This document is a comprehensive submittal package for a power control system project at the VA Manhattan Medical Center. The project involves an ASCO 7000 Series Medium Voltage Power Control System designed to automatically start, synchronize, and parallel three diesel engine generator sets (two new 2800 kW generators and one existing 2800 kW generator) at 4,160VAC. The system includes integrated switchgear with multiple sections: a master/bus PT section, three generator sections, four distribution sections, and standalone items like a 48VDC station battery system and remote terminal units.

Key technical specifications include a NEMA 1 enclosure, seismic rating, front and rear access design, and comprehensive control and monitoring features. The system will have redundant programmable logic controllers, synchronizing controls, protective relays, meters, and status indication panels. The submittal is marked "Record Only" and includes detailed documentation such as system notes, warranty information, bill of materials, compliance review, and network architecture diagrams. The project is identified by job number 12654P and involves electrical system upgrades at the VA Manhattan facility in New York.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Power Systems

15 Middle Avenue • Holtsville, NY 11742 • (631) 654-4436 • FAX (631) 654-4480

Document Transmittal To: J. Kokolakis Contracting Inc. Date: March 1, 2017 1500 Ocean Ave Project: VA Manhattan Bohemia, NY 11716 Project No: w9277

Attn : Mike Lupo Documents are submitted for: Initial Submittal For Approval

Initial Submittal For Information Re-submittal For Approval

Re-submittal For Information Other:

Number of copies submitted: (1) Electronic Document No. Description

Please find enclosed submittal package for:

VA Manhattan Medical Center – ASCO Paralleling Switchboard

This submittal is for Record only to incorporate all updates, including the switchgear depth being 100” and the updated Sequence of Operations.

Submitted By: Julia Walsh Project Manager

(631) 866-2376

CRITICAL NOTE: ALL descriptions within Attachment #2 are based on the prior comments of a separate VA facility.

This equipment was not used at the prior facility, and all descriptions of operations included within Attachment #2 must be modified to perform as required for this location, in accordance with the emergency generator expected operational scheme

POWER CONTROL SYSTEM SUBMITTAL

VAMC Electrical Upgrade New York, NY

FOR

VAMC Electrical Upgrade

ASCO PROJECT REFERENCE NO. 12654

PURCHASE ORDER NO. ELI HV2 JDW 528451-0

800-800-ASCO | customercare@asco.com | www.EmersonNetworkPower.com/asco 50 Hanover Road, Florham Park, NJ 07932

RECORD ONLY

mailto:customercare@asco.com?subject=ASCO%20Product%20Inquiry http://www.emersonnetworkpower.com/asco

VAMC ELECTRICAL UPGRADE Record Only

JOB #12654

www.asco.com

SUBMITTAL DATA

FOR

VAMC ELECTRICAL UPGRADE

NEW YORK, NY

Record Submittal Only

EQUIPMENT: SPECIFICATION SECTION 262313

PARALLELING SWITCHGEAR & DRAWING

E-607

PURCHASER: H.O. PENN MACHINERY COMPANY INC

PURCHASE ORDER NO.: ELI HV2 JDW 528451-0

VENDOR: ASCO Power Technologies

50 HANOVER ROAD

FLORHAM PARK, NEW JERSEY 07932

SALES ORDER NO.: 12654

FIELD SALES ENGINEER: ANDREW CARRENO

DATE: FEBURARY 17, 2017

Job# 12654 VAMC New York

GENERAL SYSTEM NOTES

1. The emergency paralleling system will be furnished in an Integrated Switchgear line up per Medium Voltage

UL, ASCO File No. E142645 manufactured in accordance with applicable ANSI, NEMA and IEEE Standards and utilizes insulated copper bus bars. Switchgear design will be freestanding, sheet metal enclosed, and floor supported, with front and rear access. All doors will be formed type, minimum of 11 gauge steel and will have sufficient hinges to support the door and components for an absolute minimum deflection when opening or closing. Doors swing open more than 90 degrees for safety and easy of accessibility and will have lockable handles. All panel covers are formed type, and secured with screws as necessary. Refer to project specific drawings for shipping splits.

2. All locks will have identical keying and can be operated from a single key. Openings will be included for air circulation. Finish will be ANSI 61, switchboard light gray, baked powder, over a fully cleaned, degreased, rust inhibiting surface.

3. Internal control wiring will be rated at 600 volts and made with SIS type for Medium Voltage. All wires will be numbered every eight inches as well as at both ends.

4. All electric and electronic controls associated with engine generator sets such as voltage regulator, governor, etc. shall be provided and mounted at the engine generator sets by others.

5. Load banks are required to set up load sharing between generators. They may also be required for final system sequence testing if site load is not available. Load banks must be both reactive and resistive. ASCO will not be responsible for providing load banks, cables for connecting load banks or items associated with load banks as required for load bank testing. This shall be responsibility of others.

6. Cable termination boots/taping and stress cones are to be provided by the installing contractor and are not included in ASCO’s scope of work.

7. Field service support hours are based on a normal working week.

8. All generators should have the same pitch for stable operation and to minimize circulating currents between running machines, false tripping of generator circuit breakers, temperature increase in the neural bus and neutral conductors caused by harmonics, etc. It is responsibility of others to determine if the pitch of all engines is same or different and to provide any resolution to the issues caused by paralleling different pitch engine generators. Synchronizing controls cannot compensate for different pitch engine generator sets.

9. ATS Power Managers in ASCO supplied equipment and third party meters installed in switchgear supplied by others will interface with ASCO PowerQuest. The following will be trended Ia, Ib, Ic Vavg, kW, KVA, KVAR, PF, and Frequency, utilizing Modbus. Power Quality and Wave Form capture capability are not included.

10. ASCO’s scope of work does not include a short circuit and coordination study or subsequent relay calibration and settings.

11. ASCO scope of supply does not include onsite assembly/set up of ASCO supplied station battery system.

12. If compliance with NEC article 700.10 is required, information must be provided as to which breakers are designated as emergency, legally required or optional. Any changes will require ASCO to amend this proposal.

13. The customer will be responsible for providing 120VAC input for UPS in ASCO switchgear.

ASCO 7000 SERIES MEDIUM VOLTAGE POWER CONTROL SYSTEM

System Information:

System Voltage

Frequency, Hz Phase Enclosure type Switchgear

Construction Paint

4160VAC 60 3P, 3W

NEMA1

ANSI 37.20.2 ANSI 61

Synchronizing: Quantity kW Operation Mode

Generators 2 2800 Standby Emergency

Open Transition Existing Generator 1 2800

Breaker Type/Vendor

Main Bus, A Copper Bus

System Rating

MVA/KAIC

Bus Bracing, kA (RMS)

Lug Type Ground

Bus, Size, %

VR, Square D

Insulated Silver Plated Copper 500/63KA 63 Compression 25

Field Service, Warranty and Shipment:

Start -up Assistance

Training Hrs

Warranty Months (Commences from Date of Shipment)

Factory Witness Test (Persons, Location)

Approval Drawings, Weeks

Shipment, Weeks* FOB

Included 8 18

Not Included

2-4 22-24 Origin

*NOTE: SHIPMENT LEAD TIME IS CONTINGENT UPON SIGNED RELEASE OF SUBMITTAL.

