This is an Invitation for Bid (IFB) for a construction project at the James J. Peters DVA Medical Center in Bronx, New York. The solicitation (36C24225B0038) is for Project 526-26-102 to replace Main Emergency Management Diesel (EMD) Generators and Cooling Towers, with a total project value between $10 million and $20 million. It is a 100% Service-Disabled Veteran Owned Small Business (SDVOSB) set-aside procurement, with a contract completion time of 760 calendar days from notice to proceed.

Key project details include replacing two 4160-volt generators with two new 2.8-MW Tier 4F generators, modifying the existing Motor Pool Building, constructing a new electrical switchgear building, installing new cooling towers, and implementing comprehensive electrical, mechanical, fire suppression, and security system upgrades. A pre-bid site visit is scheduled for 8/27/25 at 9:00 AM EST, with bids due on 9/22/25 at 2:00 PM EST. The project requires extensive coordination, compliance with VA specifications, and adherence to physical security and resiliency design manual requirements. Bidders must be registered in SAM and verified as an SDVOSB on the DSBS.SBA.GOV website.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C24225B0038 James J. Peters Bronx VA Medical Center

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C24225B0038 X

08-22-2025

526-25-1-5963-0001

526-26-102 36C242 Department of Veterans Affairs Network Contracting Office 2 James J. Peters DVA Medical Center 130 W. Kingsbridge Road Bronx NY 10468 Department of Veterans Affairs Network Contracting Office 2 James J. Peters DVA Medical Center 130 W. Kingsbridge Road Bronx NY 10468 Patricia Cordero 718 584-9000 This project is to furnish all necessary professional Construction services to Replace Main EMD and Replace Cooling Towers, a combined project at the James J. Peters DVA Medical Center, Bronx, New York.

The contractor shall furnish all materials, supplies, equipment, personnel and supervision to accomplish Project No.

526-26-102 Replace Main EMD and Cooling Towers.

This is a 100% Service-Disabled Veteran Owned Small Business set aside procurement. All prospective bidders must be registered in SAM (WWW.SAM.GOV) with a Unique Entity Identifier (UEI) and are verified/visible/certified as an SDVOSB on WWW.DSBS.SBA.GOV at the time of bid submission and prior to award of this procurement. Bidders must submit their annual Vets-4212 Report. Magnitude of Construction: Between $10,000,000 and $20,000,000. The North American Industry Classification System Code (NAICS) is 236220 - Business Size is $19.5 million.

Contractor will be responsible to coordinate and schedule work and shall be expected to plan work typically during duty hours of 8 AM to 4:30 PM eastern time except as noted in the general conditions and as approved by the CO. Work shall comply with VA Specifications and regulations, all applicable Federal, State and Local codes, including specific regulations related to working at the Bronx VA Campus.

A pre-bid site visit is scheduled for 8/27/25 at 9:00 AM EST. Prospective bidders shall meet at James J. Peters VAMC Building 100 GC-106 Engineering Conference Room, 130 W. Kingsbridge Road, Bronx NY 10468.

NOTE: NO OTHER SITE VISITS WILL BE ALLOWED. INTERESTED BIDDERS ARE STRONGLY ENCOURAGED TO ATTEND.

To preserve the integrity of the procurement process, all questions and request for information must be submitted in writing to Patricia Cordero via email at Patricia.Cordero@va.gov.

Questions must be received no later than 9/4/2025 at 4:00PM EST.

The bid opening will be held IN PERSON on 9/22/2025 at 2PM EST and will be held in GC-106. NO EMAILED bids will be accepted. An original bid bond must be submitted with bid. Hand carried bids must be delivered to the CO, Patricia Cordero in GC-125.

IAW 852.219-75 VA Notice of Limitations in Subcontracting, the attached Certificate of Compliance must be signed and Submitted with your bid.

IAW 52.225-2 Buy American Act, the attached Buy American Certificate must be signed and submitted with your bid.

FAR Part 36.209 Construction contracts with architect-engineer firms. No contract for the construction of a project shall be awarded to Miller-Remick or its subsidiaries or affiliates.

NOTE: CONTRACTORS MUST ACKNOWLEDGE ALL SOLICIATION AMENDMENTS.

x x

52.211-10 X

10 days 2pm

EDT

09-22-2025 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

561-3650162-5963-854200-3223-23NR0BV08

36C242 Department of Veterans Affairs Network Contracting Office 2 Stratton VA Medical Center 113 Holland Ave Albany NY 12208

