This document is a Questions & Answers document for Project 082024-01, a Telecommunication Infrastructure Project (FTTH) being procured by Newport Utilities (NU). The project involves a specific query regarding the potential placement of aerial ADSS (All-Dielectric Self-Supporting) cable and the associated personnel certification requirements.

The key clarification in this document addresses whether certified electrical linemen are necessary for the project. Newport Utilities explicitly states that no ADSS cable should be placed in the power space. If a contractor believes such placement might be necessary, they are instructed to contact NU directly. The question was submitted and answered on 08/09/2024, and the definitive response is that certified electrical linemen are not required for this telecommunications infrastructure project.

View the file

Other files

File Type Posted
Contract Certifications.pdf PDF
Middle Mile Construction Unit Cost Sheet.xlsx XLSX spreadsheet
Poles.cpg —
Q&A Document 1.pdf PDF
Q&A Document 6.pdf PDF
South_340.kmz KMZ file
Wiley_Town.kmz KMZ file
Poles.prj —
Poles.sbn —
Poles.sbx —
Q&A Document 3.pdf PDF
Q&A Document 4.pdf PDF
Q&A Document 5.pdf PDF
Q&A Document 8.pdf PDF
Revised RFP Telecommunications Project (FTTH).pdf PDF
Middle Mile Design Area Estimated Mileage.xlsx XLSX spreadsheet
Middle Mile Revised Construction Unit Cost Sheet.xlsx XLSX spreadsheet
Poles.dbf DBF file
Poles.shp —
Poles.shx —
West_Parrottsville.kmz KMZ file
Byrd Anti-Lobbying Certification.pdf PDF
Liberty_Hill.kmz KMZ file
Middle Mile Construction Contract.pdf PDF
Poles.shp.xml XML file
Q&A Document 7.pdf PDF
RFP Telecommunications Project (FTTH).pdf PDF
Revised Middle Mile Construction Contract.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions & Answers - 2

Project 082024-01 - Telecommunication Infrastructure Project (FTTH)

Buying Organization Newport Utilities

No Question/Answer Question Date

Q2 Question: Electrical Certified Lineman

If aerial ADSS cable needs to be placed in the power space, are certified electrical lineman a requirement for this project?

Answer: There should not be any ADSS cable placed in the power space. If for some reason, you might think that needs to happen, please contact NU. So the answer will be no, certified electrical lineman are not required for this project.

08/09/2024

Questions & Answers - 2