The Generator Paralleling Switchgear line-up will consist of the following sections:

(Qty 1) Master Control Section/Bus PT/ Main Bus Surge Arrestor Section (Qty 3) Generator Control and Circuit Breakers Sections (Qty 1) Distribution/Load Bank Section (Qty 3) Two High Feeder Circuit Breakser Section

Limited Warranty

300, 4000, 7000 Series Power Control Systems

This Warranty is given ONLY to purchasers who buy for commercial or industrial use in the ordinary course of each purchaser's business.

General:

ASCO Power Technologies, LP products and systems are in our opinion the finest available. We take pride in our products and are pleased that you have chosen them. Under certain circumstances we offer with our products the following Eighteen Month Limited Warranty Against Defects in Material and Workmanship.

Please read your Warranty carefully. This Warranty sets forth our responsibilities in the unlikely event of defect and tells you how to obtain performance under this Warranty.

EIGHTEEN MONTH LIMITED WARRANTY

AGAINST DEFECTS IN MATERIAL AND WORKMANSHIP

ASCO PRODUCTS COVERED:

ASCO 300, 4000, 7000 Series Commercial Power Control Systems

Terms of Warranty:

The following Limited Warranty is conditioned upon User’s compliance with the following:

1. The ASCO Power Control System is installed in accordance with ASCO specifications and state and local codes and standards by an electrician licensed in the state of installation.

2. The ASCO Power Control System is commissioned by ASCO Services Inc.

3. The ASCO Power Control System is maintained in accordance with ASCO instructions and used under normal conditions for the purposes intended by ASCO.

As provided herein, the ASCO product is warranted to be free of defects in material and workmanship for a period of eighteen (18) months from the final commission date, provided that commissioning occurs within six (6) months of the ASCO shipping date and the product has been stored in a suitable environment prior to installation. The final commission date will be determined only from the completed inspection and start-up report provided by ASCO Services to User. The product shipment date will be determined only from the ASCO bill of lading. If any part or portion of the ASCO product fails to conform to the Warranty within the Warranty period, ASCO, at its option, will furnish new or factory remanufactured products for repair or replacement of that portion or part.

All warranty related repairs, replacements or adjustments must be made by ASCO Services Inc. or its duly authorized representative.

Warranty Extends to First Purchaser for Use, Non-transferable:

This Warranty is extended to the first person, firm, association or corporation for whom the ASCO product specified herein is originally installed for use (the "User") in the fifty United States or Canada. This Warranty is not transferable or assignable without the prior written permission of ASCO.

Assignment of Warranties:

ASCO assigns to User any warranties which are made by manufacturers and suppliers of components of, or accessories to, the ASCO product and which are assignable, but ASCO makes NO REPRESENTATIONS as to the effectiveness or extent of such warranties, assumes NO RESPONSIBILITY for any matters which may be warranted by such manufacturers or suppliers and extends no coverage under this Warranty to such components or accessories.

Drawings, Descriptions:

ASCO warrants for the period and on the terms of the Warranty set forth herein that the ASCO product will conform to the descriptions and sequence of operations contained in the certified submittal package and drawings as accepted, agreed to and released by the User or their duly charged representative, if any, applicable thereto, to ASCO's final invoices, and to applicable ASCO product brochures and manuals current as of the date of product shipment (“Descriptions”). ASCO does not control the use of any ASCO product. Accordingly, it is understood that the Descriptions are NOT WARRANTIES OF PERFORMANCE and NOT

WARRANTIES OF FITNESS FOR A PARTICULAR PURPOSE.

Warranty Claims Procedure:

Within a reasonable time, but in no case to exceed thirty (30) days, after User's discovery of a defect, User shall contact ascopowerwarranty@emerson.com. Subject to the limitations specified herein, an ASCO Services field service representative will repair the non-conforming ASCO product warranted hereunder, without charge for parts, labor, or travel expenses. Warranty coverage will apply only after ASCO's inspection discloses the claimed defect and shows no signs of treatment or use that would void the coverage of this Warranty. All defective products and component parts replaced under this warranty become the property of ASCO.

Warranty Performance of Component Manufacturers:

It is ASCO's practice, consistent with its desire to remedy Warranty defects in the most prompt and effective manner possible, to cooperate with and utilize the services of component manufacturers and their authorized representatives in the performance of work to correct defects in the product components. Accordingly, ASCO may utilize third parties in the performance of Warranty work, including repair or replacement hereunder, where, in ASCO's opinion, such work can be performed in less time, with less expense, or in closer proximity to the ASCO product.

Items Not Covered By Warranty:

THIS WARRANTY DOES NOT COVER DAMAGE OR DEFECT CAUSED BY misuse, improper application, wrong or inadequate electrical current or connection, negligence, inappropriate on site operating conditions, repair by non-ASCO designated personnel, accident in transit, tampering, alterations, a change in location or operating use, exposure to the elements, water, or other corrosive liquids or gases, Acts of God, theft or installation contrary to ASCO's recommendations or specifications, or in any event if the ASCO serial number has been altered, defaced, or removed.

THIS WARRANTY DOES NOT COVER shipping costs, installation costs, external circuit breaker resetting or maintenance or service items and further, except as may be provided herein, does NOT include labor costs or transportation charges arising from the replacement of the ASCO product or any part thereof or charges to remove or reinstall same at any premises of User.

REPAIR OR REPLACEMENT OF A DEFECTIVE PRODUCT OR PART THEREOF DOES NOT EXTEND THE ORIGINAL

WARRANTY PERIOD.

THE PRODUCTS LISTED IN THIS WARRANTY ARE NOT FOR USE IN THE CONTROL AREA OR ANY REACTOR CONNECTED OR SAFETY APPLICATIONS OR WITHIN THE CONTAINMENT AREA OF A NUCLEAR FACILITY OR FOR

INTEGRATION INTO MEDICAL DEVICES.

Limitations:

THIS WARRANTY IS IN LIEU OF AND EXCLUDES ANY OTHER WARRANTIES, EXPRESS OR IMPLIED, INCLUDING

MERCHANTABILITY AND FITNESS FOR A PARTICULAR PURPOSE.

USER'S SOLE AND EXCLUSIVE REMEDY IS REPAIR OR REPLACEMENT OF THE ASCO PRODUCT AS SET FORTH HEREIN.

