A.3 PERORMANCE WORK STATEMENT (PWS)
A) This firm fixed requirement for quarterly, semi-annual and annual preventative maintenance services on the air handling units, air conditioners and filtered exhaust systems (non-filtered exhaust systems are not included in this scope of work) located at the Orange Campus of the New Jersey VA Healthcare System 385 Tremont Avenue, East Orange NJ 07018 and the Lyons Campus of the New Jersey VA Healthcare System 151 Knollcroft Rd, Lyons, NJ 07939 from 10/01/2020 through 09/30/2021 to include four option years.
B) Contractor shall possess a license to service HVAC equipment in the State of New Jersey and shall only use qualified technicians as defined by the State of New Jersey to service equipment at either location.
C) All technicians shall at the minimum have completed the OSHA 10hr safety course.
D) Contractor shall submit SDS documents for all chemicals to be used in this service agreement to the Contracting Officer’s Representative before the commencement of any work.
A.3.1 PREVENTATIVE MAINTENANCE SERVICES FOR AIR HANDLING UNITS LOCATED AT THE EAST ORANGE CAMPUS OF THE NEW JERSEY VA HEALTHCARE SYSTEM A.3.1.1 General
A) The contractor shall provide all labor, personnel, supervision, equipment, tools, and all materials (filters and belts) necessary to perform preventative maintenance on the air handling units, air conditioners and filtered exhaust systems (non-filtered exhaust systems are not included in this scope of work) as defined in this Performance Work Statement (PWS).
B) All work shall be performed during the hours of 7:00 AM to 3:30 PM, Monday thru Saturday excluding Federal Holidays (defined as: New Year's Day, Birthday of Martin Luther King, Jr., Washington's Birthday, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day and Christmas Day) unless noted within PM procedures below.
C) Preventative maintenance services shall follow the following schedule:
1. Quarterly services shall occur in the months of October, January, April and July
2. Semi-Annual services shall occur in the months of October and April
3. Annual services shall occur in the month of October.
D) Upon arrival to the East Orange VA Medical Campus, HVAC Technicians shall report to Air Conditioning Equipment Mechanic Supervisor in Bldg. 1, B-level, Room 128, Ext. 2099 .the Boiler Plant Foreman in Bldg. 8, 973-676-1000 Ext. 1882.
E) Upon completion of tasks described under section A.3.1 PREVENTATIVE MAINTENANCE SERVICES FOR AIR HANDLING UNITS LOCATED AT THE EAST ORANGE CAMPUS OF THE NEW JERSEY VA HEALTHCARE SYSTEM the contractor shall provide a copy of service report to the COR. Service reports shall be signed by both the contractor and COR at completion of work. An electronic version of same shall be sent to the COR. Service reports shall include tasks completed to include areas worked on, number of workers involved and hours worked.
F) Equipment to be serviced under this contract are listed in Table 1. Below.
Table 1
| Building |
| Level |
| Location |
| Equipment identification |
| Filter Size |
| Quantity |
| Building 1: |
| C-Level: |
| C-132 |
| AHU-10A |
| 20X25X2 |
| 2 |
| C-101 |
| MAS package Unit |
| 31½X 22X1 (polyester media) |
| 2 |
| C-102 |
| EMS Storage Unit |
| 12X18X2 |
| 1 |
| C-121 |
| EMS Supply Unit |
| 20X20X1 |
| 1 |
| C-111 |
| Mechanical Room AC Unit |
| 16x25x1 |
| 2 |
| C-112 |
| Mechanical Room AC Unit |
| 16x25x1 |
| 2 |
| B-Level: |
| B-110B |
| Dish washing room AC Unit |
| 16X20X2 |
| 8 |
| B-177 |
| Mail Room Package Unit |
| 16X20X1 |
| 4 |
| B-158C |
| MSDS Package Unit |
| 13X18X2 |
| 2 |
| B-109 |
| Retherm area AC-1 |
