This is a Business Case document and related solicitation for the Kenton County Airport Board (KCAB) in Kentucky regarding Backup Airport Operations Center (AOC) Construction. The project encompasses the construction and installation of a backup AOC facility at the South ARFF tower to replicate critical equipment and ensure business continuity should the primary AOC become unavailable. The scope includes installation of two dispatch consoles, critical systems (radios, 911 answering software, camera systems, Honeywell systems, and phones), and facility improvements (flooring, wall repair, paint, carpet, lighting, blinds, and finishes). A pre-bid meeting and site visit are scheduled for Thursday, February 26, 2026 at 1:00 pm at South ARFF Station #1, 2100 Tower Drive, Hebron, Kentucky. Questions are due by 11:59 pm on Monday, March 9, 2026, with answers to be posted no later than Thursday, March 12, 2026 at 11:59 pm. Bids must be received by Thursday, March 19, 2026 at 2:00 pm.

The total appropriations request is $430,722.50, comprised of $289,222.50 for construction (including design, construction/installation, contingency at minimum 10%, and force labor) and equipment costs totaling $141,500.00 (computer installation, furniture, force labor, and miscellaneous items). Design services were completed by Emboss and paid through Planning & Development's Professional Services O&M Budget. The project is driven by the current single-point-of-failure risk posed by operating the primary AOC out of the Airport Police Department with no backup capability, which has proven problematic during past events such as COVID evacuations and construction work. The project aligns with business objectives to ensure redundancy and continued business continuity and supports strategic goals of ensuring safety and health of passengers and employees while managing assets strategically. Construction is scheduled to commence on April 1, 2026 and be completed by June 30, 2026, with equipment purchases and installations to follow contract award.

View the file

Other files

File Type Posted
Backup_Airport_Operations_Center_(AOC)_Construction_(Addendum_#2_Revision).pdf PDF
26-008-ITB_Backup_AOC_Construction_-_Tech_Specs_-_Addendum_2_-_03.09.26.pdf PDF
26-008-ITB_Backup_AOC_Construction_-_Drawings_Addendum_1_03.03.26.pdf PDF
26-008-ITB_Pre-Bid_Sign_In_Sheets.pdf PDF
26-008-ITB_Pre-Bid_Meeting_Agenda.pdf PDF
Backup_Airport_Operations_Center_(AOC)_Construction.pdf PDF
26-008-ITB_Backup_AOC_Construction_-_Ad.pdf PDF
26-008-ITB_Backup_AOC_Construction_-_Exhibit_B_-_Contract_&_Bonds.pdf PDF
26-008-ITB_Backup_AOC_Construction_-_Exhibit_A_-_Proposal_Forms.pdf PDF
26-008-ITB_Backup_AOC_Construction_-_Drawings.pdf PDF
26-008-ITB_Backup_AOC_Construction_-_Technical_Specifications.pdf PDF
BACKUP_AOC_IFB_DRAWINGS.pdf PDF
BACKUP_AOC_IFB_SPECS.pdf PDF
BACKUP_AOC_SOUTH_ARFF_ESTIMATE_OF_PROBABLE_COST_2025.11.24.pdf PDF
Affirmative_Action_Certification.docx DOCX document
Disclosure_of_Lobbying_Activities_Certification.docx DOCX document
EEO_Certification.docx DOCX document
NonSegregated_Facilities_Certification.docx DOCX document
Certification_of_Offeror-Bidder_Regarding_Tax_Delinquency_and_Felony_Convictions.docx DOCX document
Non_Debarment_or_Suspension_Certification.docx DOCX document
Buy_American_Certification-Equipment-Building_Projects.docx DOCX document
Buy_American_Certification-Construction_Projects.docx DOCX document
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Master Plan Alignment

Strategic Plan Alignment

Sustainability Benefits

$50,000.00

$60,000.00

$10,000.00

$5,000.00

$12,500.00

$3,000.00

$1,000.00

$141,500.00

$42,475.00

$215,000.00

Construction Admin & Construction Inspection (CA/CI) $0.00

$25,747.50

$5,000.00

$1,000.00

$289,222.50

Total Appropriations Request: $430,722.50

Business Objectives: Ensure redundancy and continued business continuity should the primary AOC be impacted

Risk if Not Funded: Having only a primary AOC facility creates a single point of failure for our airport's PSAP and communications hub. By creating a backup AOC, business continuity will be enhanced. Additionally, the consoles were purchased by another project's budget and are being stored inside the bays at South ARFF.

Computer Installation:

Furniture:

Force Labor:

Miscellaneous:

Total Appropriations Request for Equipment:

Organizational Impact Justification

Design:

Construction/Installation:

Contingency (min 10%):

Force Labor:

Backup AOC Facility Construction PMWeb #

Current Situation/Background Information

The AOC currently operates out of the Airport Police Department - with 4 dispatch positions/stations. The AOC serves as CVG's communications hub and the airport-wide public safety answering point (PSAP). Currently there is not a Backup AOC that can be utilized should an incident render the current center unusable. This has been challenging for past events such as COVID required evacuations and construction work impacting the facility. Additionally, the AOC is open to additional risks such as power failures, fire and severe weather.