Tungsten Network http://www.tungsten-network.com/us/en /veterans-affairs

1-877-489-6135

Dayna Dickson-Miller Contracting Officer

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK2
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS5
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS33
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)33
2.2 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)33
2.3 52.201-1 ACQUISITION 360: VOLUNTARY SURVEY (SEP 2023)34
2.4 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)35
2.5 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021)35
2.6 52.233-2 SERVICE OF PROTEST (SEP 2006)36
2.7 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)36
2.8 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)37
2.9 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)37
2.10 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)37
2.11 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS– CPM) (NOV 2018)38
2.12 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)41
2.13 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018)41
REPRESENTATIONS AND CERTIFICATIONS43
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2025) (DEVIATION FEB 2025)43
3.2 52.204-29 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT ORDERS—REPRESENTATION AND DISCLOSURES (DEC 2023)47
3.3 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)48
3.4 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021)50
3.5 52.212-3 OFFEROR REPRESENTATIONS AND CERTIFICATIONS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (MAY 2024)52
3.6 52.213-4 TERMS AND CONDITIONS—SIMPLIFIED ACQUISITIONS (OTHER THAN COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES) (JAN 2025)72
GENERAL CONDITIONS79
4.1 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (NOV 2021)79
4.2 52.204-30 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT ORDERS—PROHIBITION (DEC 2023)81
4.3 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984)86
4.4 52.211-18 VARIATION IN ESTIMATED QUANTITY (APR 1984)86
4.5 52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR EXECUTIVE ORDERS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (JAN 2025)87
4.6 52.219-28 POSTAWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JAN 2025)96
4.7 52.225-11 BUY AMERICAN—CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (NOV 2023)100
4.8 52.236-4 PHYSICAL DATA (APR 1984)107
4.9 SUPPLEMENTAL INSURANCE REQUIREMENTS108
4.10 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)109
4.11 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (NOV 2018)112
4.12 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR VERIFIED SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (NOV 2022)113
4.13 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023) (DEVIATION)116
4.14 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)117
4.15 VAAR 852.236-72 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 2019)119
4.16 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)119
4.17 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)119
4.18 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020)120
4.19 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020)121
4.20 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019)121
4.21 MANDATORY WRITTEN DISCLOSURES122
4.22 52.225-12 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (MAY 2014) ALTERNATE I (MAY 2014) AND ALTERNATE II (NOV 2023)123
4.23 VAAR 852.201-70 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 2022)124
4.24 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)124

INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS

(a) Bidding materials consisting of Invitation for Bids, drawings, specifications and contract forms will be available on https://sam.gov/ in electronic format only by searching for solicitation number 36C24225B0038. All interested parties (subs & primes) should register at https://sam.gov/ as an “Interested Vendor” so that others will know of our interest in participating in this procurement. A Bidder’s mailing list WILL NOT BE prepared by the Contract Specialist. SOLICITATION AMENDMENTS: Amendments to the solicitation will be posted at https://sam.gov/ Paper copies of the amendments will NOT be individually mailed. By registering to “Receive Notification”, you will be notified by e-mail of any new amendments that have been issued and posted. No other notification of amendments will be provided. Bidders are reminded that they are responsible for obtaining and acknowledging all amendments to this solicitation prior to the time for receipt of bids.

(b) If bid exceeds $150,000 a bid bond must be submitted. A bid guarantee is required in an amount not less than 20 percent of the bid price but shall not exceed $3,000,000. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for opening of bids, will require rejection of the bid in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then.

(c) If the contract will exceed $150,000 (see FAR 28.102-1 for lesser amount), the bidder to whom award is made will be required to furnish two bonds, a Payment Bond, SF 25A, and a Performance Bond, SF 25, each in the penal sum as noted in the General Conditions of the Specification. Copies of SFs 25 and 25A may be obtained upon application to the issuing office.

(d) If the bid is between $30,000 - $150,000. The bidder to whom award is made will be required to furnish a Payment Bond, Standard Form 25A or alternative payment protection which conforms to the requirements set forth in FAR Clause 52.228-13, Alternative Payment Protections, as noted in the General Conditions of this Specification. Copies of the Standard Form of Payment Bond may be obtained upon application to the Issuing Office.

DESCRIPTION OF WORK: GENERAL CONSTRUCTION: : The Contractor shall furnish all necessary professional Construction services to provide complete scope of work for Project # 526-26-102 Replace Main EMD and Cooling Towers in accordance to the project drawings and specifications for the James J. Peters DVA Medical Center, Bronx, NY.

Magnitude of Construction: More than $10,000,000.00

(a) Bidding materials consisting of Invitation for Bids, drawings, specifications and contract forms will be available on https://beta.sam.gov/ in electronic format only by searching for solicitation number 36C24225B0038. All interested parties (subs & primes) should register at https://beta.sam.gov/ as an “Interested Vendor” so that others will know of our interest in participating in this procurement. A Bidder’s mailing list WILL NOT BE prepared by the Contract Specialist. SOLICITATION AMENDMENTS: Amendments to the solicitation will be posted at SAM.gov/. Paper copies of the amendments will NOT be individually mailed. By registering to “Receive Notification”, you will be notified by e-mail of any new amendments that have been issued and posted. No other notification of amendments will be provided. Bidders are reminded that they are responsible for obtaining and acknowledging all amendments to this solicitation prior to the time for receipt of bids.