| 16X25X1 |
| 2 |
| B-109 |
| Retherm area AC-2 |
| 16X25X1 |
| 2 |
| B-155 |
| Electric Shop AC Unit |
| 16X24X2 |
| 4 |
| B-154D |
| Bio-Med AC Unit |
| 16X25X1 |
| 4 |
| B-136 |
| Pharmacy AC Unit |
| 16X25X1 |
| 4 |
| B-134D |
| Linen Room AHU |
| 24X25X2 |
| 2 |
| B-140B |
| Receiving AC Unit |
| 20X22-1/4X1 |
| 1 |
| On roof over B-115 |
| AHU-9 |
| 24X24X2 |
| 16 |
| A-Level: |
| A-146 |
| A-Level Lab AHU |
| 24X24X4 |
| 8 |
| On roof over A-215 |
| Check-In AC Unit |
| 16X20X2 |
| 4 |
| On Roof over A-236 |
| AHU-1D |
| 24X24X12 |
| 4 |
| On Roof over A-236 |
| AHU-1D |
| 12X24X12 |
| 4 |
| On Roof over A-236 |
| AHU-1D |
| 16X16X2 |
| 5 |
| On Roof over A-236 |
| AHU-1D |
| 16X25X2 |
| 15 |
| A-244 |
| Cat scan Unit |
| 20X20X2 |
| 1 |
| A-216A |
| Lobby Split Unit 1 |
| Washable Filters |
| N/A |
| A-216B |
| Lobby Split Unit 2 |
| Washable Filters |
| N/A |
| A-216C |
| Lobby Split Unit 3 |
| Washable Filters |
| N/A |
| A-106 On roof above B-Level kitchen |
| Pharmacy Unit |
| 16X20X2 |
| 6 |
| A-128D |
| File Room AHU |
| 16X25X2 |
| 3 |
| A-102H |
| Prosthetics Office Unit |
| 16X20X1 |
| 1 |
| A-103E |
| Orthotics AHU |
| 16X20X2 |
| 4 |
| A-103E |
| Orthotics AHU |
| 16X20X4 |
| 4 |
| A-160 |
| Clinic Waiting Room Unit |
| 25X25X1 |
| 2 |
| 1st Floor |
| 1-115 |
| IRM Unit 1 |
| 20X24X4 |
| 4 |
| 1-115 |
| IRM Unit 2 |
| 20X25X4 |
| 3 |
| 1-103A |
| IRM Unit 3 |
| 24X24X2 |
| 3 |
| 1-103 |
| IRM Unit 4… |
| 24X24X2 |
| 3 |
| On roof over Chiller Plant |
| AHU-17 |
| 24X24X2 |
| 24 |
| 1-259 |
| Angio Room Unit |
| 16X20X2 |
| 4 |
| 1-259 |
| Angio Room Unit |
| 16X20X4...90% |
| 4 |
| 1-261A |
| Angio Equipment Room Unit |
| 16X24X4 |
| 1 |
| 1-241 |
| Cat scan Unit 1 |
| 16X25X1 |
| 3 |
| 1-243 |
| Cat scan unit 2 |
| 20X20X1 |
| 1 |
| 1-262B |
| IRM Classroom Unit |
| 18X25X1 |
| 3 |
| 1-262 |
| Medical Records Unit |
| 20X22¼X1 |
| 1 |
| 1-E-301 |
| Directors AHU |
| 16X25X2 |
| 3 |
| 1-218D |
| MRI large AC Unit |
| 24x24X1 |
| 2 |
| 1-218I |
| MRI Small Ac Unit |
| 20x20X1 |
| 1 |
| 2nd Floor |
| 2-102 |
| Museum AHU |
| 20X24X4 |
| 6 |
| 2-102 |
| Museum AHU |
| 24X24X2 |
| 6 |
| 2-192H |
| Endoscopy AHU |
| 16X18X2 |
| 6 |
| 2-181 |
| SPS AHU |
| 23⅜X19⅜X11½ |
| 6 |
| 2D AHU |
| On roof outside of room 2-437 |
| 18X25X2 |
| 10 |
| 2D AHU |
| On roof outside of room 2-437 |
| 24X24X11½ HEPA |
| 6 |
| 3rd Floor |
| Auditorium Unit |
| roof outside of room 4-102 |
| Washable Filters |
| N/A |
| 3-222 |
| Chaplin AHU |
| 16X20X2 |
| 6 |
| 3-339 |
| Dental Unit |
| 12X24X2 |
| 3 |
| 3-339 |
| Dental Unit |
| 20X25X2 |
| 3 |
| 3-327 |
| Dental Hood #1 |
| 16X20X1 |
| 1 |
| 3-327 |
| Dental Hood #2 |
| 16X20X1 |
| 1 |
| 3-327 |
| Dental Hood #3 |
| 16X20X1 |
| 1 |
| 3-327 |
| Dental Lab after filter |
| 12X18X1 |
| 4 |
| 3-165A |
| Canteen Store AC |
| 16x25X1 |
| 4 |
| 3-175B |
| Dining Room AC-1 |
| 16X25X2 |
| 4 |
| 3-181B |
| Dining Room AC-2 |
| 16X25X2 |
| 4 |
| On roof outside of 3-214 |
| 2D HEPA exhaust |
| 24X24X4 |
| 2 |
| On roof outside of 3-214 |
| 2D HEPA exhaust |
| 24X24X11½ HEPA |
| 2 |
| 4th Floor |
| 2-246 |
| Audiology AHU |
| 16X20X2 |
| 3 |
| 6th Floor |
| 6C Roof |
| 5C-AHU |
| 20X15X2 |
| 24 |
| 6C Roof |
| 5C-AHU |
| Airguard Variflow Model# X0901035-10 24x12x6 |
| 2 |
| 6C Roof |
| 5C-AHU |
| Airguard Variflow Model# X0901035-06 24x12x6 |
| 2 |
| 6C Roof |
| 5C-HEPA Exhaust 1 |
| 24X24X4 |
| 4 |
| 6C Roof |
| 5C-HEPA Exhaust 1 |
| 24X24X11½ HEPA |
| 4 |
| 6C Roof |
| 5C-HEPA Exhaust 2 |
| 24X24X4 |
| 4 |
| 6C Roof |
| 5C-HEPA Exhaust 2 |
| 24X24X11½ HEPA |
| 4 |
| 6C Roof |
| TBEF-6 HEPA Exhaust |
| 24X24X2 |
| 2 |