Project Definition

Project Scope: It is proposed to create a Backup AOC location in the South ARFF tower - which previously housed the airport's fire dispatch center. Build-out of a formal Backup AOC would include replicating all critical equipment to ensure continued operation should the primary AOC be disrupted:

•Installation of 2 dispatch consoles

•Installation of critical systems including radios, 911 answering software, camera systems, Honeywell, and phones

•Improvements to the facility (flooring, wall repair, paint, carpet, lighting, blinds, finishes, etc.)

Cost

Project Value/ROI: Ensuring continuity for the PSAP and communications hub during an emergency

Organizational Impact

Project Approach

Emboss was contracted and completed 100% designs and bid documents (construction cost-estimate) for the new Backup AOC. Design services were paid for through P&D's Professional Services O&M Budget - with the intent of "back paying" the O&M budget if the project is appropriated.

If appropriations are approved, a solicitation for general-contracting construction bids will be posted on OpenGov. Under a construction contract, the new Backup

AOC space will be demoed (including removal of unused fire-dispatch systems), re-built with a new, up-to-code raised-floor system, and finished with paint, carpet, ceiling tiles, and finishes. Once construction is complete, purchase orders for proprietary systems will be created and coordinated under the project - work station/console installs (Xybix), 911 Phones, Radios, and supporting technology.

Alternatives

Vendor Contingency:

Continue forward with the primary AOC location only with no backup available

Related Projects

N/A

911 Phones:

Fuel Performance - 2. Ensure the safety and health of passengers and employees

Fuel Performance - 4. Manage assets and space strategically

Radios:

Miscellaneous:

Total Appropriations Request for Construction:

1/28/2026

3/12/2026

3/27/2026

N/A

4/1/2026

Construction Notice to Proceed (after contract is signed) 4/1/2026

Construction Completion 6/30/2026

6/30/2026

ARFF Human Resources

Business Administration Information Technology

Capital Accounting Innovation

Commercial Management Operations

Customer Experience Planning & Development

Environmental, Social & Governance (ESG) Police Department

Facilities Procurement

Field Safety

Finance Terminal Modernization Program

Fleet Other ________________________________________________

100% - Emboss was contracted and completed 100% designs and bid documents (construction cost-estimate) for the new Backup AOC. Vendors provided equipment quotes. IT Director provided force labor estimates for IT work.

Stakeholders

Certainty of Cost Estimates

Project Funding

Larry Krauter

Chief Executive Officer

Dil Gruffydd

Chief Financial Officer

Executive Sponsor

Shannon Oldfield

Chief Operations Officer

Concurrence Leader

Steve Listerman

Vice President Public Safety, Security & Compliance

Business Unit Leader

Bill Siemer

Vice President Planning & Development

Sponsor/Originator

Eric Rysdon

Director Engineering Construction Management

CAPEX

Appropriations Approval

Approvals:

Equipment Installation

Known Risks & Limitations

CJIS Access - once computers are installed, the Backup AOC room must remain locked and accessible only by CJIS approved personnel - or under prior-approval and escort.

24/7/365 Facility - build-out/construction/installs will take place inside a 24/7/365 Facility. Work will be limited to "normal working hours" (8AM-5PM). Work will need to not interrupt facility functionality. Proprietary systems routing thru the tower (data, crash phone, etc.) are not to be interrupted without prior coordination and planning.

Recommendation

Construct the Backup AOC

Procurement (Bid/Solicitation) Completion

Contract Negotiation Finalized

Board Meeting

Equipment Purchase (after contract is signed)

Project Schedule

Out of Office. Verbally approved on 1.16.2026.

Eric Rysdon (Jan 30, 2026 16:34:40 EST) Eric Rysdon

Stephen Listerman (Jan 30, 2026 17:34:26 EST)

Dilwyn Gruffydd (Feb 2, 2026 16:32:43 EST) https://cvgairport.na2.adobesign.com/verifier?tx=CBJCHBCAABAAUwsYve-pFeS1G8ScruvYJT-DnlPBbgbr https://cvgairport.na2.adobesign.com/verifier?tx=CBJCHBCAABAAUwsYve-pFeS1G8ScruvYJT-DnlPBbgbr https://cvgairport.na2.adobesign.com/verifier?tx=CBJCHBCAABAAUwsYve-pFeS1G8ScruvYJT-DnlPBbgbr https://cvgairport.na2.adobesign.com/verifier?tx=CBJCHBCAABAAUwsYve-pFeS1G8ScruvYJT-DnlPBbgbr https://cvgairport.na2.adobesign.com/verifier?tx=CBJCHBCAABAAUwsYve-pFeS1G8ScruvYJT-DnlPBbgbr

Visuals

2026-02-06T13:27:17+0000
Certified by Adobe Acrobat Sign

File details come from the government source that posted it. Updated .