QQ58831 Questions & Answers.pdf

PDF 195 KB Posted

Attached to
Aluminum Pipe with Structural Plate Headwalls Nelson County
Solicitation number
58831
Issued by
Nelson County, Nathalie CDP, Virginia

About this file

This document is a question and answer memorandum from the Virginia Department of Transportation (VDOT) regarding solicitation QQ58831 for an Aluminum Pipe with Structural Plate Headwalls project in Nelson County, Virginia. The key details are that the requested delivery date for the structure is within 30 days of the award, and the culvert stub can be the same 10 gauge thickness specified on the provided sketch, rather than requiring crown and haunch ribs.

The related state and local contract opportunity is for the Aluminum Pipe with Structural Plate Headwalls project in Nelson County and the nearby Nathalie CDP. The request does not provide any additional details regarding pricing, funding, incumbent contractors, or other salient commercial information.

View the file

Other files

File Type Posted
Purchase Order 1282107 —
PO1282107 —
QQ58831 Specifications & Sketches.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF TRANSPORTATION

Stephen C. Brich, P.E. 1401 East Broad Street (804) 786-2701 Commissioner Richmond, Virginia 23219 Fax: (804) 786-2940

VirginiaDOT.org

WE KEEP VIRGINIA MOVING

Memorandum – Vendor Questions & VDOT Answers for QQ58831

Date February 14, 2024

The following questions were received from a vendor:

I have reviewed the bid documents and have a few questions pertaining to the referenced solicitation.

• What is the requested delivery date for this structure? Answer: Within 30 days of Award.

• Note 3 under Section IV states that the pipe should have haunch & crown ribs. I assume that this is an old note from a previous solicitation that required a structural plate structure. Can you please confirm?

Answer: Crown and haunch ribs are not required.

• Note 5 under Section IV states that the culvert stub should be 0.200” thick. I assume that this note is also from a previous solicitation that required a structural plate structure and that the culvert stubs should be the same gauge that is specified on the sketch that was provided within the bid documents (10 Gauge). Answer: The stub can be the same gauge (10) specified on the sketch.