| 6C Roof |
| TBEF-6 HEPA Exhaust |
| 24X24X11½HEPA |
| 2 |
| 6D Roof |
| Echo-Lab AHU |
| 24X24X2 |
| 4 |
| 6D Roof |
| Echo-Lab AHU |
| 12X24X2 |
| 4 |
| 7th Floor |
| 7-200 |
| Infection Control AC unit |
| 12X20X2 |
| 2 |
| 7-200 |
| Infection Control AC unit |
| 12X20X4 |
| 2 |
| 8th Floor |
| 8-188A |
| Podiatry AC Unit |
| 28X21½X1 |
| 1 |
| 8-204C |
| New Chemo-lab unit |
| 12X24X2 |
| 1 |
| 8-204C |
| New Chemo-lab unit |
| 24X24X2 |
| 1 |
| 8-204C |
| New Chemo-lab unit |
| 12X24x4…90% |
| 1 |
| 8-204C |
| New Chemo-lab unit |
| 4x24X4…90% |
| 1 |
| 8-204C |
| New Chemo-lab unit |
| 30X30X11½ HEPA |
| 1 |
| 8-204A |
| Old Chemo-lab unit |
| 16X25X2 |
| 4 |
| 8-204A |
| Old Chemo-lab unit |
| 24X24X2 |
| 1 |
| 8-204A |
| Old Chemo-lab unit |
| 24X24X11½ HEPA |
| 1 |
| 9th Floor |
| 9-163 |
| Cath Lab Unit |
| 18X24X2 |
| 2 |
| 9-163 |
| Cath Lab Unit |
| 12X24X2 |
| 1 |
| 9-163 |
| Cath Lab Unit |
| 24X24X2 |
| 2 |
| 9-163 |
| Cath Lab Unit |
| 24X24X11½ HEPA |
| 2 |
| Penthouse-A Core |
| PHA-1 |
| AHU-7 |
| 24X24X2 |
| 20 |
| PHA-1 |
| TBEF-2 HEPA Exhaust |
| 24X24X2 |
| 2 |
| PHA-1 |
| TBEF-2 HEPA Exhaust |
| 24X24X11½ HEPA |
| 2 |
| PHA-1 |
| TBEF-5 HEPA Exhaust |
| 24X24X2 |
| 1 |
| PHA-1 |
| TBEF-5 HEPA Exhaust |
| 24X24X11½ HEPA |
| 1 |
| PHA-1 |
| TBEF-7 HEPA Exhaust… |
| 24X24X2 |
| 4 |
| PHA-1 |
| TBEF-7 HEPA Exhaust… |
| 24X24X11½ HEPA |
| 4 |
| Penthouse-A East Side |
| PHA-3 |
| AHU-2 |
| 16X20X2 |
| 6 |
| PHA-3 |
| AHU-2 |
| 12X24X12 merv-11 |
| 2 |
| PHA-3 |
| AHU-2 |
| 20X20X12 merv-11 |
| 3 |
| PHA-3 |
| AHU-5 |
| 12X24X12 merv-11 |
| 3 |
| PHA-3 |
| AHU-5 |
| 20X24X12 merv-11 |
| 6 |
| Penthouse-A West Side |
| PHA-4 |
| AHU-3 |
| 12X24X2 |
| 5 |
| PHA-4 |
| AHU-3 |
| 12X24X11.5 merv-11 |
| 4 |
| PHA-4 |
| AHU-3 |
| 24X24X11.5 merv-11 |
| 20 |
| Penthouse-B Core |
| PHA-2B |
| AC Unit 5 |
| 18X24X2 |
| 3 |
| PHA-2B |
| AC Unit 6 |
| 18X24X2 |
| 3 |
| PHB-9 |
| AC Unit 1 |
| 18X24X1 |
| 4 |
| PHB-9 |
| AC Unit 1 |
| 24X24X2 |
| 2 |
| PHB-9 |
| AC Unit 2 |
| 18X24X1 |
| 4 |
| PHB-9 |
| AC Unit 2 |
| 24X24X2 |
| 2 |
| Penthouse-B East Side |
| PHB-2 |
| AC Unit 3 |
| 18X24X1 |
| 4 |
| PHB-2 |
| AC Unit 3 |
| 24X24X2 |
| 2 |
| PHB-3 |
| AHU-4 |
| 20X24X12 merv-11 |
| 4 |
| PHB-3 |
| AHU-4 |
| 20X20X12 merv-11 |
| 2 |
| Penthouse-B West Side |
| PHB-6 |
| AC Unit 4 |
| 18X24X1 |
| 4 |
| PHB-6 |
| AC Unit 4 |
| 24X24X2 |
| 2 |
| PHB-4 |
| AHU-6 |
| 24X24X11.5 merv-11 |
| 12 |
Penthouse Roof East Side
| AHU-1 |
| 12X24X12 MERV-11 |
| 14 |
| AHU-1 |
| 24X24X12 MERV-11 |
| 12 |
Penthouse Roof West Side
Building 5A:
Building 6:
| 6-01C |
| Paint Shop AHU |
| 18X22X2 |
| 2 |
| Building 7: |
| B-level |
| B-138 |
| AHU-E-Preheat |
| 20X20X2 |
| 4 |
Lower Roof
Upper Roof
| HR – D |
| No filters. Wash coil as needed |
| N/A |
| HR - E |
| No filters. Wash coil as needed |
| N/A |
Penthouse
Building 11:
| B-104A |
| AHU-1 |
| 12X24X12…85%. |
| 2 |
| B-104A |
| AHU-1 |
| 24X24X12…85% |
| 1 |
| B-103A |
| AHU-2 |
| 24X24X12…85% |
| 4 |
Building 15:
Building 15A:
Building 15B:
Building 18:
| 18-112 |
| Air Purifier 1 |
| 20X24X4 |
| 1 |
| 18-112 |
| Air Purifier 1 |
| 20X24X11½ HEPA |
| 1 |
| 18-132 |
| Air Purifier 2 |
| 20X24X4 |
| 1 |
| 18-132 |
| Air Purifier 2 |
| 20X24X11½ HEPA |
| 1 |
| 18-154B |
| 132AHU-3 |
| 29X29X2 |
| 2 |
| 18-101 corridor |
| AHU-4 |
| 12X30X1 |
| 1 |
| 18-138A corridor |
| AHU-5 |
| 12X30X1 |
| 1 |
Building 24:
Most air handlers will use UL Class 2 standard capacity merv-7 or 8 pleated air filters. Air handlers 33, 34, 35, SPS, Endoscopy and Dental will use High capacity Merv-11 pleated air filters. Rigid cell box filters will be UL class 2 merv-11 air filters. HEPA filters will be UL class 1, hospital grade air filters.