(b) If bid exceeds $150,000 a bid bond must be submitted. A bid guarantee is required in an amount not less than 20 percent of the bid price but shall not exceed $3,000,000. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for opening of bids, will require rejection of the bid in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then.

(c) If the contract will exceed $150,000 (see FAR 28.102-1 for lesser amount), the bidder to whom award is made will be required to furnish two bonds, a Payment Bond, SF 25A, and a Performance Bond, SF 25, each in the penal sum as noted in the General Conditions of the Specification. Copies of SFs 25 and 25A may be obtained upon application to the issuing office.

(d) If the bid is between $30,000 - $150,000. The bidder to whom award is made will be required to furnish a Payment Bond, Standard Form 25A or alternative payment protection which conforms to the requirements set forth in FAR Clause 52.228-13, Alternative Payment Protections, as noted in the General Conditions of this Specification. Copies of the Standard Form of Payment Bond may be obtained upon application to the Issuing Office.

DESCRIPTION OF WORK: GENERAL CONSTRUCTION: The Contractor shall furnish all necessary professional Construction services to provide complete scope of work for Project 526-26-102 Replace Main EMD’s and Cooling Towers all in accordance with strict drawings and specifications for the DVA Medical Center, James J. Peters VA, Bronx, NY.

Magnitude of Construction: more than $10,000,000

Project Number 536-26-102 Combined project to Replace Main EMD’s and Replace Cooling towers

BID PRICING SHEET

Bids providing less than 120 Calendar Days of Government Acceptance after the date bids are due will not be considered and will be rejected.

The bidder agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation if this bid is accepted by the Government in writing within 120 calendar days after the date bids are due.

BASE BID: ITEM I, GENERAL CONSTRUCTION: Work includes general construction, alterations, necessary removal of existing structures and construction and certain other items as required by the contract drawings and specifications.

The work shall be performed, as shown for Project Number 526-26-102, the combined projects to Replace Main EMD Generators and Cooling Towers at located at Department of Veterans Affairs, James J. Peters DVA Medical Center, 130 W. Kingsbridge Road, Bronx, NY 10468 in accordance with contract documents.

The contract completion time is 760 calendar days from receipt of Notice to Proceed (NTP).

BASE BID $ ___________________________

36C24225B0038

Page 1 of

Page 1 of

SCOPE OF WORK

CONSTRUCTION SERVICES

The Department of Veterans Affairs is accepting proposals from qualified firms to provide Construction services for labor, material and supervision related to the Replace Main EMD Generators and Cooling Towers Project located at the James J Peters VA Medical Center, 130 West Kingsbridge Road, Bronx, New York 10468.

The purpose of this project is to A. The primary objective of the project is to replace the Main EMD Generators at the Bronx, NY VAMC. This includes renovations to the existing Motor Pool Building.

B. As part of this effort, the tasks include evaluating locations for a new Load Bank and ensuring the project meets VA Physical Security and Resiliency Design Manual (PSRDM) mitigation measures.

C. As part of the overall project, modifications to the site area around the Motor Pool Building and other new project features will be necessary to achieve the overall project goal.

D. We are explicitly noting that it is the General Contractor’s responsibility to complete all required work related to:

· Final relay settings

· Field testing and commissioning

· Coordination with the neutral grounding resistors

· All Protective Relays and PLCs are to be replaced with NEW equipment E. It is the General Contractor's responsibility to complete all required work related to all aspects of this contract. The VA has completed prior Market Research to identify acceptable sub-contractors for specific specialized work tasks. The coordination with all subcontractors is the FULL responsibility of the General Contractor. The pre-approved subcontractors and the related specific specialized work tasks are included within Drawing E-604.

F. It is the Contractor’s responsibility to ensure that the new configuration of the circuit breakers, controls, protective replaying, PT’s, CT’s, Test Switches, etc provide the specified emergency system operation scheme.

G. It is the Contractor’s responsibility to furnish and install new Motorola Avigilon cameras and PACS system (HID for PIV readers in accordance with the design. Installation shall include providing and installing CAT6A cabling from each camera to a PoE network switch to the data center caged equipped with a minimum of two (2) fiber ports. The contractor shall also provide SFPs (MM LC modules), fiber LC aqua connectors, fiber cabinet port rack mounts, and OM3 50-micron fiber optic cables as needed. All required components shall be furnished and installed to provide a complete and operational system. The system shall be routed and fully integrated into the facility’s existing Avigilon platform, with fiber connections routed to the Network Video Recorder (NVR) located in the Police Station on the first floor of Building 100. The contractor shall supply and configure all necessary software, programming, and system adjustments to ensure a full operational system and seamless integration into the existing Avigilon system.