IF USER'S REMEDY IS DEEMED TO FAIL OF ITS ESSENTIAL PURPOSE BY A COURT OF COMPETENT JURISDICTION, ASCO'S RESPONSIBILITY FOR PROPERTY LOSS OR DAMAGE SHALL NOT EXCEED THE NET PRODUCT PURCHASE

PRICE.

IN NO EVENT SHALL ASCO ASSUME ANY LIABILITY FOR INDIRECT, SPECIAL, INCIDENTAL, CONSEQUENTIAL OR EXEMPLARY DAMAGES OF ANY KIND WHATSOEVER, INCLUDING WITHOUT LIMITATION LOST PROFITS, BUSINESS INTERRUPTION OR LOSS OF DATA, WHETHER ANY CLAIM IS BASED UPON THEORIES OF CONTRACT, NEGLIGENCE, STRICT LIABILITY, TORT, OR OTHERWISE.

Miscellaneous:

NO SALESPERSON, EMPLOYEE OR AGENT OF ASCO IS AUTHORIZED TO ADD TO OR VARY THE TERMS OF THIS WARRANTY. Warranty terms may be modified, if at all, only in writing signed by an ASCO officer.

ASCO obligations under this Warranty are conditioned upon ASCO timely receipt of full payment of the product purchase price and any other amounts due. ASCO reserves the right to supplement or change the terms of this Warranty in any subsequent warranty offering to User or others.

In the event that any provision of this Warranty should be or becomes invalid and/or unenforceable during the warranty period, the remaining terms and provisions shall continue in full force and effect.

This Warranty shall be governed by, and construed under, the laws of the State of New Jersey, without reference to the conflict of laws principles thereof.

This Warranty represents the entire agreement between ASCO and User with respect to the subject matter herein and supersedes all prior or contemporaneous oral or written communications, representations, understandings or agreements relating to this subject.

BILL OF MATERIAL

ASCO 7000 Series Medium Voltage Power Control System designed to automatically start, synchronize and parallel (2) New 2800 kW and (1) Existing 2800 kW diesel engine generator sets upon initiation of an automatic sequence. System is rated at 4160VAC, 60Hz, 3-phase, 3-wire and will consist of the following:

SECTION 1 Master/Bus PT to include the following:

Dimensions 36”W x 95”H x 99.8”D – NEMA 1 Enclosure

24 inch LCD touch screen* – (1920 x1080 resolution) Operator Interface Panel – Strongarm PowerQuest Software – ASCO Industrial Box PC, OS: Windows Embedded 7, 4GB RAM, HD, 180GB SATA SSD – Wonderware Top Server License – (For Communication to BMS Modbus Protocol) Omni Server License – (For ATS Communication)

Redundant Programmable Logic Controller with CPU, Power Supply, Ethernet communication card & single Input/output – GE Fanuc Type RX3i

Synchronizing check relay (Device 25) – Basler ES-25

Bus over/under frequency relay (Device 81O/U) – Crompton

Under/over voltage relay (Device 27/59) – Crompton

Power Manager Xp with Digital Display – Series 5200 – ASCO

(Qty-2) Voltmeter, 1% accuracy, 4½" – Yokogawa Type AB-40

(Qty-2) Frequency meter, 1% accuracy, 4½" – Yokogawa Type AB-40

Ammeter, 1% accuracy, 4½" – Yokogawa Type AB-40

Wattmeter, 1% accuracy, 4½" – Yokogawa Type AB-40

Ammeter 4 position Line-Line selector switch – Shallco

Voltmeter 4 position Line-Line selector switch – Shallco

Synchroscope, SLOW-FAST, 4½" – Yokogawa Type AB-40

Synchroscope 3 Position Plant Selector Switch – Shallco

Load Priority, Bus Optimization and Load Demand control logic

(Qty 2) 24 point LED type system status indicating panels with push-button lamp test – Saco

FUNCTION MODE COLOR VISUAL VISUAL/AUDIBLE

GEN 1 Running Status Green X

GEN 1 Online Status Red X

GEN 1 Locked Out Alarm Red X

GEN 2 Running Status Green X

GEN 2 Online Status Red X

GEN 2 Locked Out Alarm Red X

GEN 3 Running Status Green X

GEN 3 Online Status Red X

GEN 3 Locked Out Alarm Red X

System Test Status Amber X

Emergency Mode Status Amber X

Priority 2 Load Shed Active Status Amber X

Priority 2 Load Shed Bypassed Status Amber X

Priority 3 Load Shed Active Status Amber X

Priority 3 Load Shed Bypassed Status Amber X

I/O Comm. Failure Alarm Red X

System PLC Diagnostic Fault Status Amber X

Load Demand Mode Active Status Amber X

Load Demand Start TD Active Status Amber X

Load Demand Stop TD Active Status Amber X

Bus Under Frequency Alarm Red X

Bus Over Frequency Alarm Red X

Bus Under Voltage Alarm Red X

Bus Over Voltage Alarm Red X

Bus Optimization Mode Active Status Amber X

Next Load Exceeds Headroom Status Amber X

Bus Loaded To Capacity Status Amber X

Bus Overload Alarm Red X

Station Battery High Voltage Alarm Red X

Station Battery Low Voltage Alarm Red X

Station Battery Charger Failure Alarm Red X

ATS Control Fuse Blown Alarm Red X

PLC-1 Stopped Alarm Red X

PLC-2 Stopped Alarm Red X

Control Voltage Failure Alarm Red X

DC Converter Failure Alarm Red X

Load Bank CB Enable Status Green X

ASCO Master Control Station to include the following:

Alarm Silence Reset push-button Bus Alarm Reset push-button Priority Load Shed Bypass/Reset push-button (For Priority 2, 3) Manual Parallel push button

(Qty 3) Summing Current transformers, 5+5+5:5A – GE ITI Model 20X

Best DC source selector system

DC – DC Converter (48 VDC to 24VDC) – Vicor

Strip Heater, 250W – Watlow

Thermostat, Range 40º to 80º F (5º to 25º C) – Honeywell

System Test Switch – Located behind locked doors.

Miscellaneous components: (terminal blocks, control wiring, control relays, wire markers, nameplates, etc.)

Alarm horn with silencing pushbutton and circuitry to allow subsequent malfunctions to resound alarm – Mallory

Laminated mimic bus – White Face Red Core, Lamicoid attached with mechanical fasteners

The following parts are for Bus PT/Main Bus Surge Arrestor included in Master Section

(Qty-2) Bus Potential transformer assembly, open-delta, 4200:120V – GE ITI Model PTG3

5kV Intermediate Class Lightning Arresters (set of 3) – GE Tranquell

Miscellaneous components: (terminal blocks, control wiring, control relays, wire markers, nameplates, etc.)