COR-kept air filters will be UL class 2, merv-13 air filters.
A.3.1.2 QUARTERLY PREVENTATIVE MAINTENANCE SERVICES
A) The contractor shall provide the facility with a schedule detailing which pieces of equipment shall be serviced on what days at least one week before commencing quarterly preventative maintenance services. Changes to the schedules shall coordinated with the facility at least one business day in advance.
B) Before commencing work on a given day, VA personnel shall turn of the power to units being serviced using proper lock-out and tag-out procedures of the power supply will apply for V.A. and contractor personnel in accordance with NFPA 70E Standard for Electrical Safety in the Workplace.
C) The contractor shall perform the following tasks on the equipment listed in Table 1
1. Remove and dispose of all pre-filters on all Air Handling Units, Package Units, Air conditioning units and HEPA exhaust units.
2. Remove, wash, air dry and re-install washable air filters when applicable.
3. Remove and dispose of after-filters where applicable excluding HEPA Filters.
4. Inspect coils for cleanliness.
5. Wash or vacuum coils as needed.
6. Install new pre filters.
7. Install new after filters.
8. Lubricate bearings on motors and squirrel cage shaft bearings.
9. Clean grease fittings.
10. Inspect condition of belts and replace or adjust belts as necessary.
11. Install drain pan treatment and conditioner (Anti clog ATC or equivalent, Anti clog FTC or equivalent, Neutronic deodorant or equivalent and Slime Buster or equivalent)
12. Coordinate with VA personnel to remove lock-out tag-out and turn equipment back on.
D) The following Air Handlers (AHU-34, 35, SPS and AHU-1D) cannot be serviced during normal working hours. Special arrangements through the COR/Utility Shop Foreman shall be made to service these units after normal working hours or on weekends.
A.3.1.2 SEMI-ANNUAL PREVENTATIVE MAINTENANCE SERVICES
A) The Contractor shall replace belts on AHU #34, 35, SPS and Endoscopy Units – Regardless of condition.
A.3.1.3 ANNUAL PREVENTATIVE MAINTENANCE SERVICES
A) Provide all services listed in section A.3.1.2 QUARTERLY PREVENTATIVE MAINTENANCE SERVICES in addition to the following tasks:
1. Remove and dispose of all HEPA filters on the third quarter of the government fiscal year.
2. Install new HEPA filters.
3. Winterize all water filled chill water coils. The COR will determine the timing for the winterization based on the weather forecast and also which coils will be exempt from winterizing. To winterize coils, the following guideline will generally apply:
a. Close chilled water supply and return valves to the coil.
b. Open drain line and vent and drain the water to the nearest drain.
c. Connect hoses to drain line, vent, container of glycol and a pump in order to circulate Propylene Glycol throughout the coil. Freeze protection of glycol must be at least -20° F. Circulate the glycol through the coil for at least ten minutes to ensure all areas of the coil are saturated.
d. When circulation of the glycol is completed, drain the coil by reclaiming the glycol for use on the next coil.
e. Leave drain and vent valves in the open position.
f. Test the reclaimed glycol before using on the next coil to ensure protection against freezing to at least -40 F. Adjust concentration of glycol as necessary.
g. Clean up any spill that occurred during winterization.
h. Report to COR/Utility Shop Foreman if any valve does not positively stop the flow of chilled water to the coil being winterized.
