REDM2526-05 Q&A.pdf
PDF 177 KB Posted
- Solicitation number
- RFSQ-13870
- Issued by
- Leon County, Florida
About this file
This is a Questions and Answers document issued by the Florida Department of Management Services, Real Estate Development and Management division, for RFQ REDM2526-05, a Request for Qualifications for Construction Management Services for Capitol Complex Generators Replacement located at 4050 Esplanade Way, Tallahassee, Florida. The document addresses inquiries submitted by potential respondents regarding the project scope and requirements. As of the revision date of July 2025, only one question had been submitted and answered during the pre-solicitation period.
The single question addressed in this document concerns the estimated construction budget for the Capitol Complex Generators Replacement project, to which the Department responded with an estimate of $16 million. No additional project details, timeline information, response deadlines, site visit requirements, or bidder conference information are included in this particular questions and answers document. The document includes standard Florida statutory language regarding protest procedures and bonding requirements under Chapter 120, Florida Statutes.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers (Rev. 07/2025) RFQ REDM2526-05
Real Estate Development and Management 4050 Esplanade Way
Tallahassee, FL 32399-0950 850-488-2074
Ron DeSantis, Governor
Pedro Allende, Secretary
QUESTIONS AND ANSWERS
RFQ REDM2526-05
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT SERVICES FOR
CAPITOL COMPLEX GENERATORS REPLACEMENT
FAILURE TO FILE A PROTEST WITHIN THE TIME PRESCRIBED IN SECTION 120.57(3), FLORIDA
STATUTES, OR FAILURE TO POST THE BOND OR OTHER SECURITY REQUIRED BY LAW WITHIN
THE TIME ALLOWED FOR FILING A BOND SHALL CONSTITUTE A WAIVER OF PROCEEDINGS
UNDER CHAPTER 120, FLORIDA STATUTES.
The Department’s responses to timely submitted questions are below.
Question Number Question Response
1. What is the estimated construction budget? $16 million.
File details come from the government source that posted it. Updated .