Main bus, 2000A, fully insulated silver-plated copper, 3-phase, 3-wire with 25% ground

SECTION 2 Generator 1 to include the following:

Dimensions 36”W x 95”H x 99.8”D – NEMA 1 Enclosure

Generator circuit breaker PSG1 (Square D, type VR), 1200A, 500MVA/63KAIC, electrically operated, drawout, 48VDC charge and close, 48VDC shunt trip, 6a & 6b auxiliary contacts, mechanically operated cell-MOC, truck operated cell-TOC (63kA)

Single Programmable Logic Controller with CPU, Power Supply, Ethernet communication card & single Input/output – GE Fanuc Type RX3i

Generator Multifunctional Protective Relay – SEL 351SL

Lockout relay (Device 86) – Shallco

Circuit breaker control switch, OPEN-TRIP-CLOSE with LED Indicating Lights – Shallco

Voltmeter, 1% accuracy, 4½" – Yokogawa Type AB-40

Frequency meter, 1% accuracy, 4½" – Yokogawa Type AB-40

Ammeter, 1% accuracy, 4½" – Yokogawa Type AB-40

Wattmeter, 1% accuracy, 4½" – Yokogawa Type AB-40

Ammeter 4 position Line-Line selector switch – Shallco

Voltmeter 4 position Line-Line selector switch – Shallco

(Qty 2) 24 point LED type system status indicating panels with push-button lamp test – SACO

FUNCTION MODE COLOR VISUAL VISUAL/AUDIBLE

Parallel CB Open Status Green X

Parallel CB Closed Alarm Red X

Parallel CB Lockout Alarm Red X

Parallel CB Fail To Close Alarm Red X

Failure to Synch Alarm Red X

GEN Output CB Open Status Green X

GEN Output CB Closed Alarm Red X

Parallel CB Not Connected Alarm Red X

Parallel CB Fail To Open Alarm Red X

Over Crank Shutdown Shutdown Red X

Over Speed Shutdown Shutdown Red X

Reverse Power Shutdown Shutdown Red X

Low Oil Pressure Shutdown Shutdown Red X

High Water Temp Shutdown Shutdown Red X

Auto Start Status Green X

ECS Reset Required Alarm Red X

Engine Control Not in Auto Alarm Red X

Low Oil Pressure Alarm Pre-Alarm Amber X

High Water Temp Alarm Pre-Alarm Amber X

Engine Running Status Green X

PLC Stopped Alarm Red X

Control Voltage Failure Alarm Red X

Controls Not In Auto Alarm Red X

Local/Remote Emergency Stop Alarm Red X

Low Water Level Alarm Pre-Alarm Amber X

Low Water Temp Alarm Pre-Alarm Amber X

PQ In Control Pre-Alarm Amber X

Day Tank Low Fuel Pre-Alarm Amber X

Day Tank High Fuel Pre-Alarm Amber X

Day Tank Rupture Basin Pre-Alarm Amber X

Battery Charger Failure Alarm Red X

High Battery Voltage Pre-Alarm Amber X

Low Battery Voltage Pre-Alarm Amber X

Relay Common Alarm Pre-Alarm Amber X

Relay Common Shutdown Shutdown Red X

48 VDC Trip/Cls Voltage Failure Alarm Red X

GEN Common Shutdown Shutdown Red X

GEN Common Alarm Alarm Red X

DSLC2 Self Test Failed Alarm Red X

ASCO Generator Control Station to include the following:

Alarm Reset push-button Emergency Stop push button (Red colored with mushroom head) – Square D Synchronizing mode selector switch with Permissive, Check, Off and Run positions – Shallco 5-Position Engine-Generator Control Switch with the following positions – Shallco

Automatic, Lockout/Reset, Off/Cool down, Test Off-Line, Test On-Line Voltage/Speed Control (Return-To-Center) selector switches with Lower-Off-Raise positions

Ampere/Voltage Test Switch - ABB FT1

(Qty 3) Current transformers, 600:5A – GE ITI Model 780

(Qty 3) Current transformers, 600:5A– provided for use with SEL 351SL relay – GE ITI Model 780

Potential transformer assembly, open-delta, 4200:120V – GE ITI Model PTG3 (Voltage Range 2400V – 4800V)

DC – DC Converter (48 VDC to 24VDC) – Vicor

Strip Heater, 250W – Watlow

Thermostat, Range 40º to 80º F (5º to 25º C) – Honeywell

Compression lugs, two hole mounting, long barrel, sizes listed with each breaker

Miscellaneous components: (terminal blocks, current shorting blocks, control wiring, control relays, wire markers, nameplates, etc.)

SECTION3 Generator 2 to include the following:

Dimensions 36”W x 95”H x 99.8”D – NEMA 1 Enclosure

Generator circuit breaker PSG2 (Square D, type VR), 1200A, 500MVA/63KAIC, electrically operated, drawout, 48VDC charge and close, 48VDC shunt trip, 6a & 6b auxiliary contacts, mechanically operated cell-MOC, truck operated cell-TOC (63kA)

Versamax Programmable Logic Controller with CPU, Power Supply, Input/output and Ethernet communication card

– GE Fanuc

Digital Synchronizer and Load Control (DSLC-2) – Woodward

Generator Multifunctional Protective Relay – SEL 700G

Lockout relay (Device 86) – Shallco

Circuit breaker control switch, OPEN-TRIP-CLOSE with LED Indicating Lights – Shallco

Voltmeter, 1% accuracy, 4½" – Yokogawa Type AB-40

Frequency meter, 1% accuracy, 4½" – Yokogawa Type AB-40

Ammeter, 1% accuracy, 4½" – Yokogawa Type AB-40

Wattmeter, 1% accuracy, 4½" – Yokogawa Type AB-40

Ammeter 4 position Line-Line selector switch – Shallco

Voltmeter 4 position Line-Line selector switch – Shallco

(Qty 2) 24 point LED type system status indicating panels with push-button lamp test – SACO

FUNCTION MODE COLOR VISUAL VISUAL/AUDIBLE

Parallel CB Open Status Green X

Parallel CB Closed Alarm Red X

Parallel CB Lockout Alarm Red X

Parallel CB Fail To Close Alarm Red X

Failure to Synch Alarm Red X

GEN Output CB Open Status Green X

GEN Output CB Closed Alarm Red X

Parallel CB Not Connected Alarm Red X

Parallel CB Fail To Open Alarm Red X

Over Crank Shutdown Shutdown Red X

Over Speed Shutdown Shutdown Red X

Reverse Power Shutdown Shutdown Red X

Low Oil Pressure Shutdown Shutdown Red X

High Water Temp Shutdown Shutdown Red X

Auto Start Status Green X

ECS Reset Required Alarm Red X

Engine Control Not in Auto Alarm Red X

Low Oil Pressure Alarm Pre-Alarm Amber X

High Water Temp Alarm Pre-Alarm Amber X

Engine Running Status Green X

PLC Stopped Alarm Red X

Control Voltage Failure Alarm Red X

Controls Not In Auto Alarm Red X

Local/Remote Emergency Stop Alarm Red X

Low Water Level Alarm Pre-Alarm Amber X

Low Water Temp Alarm Pre-Alarm Amber X

PQ In Control Pre-Alarm Amber X

Day Tank Low Fuel Pre-Alarm Amber X

Day Tank High Fuel Pre-Alarm Amber X

Day Tank Rupture Basin Pre-Alarm Amber X

Battery Charger Failure Alarm Red X

High Battery Voltage Pre-Alarm Amber X

Low Battery Voltage Pre-Alarm Amber X

Relay Common Alarm Pre-Alarm Amber X

Relay Common Shutdown Shutdown Red X

48 VDC Trip/Cls Voltage Failure Alarm Red X

GEN Common Shutdown Shutdown Red X

GEN Common Alarm Alarm Red X

Emergency Stop push button (Red colored with mushroom head) – Square D Synchronizing mode selector switch with Permissive, Check, Off and Run positions – Shallco 5-Position Engine-Generator Control Switch with the following positions – Shallco