1) Utility shop personnel shall reactivate the coil if and when needed and re-winterize if necessary
i. Replace all belts, regardless of condition.
B) The air handling units to be winterized shall be listed below in Table 2.
Table 2.
Units to be Serviced
AHU-1
AHU-2
AHU-3
AHU-4
AHU-5
AHU-6
AHU-7
AHU-8
AHU-9
AHU-10
AHU-10A
AHU-11
AHU-11A
AHU-12
AHU-13
AHU-Linen Room
AHU-A-level Lab
AHU-17
AHU-33
AHU-34
AHU-35
AHU-Director
AHU-2D
AHU-Museum
AHU-Endoscopy
AHU-Audiology
AHU-5C
AHU-Echo-Lab
AHU-SPS
AHU-Chaplin
AHU-Dental
C) In the month of July, unless instructed otherwise by COR, the contractor shall drain all glycol heating systems into containers for reuse. Inspect glycol for reusability and replace if necessary. Chemically clean each system following manufactures recommendations. Drain chemically treated water and refill using saved or new propylene glycol. Add glycol as necessary to maintain a 30% glycol and 70% water mix. Strainers that are affected on the air handlers of each glycol heating system shall be removed, cleaned and reinstalled.
D) The Glycol systems and their related air handler that shall be cleaned are listed in Table 3. below.
Table 3
| Building |
| System |
| Sub-units |
| Building 1: |
| O.R. system…C-level |
| AHU-17 |
| O.R. system…C-level |
| AHU-33 |
| O.R. system…C-level |
| AHU-34 |
| O.R. system…C-level |
| AHU-35 |
| P13 & 14 system…C-level |
| AHU-9 |
| P13 & 14 system…C-level |
| AHU-10 |
| P13 & 14 system…C-level |
| AHU-10A |
| P13 & 14 system…C-level |
| AHU-11 |
| 5C system…C-level (two systems) |
| AHU-5C |
| Radiology system…A-236E |
| AHU-1D |
| Echo lab system…6-208B |
| AHU Echo lab |
| Penthouse system…Penthouse A core |
| AHU-1 |
| Penthouse system…Penthouse A core |
| AHU-2 above. |
| Penthouse system…Penthouse A core |
| AHU-3 |
| Penthouse system…Penthouse A core |
| AHU-4 |
| Penthouse system…Penthouse A core |
| AHU-5 |
| Penthouse system…Penthouse A core |
| AHU-6 |
| Chemo Lab system…Penthouse A core |
| New chemo lab AHU |
Building 15:
AHU-1…bldg. 15 machine room
AHU-2…bldg. 15 machine room
Building 18:
AHU-1…bldg. 18 ceiling
AHU-2…bldg. 18 ceiling
AHU-3…bldg. 18 ceiling
AHU-4…bldg. 18 ceiling
AHU-5…bldg. 18 ceiling
E) Building 15 and 18 glycol cooling systems shall to be done in January. These units are co-located with the air handling units listed in table 3 above.
A.3.2 PREVENTATIVE MAINTENANCE SERVICES FOR AIR HANDLING UNITS LOCATED AT Lyons CAMPUS OF THE NEW JERSEY VA HEALTHCARE SYSTEM A.3.2.1 General A) The contractor shall provide all labor, personnel, supervision, equipment, tools, and all materials (filters and belts) necessary to perform preventative maintenance on the air handling units, air conditioners and filtered exhaust systems (non-filtered exhaust systems are not included in this scope of work) as defined in this Performance Work Statement (PWS).
B) All work shall be performed during the hours of 8:00 AM to 4:00 PM, Monday thru Saturday excluding Federal Holidays (defined as: New Year's Day, Birthday of Martin Luther King, Jr., Washington's Birthday, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day and Christmas Day) unless noted within PM procedures below.
C) Preventative maintenance services shall follow the following schedule:
1. Quarterly services shall occur in the months of November, February, May and August
2. Annual services shall occur in the month of May.
D) Upon arrival to the Lyons VA Medical Campus, HVAC Technicians shall report to HVAC Shop Foreman, Bldg. 136, Ext. 4845.
E) Upon completion of tasks described under section A.3.2 PREVENTATIVE MAINTENANCE SERVICES FOR AIR HANDLING UNITS LOCATED AT THE LYONS CAMPUS OF THE NEW JERSEY VA HEALTHCARE SYSTEM the contractor shall provide a copy of service report to the COR. Service reports shall be signed by both the contractor and COR at completion of work. An electronic version of same shall be sent to the COR. Service reports shall include tasks completed to include areas worked on, number of workers involved and hours worked.
F) Equipment to be serviced under this contract are listed in Table 4. Below.