H. It is the Contactor`s responsibility for transporting and the delivery of the two (2) generators, switch gears, neutral grounding resistors, loose crates, and JW/AC Radiator and all other equipment in accordance with the design from the storage location to the final installation site as indicated in the contract documents.

The equipment storage site is located at Brothers & Company Inc.

830 Long Island Ave Deer Park NY 11729

The project entails design for replacement of existing EMD generators and their associated cooling towers. Modification of the existing “Motor Pool Building” to house new electrical switchgear serving the EMD Generators. Compliance with the PSRDM is required. The Motor Pool building has offices, work areas and a storage areas. The office and work areas are to remain. Existing storage room will be demolished. A new addition will be constructed to house the new electrical switchgear. Two means of egress are required, not through the Motor Pool Building. Addition must be constructed in accordance with the VA PSRDM. Two new dry coolers will replace the existing cooling towers and will be located on the roof of the new addition. The existing building is currently protected with a fire sprinkler system. The sprinkler system will be modified as necessary for this project. Piping will be extended from the existing system and designed to provide protection for the new switchgear room. The fire alarm system will be extended to provide notification and initiation devices for the new switchgear room. The existing building fire alarm site-wide panel is located on the first floor in the Graphic Control Room.

All work shall be completed as specified on the plans, specifications, and contract documents.

REPLACE EMD GENERATORS:

CIVIL

1) Per PSRDM mitigation measures, bollards are needed near the building southwest corners and new exterior door locations.

2) Sidewalks, ramps and elevated pad are needed to accommodate new building exterior doors.

3) All exterior grades around the Motor Pool Building will be adjusted as necessary to accommodate the renovated building.

4) Curbing shall be replaced where necessary due to utility trenching.

5) The new load bank will be placed on a slope requiring a retaining wall to create a level pad area for the structure. The load bank is proposed to be best situated to conform to the existing slope and to avoid impact to the nearby existing sanitary sewer line. All grades shall be adjusted as necessary to accommodate the load bank pad and wall. A sidewalk/access will be needed to the load bank.

6) The building is proposed to expand over an existing sanitary manhole. The sanitary manhole collects sewage from Building 101, stormwater from the parking area north of the Motor Pool Building and overflow from a sand trap manhole to the south. The stormwater is currently piped under the Motor Pool Building. All existing stormwater connections to this manhole are proposed to be rerouted around the building. The manhole shall be removed, and the sanitary line extended to a new manhole outside of the new building expansion where it shall be routed back to the existing downstream sanitary sewer line.

7) The sanitary lateral from the Motor Pool Building shall also be replaced/reset to accommodate the access ramp to a new building doorway.

8) The existing out of service steam line from Building 101 to Building 16 shall be removed where needed to accommodate all new infrastructure, capped and abandoned in other areas.

9) A new security gate will be added near Building 102 (Fisher House).

10) Temporary erosion controls will be needed during construction.

11) All disturbed asphalt and concrete areas will need to be restored. All pavement markings disturbed shall be repainted.

12) All disturbed turf grass areas will need to be re-vegetated.

STRUCTURAL

1) The existing walkway (Elev. 158’-5”) needs to be demolished and replaced with a new platform to meet the maintenance requirement of the new equipment.

2) The existing generator pad will be verified with the installation requirement of the new generator.

3) New concrete equipment pad.

4) Extension on the existing equipment pad.

5) Partially demo the existing Motor Pool Building (MPB) to build the Electrical Switch Gear Building (ESGB).

6) Supporting new load bank

7) New cast-in-place concrete equipment pads will be installed for the proposed electrical and mechanical equipment as required.

8) Existing cast-in-place equipment pads will be extended as required to fit new equipment as required.

9) Two SCRs will be located at different elevations. The SCR 101-SCR-01 will be located on the radiator room floor while the SCR 101-SCR-02 will be installed in the generator room located on the SCR platform.

10) Additional WF steel will be added as required to support the new equipment on the floor and hangers for supporting the platforms in the generator room.

11) A new service platform will be installed to support two DPFs, starting from the North access door/landing (located at EL. 158’-5”) to the edge location of the existing platform on the south side, between Column B6 and C4. The railing of the North access door/landing will be removed to accommodate this extension.

12) The door at the South-East shall be demolished and the opening of the door will be moving down to the floor elevation (EL. 158’-5”) to accommodate the new access to the DPF’s platform.

(ii) A staircase will be attached to the new platform on the North side to facilitate access to the existing platform.

(iii) A ladder will be installed on the South side to serve as an additional access point to the existing platform.

13) A platform for SCR (Selective Catalytic Reduction) equipment, including a 3ft wide maintenance area, will be installed approximately 4 ft above the existing platform. A ship ladder will be affixed to allow access to the maintenance area.

14) Safety guardrails will be installed around the service platform as per applicable safety standards and regulations to ensure the safety of personnel working on or around the platform.

14) The service platform will be supported by posts on the North wall side, while hangers will be used on the other side to ensure structural stability. Lateral supports and bracings will be installed for bracing the platform to move horizontally.

15) A blast catch system shall be adapted for the overhead rollup door of the generator room to mitigate the effects of an explosion.

16) The blast catch system's curtain shall be anchored to the existing floor slab at the bottom of the curtain to prevent the system from moving during an explosion.

17) A couple of pipes shall penetrate the north exterior wall of the generator room. As the pipes are relatively close to each other, top three courses of the CMU wall shall be removed for the pipe penetration. The opening shall be grouted, and the wall shall be reinforced with a C8 channel steel and braced back to the radiator floor frame.

18) The Motor Pool Building will be partially demolished for the new Switchgear Building (SGB). Sheet piles will be utilized for foundation excavation.

19) The new Electrical Switchgear Building (ESGB) will be a steel-framed structure. The steel frame will consist of moment connection frames in the South-North and East-West direction respectively to resist lateral loads such as wind, seismic, and blast loads.

20) For blast protection purposes, a high parapet will be provided on the three exterior sides of the building. The height of the parapet will be the same as that of the radiators.

21) The load bank will be located on the opposite side of the drive from the ESGB.

22) A retaining wall will be adopted for developing a flat area for locating the load bank. The exterior mat foundation will be used for supporting the load bank.

23) The backfill under the mat foundation shall be 95% engineering compacted fill.

24) In accordance with Section 1704 of the international building code, and all applicable state and local requirements, the Contractor shall contract with an independent approved agency to make periodic and/or continuous inspections of the construction progress in accordance with the following requirements: Steel Construction Section 1705.2 Concrete Construction Section 1705.3, Table 1705.3

ARCHITECTURAL

1) Demolition of the southern (plan west) portion of the one-story Motor Pool Building (Building 113) corresponding with Storage, Bathroom and Office –approximately 1,000 sq. ft. The Storage area will be permanently removed, while the Bathroom and Office area (approximately 390 sq. ft.) will be rebuilt after structural modifications are complete.

2) The existing drywall partition at the Motor Pool Storage room will be the location of a new demising wall between the proposed addition and the remaining Motor Pool structure. The demising wall will be a load-bearing concrete masonry wall on concrete foundation with furred gypsum board on the Office and Bathroom side. Structural work includes a new steel framed roof, and concrete slab. The Office and Bathroom will be recreated. Finishes, doors, and windows include the following:

(i) Painted walls. Office and Bathroom walls will be gypsum board over metal studs.

(ii) Porcelain tile floors and ceramic tile wainscot in the Bathroom.

(iii) Prefabricated shower stall, toilet fixture and accessories in the Bathroom.

(iv) Vinyl floor tile with 4” high rubber base in the Office.

(v) Acoustic panel ceilings in the Office and Bathroom. The open shop ceiling will be exposed structure.

(vi) Wood doors on hollow metal frames.

(vii) Office interior windows tempered glass in hollow metal frames.

3) Existing Generator and Switchgear Rooms: Several doors will be replaced including the overhead coiling door, exterior exit door, and doors at the exiting switchgear room. To meet blast resistance requirements, the new insulated coiling door will have a blast curtain catchment system located behind. Other doors will be blasting resistance. A door will be added between the Generator Room and the new addition to allow for staff access between these spaces. The Generator Room walls, and floor will be repainted.

4) Addition Construction: One-story addition on the south (plan west) side of the Motor Pool Building to house electric switchgear, and cooling towers on the roof. The addition will be approximately 1,070 sq. ft. with reinforced concrete masonry exterior walls, steel framed, concrete slab-on-grade, and steel roof deck. The masonry exterior walls extend above the roof to shield the cooling towers. New structure (columns and roof) will be 1-hour fire rated.

5) The floor of the addition will align with the existing Motor Pool floor elevation. Due to the sloping site, a stair and elevated walk will be required at entries to the addition.

6) Exterior walls and the roof screen of the addition are designed to be blast resistant. Exterior wall cladding will be 2-inch-thick insulated metal panels (R-16) over 1-inch girts. Insulated panels will extend at least 24” below the finished floor elevation to provide slab edge insulation. At the masonry screen wall (above the roof) metal panels will be uninsulated.

7) The addition will have two exterior doors. Double doors on the west (plan north) side for staff and equipment access, and a secondary exit on the south (plan west) side. Exterior doors will be hollow metal 14-gauge for blast resistance.

8) The existing built-up Motor Pool roof will be replaced with a new cold applied SBS modified bituminous roof system with R-30 insulation. The addition will have a similar new roof system with tapered insulation (R-30 average) & flashing work at curbs and penetrations for equipment. To avoid roof drains over electrical equipment, the new roof will drain to scuppers and downspouts on the north and south sides. The roof will be accessed from an interior ladder and roof scuttle.

9) The stairs will have steel pipe guardrails and handrails suitable for non-public use.

10) The addition will have (RES-2) Stonhard epoxy flooring, rubber base, and painted concrete masonry walls. The ceiling will be exposed structure with spray fireproofing. Column enclosures will be gypsum board over metal studs to achieve the required fire rating.

11) Wall mounted fire extinguishers will be provided by the VA in locations indicated on the drawings. Similar to the existing, fire extinguisher cabinets will not be needed.

12) The Contractor should replace the EMD Generators flooring and install new flooring for the new switchgear room using the Stonhard waterproofing mortar system which includes the primer with Stonclad GS—a ¼" troweled mortar system—providing enhanced impact resistance and a smooth, uniform finish that eliminates surface imperfections. Floors should be repaired and leveled as needed to receive the new flooring.

FIRE SUPPRESSION AND FIRE ALARM

1) Modify the existing Simplex fire alarm system and install new notification and initiation devices in accordance with the project codes and VA TIL.

2) Provide extension of the existing wet-pipe system for the main switchgear room including drip pans below sprinkler piping and head guards. Piping will be located in equipment corridors (not above electrical equipment).

FIRE SUPPRESSION SYSTEM

1) The existing fire suppression system will be modified based upon the project scope of work. The existing wet pipe system will be modified to provide code compliant protection of the existing project scope areas and will be extended to provide protection in the new switchgear room addition.

2) The required fire flows and pressures for buildings provided with automatic sprinkler protection shall comply with NFPA 13 and other applicable NFPA standards. A minimum hose stream allowance for total combined inside and outside firefighting to be provided to comply with NFPA 13.

3) The local responding fire department will provide the necessary flow and pressure for manual firefighting operations.

VA occupied buildings are required to have sprinkler protection. A wet pipe automatic sprinkler system in accordance with NFPA 13, except as indicated in the VA Fire Protection Design Manual, will be provided to protect all areas of the building. Sprinkler protection shall be provided in all spaces including, but not limited to, elevator machine rooms, walk-in freezers and cold rooms, computer rooms, telephone switch rooms, radiology and MRI suites, loading docks, electrical rooms, plumbing or utility closets, audiometric booths, paint spray booths, dry type lint collectors, dust collectors, and generator rooms. Sprinklers are not required where specifically exempted by NFPA 13 and the VA Fire Protection Design Manual.

A flow switch, isolation valve, tamper switch, and pressure gage shall be provided for each zone. System status will be annunciated on the fire alarm control panel with signaling to the fire alarm reporting system. Drainpipes for each sprinkler riser and test connection shall be routed to the building exterior to facilitate testing. Drains shall not terminate at service sinks.

Drain piping shall be 2-inch minimum to accommodate discharge from full flow tests at maximum system pressure.

Sprinkler systems shall be hydraulically calculated by any design approach allowed by NFPA 13, except that the Special Design Approach shall not be used in health care. Pipe schedule systems may be used for extension of existing pipe schedule systems where the water supply is adequate. A safety factor of 10% for each sprinkler demand including required hose streams shall be included. Sprinkler densities shall comply with NFPA 13 and the VAFPDM except in rooms containing moveable/mobile shelving (high density storage) where the density shall be Ordinary Hazard (Group 2).

Quick response sprinkler shall be installed in all areas, except where specifically prohibited or noted elsewhere in the VA Fire Protection Design Manual. Sprinklers shall be Factory Mutual (FM) approved as quick response except as identified below:

(i) Concealed sprinklers that are UL listed quick response and FM approved standard response are permitted in clean rooms provided that the rooms are not designed under negative pressure.

(ii) Concealed sprinklers that are UL Listed quick response and FM approved standard response may be used with the approval of the VHA Central Office Fire Protection Engineer.

(iii) FM approved standard response sprinklers shall be permitted where quick response sprinklers are prohibited.

FIRE ALARM SYSTEM

The existing fire alarm system will be modified for the project scope of work. New manual pull stations will be provided near the exits in the new switchgear room. New alarm devices will be provided throughout the project scope area to comply with NFPA 72 and the VA Fire Protection Design Manual.

General Evacuation

1) Provide audible notification appliances to be heard in all locations throughout the project scope area.

Provide visible notification appliances in all publicly accessible areas of the building such as corridors, auditoriums, cafeterias, open assembly rooms ≥750 SF, canteens, retail stores, etc. Flash rate shall not exceed one flash per second for visible appliances. Strobes that operate on adjacent zones on each floor shall be synchronized with one another as required by NFPA 72. Visible notification appliances are not required in the following spaces which are not considered to be public accessible:

(i) Individual office spaces unless the space is known to have a hearing-impaired person stationed there

(ii) Closets (janitors’ clothes, etc.)

(iii) Utility shafts

(iv) Crawl spaces

(v) Normally unoccupied rooms ≤100 SF

(vi) Normally unoccupied storage spaces where no regular activities take place other than placement and retrieval of storage

(vii) Stairway enclosures and elevators

(viii) Patient exam/treatment rooms F. Special Requirements

1) Where smoke detectors are required, they shall be photoelectric type only. Duct detectors are to be installed only where required by NFPA 101 or NFPA 90A.

Where a duct smoke detector is located above a ceiling or in a difficult to reach location, provide a remote indicating lamp and test key switch on nearby wall at 7-feet AFF to facilitate testing.

G. Carbon Monoxide Detection

1) Carbon monoxide detection shall be provided as required by NFPA 101.

PLUMBING

1) Remove all the existing restroom plumbing fixtures and associated appurtenances including water closet, lavatory, shower, and emergency shower.

2) Remove existing roof drains.

3) Remove existing water heater and associated appurtenances.

4) All storm drain, domestic water, sanitary and vent piping shall be removed back to mains and capped.

5) Remove existing eye wash, salvage for re-installation. Provide portable eye wash during construction.

6) Provide temporary plumbing to serve restrooms fixtures in construction trailer.

Contractor to verify route temporary piping and connections to plumbing mains.

7) Provide plumbing fixtures and associated appurtenances including water closet, lavatory, shower in the new second floor restroom.

8) Re-install emergency eye wash in motor pool room.

9) Connect new plumbing piping from mains to new fixtures. Provide appropriate isolation valves and wheel stops at all fixtures.

10) Provide a new 20-gallon electric water heater to serve new lavatory, shower, and emergency shower.

11) Provide new roof drains and storm drainage piping for the motor pool building area. Connect new piping to existing.

12) Provide downspout boots at new downspout locations on the new electrical switchgear addition. Connect new piping to below grade site drainage system.

MECHANICAL

1) Demolish the two (2) existing 4160-volt generators and their appurtenances and replace them with two new (2) 2.8-MW Tier 4F generators, including the exhaust systems, fuel oil systems, generator cooling systems and compressed air system. The contractor shall be responsible for loading these generators up from the warehouse/manufacture where they are stored/being worked on and transporting them to the job site.

2) Two (2) new generators and all their appurtenances will be provided, including a new generator flue stack for each genset. Each flue stack will be comprised, but not limited to 26” ⌀ black steel with 3” calcium silicate insulation with canvas jacket, a diesel particulate filter (DPF), a mixing duct, a selective catalytic reduction (SCR) system, expansion joints. Two (2) new aqueous urea tank systems will be provided to mitigate NOx levels of the generator exhaust to comply with TIER 4 Requirements.

3) Demolish the existing heating and ventilating unit, HV-2 and ventilating unit HV-3 serving the generator room and its appurtenances including the ductwork system and steam and condensate return piping. The existing intake louver associated with the heating and ventilating units, will remain and be reused for the new combustion and ventilation air systems. The heating and ventilating unit, HV-1 serving the Central Plant and Switch Gear Room and its appurtenances, including the ductwork and chilled water coil/piping systems will remain.

4) The existing unit heaters and their appurtenances serving the Generator Room, including the steam and condensate return piping will be demolished. New increased capacity steam unit heaters will be provided to accommodate the combustion air intake airflow amounts for the new generator operation requirements.

5) Provide a new combination combustion / ventilation supply and cooling exhaust air systems for the Generator Room to accommodate both on-and-off times, as well as individual generator operation.

6) The existing steam heaters in the generators room shall be demolished.

7) A large fan is located on a mezzanine level above the generator room. This fan shall be replaced as part of this project in order to provide the proper level of cooling to the generator room.

4) The Generators must meet Tier 4 exhaust requirements, thus a Tier 4 exhaust system is included in the project. The system included a Selective Catalyst Reduction Unit (SCR) and a Diesel Particulate Filter (DPF). The existing catwalk will be expanded/reconfigured to provide access to the new Tier-4 exhaust and HVAC combustion/ventilation equipment.

5) The existing 3-inch high-pressure steam and 1-1/2” pumped condensate serving building 16, currently drops down into an existing pit in the Generator Room and then exits building 101 underground in a conduit that runs over to building 16.

The steam and condensate lines will be removed within the generator room, pit and 5 feet beyond the footprint of the new Motor Pool building foundation.

6) There two (2) existing duplex condensate pump and receivers in the Generator Room. The one on the plan north wall serves the existing cooling tower basin heater, which are being demolished. Thus, the steam and condensate piping and the condensate pump will be demolished. The condensate receiver tank and duplex pump on the plan south wall will remain as is to return condensate from the steam unit heaters back to the boiler plant.

7) The exhaust fans will be Greenheck tube axial type, model # AX with a 50,500 CFM capacity per fan and a total of two (2) fans. Each fan will be provided with and controlled by a VFD via the Engineering Control Center (ECC).

8). The (2) supply fans will be Greenheck tube axial type, model # AX with a 25,000 CFM capacity per fan and a total of four (4) fans. Each fan will be provided with and controlled by a VFD via the ECC.

9) The (2) generator exhaust fans, (4) supply fans and their associated dampers will connect into the controls for the engine generators.

10) Two new 330-gallon day tanks, with integral transfer pumps, shall be installed for each generator. Day tanks shall be reconnected to existing fuel oil piping leading back to the existing 30,000-gallon underground fuel tank. Additionally, a new fuel oil maintenance and cleaning system will be provided and located in the Generator Room. The fuel oil maintenance system will be piped to the existing fuel oil piping just inside the building. Control valves will control the operation of the fuel oil maintenance skid.

11) A new direct current battery start package will be provided to start the generator engine.

12) All new equipment requiring automated controls will be integrated with the existing nearby boiler room ECC and local controller point capacity and wiring extended as required to accommodate the new scope.

13) Inspect, test, and polish the fuel for Underground storage Tank 30,000 gallons that serves the EMD in accordance with NFPA and manufacturer recommendations.

ELECTRICAL

A. The following systems will be modified to suit the electrical demands of the renovation:

1) Electrical Distribution (4160/2400V, 3PH, 4W) (480/277V, 3PH, 4W) and (208/120V, 3PH, 4W)

2) Fire Alarm System

3) Communications and IT Systems

4) MCC-3A shall be demolished as part of this project.

5) contractor shall be responsible for loading this equipment up from the warehouse where they are stored and transporting them to the job site. All eight sections of switchgear shall be delivered to the site: (1) Master/Bus PT section, (3) generator input circuit breaker sections, (4) stacked distribution circuit breakers sections.

6) The VA has requested that H.O. Penn, who is currently responsible for storing the equipment, prepare and re-commission the generators and paralleling switchgear for transit and certify the condition of the equipment prior to delivery.

7) After all of the demolition of the equipment, piping, and gear in Generator Room GK04, the new generators shall be set on the existing/extended concrete pads.

8) New generator system status panels shall be installed in three locations within the hospital: Switchgear Room GM04, the boiler plant main office, and the VA police office. Each panel shall be tied back to generator control panel via fiber optic cable pair.

9) A new load bank shall be provided for the generators. Load bank will be set on structural piers across the driveway from the Switchgear Room GM04. A concrete encased duct bank shall be constructed to route conduit from switchgear room to load bank. Existing tree shall be removed, and hill shall be prepared as required for installation of load bank.

10) A generator tap box shall be installed adjacent to the load bank. The tap box will be connected to one of the generator input circuit breakers in the paralleling switchgear.

11) The ASCO paralleling switchgear shall be installed in the newly built switchgear room adjacent to the existing Motor Pool Building. Feeders shall be installed between each generator circuit breakers and the incoming generator breakers within the paralleling switchgear. After the generators and paralleling switchgear are fully installed and tested, new 5” conduits shall be run from the existing medium voltage ConEd utility switchgear to the new utility input circuit breakers within the paralleling gear. The four utility services can they be cut over to the paralleling switchgear in stages, utilizing the existing sync bus to keep all of the loads online.

12) The paralleling gear will need to be modified as required by one of the pre approved subcontractor to support the new program, including adding interlocks, updating the processor and programming, etc. Potential transformers shall be added to each of the utility circuit breakers. This will be done by adding an ASCO “top hat” mounted to the top of the gear above each of the four utility breakers.

13) Contractor shall provide and install a new 16” high pullbox on top of each of the four “top hats.” The feeders from the medium voltage switchgear shall terminate to the side of these pullboxes. The cables shall then be routed down into the top of the new ASCO PT ‘top hats”.

14) Controls will stage the utility feeds into the new switchgear as required so that the 50-kAIC withstand rating of the paralleling switchgear bus is sufficient.

15) The controls shall also be programmed to run load bank testing, to send signals to the existing 480-demand response program. This program requires the generators to run upon notification from ConEd to remove the hospital from its electric grid. The program generates credits back to the VA. See Drawing E-602 for further information on this sequencing.

16) ASCO remote terminal I/O units shall be provided in existing Switchgear Room GK05 and within the rooms that house the existing 480-volt ATS’s that run the emergency system. Cabling or fiber shall be run from these I/O units back to the master control section of the paralleling gear. This system will handle the communication to the existing emergency 480-volt emergency system.

17) The bus duct currently servicing MCC-3A shall be cut back to a convenient overhead point and new cable tap box shall be installed at the end. From this tap box, feeders in conduit shall be extended down to a new 800-amp, 480-volt Panelboard E3A that will be installed in the previous location of MCC-3A.