Automatic, Lockout/Reset, Off/Cool down, Test Off-Line, Test On-Line Voltage/Speed Control (Return-To-Center) selector switches with Lower-Off-Raise positions

Ampere/Voltage Test Switch - ABB FT1

(Qty 3) Current transformers for Metering, 600:5A – GE ITI Model 780

(Qty 3) Current transformers, 600:5A, for Percentage differential protective relaying function (87G) – provided foruse with SEL 700G relay – GE ITI Model 785

(Qty 3) Current transformers, 600:5A, for Percentage differential protective relaying function (87G) – provided for use with SEL 700G relay (supplied loose for mounting at the generator) – GE ITI Model 785

Potential transformer assembly, open-delta, 4200:120V – GE ITI Model PTG3 (Voltage Range 2400V – 4800V)

DC – DC Converter (48 VDC to 24VDC) – Vicor

Strip Heater, 250W – Watlow

Thermostat, Range 40º to 80º F (5º to 25º C) – Honeywell

Compression lugs, two hole mounting, long barrel, sizes listed with each breaker

Miscellaneous components: (terminal blocks, current shorting blocks, control wiring, control relays, wire markers, nameplates, etc.)

Main bus, 2000A, fully insulated silver-plated copper, 3-phase, 3-wire with 25% ground

Laminated mimic bus – White Face Red Core, Lamicoid attached with mechanical fasteners

SECTION 4 Generator 3 to include the following:

Dimensions 36”W x 95”H x 99.8”D – NEMA 1 Enclosure

Generator circuit breaker PSG3 (Square D, type VR), 1200A, 500MVA/63KAIC, electrically operated, drawout, 48VDC charge and close, 48VDC shunt trip, 6a & 6b auxiliary contacts, mechanically operated cell-MOC, truck operated cell-TOC (63kA)

Versamax Programmable Logic Controller with CPU, Power Supply, Input/output and Ethernet communication card

– GE Fanuc

Digital Synchronizer and Load Control (DSLC-2) – Woodward

Generator Multifunctional Protective Relay – SEL 700G

Lockout relay (Device 86) – Shallco

Circuit breaker control switch, OPEN-TRIP-CLOSE with LED Indicating Lights – Shallco

Voltmeter, 1% accuracy, 4½" – Yokogawa Type AB-40

Frequency meter, 1% accuracy, 4½" – Yokogawa Type AB-40

Ammeter, 1% accuracy, 4½" – Yokogawa Type AB-40

Wattmeter, 1% accuracy, 4½" – Yokogawa Type AB-40

Ammeter 4 position Line-Line selector switch – Shallco

Voltmeter 4 position Line-Line selector switch – Shallco

(Qty 2) 24 point LED type system status indicating panels with push-button lamp test – SACO

FUNCTION MODE COLOR VISUAL VISUAL/AUDIBLE

Parallel CB Open Status Green X

Parallel CB Closed Alarm Red X

Parallel CB Lockout Alarm Red X

Parallel CB Fail To Close Alarm Red X

Failure to Synch Alarm Red X

GEN Output CB Open Status Green X

GEN Output CB Closed Alarm Red X

Parallel CB Not Connected Alarm Red X

Parallel CB Fail To Open Alarm Red X

Over Crank Shutdown Shutdown Red X

Over Speed Shutdown Shutdown Red X

Reverse Power Shutdown Shutdown Red X

Low Oil Pressure Shutdown Shutdown Red X

High Water Temp Shutdown Shutdown Red X

Auto Start Status Green X

ECS Reset Required Alarm Red X

Engine Control Not in Auto Alarm Red X

Low Oil Pressure Alarm Pre-Alarm Amber X

High Water Temp Alarm Pre-Alarm Amber X

Engine Running Status Green X

PLC Stopped Alarm Red X

Control Voltage Failure Alarm Red X

Controls Not In Auto Alarm Red X

Local/Remote Emergency Stop Alarm Red X

Low Water Level Alarm Pre-Alarm Amber X

Low Water Temp Alarm Pre-Alarm Amber X

PQ In Control Pre-Alarm Amber X

Day Tank Low Fuel Pre-Alarm Amber X

Day Tank High Fuel Pre-Alarm Amber X

Day Tank Rupture Basin Pre-Alarm Amber X

Battery Charger Failure Alarm Red X

High Battery Voltage Pre-Alarm Amber X

Low Battery Voltage Pre-Alarm Amber X

Relay Common Alarm Pre-Alarm Amber X

Relay Common Shutdown Shutdown Red X

48 VDC Trip/Cls Voltage Failure Alarm Red X

GEN Common Shutdown Shutdown Red X

GEN Common Alarm Alarm Red X

Emergency Stop push button (Red colored with mushroom head) – Square D Synchronizing mode selector switch with Permissive, Check, Off and Run positions – Shallco 5-Position Engine-Generator Control Switch with the following positions – Shallco

Automatic, Lockout/Reset, Off/Cool down, Test Off-Line, Test On-Line Voltage/Speed Control (Return-To-Center) selector switches with Lower-Off-Raise positions

Ampere/Voltage Test Switch - ABB FT1

(Qty 3) Current transformers for Metering, 600:5A – GE ITI Model 780

(Qty 3) Current transformers, 600:5A, for Percentage differential protective relaying function (87G) – provided foruse with SEL 700G relay – GE ITI Model 785

(Qty 3) Current transformers, 600:5A, for Percentage differential protective relaying function (87G) – provided for use with SEL 700G relay (supplied loose for mounting at the generator) – GE ITI Model 785

Potential transformer assembly, open-delta, 4200:120V – GE ITI Model PTG3 (Voltage Range 2400V – 4800V)

DC – DC Converter (48 VDC to 24VDC) – Vicor

Strip Heater, 250W – Watlow

Thermostat, Range 40º to 80º F (5º to 25º C) – Honeywell

Compression lugs, two hole mounting, long barrel, sizes listed with each breaker

Miscellaneous components: (terminal blocks, current shorting blocks, control wiring, control relays, wire markers, nameplates, etc.)

