted after Contract award using the awarded Contract number instead of the Solicitation number currently shown. The reprint shall have all changes indicated incorporated.

Reissuance of the awarded Scope of Work with the Contract number will proceed without an amendment or modification.

Reissuance with the Contract number will NOT result in a new date being displayed on the Scope of Work.

PLEASE NOTE - Scope of Work should be printed double sided.

Please conserve paper and print double sided.

USIBWC Retamal Dam New Waterway Barrier Line with Anchors, Alert System, and Warning Signs

March 18, 2026 Division 00 USIBWC Solicitation 191BWC26Rxxxx Procurement and Contracting Requirements-Page 1

International Boundary and Water Commission United States Section

SCOPE OF WORK

DIVISION 00

PROCUREMENT AND CONTRACTING

REQUIREMENTS

New Waterway Barrier Line with Anchors, Alert System, and Warning Signs US International Boundary & Water Commission Retamal Dam

Procurement and Contracting Requirements Division 00 Division 00-Procurement and Contracting Requirements

Division 00 March 18, 2026 Procurement and Contracting Requirements-Page 2 USIBWC Solicitation 191BWC26Rxxxx

This page intentionally left blank for double sided printing.

March 18, 2026 Table of Contents Governing USIBWC Solicitation 191BWC26Rxxxx 00.01.10.01-Page 1

SECTION 00.01.10.01

TABLE OF CONTENTS GOVERNING

00.01.10.01 Table of Contents Governing 00.01.10.01-Table of Contents Governing

Table of Contents

DIVISIONS AND SECTIONS

Division 00-Procurement and Contracting Requirements 00.01.10.01-Table of Contents Governing 00.21.13.01-◊●◊●◊ Instructions to Bidders 00.23.00.01-◊●◊●◊ Design-Build Procurement Definitions 00.24.00.01-Procurement Scope 00.31.00.01-Project Information 00.31.13.01-◊●◊●◊ Project Time Constraints & Milestones 00.31.19.01-Existing Condition Information 00.31.24.01-Environmental Information 00.31.26.01-Existing Hazardous Material Information 00.31.43.01-Permit Application 00.60.00.01-◊●◊●◊ USIBWC Forms and Standard Documents 00.70.00.01-◊●◊●◊ Delivery of Data to USIBWC 00.70.13.01-◊●◊●◊ Project Data 00.72.00.01-General Conditions 00.73.63.01-Security Requirements 00.73.73.01-Requirements for Sensitive But Unclassified Information 00.90.00.01-◊●◊●◊ Revisions, Clarifications, and Modifications 00.91.16.01-Bid Revisions

Division 01-General Requirements 01.20.00.01-◊●◊●◊ Measurement and Payment 01.29.00.01-◊●◊●◊ Payment Procedures 01.29.15.01-◊●◊●◊ Certified Payroll 01.31.00.01-◊●◊●◊ Project Coordination 01.31.19.01-◊●◊●◊ Project Meetings 01.32.16.01-◊●◊●◊ Progress Schedule 01.32.33.01-◊●◊●◊ Photographic Documentation 01.33.00.01-◊●◊●◊ Submittal Procedures 01.33.16.01-Design Submittals 01.33.33.01-◊●◊●◊ Document Requirements 01.35.23.01-◊●◊●◊ Safety 01.40.00.01-◊●◊●◊ Quality Requirements 01.41.00.01-Regulatory Requirements 01.42.00.01-References 01.43.26.01-◊●◊●◊ Testing and Inspection Agencies 01.51.00.01-Temporary Utilities 01.52.13.01-Field Offices and Sheds 01.55.00.01-Vehicular Access and Parking 01.57.00.01-◊●◊●◊ Temporary Controls for Work Areas 01.57.19.01-◊●◊●◊ Temporary Environmental Controls 01.58.00.01-Project Identification 01.61.00.01-Common Product Requirements 01.61.16.01-◊●◊●◊ Use of Recovered Materials and Biobased Products 01.71.13.01-Mobilization

Table of Contents Governing March 18, 2026 00.01.10.01-Page 2 USIBWC Solicitation 191BWC26Rxxxx

01.74.19.01-◊●◊●◊ Construction Waste Management and Disposal 01.77.19.01-◊●◊●◊ Closeout Requirements 01.78.23.01-Operations and Maintenance Data 01.78.36.01-◊●◊●◊ Warranties 01.78.39.01-Record Drawings 01.79.00.01-Demonstration and Training 01.80.05.01-General Design Requirements 01.80.23.01-General Structural Requirements 01.80.26.01-General Concrete Requirements 01.81.63.01-General Civil/Architectural Requirements 01.86.29.01-Electrical Requirements 01.88.00.01-General Construction Requirements 01.88.59.01-General Geological Materials Requirements 01.89.16.01-Site Improvements Requirements 01.91.13.01-General Commissioning Requirements

Division 02-Existing Conditions 02.01.00.01-◊●◊●◊ Existing Conditions & Facilities 02.21.00.01-◊●◊●◊ Surveys 02.21.13.01-◊●◊●◊ Cultural Resources Surveys 02.22.13.01-Existing Conditions Assessment

Scope of Work Tables Table 1 - CLIN 001 (Design) Schedule of Values Table 2 - CLIN 002 (Construction) Schedule of Values Table 3 - CLIN 003 (Closeout) Schedule of Values Table 4 - Acceptable Methods of Access Table 5 - Required Minimum Biobased Content Table 6 - Required Minimum Recovered Content Table 7 - Minimum Warranties Table 8 - Warranty Priority Code A Table 9 - Warranty Priority Code B Table 10 - Warranty Priority Code C Table 11 - Warranty Priority Code D Table 13 - Overdesign to Meet Compressive Strength Requirements (1) Table 14 - Overdesign to Meet Compressive Strength Requirements (2) Table 15 - Duration of Curing

Scope of Work Figures Figure 1 - Fillable Form (not printed) Figure 2 - Printed Fillable Form Figure 3 - Site Access Methods by Angle Figure 4 - Design-Build QA Organizational Chart Figure 6 - Sample Project Sign Figure 7 - Equipment Tag Example

--End of Section--

March 18, 2026 ◊●◊●◊ Instructions to Bidders USIBWC Solicitation 191BWC26Rxxxx 00.21.13.01-Page 1