Table 4.
| Building |
| Location |
| Equipment identification |
| Filter Size/ type |
| Quantity |
| Bldg. #3 |
| Mech. Rm S230 |
| AHU-1 |
| 24 x 24 x 4/4" Perfect Pleat |
| 6 |
| Mech. Rm S230 |
| AHU-1 |
| 12 x 24 x 4/4" Perfect Pleat |
| 2 |
| Mech. Rm S230 |
| AHU-1 |
| 24 x 24 x 15 - 6P/DriPak2000 - 90-95% |
| 6 |
| Mech. Rm S230 |
| AHU-1 |
| 12 x 24 x 15 - 3P/DriPak2000 - 90-95% |
| 2 |
| Mech. Rm S207 |
| AHU-2 |
| 24 x 24 x 4/4" Perfect Pleat |
| 6 |
| Mech. Rm S207 |
| AHU-2 |
| 12 x 24 x 4/4" Perfect Pleat |
| 2 |
| Mech. Rm S207 |
| AHU-2 |
| 24 x 24 x 15 - 6P/DriPak2000 - 90-95% |
| 6 |
| Mech. Rm S207 |
| AHU-2 |
| 12 x 24 x 15 - 3P/DriPak2000 - 90-95% |
| 2 |
| AHU-3 |
| 24 x 24 x 4/4" Perfect Pleat |
| 9 |
| AHU-3 |
| 24 x 24 x 15 - 6P/DriPak2000 - 90-95% |
| 9 |
| AHU-4 |
| 24 x 24 x 4/4" Perfect Pleat |
| 9 |
| AHU-4 |
| 24 x 24 x 15 - 6P/DriPak2000 - 90-95% |
| 9 |
| AHU-5 |
| 24 x 24 x 4/4" Perfect Pleat |
| 9 |
| AHU-5 |
| 24 x 24 x 15 - 6P/DriPak2000 - 90-95% |
| 9 |
| AHU-6 |
| 24 x 24 x 4/4" Perfect Pleat |
| 2 |
| AHU-6 |
| 24 x 24 x 4/4" Perfect Pleat |
| 2 |
| AHU-6 |
| 24 x 24 x 15 - 6P/DriPak2000 - 90-95% |
| 2 |
| AHU-6 |
| 24 x 24 x 15 - 6P/DriPak2000 - 90-95% |
| 2 |
| FCU-1 |
| 16 x 25 x 2/2" Perfect Pleat |
| 4 |
| FCU-1 |
| 20 x 25 x 2/2" Perfect Pleat |
| 2 |
| FCU-2 |
| 16 x 25 x 2/2" Perfect Pleat |
| 4 |
| FCU-2 |
| 20 x 25 x 2/2" Perfect Pleat |
| 2 |
| Bldg. #4 |
| Roof |
| AC-1 |
| 16 x 25 x 4/4" Perfect Pleat |
| 2 |
| Roof |
| AC-1 |
| 20 x 25 x 4/4" Perfect Pleat |
| 7 |
| Roof |
| AC-1 |
| 20 x20 x 4/4" Perfect Pleat |
| 2 |
| Roof |
| AC-1 |
| 20 x 24 x 15 - 6P/DriPak2000 - 90-95% |
| 4 |
| Roof |
| AC-1 |
| 20 x 20 x 15 - 6P/DriPak2000 - 90-95% |
| 6 |
| Roof |
| AC-2 |
| 16 x 20 x 4/4" Perfect Pleat |
| 5 |
| Roof |
| AC-2 |
| 20 x 25 x 4/4" Perfect Pleat |
| 1 |
| Roof |
| AC-2 |
| 20 x 24 x 15 - 6P/DriPak2000 - 90-95% |
| 2 |
| Roof |
| AC-2 |
| 12 x 24 x 15 - 4P/DriPak2000 - 90-95% |
| 2 |
| Attic |
| AC-3 |
| 16 x 20 x 4/4" Perfect Pleat |
| 7 |
| Attic |
| AC-3 |
| 16 x 25 x 4/4" Perfect Pleat |
| 7 |
| Bldg. #7 |
| Attic |
| EF-1 |
| 24 x 24 x 4/4" Perfect Pleat |
| 8 |
| Attic |
| AH-1 |
| 20 x 24 x 4/4" Perfect Pleat |
| 2 |
| Attic |
| AH-1 |
| 24 x 24 x 2/2" Perfect Pleat |
| 8 |
| Attic |
| AH-1 |
| 20 x 24 x 2/2" Perfect Pleat |
| 2 |
| Basement |
| SF-1 |
| 24 x 24 x 15 - 6P/DriPak2000 - 90-95% |
| 8 |
| Basement |
| SF-1 |
| 12 x 24 x 15 - 4P/DriPak2000 - 90-95% |
| 2 |
| Basement |
| SF-1 |
| 24 x 24 x 2/2" Perfect Pleat |
| 8 |
| Basement |
| SF-1 |
| 12 x 24 x 2/2" Perfect Pleat |
| 2 |
| Basement |
| AH-2 |
| 12 x 24 x 4/4" Perfect Pleat |
| 4 |
| Basement |
| AH-2 |
| 24 x 24 x 4/4" Perfect Pleat |
| 8 |
| Basement |
| AH-2 |
| 20 x 24 x 4/4" Perfect Pleat |