SECTION 5 Distribution Circuit Breakers to include the following:

Dimensions 36”W x 95”H x 99.8”D – NEMA 1 Enclosure

Distribution circuit breaker PS-1 to Load Bus J-1 (Square D, type VR), 1200A, 500MVA/63KAIC, electrically operated, drawout, 48VDC charge and close, 48VDC shunt trip, 6a & 6b auxiliary contacts, mechanically operated cell-MOC, truck operated cell-TOC (63kA)

Distribution circuit breaker PS-2 to Load Bus J-2 (Square D, type VR), 1200A, 500MVA/63KAIC, electrically operated, drawout, 48VDC charge and close, 48VDC shunt trip, 6a & 6b auxiliary contacts, mechanically operated cell-MOC, truck operated cell-TOC (63kA)

(Qty 2) Feeder Protective Relays – SEL 751A

(Qty 2) Lockout relays (Device 86), TRIP-RESET indication – Shallco

(Qty 2) Circuit breaker control switches, OPEN-TRIP-CLOSE with LED Indicating Lights – Shallco

(Qty 6) Current transformers, 600:5A – GE ITI Model 780

(Qty 2) Zero Sequence Current transformers, 50:5A – GE ITI Model 143

(Qty 2) Test Switch – ABB FT-1 Flexitest

Compression lugs, two hole mounting, long barrel, sizes listed with each breaker

Miscellaneous components: (terminal blocks, control wiring, control relays, wire markers, nameplates, etc.)

Main bus, 2000A, fully insulated silver-plated copper, 3-phase, 3-wire with 25% ground

SECTION 6 Distribution Circuit Breakers to include the following:

Dimensions 36”W x 95”H x 99.8”D – NEMA 1 Enclosure

Distribution circuit breaker PS-3 to US-1EM1 (Square D, type VR), 1200A, 500MVA/63KAIC, electrically operated, drawout, 48VDC charge and close, 48VDC shunt trip, 6a & 6b auxiliary contacts, mechanically operated cell-MOC, truck operated cell-TOC (63kA)

Distribution circuit breaker PS-4 to US-1EM2 (Square D, type VR), 1200A, 500MVA/63KAIC, electrically operated, drawout, 48VDC charge and close, 48VDC shunt trip, 6a & 6b auxiliary contacts, mechanically operated cell-MOC, truck operated cell-TOC (63kA)

(Qty 2) Feeder Protective Relays – SEL 751A

(Qty 2) Lockout relays (Device 86), TRIP-RESET indication – Shallco

(Qty 2) Circuit breaker control switches, OPEN-TRIP-CLOSE with LED Indicating Lights – Shallco

(Qty 6) Current transformers, 600:5A – GE ITI Model 780

(Qty 2) Zero Sequence Current transformers, 50:5A – GE ITI Model 143

(Qty 2) Test Switch – ABB FT-1 Flexitest

Compression lugs, two hole mounting, long barrel, sizes listed with each breaker

Miscellaneous components: (terminal blocks, control wiring, control relays, wire markers, nameplates, etc.)

SECTION 7 Distribution Circuit Breakers to include the following:

Dimensions 36”W x 95”H x 99.8”D – NEMA 1 Enclosure

Distribution circuit breaker PS-5 to US-6EM1 (Square D, type VR), 1200A, 500MVA/63KAIC, electrically operated, drawout, 48VDC charge and close, 48VDC shunt trip, 6a & 6b auxiliary contacts, mechanically operated cell-MOC, truck operated cell-TOC (63kA)

Distribution circuit breaker PS-6 to US-6EM2 (Square D, type VR), 1200A, 500MVA/63KAIC, electrically operated, drawout, 48VDC charge and close, 48VDC shunt trip, 6a & 6b auxiliary contacts, mechanically operated cell-MOC, truck operated cell-TOC (63kA)

(Qty 2) Feeder Protective Relays – SEL 751A

(Qty 2) Lockout relays (Device 86), TRIP-RESET indication – Shallco

(Qty 2) Circuit breaker control switches, OPEN-TRIP-CLOSE with LED Indicating Lights – Shallco

(Qty 6) Current transformers, 600:5A – GE ITI Model 780

(Qty 2) Zero Sequence Current transformers, 50:5A – GE ITI Model 143

(Qty 2) Test Switch – ABB FT-1 Flexitest

Compression lugs, two hole mounting, long barrel, sizes listed with each breaker

Miscellaneous components: (terminal blocks, control wiring, control relays, wire markers, nameplates, etc.)

Main bus, 2000A, fully insulated silver-plated copper, 3-phase, 3-wire with 25% ground

Laminated mimic bus – White Face Red Core, Lamicoid attached with mechanical fasteners

SECTION 8 Load Bank/Distribution Circuit Breakers to include the following:

Dimensions 36”W x 95”H x 99.8”D – NEMA 1 Enclosure

Distribution circuit breaker PS-7 – Spare (Square D, type VR), 1200A, 500MVA/63KAIC, electrically operated, drawout, 48VDC charge and close, 48VDC shunt trip, 6a & 6b auxiliary contacts, mechanically operated cell- MOC, truck operated cell-TOC (63kA)

Distribution circuit breaker PS-8 to ETR, Load Bank (Square D, type VR), 1200A, 500MVA/63KAIC, electrically operated, drawout, 48VDC charge and close, 48VDC shunt trip, 6a & 6b auxiliary contacts, mechanically operated cell-MOC, truck operated cell-TOC (63kA)

(Qty 2) Feeder Protective Relays – SEL 751A

(Qty 2) Lockout relays (Device 86), TRIP-RESET indication – Shallco

(Qty 2) Circuit breaker control switches, OPEN-TRIP-CLOSE with LED Indicating Lights – Shallco

(Qty 6) Current transformers, 600:5A – GE ITI Model 780

(Qty 2) Zero Sequence Current transformers, 50:5A – GE ITI Model 143

(Qty 2) Test Switch – ABB FT-1 Flexitest

Compression lugs, two hole mounting, long barrel, sizes listed with each breaker

Miscellaneous components: (terminal blocks, control wiring, control relays, wire markers, nameplates, etc.)

Main bus, 2000A, fully insulated silver-plated copper, 3-phase, 3-wire with 25% ground

STANDALONE ITEMS:

(Qty 1) 48VDC Station Battery System to contain the following:

Battery cells, NiCad, 277AH – Model SBM277 - Saft Battery charger, 120VAC Input, 48VDC/50A Output – Saft 2 Step, 2 Tier Battery Rack, 54”L x 30”D x 66”H – Saft

(Qty 1) Remote Terminal Unit (RTU) in NEMA 1 enclosure to include the following:

(For Existing Generator)

Digital Synchronizer and Load Control (DSLC-2) – Woodward Versamax I/Os.

(Lot) Ethernet Switch with Ethernet/Fiber Connectivity – Moxa AC-DC Converter – Sola UPS – 500VA/450W, 120VAC Input, Full Load 17 min. with Audible Alarm – Liebert

(Qty 2) Remote Touch Screen Annunciator Panel in NEMA 1 enclosure (For Building #1 & Building #6)

PowerQuest Software – ASCO 24 inch LCD touch screen – (1920 x 1080 resolution) Operator Interface Panel – Strongarm Industrial Box PC, Microsoft OS Windows 7 Pro, 4GB RAM – Wonderware Power Supply, Input 115/230VAC 6A/3A, Output 24VDC 20A (480W) – Sola UPS – 500VA/450W, 120VAC Input, Full Load 17 min. with Audible Alarm – Liebert Alarm horn with silencing push-button and resound alarm circuitry – Mallory Monitoring of the emergency power system

(Qty 2) Remote Terminal Unit (RTU) in NEMA 1 enclosure to include the following:

(For SWGR Load Bus J-1 and Load Bus J-2 in Building #5)

Versamax I/Os (Lot) Ethernet Switch with Ethernet/Fiber Connectivity – Moxa AC-DC Converter – Sola UPS – 500VA/450W, 120VAC Input, Full Load 17 min. with Audible Alarm – Liebert

MISCELLANEOUS ITEMS:

(Qty 1) Racking Handle – Square D

(Qty 1) Portable circuit breaker lifting device – Square D

(Qty 1) Test Cabinet & Test Jumper – Square D

SPECIFICATION & PLAN’S COMPLIANCE REVIEW

ASCO offers our standard 7000 Series Medium Voltage Power Control System design and corresponding material summary as per attached proposal. Any changes will require ASCO to revise pricing of the system.

ASCO makes the following compliance review notes to the received Specification Section 262313 and one-line diagram # E-607 as received:

# Code Paragraph Page (s) Clarification (CL) / Deviation (D) / Exception (E)

1 CL 1.1

3.1

7-8

Installation, connection shall be responsibility by others.

Coordination for installation with utility is not required. If it is needed, then it shall be responsibility by others.

2 E 1.2-1.3 3.2.C

9 ASCO has not received these specification sections for review.

3 D 1.6.B 3 Quoted switchgear & controls are seismically tested for IBC-2009.

4 D 2.1.A 4

ASCO will provide generator paralleling and master controls as per our standard design and as described in this bill of material. This quote includes all paralleling controls integral of switchgear. ASCO will control switchgears LOAD BUS J-1 & LOAD BUS J-2 only.

5 D 2.1.C 4 This quote does not included two paralleling controls. ASCO will provide redundant System PLC and manual paralleling for gen.

6 D

2.1.D-F 2.3

DWG:E-571 &

Spec:262313

4-5

This quote includes 24” HMI for master section with standard screen as described in this bill of material. ASCO will not display utility metering and relaying information on HMI. ASCO will not provide any fiber optic cable, hardware, copper media etc., for connection. It shall be responsibility by others. ASCO will provide RTU for switchgears LOAD BUS J-1 & LOAD BUS J-2 only. All other switchgears/switcboards shall be controlled and monitor by others. ASCO will not logic for M-T-M-T-M switchgears. It shall be provided by others.

7 D DWG:E-607

& E-571

This quote does not include multi-ration CT’s. ASCO will use C100 CT’s for all metering and relaying. This quote include (qty-2) 24” Touch screen for remote annunciator system. As an adder ASCO can provide more annunciator in future, if required.

Generator protective relay for existing generator shall be provided by others. ASCO will provide feeder protective relay for that breaker.

VAMC NY

JOB # 12654P

ELECTRICAL SYSTEMS MODIFICATIONS FOR STORM DAMAGE

MITIGATION

12654P

Cat: 94612654P

DESCRIPTION OF OPERATION

Table of Contents

I. GENERAL

A. EQUIPMENT DESCRIPTION

II. OPERATING MODE (S)

A. EMERGENCY MODE

B. BLOCK LOAD CONTROL

III. FEATURES

A. LOAD BUS OPTIMIZATION

B. GENERATOR LOAD DEMAND CONTROL

C. TEST FACILITIES

1. ATS Load Test

2. Generator No Load Test

3. Single Engine Test

D. LOAD HAND – OFF – AUTO CONTROLS (NOT FOR ATS TESTING)

IV. OPERATOR CONTROLS

A. GENERATOR SECTION(S)

1. Generator Control Switch (GCS)

2. Synchronizing Mode Switch (SMS)

3. Engine Malfunction Indication

4. Generator PLC Failure

B. MASTER SECTION

1. Bus Alarm Reset

2. Alarm Silence

3. Priority # Load Shed Bypass/Reset

4. Load Demand Mode

5. System Test

6. Bus Optimize

7. Manual Parallel

8. Operator Interface Touch screen (OIT)

APPENDIX-1. FACTORY DEFAULT SETTINGS

DEFAULT RELAY SETTINGS LIST

I. GENERAL

A. Equipment Description

This ASCO Series 7000 Digital Paralleling system is consists of the following sections: (3) Generator sections, (1) Master/Bus PT section, (4) Distribution sections, and (2) Remote annunciators.

This system is designed to start (3) 2800 kW engine-generator sets (2 New Gens + 1 Existing Gen) upon receipt of a signal that emergency power is required from any of the automatic transfer switches (ATS) or electrically operated circuit breakers.

Description of Normal Breaker positions for SWGR-GEN (12654P)

- Normally Open o PSG-1, PSG-2, and PSG-3 (All Generator Breakers) o PS-1 (Load Bus J1), PS-2 (Load Bus J2), PS-7 (Spare), and PS-8 (Load Bank) o PS-4, PS-6 (Essential Loads 1EM2 & 6EM2)

- Normally Closed o PS-3, PS-5 (Essential loads 1EM1 & 6EM1)

Please reference Overall customer one line (Drawing E-607)

II. OPERATING MODE (S)

A. Emergency Mode

Whenever the individual engine generator control switches are placed in their automatic position, the engine generator system is on standby in readiness for automatic starting and synchronization in the event of a power failure signal.

In the event of a power failure, all generator(s) automatically start and come up to speed. The first generator set to achieve 90% of nominal voltage and frequency shall be connected to the bus.

Electronic interlocks permit the connection of only one engine generator to the dead generator bus in the event of simultaneous generator relay operation. Normally closed feeders (PS-3 & PS-5) will be energized as soon as the first generator comes on to the bus. Immediately thereafter, normally open feeder breakers (PS-4, PS-6, PS-1, and PS-2) will step add in that order to the emergency bus in one second intervals. Upon sensing the availability of emergency power, the priority-1 load block will be allowed to transfer their loads to the emergency bus, through a “permissive signal” to the automatic transfer switches (if equipped), subject to their individual Step Add timers as detailed in section B. Block Load Control. (Note: If priority 1 loads are not calling for an engine start because they have not lost normal power, a priority-pass along feature will be activated. Generally, if no loads in any priority block are calling for an engine start, all loads in lower priority blocks will be shifted up to a higher priority for block load add/shed purposes.) The synchronizer will automatically adjust the frequency of the on-coming generator to synchronize with the bus. When synchronism is achieved, the on-coming generator is paralleled to the bus. When the second generator’s circuit breaker is closed the priority-2 load block will be allowed to transfer their loads to the emergency bus. As each generator parallels to the bus, another block of load is allowed to add, until all generators and all loads are online.

Note - Load Bus J1 & Load Bus J2 are manually operated switchboards and require manual operation due to kirk key application.

Switchgear Feeder breakers feeding Load Bus J1 & Load Bus J2 (Switchgear Feeder Breakers:

PS-1 & PS-2) will close on emergency bus as the generators are coming on to the bus;

however, it will not energize the load until manually closed by operator on the side of the Kirk key operated equipment.

Upon sensing that normal utility power has been restored to acceptable limits, a sequence shall begin to transfer the load back to the utility source. The re-transfer shall be initiated after the retransfer to utility time delay has expired (adjustable at each ATS from 0 minute to 30 minutes) allowing an open transition transfer return to utility.

All feeder breakers on SWGR-GEN (12654P) feeding the loads will open and return to Utility except feeder breakers PS-1 & PS-2 feeding Load Bus J1 & Load Bus J2 respectively.

Therefore, the paralleling switchgear and ATSs associated (if any) with Load Bus J1 & Load Bus J2 in Building #5 already in Emergency will remain on Emergency and will not fully return to respective Utility until Load Bus J1 & Load Bus J2 are manually opened due to existing kirk key application on its respective utility breakers. (Load Bus J1 and Load Bus J2 will send signal to SWGR-GEN (12654P) via dry contacts (Aux contacts to be provided by customer) once kirk key is manually engaged and then ATSs will retransfer upon sensing Utility source and begin generator cooldown for the generators designated to continue running via Generator Load Demand)

After all the transfer switches have re-transferred their loads to the normal source, the generator circuit breakers are simultaneously opened and the engine generators run for an adjustable no-load cool-down period of zero to thirty minutes; factory set at 5-minutes. The controls are released and the generators placed in readiness for the next power failure.

B. Block Load Control

Each load has an adjustable priority setting, estimated KW value and step time delay associated with

it. As each block of load is allowed to transfer to emergency power, the individual loads will begin their step time delay. As the time delay for each load completes, the load will receive a permissive signal to transfer to emergency power. If no delay is desired, the individual step times can be set to zero seconds, and the loads will transfer immediately when the load block is permitted to transfer to emergency.

Note: Any automatic transfer switch without the 30B accessory (Load Shed) will automatically transfer to emergency on its own regardless of the permissive signal. Typically, critical priority 1 loads will not have a 30B accessory.

If a generator fails while operating in the automatic mode, it is disconnected from the bus and shutdown. Audible and visual alarms will be activated to indicate the condition. System loads will not shed unless a bus overload or a bus under frequency occurs. This feature is referred to as “Load- Latch”.

A push-button permits override of the load-shed circuits for supervised operation (one for each priority except priority 1). Loads that have been block shed can be manually re-added using the priority-# Load Shed Bypass/Reset push-button located on the Master control section. By pressing the Load Shed Bypass/Reset push-button, the system will transfer the selected load block to the emergency bus. By pressing the Load Shed Bypass/Reset push-button a second time, the ENTIRE selected load block will shed. Indicating lights will annunciate the status of each Priority load block, indicating if it is shed or manually bypassed. If the operator inadvertently bypasses the load shed and overloads the Generator(s) resulting in a bus under-frequency, all manually bypassed loads will be automatically shed along with blocks of load such that the remaining load blocks shall be one less than the number of generators remaining on the bus. The “Bus Under Frequency” annunciator light will indicate this condition.

If the online load exceeds 105% of rated generator capacity, unsupported loads (loads in priority blocks greater than the number of generators online) will be step shed in reverse priority at one second intervals. No loads in priority blocks equal to or less than the number of generators online will be shed. (Ex. If you have three generators online, load blocks 1. 2, and 3 will stay online, priority 4 and above will be shed). The Bus Overload light will light to indicate that the bus is overloaded automatically reset as the overload is corrected. When the online load no longer exceeds 105% of the generator capacity, step shedding will cease, and the system will continue to power the loads that are left online. Indicating lights will annunciate the status of each Priority load block, indicating if any loads in that block are shed or if the load block is manually bypassed. If the operator bypasses the load shed to bring those shed loads back online, and the online load exceeds 105% of capacity again, the system will again step shed loads in reverse priority until the load no longer exceeds 105% of capacity.

This is done in an attempt to prevent an under frequency situation, thereby preventing the entire load block from being shed.

III. Features

A. Load Bus Optimization

Each load should be programmed with a load priority value (field adjustable, accessible via the OIT on the master section door). A load’s priority value is a 3-digit number. The most significant digit refers to the load’s block priority value (i.e. 201 => priority 2 load block, whereas 118 => priority 1 load block).

The two lower significant digits refer to the load’s sub-priority value, or load step priority (i.e. 201 => priority 2 block, step 1; and 118 => priority 1 block, step 18). Valid priority values are 1 – 10 while valid sub-priority values are 1 - 99. Therefore, valid three digit priority values are 101 - 1099. Note: priority 1 loads (101 - 199) have insignificant sub-priority values since priority 1 loads are never optimized, also 3 digit priority values of 200, 300 and 400, etc. are not valid priority numbers. However, because of the dynamic nature of the adjustable load priorities, all loads, even priority 1 need to have sub-priority step values.

Should a Priority Block fail to be added to the bus while operating in the Emergency Mode, loads may be added manually by the operator as described above in section B. Block Load Control or automatically through "Load Bus Optimization". Load Bus Optimization is provided to re-add shed loads one at a time based on predetermined kW loading values up 95% (adjustable via OIT) of the capacity of the on-line power. This percentage value is referred to as the Bus Optimization KW de-rating value.

With the Bus Optimization switch in the "on" position during emergency mode and with loads shed (loads requiring power but are not connected to the emergency bus), after a stabilization time delay (Bus Opt stable delay) the optimization feature is activated and a Bus Optimize Active light illuminates.

The Bus Optimize Active light flashes through the duration of the stabilization time delay (default 30 seconds, adjustable via OIT). At this time, the Bus Optimization loading control will determine if there is enough room to add the next load by checking the pre-set Load Value (field adjustable, accessible via the OIT) assigned to the first sub-priority within…