SECTION 00.21.13.01

INSTRUCTIONS TO BIDDERS

00.21.13.01 ◊●◊●◊ Instructions to Bidders 00.21.13.01-◊●◊●◊ Instructions to Bidders

PART 1 - GENERAL

1.1. SECTION INCLUDES

Part 1 - General

1.1. Section Includes

1.2. Reference Standards

1.3. Measurement and Payment

1.4. Definitions

1.5. Duty to Inquire

1.6. Investigation of Site Conditions

1.7. Bid Items

1.8. Statement of Work

1.9. Bid Submission

Part 2 - Products (Not Used) Part 3 - Execution

3.1. Requests for Interpretation (Duty to Inquire)

--End of Section--

1.2. REFERENCE STANDARDS

1.2.A. Federal Acquisition Regulation (FAR)

1. FAR 52.236-3, Site Investigation and Conditions Affecting the Work

1.3. MEASUREMENT AND PAYMENT

The work performed by the Design-Builder under this Section shall not be paid for directly but shall be included in the various Bid Items under this Contract.

1.4. DEFINITIONS

1.4.A. Within this Section, the following terms are used interchangeably.

1. Bid - Offer - Proposal

2. Solicitation - Request for Proposal - RFP

3. Bidder - Offeror - Design-Builder

1.5. DUTY TO INQUIRE

1.5.A. Bidders shall review the full Solicitation and all Contract Documents including, but not limited to, Scope of Work, Contract Drawings, USIBWC provided data, referenced items, attachments, etc. to determine the full scope of work required.

1.5.B. If during review of these items, the Bidder finds discrepancies, omissions, conflicts, defects, errors, or ambiguities, they have a duty to inquire. The Bidder shall also inquire about items that are open to interpretation.

1.5.C. The Bidder shall inquire about items as soon as they are discovered, whether before deadline for submission of bidder questions, whether after deadline for submission of bidder questions, whether after submission of bids, or whether after Contract award.

◊●◊●◊ Instructions to Bidders March 18, 2026 00.21.13.01-Page 2 USIBWC Solicitation 191BWC26Rxxxx

1.5.D. If the Bidder fails to inquire, they forfeit their right to any claim based upon said discrepancies, omissions, conflicts, defects, errors, ambiguities, or items that are open to interpretation. The Bidder shall be proceeding at their own risk based upon only their unilateral interpretation.

1.5.E. The Bidder shall take no advantage of any item of which they have a duty to inquire.

1.6. INVESTIGATION OF SITE CONDITIONS

1.6.A. The Bidder, as well as their subcontractors, is urged to visit the worksite and project area to become fully aware as to the existing conditions affecting the work to be performed under the Contract Documents. A site visit will be announced during the solicitation. Each Bidder shall attend at their own expense. The Government will not pay for any site visits. This visit is intended to provide the potential Bidders the opportunity to observe site conditions and incorporate into their proposal any required work based on site conditions. The Bidder will have the opportunity to walk around during the site visit. Unless otherwise noted, no other opportunity will exist for visits to the site.

1.6.B. The Bidder shall be responsible for ensuring that all of its suppliers, manufactures and subcontractors have reviewed all applicable Contract Documents relative to their work. The Bidder shall provide all labor, material, equipment, and services not provided by the Bidder’s suppliers, manufacturers, fabricators, and/or subcontractors but required for complete and operable facilities as described in the Contract Documents.

1.6.C. Bidder has the sole responsibility to make such independent investigation and examination as they deem necessary in order to satisfy themselves as to the conditions to be encountered in the performance of work and the quantities required to complete the work in accordance with the SOW.

1.6.D. The Government assumes no responsibility for any understanding reached or representation made concerning conditions which can affect the work by any of the Bidder's officers or agents before the execution of this Contract, unless that understanding or representation is expressly stated in the Contract Documents.

1.6.E. Any failure of the Bidder to take the actions described and acknowledged in this Section will not relieve the Bidder from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work.

1.7. BID ITEMS

1.7.A. The Contract Line Item Numbers (CLIN) that shall be bid upon are identified in Section B (bid schedule) of the Solicitation.

1.7.B. The Bidder shall include all work related costs within its bid prices even if not specifically listed in the bid schedule.

1.7.C. If an error exists on the bid schedule between the CLIN total cost provided and the resultant value of the CLIN quantity multiplied by the bid unit price, the bid unit price provided shall govern.

1.8. STATEMENT OF WORK

1.8.A. The Government does not implicitly warrant performance specifications (SOW requirements) for complete accuracy or adequacy. Typical performance type requirements set forth an objective or standard to be achieved, and the successful Bidder is expected to exercise their ingenuity in achieving that objective or standard of performance, selecting the means and assuming a corresponding responsibility for that selection.

1.8.B. When a particular product or manufacturer is identified by name, but permits substitution of ‘an approved equal,’ such a requirement is ‘performance’ in nature and, as a result, carries no implied warranty.

March 18, 2026 ◊●◊●◊ Instructions to Bidders USIBWC Solicitation 191BWC26Rxxxx 00.21.13.01-Page 3

1.8.C. The Scope of Work is written in imperative and abbreviated form. This imperative language is directed at the Design-Builder, unless specifically noted otherwise. Incomplete sentences shall be completed by inserting "shall", "the Design-Builder shall", and "shall be" or similar mandatory phrases by inference.

The words "shall be" are to be placed by inference where a colon (:) is used within sentences or phrases.

Except as worded to the contrary, the Design-Builder shall fulfill (perform) all indicated requirements whether stated imperatively or otherwise.

1.8.D. All equipment and facilities shall be furnished, installed, and constructed by the Design-Builder to provide the Government with complete, ready to use components, systems, and facilities. All necessary materials and work required to accomplish this are the responsibility of the Design-Builder alone, whether or not specifically stated in the Scope of Work.

1.9. BID SUBMISSION

1.9.A. Submission of a bid shall be conclusive evidence that the Bidder has reviewed, investigated, and acknowledged all items detailed in FAR 52.236-3 and listed below.

1. Conditions bearing upon transportation, disposal, handling, and storage of materials.

2. The availability of labor, water, electric power, and roads.

3. Uncertainties of weather and similar physical conditions at the site.

4. The conformation and conditions of the ground.

5. The security and safety conditions at and around the site.

6. The character of equipment and facilities needed preliminary to and during work performance.

1.9.B. Submission of a bid shall be conclusive evidence that the Bidder has reviewed all Contract Documents.

1.9.C. Submission of a bid shall be conclusive evidence that the Bidder has investigated and is satisfied as to the conditions to be encountered, the character, quality, and scope of work to be performed, and the quantities of materials to be furnished.

1.9.D. Submission of a bid constitutes agreement that Bidder has provided written notice of all discrepancies, omissions, conflicts, defects, errors, ambiguities, or items that are open to interpretation discovered in the Contract Documents, that responses to these written notices are acceptable to Bidder, and that Contract Documents are sufficient to indicate and convey understanding of all terms and conditions for performing and furnishing required work.

1.9.E. Bidder has the sole responsibility to make such independent investigation and examination as they deem necessary in order to satisfy themselves as to the conditions to be encountered in the performance of work and the quantities required to complete the work in a accordance with the Contract Documents. The Government will not award a modification or additional funds for conditions that were observable but not considered by Bidder.

PART 2 - PRODUCTS

(Not Used)

PART 3 - EXECUTION

3.1. REQUESTS FOR INTERPRETATION (DUTY TO INQUIRE)

3.1.A. Bidder shall submit requests for interpretation, questions, and other concerns about the Solicitation and Contract Documents including, but not limited to, Scope of Work, Contract Drawings, USIBWC provided data, referenced items, attachments, etc. to the Contracting Officer identified on SF-1442.

3.1.B. Such requests shall be made even if the question and answer period identified in the Solicitation has passed.

◊●◊●◊ Instructions to Bidders March 18, 2026 00.21.13.01-Page 4 USIBWC Solicitation 191BWC26Rxxxx

3.1.C. Failure to request interpretation prior to providing a bid shall result in the Bidder being fully responsible for any cost or time impacts involved to perform the work required.

March 18, 2026 ◊●◊●◊ Design-Build Procurement Definitions USIBWC Solicitation 191BWC26Rxxxx 00.23.00.01-Page 1

SECTION 00.23.00.01

DESIGN-BUILD PROCUREMENT DEFINITIONS

00.23.00.01 ◊●◊●◊ Design-Build Procurement Definitions 00.23.00.01-◊●◊●◊ Design-Build Procurement Definitions

PART 1 - GENERAL

1.1. SECTION INCLUDES

Part 1 - General

1.1. Section Includes

1.2. Related Requirements

1.3. Reference Standards

1.4. Measurement and Payment

1.5. Design-Build Definitions

1.6. Other Project Definitions

Part 2 - Products (Not Used) Part 3 - Execution (Not Used) --End of Section--

1.2. RELATED REQUIREMENTS

1.2.A. Section 01.42.00.01-References

1.3. REFERENCE STANDARDS

1.3.A. Federal Acquisition Regulations (FAR)

1.4. MEASUREMENT AND PAYMENT

The work performed by the Design-Builder under this Section shall not be paid for directly but shall be included in the various Bid Items under this Contract.

1.5. DESIGN-BUILD DEFINITIONS

Construction Contractor The subcontractor hired by the Design-Builder who is involved in the actual construction of the project.

Construction Drawings The drawings provided by the Design-Builder, usually through the Designer, to accomplish construction in concert with the Technical Specifications.

Contract Documents The Contract Documents include the Solicitation and eventual Contract, any documents provided by USIBWC identified in this Scope of Work, any documents provide with the Solicitation, all design documents produced by the Designer, all construction drawings, all Technical Specifications, and all submittals required by either the Scope of Work or the construction specifications.

Design-Builder The Design-Builder is the entity, firm, partnership, joint venture, or organization that Contracts with the United States Section of the International Boundary and Water Commission (USIBWC) to design and construct items meeting this Scope of Work The Design-Builder may be the Designer, the Construction Contractor, and/or the project manager.

The Design-Builder has full responsibility for completion of the Contract.

◊●◊●◊ Design-Build Procurement Definitions March 18, 2026 00.23.00.01-Page 2 USIBWC Solicitation 191BWC26Rxxxx

Designer A subcontractor or in-house participant that leads the team furnishing the design for the project. The Designer must be registered to practice engineering in the state where the construction will occur.

Government The Government usually refers to the USIBWC or its representatives although it can also cover DHS or other entities associated with the project.

Government Representative The Government Representative refers to the Contracting Officer (CO) or the Contracting Officer’s Representative (COR). These individuals are designated by the USIBWC to act in the capacity as the "Government Representative" as defined by the Federal Acquisitions Regulations (FAR) and shall be the final interpreter of any project issues that may arise in the course of the Work. The USIBWC’s Government Representative shall be responsible for the Compliance Review of the Work.

Subcontractor Any supplier, distributor, vendors, individual, partnership, joint-venture, or corporation who performs work, provides services, or furnishes supplies for the Design-Builder under this Contract.

Supplier or Vendor Any individual, partnership, joint-venture, or corporation who only furnishes materials for work under this Contract. They provide no service nor perform any work onsite except for inspection of their products or training of personnel.

Technical Specifications The construction specifications provided by the Design-Builder, in concert with the Designer, to accomplish construction of this project by their Construction Contractor.

1.6. OTHER PROJECT DEFINITIONS

1.6.A. General terms, abbreviations, and definitions are shown in Section 01.42.00.01.

1.6.B. If terms are defined in both Section 01.42.00.01 and in this Section, the definition in this Section governs.

PART 2 - PRODUCTS

(Not Used)

PART 3 - EXECUTION

(Not Used)

March 18, 2026 Procurement Scope USIBWC Solicitation 191BWC26Rxxxx 00.24.00.01-Page 1

SECTION 00.24.00.01

PROCUREMENT SCOPE

00.24.00.01 Procurement Scope 00.24.00.01-Procurement Scope

PART 1 - GENERAL

1.1. SECTION INCLUDES

Part 1 - General

1.1. Section Includes

1.2. Related Requirements

1.3. Reference Standards

1.4. Measurement and Payment

1.5. Project Goal

1.6. Work Elements

1.7. Sequence of Work/Time for Completion of Work

1.8. Work Under Other Contracts

1.9. Labor and Staffing

1.10. Project Location

1.11. Conflict Order of Precedence

Part 2 - Products

2.1. Government Furnished Materials

2.2. Products to be Furnished by the Design-Builder

Part 3 - Execution

3.1. Submittals Required Prior to Construction Mobilization

3.2. Use of Right-of-Way

3.3. Occupancy of Right-of-Way

3.4. Site Work Restrictions

--End of Section--

1.2. RELATED REQUIREMENTS

1.2.A. Section 01.33.16.01-Design Submittals

1.2.B. Section 00.31.43.01-Permit Application

1.2.C. Section 01.32.16.01-◊●◊●◊ Progress Schedule

1.2.D. Section 01.32.33.01-◊●◊●◊ Photographic Documentation

1.2.E. Section 01.33.00.01-◊●◊●◊ Submittal Procedures

1.2.F. Section 01.35.23.01-◊●◊●◊ Safety

1.2.G. Section 01.40.00.01-◊●◊●◊ Quality Requirements

1.2.H. Section 01.52.13.01-Field Offices and Sheds

1.2.I. Section 01.57.00.01-◊●◊●◊ Temporary Controls for Work Areas

1.2.J. Section 01.57.19.01-◊●◊●◊ Temporary Environmental Controls

1.2.K. Section 01.58.00.01-Project Identification

1.2.L. Section 01.61.00.01-Common Product Requirements

1.2.M. Section 01.61.16.01-◊●◊●◊ Use of Recovered Materials and Biobased Products

1.2.N. Section Error! Reference source not found.

Procurement Scope March 18, 2026 00.24.00.01-Page 2 USIBWC Solicitation 191BWC26Rxxxx

1.2.O. Section 01.74.19.01-◊●◊●◊ Construction Waste Management and Disposal

1.2.P. Section 02.01.00.01-◊●◊●◊ Existing Conditions & Facilities

1.2.Q. Section 02.21.00.01-◊●◊●◊ Surveys

1.2.R. Section 02.22.13.01-Existing Conditions Assessment

1.3. REFERENCE STANDARDS

1.3.A. Federal Emergency Management Agency (FEMA)

1. 44 CFR 65.10, Mapping of Areas Protected by Levee Systems

1.3.B. US Army Corps of Engineers (USACE)

1. EM 1110-2-1913, Design and Construction of Levees, April 30, 2000

1.3.C. United States Code (USC)

1. Davis Bacon Act (DBA), 40 USC 3141-3148

1.4. MEASUREMENT AND PAYMENT

The work performed by the Design-Builder under this Section shall not be paid for directly but shall be included in the various Bid Items under this Contract.

1.5. PROJECT GOAL

Retamal Dam is in Hidalgo County, Texas approximately 2.5 miles east of Donna Point international port of entry.

1.5.A. The final product shall be capable of or shall meet these requirements:

1. The final design for this project shall provide a waterway barrier line to include anchors, alert system, and warning signs at the Retamal Dam.

2. The design, procurement, and commissioning of the barrier system shall provide the following:

a. Protection to the public by excluding boaters/swimmers from hazardous zones.

b. Deflect/Contain debris to reduce intake clogging and structural impacts.

c. Provide clear warning signs and alert system compliant with applicable safety and waterway standards.

d. Provide adequate mooring and anchor system.

e. Provide conspicuous marking, retroreflective elements, and lighting per applicable guidance.

f. Enable inspection access and simple component replacement.

g. Provide a minimum service life of 10-15 years with defined maintenance plan and corrosion protection.

h. The system will avoid or mitigate impacts to habitants, water quality, and listed species.

i. Provide a topographic and bathymetric survey of the dam.

j. Provide a geotechnical investigation.

k. Provide a Hydraulic and Hydrology (H&H) memo with design events and velocities.

1.5.B. Upon conclusion of the project, the new waterway barrier line will prevent public access to dangerous hydraulics upstream/downstream of the dam, the warning system and signage will alert the public of the danger ahead.

1.5.C. Utilities It is the Design-Builder’s responsibility to identify all existing utilities within the project limits as well as coordinating any work associated with these utilities with the utility company.

USIBWC Solicitation 191BWC26Rxxxx 00.24.00.01-Page 3

1.5.D. Permits Refer to Section 00.31.43.01.

1.6. WORK ELEMENTS

1.6.A. The work shall include all planning, design work, coordination, permitting, labor, material, tools, equipment, construction, testing, inspection, commissioning, and all necessary general conditions, that may be reasonably inferred from the Contract Documents to provide for all work for the design and construction of a waterway barrier line to include anchors, surveys, studies, alert system, and warning signs.

1.6.B. The work shall be broken out into 2 phases.

1. Phase 1 is the Design Phase.

The Design Phase includes, but is not limited to:

a. Site investigation

b. Site surveying

c. Topographic survey

d. Bathymetric survey

e. H&H study and memo

f. Any required geotechnical investigations, modeling, or testing.

g. Design

h. Production of construction documents (minimum of drawings and technical specifications)

i. Production of all project reports

j. Coordination with stakeholders

2. Phase 2 is the Construction Phase.

The Construction Phase includes, but is not limited to:

a. Site preparation

b. Construction

c. Disposal of debris and construction waste

d. Quality control testing

e. Commissioning

1.6.C. Each phase shall have a separate Notice to Proceed (NTP).

1.6.D. The final product shall be a 100% completed construction project (turnkey) in accordance with the Design-Build Contract, this Scope of Work, and the construction drawings and specifications.

1.7. SEQUENCE OF WORK/TIME FOR COMPLETION OF WORK

1.7.A. After receipt of the Notice to Proceed (NTP) the Design-Builder shall comply with all submittal requirements as covered under this Scope of Work.

1. No construction shall be started, until the Government compliance confirms the required premobilization submittals. Once the Government determines that construction may proceed, will mobilization be allowed.

2. The Government will not grant any time extension for any resubmittal required when, in the opinion of the CO, the initial submission failed to meet the minimum quality requirements as set forth in the Contract.

3. If the Government allows the Design-Builder to proceed with limited construction based on pending minor revisions to the reviewed submittals, no payment will be made for any in-place construction related to the pending revisions until they are completed, resubmitted and are satisfactory to the Government.

00.24.00.01-Page 4 USIBWC Solicitation 191BWC26Rxxxx

4. No payment will be made for any in-place construction until all submittals required for that portion of the work and/or required prior to the start of construction have been made, reviewed, and are satisfactory to the Government.

1.7.B. Unless otherwise agreed to with the COR, mobilization and sitework shall begin within 90 days of the issuance of the Construction Notice to Proceed (NTP).

1. Design-Builder and Construction Contractor shall expeditiously plan and prepare their premobilization submittals and any resubmittals as well as take into account the Government's review time to meet this requirement.

2. Surveying, photographing/videotaping site, and vibration condition survey do not constitute sitework for this requirement.

1.7.C. The work under this Contract shall be completed within the timeframe specified in the Contract Provisions. Time will only stop being counted once substantial completion is achieved (Section 01.78.36.01).

1.7.D. Where FAR 52.211-10 provides specific timeframes for completion of the design, construction, and revegetation, the following shall apply:

1. Design shall be completed within the timeframe noted in FAR 52.211-10.

2. If the design is completed prior to the timeframe noted in FAR 52.211-10, the remaining days shall be applied to the construction phase. For example, if the design is completed 20 days early, 20 days shall be added to the construction timeframe.

3. If the design is completed after the specified timeframe noted in FAR 52.211-10, then the Design-Builder is behind schedule and subject to any liquidated damages or other repercussions determined by the CO. The additional time required for completion of the design shall be subtracted from the allowed construction timeframe. For example, if the design is completed 20 days late, 20 days shall be subtracted from the construction timeframe.

4. Regardless of the design completion time and the construction completion time, the timeframe noted in FAR 52.211-10 for revegetation shall begin after substantial completion has been reached.

1.8. WORK UNDER OTHER CONTRACTS

No work is anticipated to be performed at the project site under separate Contract with other Contractors during the Design-Builder’s performance period.

1.9. LABOR AND STAFFING

1.9.A. The Design-Builder is responsible for determining the appropriate staffing necessary to perform the Contract work. The Design-Builder is also responsible for complying with the minimum wage and benefits requirements for each labor classification performing work on the Contract.

1.9.B. If a classification considered necessary by the Design-Builder for performance of the work is not listed on the applicable wage determination, the Design-Builder must initiate a request for approval of an additional classification along with the proposed wage and benefit rates for that classification.

1.9.C. The Contracting Officer will attach the appropriate Davis-Bacon wage determination to this Contract. The Design-Builder is responsible for all requirements of the Davis-Bacon Act.

1.10. PROJECT LOCATION

1.10.A. The work is within the United States Section of the International Boundary and Water Commission's (USIBWC) Retamal Dam, in Hidalgo County, Texas.

1.10.B. The work is located completely in the United States and Mexico.

USIBWC Solicitation 191BWC26Rxxxx 00.24.00.01-Page 5

1.11. CONFLICT ORDER OF PRECEDENCE

1.11.A. In any case where this Scope of Work conflicts with the Federal Acquisition Regulations (FAR), use the following rules of precedence.

1. In any case where FAR requirements are stricter or impose a higher standard than these Scope of

Work, FAR requirements will take precedence.

2. In any case where Scope of Work requirements are stricter or impose a higher standard than FAR, Scope of Work requirements will take precedence.

1.11.B. Upon acceptance of the construction specifications and drawings by USIBWC, those documents become part of the Contract. If the construction specifications and drawings differ from this Scope of Work, the more stringent requirement will govern.

PART 2 - PRODUCTS

2.1. GOVERNMENT FURNISHED MATERIALS

1. The Government will not be furnishing any materials for this project.

2.2. PRODUCTS TO BE FURNISHED BY THE DESIGN-BUILDER

2.2.A. The Design-Builder shall provide all labor, all equipment, and all products required to execute the project.

2.2.B. All materials provided by the Design-Builder for the project shall be new (or recycled if allowed elsewhere in this SOW), high grade, free from defects, meeting the specifications herein. The minimum quality of the work shall be in accordance with the specifications herein.

2.2.C. The Design-Builder's QSM will ensure compliance confirmation and the Design-Builder's testing company will ensure that materials, equipment and work quality strictly adhere to the requirements of the construction documents.

2.2.D. Materials, equipment, and work quality not conforming to the requirements of this SOW, the construction specifications, and/or the construction drawings shall be considered defective and will be subject to rejection. Defective work material, whether in place or not, or equipment shall be removed immediately from the site by the Design-Builder, at its expense, when so directed by the COR.

2.2.E. If the Design-Builder fails to replace any defective or damaged work, materials or equipment after receiving notice, the COR may cause such work or materials to be replaced by other forces. The replacement expense shall be deducted from the amount to be paid to the Design-Builder. Defective equipment will not be allowed in the performance of any work.

2.2.F. Water for All Construction Activities.

1. The water required for all construction activities including, but not limited to, dust control (Section

01.57.19.01) and vegetation establishment shall be considered as incidental and shall be provided from a metered source that is compliance confirmed by the USIBWC.

2. Water from the Rio Grande shall not be used by the Design-Builder at any time.

3. Water use must be in accordance with Texas water law.

00.24.00.01-Page 6 USIBWC Solicitation 191BWC26Rxxxx

PART 3 - EXECUTION

3.1. SUBMITTALS REQUIRED PRIOR TO CONSTRUCTION MOBILIZATION

3.1.A. Specific specifications detail submittal requirements. The list below are the submittals required to have compliance confirmation from the COR prior to full construction mobilization and prior to starting construction activities.

1. Code of Business Ethics (Section Error! Reference source not found.)

2. Construction Schedule (Section 01.32.16.01)

3. Scheduler Qualifications (Section 01.32.16.01)

4. Video and Photographs of Existing Conditions (Section 01.32.33.01)

5. Submittal Register (Section 01.33.00.01)

6. Construction Accident Prevention Plan (Section 01.35.23.01)

7. Applicable AHAs to start mobilization and construction (Section 01.35.23.01)

8. Site Safety and Health Officer Qualifications (Section 01.35.23.01)

9. Construction Contingency Evacuation Plan (Section 01.35.23.01)

10. Construction Employee First-Aid and CPR Training Records (Section 01.35.23.01)

11. Design-Builder Quality Assurance Plan (Section 01.40.00.01)

12. Design-Builder QC/QA Personnel Qualifications (Section 01.40.00.01)

13. Construction Staging Area/Haul Routes/Trailer Location/Storage (Sections 01.52.13.01 and

01.57.19.01)

14. Construction SWPP Plan (Section 01.57.00.01)

15. Construction SWPP NOI (Section 01.57.00.01)

16. Resource Conservation Construction Plan (Sections 01.61.00.01, 01.61.16.01, and 01.74.19.01)

17. Construction Flood Protection Plan (Section 02.01.00.01)

18. Construction Vibration Control Plan (Section 02.22.13.01)

19. Preconstruction Condition Survey (Section 02.22.13.01)

3.1.B. The design report, survey data/report, geotechnical report, construction drawings, GIS data, and construction specifications outlined in Section 01.33.16.01 Paragraph 1.6.A. shall have reached 100% and been accepted by USIBWC.

3.1.C. The construction specifications and construction drawings shall have been added to the Contract via a no-cost modification.

3.1.D. Once these required items are complete, the Design-Builder will be allowed to mobilize their Construction Contractor and begin work within USIBWC's right-of-way (ROW).

3.2. USE OF RIGHT-OF-WAY

3.2.A. Limits

1. Construction operations shall be confined to the USIBWC ROW.

3.2.B. It is the Design-Builder’s responsibility to locate and/or verify the areas required for construction beyond the USIBWC ROW, identify the owners of the affected properties, and acquire necessary easements, prior to commencement of construction, at no cost to the USIBWC.

3.2.C. Roads serving the right-of-way, identified as such or not, owned by the USIBWC or CBP shall be clear and available to these agencies.

USIBWC Solicitation 191BWC26Rxxxx 00.24.00.01-Page 7

3.3. OCCUPANCY OF RIGHT-OF-WAY

3.3.A. Partial Government Occupancy The Government may need to occupy the right-of-way during the entire construction period, with the exception of areas under construction. The Construction Contractor via the Design-Builder shall cooperate with the Government during construction operations to minimize conflicts and facilitate Government access. The Design-Builder needs to maintain existing access to the facility, unless otherwise indicated in the construction drawings. The Design-Builder shall provide not less than 72 hours' notice to the Government of construction activities that will affect any Government activities.

3.3.B. Government Occupancy of Completed Areas of Construction The Government reserves the right to occupy and to place and install equipment in completed areas of the facility, before Substantial Completion, provided such occupancy does not interfere with completion of the work. Such placement of equipment and partial occupancy shall not constitute acceptance of the total work.

3.4. SITE WORK RESTRICTIONS

3.4.A. Onsite Work Hours The Design-Builder’s attention is directed to the Contract Provisions.

3.4.B. Facility Office Hour

1. The working hours of the adjacent USIBWC facility are 07:30 am to 04:00 pm, Monday through

Friday. The Design-Builder, the Construction Contractor, and any subcontractors shall only work onsite during these proposed hours.

2. USIBWC facilities are closed during all Federal Holidays.

00.24.00.01-Page 8 USIBWC Solicitation 191BWC26Rxxxx

March 18, 2026 Project Information USIBWC Solicitation 191BWC26Rxxxx 00.31.00.01-Page 1

SECTION 00.31.00.01

PROJECT INFORMATION

00.31.00.01 Project Information 00.31.00.01-Project Information

PART 1 - GENERAL

1.1. SECTION INCLUDES

Part 1 - General

1.1. Section Includes

1.2. Related Requirements

1.3. Measurement and Payment

1.4. Information Provided by the USIBWC

Part 2 - Products (Not Used) Part 3 - Execution (Not Used) --End of Section--

1.2. RELATED REQUIREMENTS

1.2.A. Section 00.60.00.01-◊●◊●◊ USIBWC Forms and Standard Documents

1.2.B. Section 00.73.73.01-Requirements for Sensitive But Unclassified Information

1.3. MEASUREMENT AND PAYMENT

The work performed by the Design-Builder under this Section shall not be paid for directly but shall be included in the various Bid Items under this Contract.

1.4. INFORMATION PROVIDED BY THE USIBWC

1.4.A. USIBWC shall provide the following project documents to the Design-Builder.

1. As-built Drawings of Retamal Dam.

2. USIBWC's standard AutoCAD border (USIBWC's CAD files and Drawing and CAD Standards link on www.ibwc.gov/resources-info/)

3. USIBWC's AutoCAD ctb file (USIBWC's CAD files and Drawing and CAD Standards link on www.ibwc.gov/resources-info/)

4. IBWC's Drawing and CAD Standards (USIBWC's CAD files and Drawing and CAD Standards link on www.ibwc.gov/resources-info/)

5. USIBWC Standard Technical Specifications Boilerplate (USIBWC's Construction Specifications

Template link on www.ibwc.gov/resources-info/)

6. USIBWC shall provide the following CUI project documents to the Design-Builder after completion of a nondisclosure agreement (IBWC Form 358). See Section 00.73.73.01 for guidance on CUI data.

1.4.B. CUI items will be provided via a Sharepoint link to each Offeror requesting access to this data. The Offerors shall provide an email address along with IBWC Form 358 to the CO for this link.

1. No more than 2 Sharepoint links will be provided to each Bidder.

2. To use Sharepoint, a user must have a valid Microsoft account. If this method fails, data can be provided to the Offeror via a DVD, but there will be a delay in getting the DVD mailed to each Bidder.

3. All unsuccessful Offerors shall provide IBWC Form 358A to the CO within 7 days of being notified of their unsuccessful offer.

https://www.ibwc.gov/resources-info/ https://www.ibwc.gov/resources-info/ https://www.ibwc.gov/resources-info/

Project Information March 18, 2026 00.31.00.01-Page 2 USIBWC Solicitation 191BWC26Rxxxx

1.4.C. See Section 00.60.00.01 for instructions on accessing data on USIBWC's website.

1.4.D. The Design-Builder is responsible for printing copies of items provided in electronic format for their own use.

1.4.E. Any hardcopy documents provided to the Design-Builder are the property of the USIBWC and shall be returned upon completion of this project.

PART 2 - PRODUCTS

(Not Used)

PART 3 - EXECUTION

March 18, 2026 ◊●◊●◊ Project Time Constraints & Milestones USIBWC Solicitation 191BWC26Rxxxx 00.31.13.01-Page 1

SECTION 00.31.13.01

PROJECT TIME CONSTRAINTS & MILESTONES

00.31.13.01 ◊●◊●◊ Project Time Constraints & Milestones 00.31.13.01-◊●◊●◊ Project Time Constraints & Milestones

PART 1 - GENERAL

1.1. SECTION INCLUDES

Part 1 - General

1.1. Section Includes

1.2. Measurement and Payment

1.3. Design Milestones

1.4. Schedule Limitations

Part 2 - Products (Not Used) Part 3 - Execution (Not Used) --End of Section--

1.2. MEASUREMENT AND PAYMENT

The work performed by the Design-Builder under this Section shall not be paid for directly but shall be included in the various Bid Items under this Contract.

1.3. DESIGN MILESTONES

1.3.A. Required submittals include:

1. Conceptual Layout / Design Development Documents

2. 30% Design

3. 60% Design

4. 90% Design

5. Pre-100% Design

6. 100% Design

1.4. SCHEDULE LIMITATIONS

1.4.A. The complete period of performance shall include the design, including production of design and construction documents, and construction.

1.4.B. The Design-Builder shall submit the 30% design documents as stipulated under the design criteria.

1. The USIBWC shall provide comments within 28 calendar days of receipt of these deliverables and the Design-Builder shall incorporate the Government's comments prior to the next submittal.

1.4.C. The Design-Builder shall submit the 60% design documents as stipulated under the design criteria.

1. The USIBWC shall provide comments within 28 calendar days of receipt of these deliverables and the Design-Builder shall incorporate the Government's comments prior to the next submittal.

1.4.D. The Design-Builder shall submit the 90% design documents as stipulated under the design criteria.

1. The USIBWC shall provide comments within 28 calendar days of receipt of these deliverables and the Design-Builder shall incorporate the Government's comments prior to the next submittal.

1.4.E. The Design-Builder shall submit the 100% design documents of construction specifications, construction drawings, and Design Memorandum as stipulated under Design Work Requirements.

1. Initial 100% submittal shall be in electronic form only. This shall be known as the pre-100% submittal.

◊●◊●◊ Project Time Constraints & Milestones March 18, 2026 00.31.13.01-Page 2 USIBWC Solicitation 191BWC26Rxxxx

2. The USIBWC shall provide additional comments on the 100% deliverables in the event that the Design-Builder failed to incorporate accordingly or adequately address all of the USIBWC’s 90% comments. Comments will be provided within 28 calendar days of receipt of these submittals.

3. After acceptance of the 100% submittal, then Design-Builder shall provide required hard and electronic copies of all 100% documents.

1.4.F. After completion of Phase 1, the Design-Builder shall construct the metal building.

PART 2 - PRODUCTS

(Not Used)

PART 3 - EXECUTION

March 18, 2026 Existing Condition Information USIBWC Solicitation 191BWC26Rxxxx 00.31.19.01-Page 1

SECTION 00.31.19.01

EXISTING CONDITION INFORMATION

00.31.19.01 Existing Condition Information 00.31.19.01-Existing Condition Information

PART 1 - GENERAL

1.1. SECTION INCLUDES

Part 1 - General

1.1. Section Includes

1.2. Measurement and Payment

1.3. General

1.4. Existing Structures

1.5. Existing Utilities

Part 2 - Products (Not Used) Part 3 - Execution (Not Used) --End of Section--

1.2. MEASUREMENT AND PAYMENT

The work performed by the Design-Builder under this Section shall not be paid for directly but shall be included in the various Bid Items under this Contract.

1.3. GENERAL

1.3.A. The final design shall take all existing conditions into account as well as information discovered during investigations under this Contract.

1.4. EXISTING STRUCTURES

Retamal Dam is an existing diversion structure located in Hidalgo County, Texas, approximately 2.5 miles east of the Donna Point International Port of Entry along the U.S.–Mexico border. The dam stands about 33 feet high, has a maximum bottom‑slab width of 200 feet, and includes four interior piers and two abutment piers that support three radial gates. The central radial gate is 82 feet wide by 24 feet high and provides a discharge capacity of up to 20,000 cfs; its hydraulic lifting system has been replaced with an electrical system. The two side radial gates are each 40 feet wide by 29 feet high and collectively provide an additional discharge capacity of 10,000 cfs (see Figure 1).

Existing Condition Information March 18, 2026 00.31.19.01-Page 2 USIBWC Solicitation 191BWC26Rxxxx

Figure 1

1.5. EXISTING UTILITIES

1.5.A. USIBWC's records for installed utilities are often incomplete. The Design-Builder is responsible for locagates.l utilities including, but not limited to, irrigation structures, buried communication, gas, water, and electrical lines.

PART 2 - PRODUCTS

(Not Used)

PART 3 - EXECUTION

March 18, 2026 Environmental Information USIBWC Solicitation 191BWC26Rxxxx 00.31.24.01-Page 1

SECTION 00.31.24.01

ENVIRONMENTAL INFORMATION

00.31.24.01 Environmental Information 00.31.24.01-Environmental Information

PART 1 - GENERAL

1.1. SECTION INCLUDES

Part 1 - General

1.1. Section Includes

1.2. Related Requirements

1.3. Reference Standards

1.4. Measurement and Payment

1.5. General

1.6. Preservation of Cultural and Natural Resources and the Environment

1.7. Other Considerations

1.8. Use of Geologic Materials on a Federally Funded Project

Part 2 - Products (Not Used) Part 3 - Execution (Not Used) --End of Section--

1.2. RELATED REQUIREMENTS

1.2.A. Section 01.57.00.01-◊●◊●◊ Temporary Controls for Work Areas

1.2.B. Section 01.57.19.01-◊●◊●◊ Temporary Environmental Controls

1.2.C. Section 02.21.13.01-◊●◊●◊ Cultural Resources Surveys

1.3. REFERENCE STANDARDS

1.3.A. United States Code (USC)

1. Clean Air Act, 42 USC 7401 et seq.

2. Clean Water Act (CWA), 33 USC 1251 et seq.

3. Endangered Species Act (ESA), 16 USC 1531 et seq.

4. Migratory Bird Treaty Act (MBTA), 16 USC 703 - 712

5. National Environmental Policy Act (NEPA), 42 USC 4321-4347

6. National Historic Preservation Act (NHPA), 54 USC 300101 et seq.

7. National Wildlife Refuge System Improvement Act of 1997, 16 USC 668dd

8. Native American Graves Protection and Repatriation Act (NAGPRA), 25 USC 3001 et. seq.

9. Refuge Recreation Act, 16 USC 460k - 460k-4

1.4. MEASUREMENT AND PAYMENT

The work performed by the Design-Builder under this Section shall not be paid for directly but shall be included in the various Bid Items under this Contract.

1.5. GENERAL

1. Biological Resources

Work should be scheduled to occur outside of the bird breeding season whenever possible.

Migratory birds may be present within the project area; birds, nests, and eggs are to be protected and avoided during construction. The breeding and nesting season is identified in Section 01.57.19.01. If

Environmental Information March 18, 2026 00.31.24.01-Page 2 USIBWC Solicitation 191BWC26Rxxxx work continues into the bird breeding/nesting season the areas proposed for disturbance shall be surveyed in order to avoid the inadvertent destruction of nests and eggs.

2. Natural Resources Equipment cannot be parked, staged, or used under large, mature trees. Keeping equipment away from the large, mature trees will prevent incidental damage to the tree and prevent compression of the root ball.

1.5.B. Further details of environmental requirements are in Sections 01.57.00.01 and 01.57.19.01.

1.6. PRESERVATION OF CULTURAL AND NATURAL RESOURCES AND THE ENVIRONMENT

1.6.A. If the Design-Builder initiates changes to the Contract and USIBWC approves the changes, the Design-Builder is responsible for obtaining clearances and coordinating with the appropriate regulatory agencies.

1.6.B. Culturally Sensitive Areas If a site, building, or location of historical, archaeological, educational, or scientific interest is discovered within the right of way, cease all work immediately, secure the site from further disturbance and possible vandalism, and notify USIBWC. The site, building, or location will be investigated and evaluated by

USIBWC.

1.7. OTHER CONSIDERATIONS

The Design-Builder is required to ensure that all Environmental Permits, Issues, and Comments (EPIC), which are included within the Contract Documents are followed and implemented to ensure potential impacts are avoided.

1.8. USE OF GEOLOGIC MATERIALS ON A FEDERALLY FUNDED PROJECT

1.8.A. To ensure preservation of historical and archaeological data, prior to use of any soil, rock, or gravel including aggregate in concrete, the source must first be compliance confirmed by the COR to ensure compliance with Section 106 of the National Historic Preservation Act (NHPA).

1.8.B. Take no action to use or alter the proposed location until written approval for site use is received from the

COR.

1.8.C. If the quarry or borrow site already provides materials for TxDOT, USACE, or other governmental agency, a copy of the environmental approvals from said agencies may be provided to the COR.

1.8.D. Include permission for Government access to any geological source locations.

1.8.E. Full details of requirements for geological materials are in Section 02.21.13.01.

PART 2 - PRODUCTS

(Not Used)

PART 3 - EXECUTION

March 18, 2026 Existing Hazardous Material Information USIBWC Solicitation 191BWC26Rxxxx 00.31.26.01-Page 1

SECTION 00.31.26.01

EXISTING HAZARDOUS MATERIAL INFORMATION

00.31.26.01 Existing Hazardous Material Information 00.31.26.01-Existing Hazardous Material Information

PART 1 - GENERAL

1.1. SECTION INCLUDES

Part 1 - General

1.1. Section Includes

1.2. Related Requirements

1.3. Measurement and Payment

1.4. General

Part 2 - Products (Not Used) Part 3 - Execution (Not Used) --End of Section--

1.2. RELATED REQUIREMENTS

1.2.A. Section 00.31.24.01-Environmental Information

1.3. MEASUREMENT AND PAYMENT

The work performed by the Design-Builder under this Section shall not be paid for directly but shall be included in the various Bid Items under this Contract.

1.4. GENERAL

No hazardous materials, waste storage facilities, disposal sites, or spill sites have been identified within the immediate project area.

PART 2 - PRODUCTS

(Not Used)

PART 3 - EXECUTION

March 18, 2026 Permit Application USIBWC Solicitation 191BWC26Rxxxx 00.31.43.01-Page 1

SECTION 00.31.43.01

PERMIT APPLICATION

00.31.43.01 Permit Application 00.31.43.01-Permit Application

PART 1 - GENERAL

1.1. SECTION INCLUDES

Part 1 - General

1.1. Section Includes

1.2. Reference Standards

1.3. Measurement and Payment

1.4. General

1.5. Work in Waters of the United States

1.6. Responsibilities

Part 2 - Products (Not Used) Part 3 - Execution (Not Used) --End of Section--

1.2. REFERENCE STANDARDS

1.2.A. Error! AutoText entry not defined.US Army Corps of Engineers (USACE)

1. Section 404 of Clean Water Act, 33 USC 1251 et seq.

1.3. MEASUREMENT AND PAYMENT

The work performed by the Design-Builder under this Section shall not be paid for directly but shall be included in the various Bid Items under this Contract.

1.4. GENERAL

Prior to the beginning of construction, the Design-Builder shall be responsible for researching, coordinating, obtaining, and paying all applicable fees for all permits required by Federal, state, and local entities, including, but not limited to, a specific or general stormwater permit prepared in accordance with the requirements of Stormwater Pollution Prevention Plan (SWPPP) and Texas Pollutant Discharge Elimination System (TPDES) 2018 General Permit TXR150000.

1.5. WORK IN WATERS OF THE UNITED STATES.

1.5.A. For work in the right-of-way, USIBWC will obtain any required Section 404 permits from the US Army Corps of Engineers before work begins.

1.5.B. The Design-Builder must adhere to all agreements, mitigation…