| 2 |
| Basement |
| AH-2 |
| 12 x 24 x 2/2" Perfect Pleat |
| 4 |
| Basement |
| AH-2 |
| 24 x 24 x 2/2" Perfect Pleat |
| 8 |
| Basement |
| AH-2 |
| 20 x 24 x 2/2" Perfect Pleat |
| 2 |
| MER |
| SF-2 |
| 24 x 24 x 15 - 6P/DriPak2000 - 90-95% |
| 10 |
| MER |
| SF-2 |
| 12 x 24 x 15 - 4P/DriPak2000 - 90-95% |
| 7 |
| Building #53 |
| MER 11 Basement |
| AHU-1 |
| 16 x 20 x4/4" Perfect Pleat |
| 2 |
| MER 11 Basement |
| AHU-1 |
| 16 x 25 x 4/4" Perfect Pleat |
| 3 |
| MER 11 Basement |
| AHU-1 |
| 20 x 20 x 4/4" Perfect Pleat |
| 6 |
| MER 11 Basement |
| AHU-1 |
| 20 x 25 x 4/4" Perfect Pleat |
| 4 |
| MER 11 Basement |
| AHU-1 |
| 24 x 24 x 15 - 6P/DriPak2000 - 90-95% |
| 8 |
| MER 11 Basement |
| AHU-1 |
| 12 x 24 x 15 - 3P/DriPak2000 - 90-95% |
| 2 |
| Left - Attic |
| AHU-2 |
| 16 x 25 x 4/4" Perfect Pleat |
| 14 |
| Left - Attic |
| AHU-2 |
| 24 x 24 x 15 - 6P/DriPak2000 - 90-95% |
| 8 |
| Left - Attic |
| AHU-2 |
| 12 x 24 x 15 - 3P/DriPak2000 - 90-95% |
| 2 |
| Attic |
| EF-2 & EF-3 |
| 16 x 25 x 4/4" Perfect Pleat |
| 28 |
| Right - Attic |
| AH-3 |
| 16 x20 x 4/4" Perfect Pleat |
| 3 |
| Right - Attic |
| AH-3 |
| 20 x 20 x 4/4" Perfect Pleat |
| 15 |
| Right - Attic |
| AH-3 |
| 24 x 24 x 15 - 6P/DriPak2000 - 90-95% |
| 10 |
| Right - Attic |
| AH-3 |
| 12 x 24 x 15 - 3P/DriPak2000 - 90-95% |
| 2 |
| Building #54 |
| Mech Rm 8 |
| AC -1 |
| 16 x 20 x 2/2" Perfect Pleat |
| 1 |
| Mech Rm 8 |
| AC -1 |
| 20 x 25 x 2/2" Perfect Pleat |
| 4 |
| Mech Rm 8 |
| AC -1 |
| 20 x 20 x 2/2" Perfect Pleat |
| 1 |
| Mech Rm 8 |
| AC -1 |
| 16 x 25 x 2/2" Perfect Pleat |
| 6 |
| Mech Rm 8 |
| AC-2 |
| 16 x 25 x 2/2" Perfect Pleat |
| 1 |
| Mech Rm 8 |
| AC-2 |
| 16 x 20 x 2/2" Perfect Pleat |
| 1 |
| Mech Rm 8 |
| AC-3 |
| 20 x 25 x 2/2" Perfect Pleat |
| 2 |
| Mech Rm 8 |
| AC-3 |
| 16 x 25 x 2/2" Perfect Pleat |
| 2 |
| Mech Rm 8 |
| AC-3 |
| 16 x 20 x 2/2" Perfect Pleat |
| 1 |
| Building #57 |
| Basement MER9 |
| SF-1 |
| 24 x 24 x 2/2" Perfect Pleat |
| 8 |
| Basement MER9 |
| SF-1 |
| 18 x 24 x 2/2" Perfect Pleat |
| 2 |
| Basement MER9 |
| SF-1 |
| 24 x 24 x 15 - 6P/DriPak2000 - 90-95% |
| 8 |
| Basement MER9 |
| SF-1 |
| 12 x 24 x 15 - 4P/DriPak2000 - 90-95% |
| 2 |
| AH-2 |
| 18 x 24 x 4/4" Perfect Pleat |
| 2 |
| AH-2 |
| 24 x 25 x 4/4" Perfect Pleat |
| 12 |
| Basement MER9 |
| SF-2 |
| 24 x 24 x 2/2" Perfect Pleat |
| 8 |
| Basement MER9 |
| SF-2 |
| 12 x 24 x 2/2" Perfect Pleat |
| 6 |
| Basement MER9 |
| SF-2 |
| 24 x 24 x 15 - 6P/DriPak2000 - 90-95% |
| 8 |
| Basement MER9 |
| SF-2 |
| 12 x 24 x 15 - 3P/DriPak2000 - 90-95% |
| 6 |
| Attic |
| EF-1, EF-2 & EF-3 |
| 24 x 24 x 4/4" Perfect Pleat |
| 18 |
| Building #143 |
| Mech Rm E104 |
| SF-2 |
| 20 x 25 x 4/4" Perfect Pleat |
| 16 |
| Mech Rm E104 |
| SF-2 |
| 24 x 24 x 15 - 6P/DriPak2000 - 90-95% |
| 10 |
| Mech Rm E104 |
| SF-2 |
| 12 x 24 x 15 - 3P/DriPak2000 - 90-95% |
| 5 |
| Mech Rm W105 |
| SF-1 |
| 20 x 25 x 4/4" Perfect Pleat |
| 18 |
| Mech Rm W105 |
| SF-1 |
| 20 x 20 x 4/4" Perfect Pleat |
| 2 |
| Mech Rm W105 |
| SF-1 |
| 24 x 24 x 15 - 6P/DriPak2000 - 90-95% |
| 10 |
| Mech Rm W105 |
| SF-1 |
| 20 x 24 x 15 - 5P/DriPak2000 - 90-95% |
| 7 |
| Mech Rm W105 |
| SF-7 |
| 20 x 25 x 4/4" Perfect Pleat |
| 2 |
| 3rd Flr. MER |
| SF -5 |
| 16 x 20 x 4/4" Perfect Pleat |
| 3 |
| 3rd Flr. MER |
| SF -5 |
| 16 x 25 x 4/4" Perfect Pleat |
| 4 |
| 3rd Flr. MER |
| SF -5 |
| 20 x 20 x 4/4" Perfect Pleat |
| 6 |
| 3rd Flr. MER |
| SF -5 |
| 20 x 25 x 4/4" Perfect Pleat |
| 4 |
| 3rd Flr. MER |
| SF -5 |
| 24 x 24 x 15 - 6P/DriPak2000 - 90-95% |
| 8 |
| 3rd Flr. MER |
| SF -5 |
| 12 x 24 x 15 - 3P/DriPak2000 - 90-95% |
| 6 |
| 3rd Flr. MER |
| SF-6 |
| 20 x 25 x 4/4" Perfect Pleat |
| 18 |
| 3rd Flr. MER |
| SF-6 |
| 20 x 20 x 4/4" Perfect Pleat |
| 2 |
| 3rd Flr. MER |
| SF-6 |
| 24 x 24 x 15 - 6P/DriPak2000 - 90-95% |
| 10 |
| 3rd Flr. MER |
| SF-6 |
| 20 x 20 x 15 - 5P/DriPak2000 - 90-95% |
| 7 |
| 3rd Flr. MER |
| SF-6 |
| 20 x 24 x 15 - 3P/DriPak2000 - 90-95% |
| 2 |
| Mech Rm N107 |
| SF-3 |
| 20 x 24 x 4/4" Perfect Pleat |
| 6 |
| Mech Rm N107 |
| SF-3 |
| 20 x 20 x 4/4" Perfect Pleat |
| 4 |
| Mech Rm N107 |
| SF-3 |
| 16 x 20 x 4/4" Perfect Pleat |
| 3 |
| Mech Rm N107 |
| SF-3 |
| 16 x 25 x 4/4" Perfect Pleat |
| 2 |
| Mech Rm N107 |
| SF-3 |
| 24 x 24 x 15 - 6P/DriPak2000 - 90-95% |
| 8 |
| Mech Rm N107 |
| SF-3 |
| 12 x 24 x 15 - 3P/DriPak2000 - 90-95% |
| 6 |
| Mech Rm N107 |
| SF-4 |
| 20 x 20 x 4/4" Perfect Pleat |
| 4 |
| Mech Rm N107 |
| SF-4 |
| 20 x 24 x 4/4" Perfect Pleat |
| 6 |
| Mech Rm N107 |
| SF-4 |
| 16 x 20 x 4/4" Perfect Pleat |
| 3 |
| Mech Rm N107 |
| SF-4 |
| 16 x 25 x 4/4" Perfect Pleat |
| 2 |
| Mech Rm N107 |
| SF-4 |
| 24 x 24 x 15 - 6P/DriPak2000 - 90-95% |
| 8 |
| Mech Rm N107 |
| SF-4 |
| 12 x 24 x 15 - 3P/DriPak2000 - 90-95% |
| 6 |
| Building 135 |
| Main Tower A |
| SF-4 & RF-4 |
| 12 x 24 x 2/2" Perfect Pleat |
| 10 |
| Main Tower A |
| SF-4 & RF-4 |
| 24 x 24 x 2/2" Perfect Pleat |
| 20 |
| Main Tower A |
| SF-4 |
| 12 x 24 x 15 - 3P/DriPak2000 - 90-95% |
| 5 |
| Main Tower A |
| SF-4 |
| 24 x 24 x 15 - 6P/DriPak2000 - 90-95% |
| 10 |
| Main Tower A |
| SF-4 |
| 12 x 24 x 15 - 3P/DriPak2000 - 90-95% |
| 5 |
| Main Tower A |
| SF-4 |
| 24 x 24 x 15 - 6P/DriPak2000 - 90-95% |
| 10 |
| Main Tower A |
| SF-3 & RF-1 |
| 24 x 24 x 2/2" Perfect Pleat |
| 36 |
| Main Tower A |
| SF-3 |
| 24 x 24 x 15 - 6P/DriPak2000 - 90-95% |
| 36 |
| Main Tower B |
| SF-1 |
| 12 x 24 x 2/2" Perfect Pleat |
| 5 |
| Main Tower B |
| SF-1 |
| 24 x 24 x 2/2" