PWS USNS AMELIA EARHART HULL CLEANING and UWILD.pdf
PDF 151 KB Posted
- Attached to
- UWILD HULL INSPECTION
- Solicitation number
- N3220526Q7258
About this file
This is a Performance Work Statement (PWS) for an Underwater Inspection in Lieu of Drydocking (UWILD) service for the USNS Byrd, a T-AKE class vessel. The work is categorized as TAKE-CCSI and covers a five-year contract period with the initial performance scheduled for September 24, 2026 through October 7, 2026 in Guam. The vessel specifications include a length of 688 feet 11 inches, breadth of 654 feet, forward draft of 22 feet 10 inches, and aft draft of 27 feet 9 inches, with one rudder and one propeller.
The primary objective is to conduct a comprehensive underwater hull cleaning and inspection as an alternative to traditional drydocking survey, utilizing closed-circuit television with two-way communication and supplemented with color photographic and video documentation. The contractor must hire an ABS-recognized External Specialist diving contractor to perform all examinations, servicing, and photography under ABS, USCG, and manufacturer requirements. Key work activities include conducting a pre-survey planning meeting with the OMT REP, ABS Surveyor, ship's master, and chief engineer; examining and recording detailed underwater hull conditions including sea chests, anodes, rudder, propeller, stern bearings, and all inlets and discharges; taking stern and rudder bearing clearance measurements; internally examining representative sample tanks and cargo holds; and submitting condition reports in PDF format and three copies of comprehensive video documentation on DVD. The contractor must also provide electronic copies of all revised technical documentation, comply with all applicable General Technical Requirements (GTRs 1-7, 22-24, 28-29), and follow strict high-voltage electrical safety protocols specific to T-AKE class vessels. The Principal Point of Contact is Michael Perry, Principal Port Engineer USNS EARHART T-AKE 6.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AMENDMENT 3.pdf | ||
| TAKE-CCSI-UNDERWATER INSPECTION IN LIEU OF DRYDOCKING (UWILD) 9.21.26.docx | DOCX document | |
| Solicitation - N3220526Q7258.pdf | ||
| AME SOR 26-011- PWS-002.docx | DOCX document | |
| Solicitation Questions for N3220526Q7258 2.docx | DOCX document | |
| Solicitation N3220526Q7258 Amendment 1.pdf | ||
| CDRLS UNDERWARTER HUlL IDIQ.pdf | ||
| Solicitation - N3220526Q7258.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USNS Byrd
( TAKE-04 )
DRYDOCKING CONTRACT NO. XXXX-XXX
ITEM NO. 0952 SOR 26-
CATEGORY "A" 2025-10-26
TAKE-CCSI-UNDERWATER INSPECTION IN
LIEU OF DRYDOCKING (UWILD) (5 YR)
Narvarte, Cesar
0952 SOR 26-011 - 1
1.0 ABSTRACT
The purpose of this item is to conduct an Underwater Hull Cleaning and Inspection in Lieu of Dry-docking (UWILD) as an alternate to the Dry-docking Survey.
Location: GUAM
Period of Performance: 24 Sep 2026 – 07 Oct 2026
1.1 TPOC: Michael Perry, Principal Port Engineer USNS
EARHART T-AKE 6
Desk: 757.443.0983 Cell: 757.754.3196 Email: michael.t.perry.civ@us.navy.mil
2.0 REFERENCES
NOTE: PPE verify and update references as required for the applicable vessel prior to submission.
2.1 NAVSEA Drawing No. 801-8388071, Capacity Plan
2.2 NAVSEA Drawing No. 801-8388177, Docking Plan
2.3 NAVSEA Drawing No. 085-7488873, Shell Expansion
2.4 NAVSEA Drawing No. 085-7488875, Scantling Plan Decks
and Profiles
2.5 NAVSEA Drawing No. 085-7488876, Scantling Plan -
Sections
3.0 ITEM LOCATION/DESCRIPTION
NOTE: PPE verify and update location, description (Nomenclature, Manufacturer, Model, Serial number) and quantities as required for the applicable vessel prior to submission.
3.1 Location/Quantity
3.1.1 Locations: Underwater hull
mailto:michael.t.perry.civ@us.navy.mil
DRYDOCKING CONTRACT NO. XXXX-XXX
ITEM NO. 0952 SOR 26-
CATEGORY "A" 2025-10-26
TAKE-CCSI-UNDERWATER INSPECTION IN
0952 SOR 26-011 - 2
3.1.2 Quantity: One
3.2 Item Description/Manufacturer’s Data
Vessel length: 688 ft 11 in
Vessel breadth: 654 ft
Vessel draft (fwd): 22 ft 10 in
Vessel draft (aft): 27 ft 9 in
# of Rudders One
# of Propellers One
4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICE: None
5.0 NOTES
5.1 The contractor and all subcontractors, regardless of
tier must consult the General Technical Requirements (GTR) to determine applicability to this work item. In performance of this work item, the contractor and all subcontractors regardless of tier must comply with the requirements of all applicable GTRs including but not limited to GTRs 1 through 7, 22, 23, 24, 28, and 29.
5.2 This work item is applicable to vessels who have
approval from ABS to conduct ABS Rules for Survey After Construction, Part 7, Appendix, Section 1, Underwater Inspections in Lieu of Drydocking Surveys. If a vessel has any outstanding recommendations for repairs to the propeller, rudder, stern frame, underwater structure, or sea valves it may not be eligible for UWILD.
5.3 THIS SHIP CONTAINS HIGH VOLTAGE (HV) ELECTRICAL
SYSTEMS. OBEY ALL POSTED AND VERBAL INSTRUCTIONS REGARDING
SAFETY AND EXCLUSION FROM HIGH VOLTAGE AREAS. AT NO TIME
APPROACH, WORK ON, OR ENTER A HIGH VOLTAGE AREA WITHOUT PROPER
AUTHORIZATION.
DRYDOCKING CONTRACT NO. XXXX-XXX
ITEM NO. 0952 SOR 26-
CATEGORY "A" 2025-10-26
TAKE-CCSI-UNDERWATER INSPECTION IN
0952 SOR 26-011 - 3
5.4 THE T-AKE CLASS ELECTRICAL COLOR CODING DOES NOT
FOLLOW CONSISTENT COLOR SCHEME. THE SHIP IS KNOWN TO HAVE
CURRENT CARRYING CONDUCTORS COLORED GREEN, BLUE, BLACK, AND
WHITE. ASSUME ALL ELECTRICAL CABLES ARE ENERGIZED UNTIL TESTED
AND PROVEN OTHERWISE. TEST ALL ELECTRICAL CABLES TO ENSURE THEY
ARE DE-ENERGIZED PRIOR TO WORKING ON THE ITEM.
5.5 POP LOCATION: 7th Fleet AOR or GUAM. September 24, 2026
through October 30, 2026.
6.0 And QUALITY ASSURANCE REQUIREMENTS: None additional
7.0 STATEMENT OF WORK REQUIRED
7.1 Conduct an Underwater Cleaning and Inspection in Lieu
of Drydocking (UWILD) as an alternate to the Drydocking Survey using References 2.1 through 2.5 as guidance.
7.2 Coordinate with ship’s force to have associated
equipment locked and/or tagged out per ship’s lock out/tag out policy. When the maintenance is complete, coordinate with ship’s force to have associated equipment unlocked and/or tagged in per ship’s lock out/tag out policy.
7.2.1 With assistance from the OMT REP tag out all
overboard discharges, pump suctions, cathodic protection systems, jacking gear, and other systems or equipment that could affect divers.
7.3 Conduct a Pre-Survey Planning Meeting with the OMT
REP, Divers Rep, Master, Chief Engineer, ABS Surveyor and OMT REP in attendance. The meeting agenda and discussion shall, at a minimum, cover:
7.3.1 The vessel’s Master, Chief Engineer, or person in
charge, is to submit a signed letter to the ABS Surveyor stating the general overall condition of the vessel, level of maintenance, any known or suspected damage and cleanliness of the underwater body.
7.3.2 Confirm that the vessel has made no unapproved
repairs.
7.3.3 Confirm there is no record or indication of
DRYDOCKING CONTRACT NO. XXXX-XXX
ITEM NO. 0952 SOR 26-
CATEGORY "A" 2025-10-26
TAKE-CCSI-UNDERWATER INSPECTION IN
0952 SOR 26-011 - 4
abnormal deterioration, outstanding recommendations, or damage to underwater body, propeller, rudder, stern frame, underwater structure, or sea valves.
7.3.4 OMT REP is to provide the ABS Surveyor with the
most recent gaugings and gauging report from the last Special Survey.
7.3.5 OMT REP is to provide the Shipyard Superintendent, Divers and ABS with plans and drawings showing the external details of the hull below the sheer strake, including the following items and their location:
a. All shell openings
b. All docking plugs
c. Bilge keels
d. Welded seams and butts
e. Appendages
f. Anodes, including methods of attachment
g. Rudder
h. Propeller
i. Reference points
j. Watertight and oil-tight bulkheads
7.3.6 Confirm there are hull markings or other means to
orient the in-water survey and identify photographs.
7.3.7 Identify the Diving contractor, the number of
divers to be employed and the type of dive equipment to be used.
Discuss their experience, training and qualifications in underwater photography and NDT.
7.3.8 Discuss means of communication between the bridge, dive team and engine room (direct communications via sound powered phones are preferred).
DRYDOCKING CONTRACT NO. XXXX-XXX
ITEM NO. 0952 SOR 26-
CATEGORY "A" 2025-10-26
TAKE-CCSI-UNDERWATER INSPECTION IN
0952 SOR 26-011 - 5
7.3.9 Discuss procedure/plan for emergencies.
7.3.10 Provide Divers with any reference data and
instructions necessary for underwater operations such as means of access to sea chests to inspect the external side of hull connections and sea valves, to rudder bearings to determine clearances of rudder bearings or to propeller shaft strut and stern bearings.
7.3.11 Discuss method of installing blanks/plugs for sea
chests/valves.
7.3.12 Discuss means to take stern bearing and rudder
bearing clearances.
7.3.13 Determine which tanks and cargo holds are to be
internally examined as a representative sample.
7.3.14 Determine if underwater or internal thickness
measurements of suspect areas are required.
7.3.15 Discuss divers means to conduct underwater
nondestructive testing for fracture detection.
7.3.16 Discuss the in-water clarity (visibility) and the
current or spot cleaning will be necessary.
7.3.17 Discuss vessels anticipated drafts, pier side
clearance and under keel clearance at the time of the survey.
7.3.18 Discuss impact of tides and currents on divers and
the examination.
7.3.19 Discuss anticipated duration of the underwater
survey
7.4 Conduct an underwater examination of the entire vessel
by an in-water survey company recognized by ABS using closed-circuit television with two-way communication using ABS requirements as guidance. The in-water survey is to be monitored and conducted under the surveillance of the attending ABS Surveyor and is to be supplemented with color photographic or video documentation. The ABS Surveyor is to be satisfied with the method of pictorial representation, and a good two-way
DRYDOCKING CONTRACT NO. XXXX-XXX
ITEM NO. 0952 SOR 26-
CATEGORY "A" 2025-10-26
TAKE-CCSI-UNDERWATER INSPECTION IN
0952 SOR 26-011 - 6
communication between the Surveyor and divers is to be provided.
7.4.1 Items that must be recorded on the tape/photograph
include but are not limited to:
a. Vessel’s draft
b. Time at which dive commences
c. Point of commencement
d. Time viewed
e. Conditions of hull markings
f. Random areas of plating
g. All sea chests
h. All inlets and discharges
i. Bow and stern thrusters
j. Fathometer, Speed Log and other transducers
k. Anodes and reference cells of cathodic protection system
l. Rudder(s)
m. Pintles
n. Propeller(s) to include rope guards and net and line cutters
o. Areas showing signs of damage and/or corrosion
p. Time and point of completion of the dive
7.4.2 Items that must be examined, measured and recorded
include but are not limited to:
a. Confirm that the sea suction openings are clear.
b. Ascertain that the shaft seal assembly remains
DRYDOCKING CONTRACT NO. XXXX-XXX
ITEM NO. 0952 SOR 26-
CATEGORY "A" 2025-10-26
TAKE-CCSI-UNDERWATER INSPECTION IN
0952 SOR 26-011 - 7
intact on oil-lubricated bearings.
c. Determine stern bearing clearances. Verify that the clearance or weardown is within limits on the stern bearing.
d. Determine the rudder bearing clearances and condition.
e. Determine the rudder pintle clearances and condition.
f. Verify that all parts of the pintle and gudgeon assemblies are intact and secure.
g. This work may require removal of bolted access plates, threaded plugs, and a measuring arrangement.
7.5 Hinged gratings must be opened on all sea chests to
allow divers access into each sea chest to inspect the anodes, internal sides of through hull connections and sea valves.
7.6 Sea valves and their attachment to sea chests are to
be examined externally, including expansion pieces in sea water cooling and circulating systems.
7.7 Examine the outside of the shell plating above the
waterline and exposed portions of appendages, such as propeller, rudder and rudder bearings. Provide a small boat with operator to aid the ABS surveyor accomplish this inspection.
7.8 Upon completion of the survey, restore all access
cover plates, threaded plugs, suction grates, remove all blanks, leaving the vessel in a ready for service condition.
7.9 Reports
7.9.1 When examination and servicing reveal any
deficiency a condition report is to be submitted to the OMT REP with recommended repair and parts required. Submit one electronic copy in Portable Document Format (PDF).
7.9.2 Submit three copies of a video tape with audio
commentary of all external areas of the underwater hull identified in 7.4 and 7.4.1, including rudder, propeller,tail
DRYDOCKING CONTRACT NO. XXXX-XXX
ITEM NO. 0952 SOR 26-
CATEGORY "A" 2025-10-26
TAKE-CCSI-UNDERWATER INSPECTION IN
0952 SOR 26-011 - 8
shaft, hull protective system, and all other attached appurtenances. Publish the video on DVD in a format readily accessible/playable using Windows™ software applications such as Windows Media Player, or others. Provide one copy to the OMT REP, one copy to the ship, and one copy to the ABS Surveyor.
7.10 Painting: None additional
7.11 Manufacturer’s Representative
7.11.1 Provide the services of a Diving contractor who is
an ABS recognized External Specialist for conducting In-Water Surveys. The contractor is to perform all examinations, servicing, testing and photography/videography of the underwater hull in accordance with ABS, USCG and manufacturer’s requirements.
https://ww2.eagle.org/en/rules-and-resources/recognized external-specialists.html.
https://www.eagle.org/ABSEaglePrograms/es/es-search.jsp
7.11.2 Provide the OMT REP with a signed letter of
qualification and copy of the ABS Certificate prior to the start of any work.
7.12 Preparation of Drawings
7.12.1 Provide electronic copies of all revised
and/or updated technical documentation including drawings, technical manuals, service bulletins, parts lists, certification and test data associated with the work performed or parts supplied to the OMT REP.
8.0 GENERAL REQUIREMENTS: None additional
https://www.eagle.org/ABSEaglePrograms/es/es-search.jsp
| 1.0 ABSTRACT |
| The purpose of this item is to conduct an Underwater Hull Cleaning and Inspection in Lieu of Dry-docking (UWILD) as an alternate to the Dry-docking Survey. |
| Location: GUAM |
| Period of Performance: 24 Sep 2026 – 07 Oct 2026 |
| 1.1 TPOC: Michael Perry, Principal Port Engineer USNS EARHART T-AKE 6 |
| 2.0 REFERENCES |
| NOTE: PPE verify and update references as required for the applicable vessel prior to submission. |
| 2.1 NAVSEA Drawing No. 801-8388071, Capacity Plan |
| 2.2 NAVSEA Drawing No. 801-8388177, Docking Plan |
| 2.3 NAVSEA Drawing No. 085-7488873, Shell Expansion |
| 2.4 NAVSEA Drawing No. 085-7488875, Scantling Plan Decks and Profiles |
| 2.5 NAVSEA Drawing No. 085-7488876, Scantling Plan - Sections |
| 3.0 ITEM LOCATION/DESCRIPTION |
| NOTE: PPE verify and update location, description (Nomenclature, Manufacturer, Model, Serial number) and quantities as required for the applicable vessel prior to submission. |
| 3.1 Location/Quantity |
| 3.1.1 Locations: Underwater hull |
| 3.1.2 Quantity: One |
3.2 Item Description/Manufacturer’s Data
| 4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICE: None |
| 5.0 NOTES |
| 5.1 The contractor and all subcontractors, regardless of tier must consult the General Technical Requirements (GTR) to determine applicability to this work item. In performance of this work item, the contractor and all subcontractors regardless of tie... |
| 5.2 This work item is applicable to vessels who have approval from ABS to conduct ABS Rules for Survey After Construction, Part 7, Appendix, Section 1, Underwater Inspections in Lieu of Drydocking Surveys. If a vessel has any outstanding recommendatio... |
| 5.3 THIS SHIP CONTAINS HIGH VOLTAGE (HV) ELECTRICAL SYSTEMS. OBEY ALL POSTED AND VERBAL INSTRUCTIONS REGARDING SAFETY AND EXCLUSION FROM HIGH VOLTAGE AREAS. AT NO TIME APPROACH, WORK ON, OR ENTER A HIGH VOLTAGE AREA WITHOUT PROPER AUTHORIZATION. |
| 5.4 THE T-AKE CLASS ELECTRICAL COLOR CODING DOES NOT FOLLOW CONSISTENT COLOR SCHEME. THE SHIP IS KNOWN TO HAVE CURRENT CARRYING CONDUCTORS COLORED GREEN, BLUE, BLACK, AND WHITE. ASSUME ALL ELECTRICAL CABLES ARE ENERGIZED UNTIL TESTED AND PROVEN OTHERW... |
| 5.5 POP LOCATION: 7th Fleet AOR or GUAM. September 24, 2026 through October 30, 2026. |
| 6.0 And QUALITY ASSURANCE REQUIREMENTS: None additional |
| 7.0 STATEMENT OF WORK REQUIRED |
| 7.1 Conduct an Underwater Cleaning and Inspection in Lieu of Drydocking (UWILD) as an alternate to the Drydocking Survey using References 2.1 through 2.5 as guidance. |
| 7.2 Coordinate with ship’s force to have associated equipment locked and/or tagged out per ship’s lock out/tag out policy. When the maintenance is complete, coordinate with ship’s force to have associated equipment unlocked and/or tagged in per ship’s... |
| 7.2.1 With assistance from the OMT REP tag out all overboard discharges, pump suctions, cathodic protection systems, jacking gear, and other systems or equipment that could affect divers. |
| 7.3 Conduct a Pre-Survey Planning Meeting with the OMT REP, Divers Rep, Master, Chief Engineer, ABS Surveyor and OMT REP in attendance. The meeting agenda and discussion shall, at a minimum, cover: |
| 7.3.1 The vessel’s Master, Chief Engineer, or person in charge, is to submit a signed letter to the ABS Surveyor stating the general overall condition of the vessel, level of maintenance, any known or suspected damage and cleanliness of the underwater... |
| 7.3.2 Confirm that the vessel has made no unapproved repairs. |
| 7.3.3 Confirm there is no record or indication of abnormal deterioration, outstanding recommendations, or damage to underwater body, propeller, rudder, stern frame, underwater structure, or sea valves. |
| 7.3.4 OMT REP is to provide the ABS Surveyor with the most recent gaugings and gauging report from the last Special Survey. |
| 7.3.5 OMT REP is to provide the Shipyard Superintendent, Divers and ABS with plans and drawings showing the external details of the hull below the sheer strake, including the following items and their location: |
| a. All shell openings |
| b. All docking plugs |
| c. Bilge keels |
| d. Welded seams and butts |
| e. Appendages |
| f. Anodes, including methods of attachment |
| g. Rudder |
| h. Propeller |
| i. Reference points |
| j. Watertight and oil-tight bulkheads |
| 7.3.6 Confirm there are hull markings or other means to orient the in-water survey and identify photographs. |
| 7.3.7 Identify the Diving contractor, the number of divers to be employed and the type of dive equipment to be used. Discuss their experience, training and qualifications in underwater photography and NDT. |
| 7.3.8 Discuss means of communication between the bridge, dive team and engine room (direct communications via sound powered phones are preferred). |
| 7.3.9 Discuss procedure/plan for emergencies. |
| 7.3.10 Provide Divers with any reference data and instructions necessary for underwater operations such as means of access to sea chests to inspect the external side of hull connections and sea valves, to rudder bearings to determine clearances of rud... |
| 7.3.11 Discuss method of installing blanks/plugs for sea chests/valves. |
| 7.3.12 Discuss means to take stern bearing and rudder bearing clearances. |
| 7.3.13 Determine which tanks and cargo holds are to be internally examined as a representative sample. |
| 7.3.14 Determine if underwater or internal thickness measurements of suspect areas are required. |
| 7.3.15 Discuss divers means to conduct underwater nondestructive testing for fracture detection. |
| 7.3.16 Discuss the in-water clarity (visibility) and the current or spot cleaning will be necessary. |
| 7.3.17 Discuss vessels anticipated drafts, pier side clearance and under keel clearance at the time of the survey. |
| 7.3.18 Discuss impact of tides and currents on divers and the examination. |
| 7.3.19 Discuss anticipated duration of the underwater survey |
| 7.4 Conduct an underwater examination of the entire vessel by an in-water survey company recognized by ABS using closed-circuit television with two-way communication using ABS requirements as guidance. The in-water survey is to be monitored and conduc... |
| 7.4.1 Items that must be recorded on the tape/photograph include but are not limited to: |
| a. Vessel’s draft |
| b. Time at which dive commences |
| c. Point of commencement |
| d. Time viewed |
| e. Conditions of hull markings |
| f. Random areas of plating |
| g. All sea chests |
| h. All inlets and discharges |
| i. Bow and stern thrusters |
| j. Fathometer, Speed Log and other transducers |
| k. Anodes and reference cells of cathodic protection system |
| l. Rudder(s) |
| m. Pintles |
| n. Propeller(s) to include rope guards and net and line cutters |
| o. Areas showing signs of damage and/or corrosion |
| p. Time and point of completion of the dive |
| 7.4.2 Items that must be examined, measured and recorded include but are not limited to: |
| a. Confirm that the sea suction openings are clear. |
| b. Ascertain that the shaft seal assembly remains intact on oil-lubricated bearings. |
| c. Determine stern bearing clearances. Verify that the clearance or weardown is within limits on the stern bearing. |
| d. Determine the rudder bearing clearances and condition. |
| e. Determine the rudder pintle clearances and condition. |
| f. Verify that all parts of the pintle and gudgeon assemblies are intact and secure. |
| g. This work may require removal of bolted access plates, threaded plugs, and a measuring arrangement. |
| 7.5 Hinged gratings must be opened on all sea chests to allow divers access into each sea chest to inspect the anodes, internal sides of through hull connections and sea valves. |
| 7.6 Sea valves and their attachment to sea chests are to be examined externally, including expansion pieces in sea water cooling and circulating systems. |
| 7.7 Examine the outside of the shell plating above the waterline and exposed portions of appendages, such as propeller, rudder and rudder bearings. Provide a small boat with operator to aid the ABS surveyor accomplish this inspection. |
| 7.8 Upon completion of the survey, restore all access cover plates, threaded plugs, suction grates, remove all blanks, leaving the vessel in a ready for service condition. |
| 7.9 Reports |
| 7.9.1 When examination and servicing reveal any deficiency a condition report is to be submitted to the OMT REP with recommended repair and parts required. Submit one electronic copy in Portable Document Format (PDF). |
| 7.9.2 Submit three copies of a video tape with audio commentary of all external areas of the underwater hull identified in 7.4 and 7.4.1, including rudder, propeller,tail shaft, hull protective system, and all other attached appurtenances. Publish the... |
| 7.10 Painting: None additional |
| 7.11 Manufacturer’s Representative |
| 7.11.1 Provide the services of a Diving contractor who is an ABS recognized External Specialist for conducting In-Water Surveys. The contractor is to perform all examinations, servicing, testing and photography/videography of the underwater hull in ac... |
| https://ww2.eagle.org/en/rules-and-resources/recognized external-specialists.html. |
| https://www.eagle.org/ABSEaglePrograms/es/es-search.jsp |
7.11.2 Provide the OMT REP with a signed letter of qualification and copy of the ABS Certificate prior to the start of any work.
| 7.12 Preparation of Drawings |
| 7.12.1 Provide electronic copies of all revised and/or updated technical documentation including drawings, technical manuals, service bulletins, parts lists, certification and test data associated with the work performed or parts supplied to the OMT REP. |
8.0 GENERAL REQUIREMENTS: None additional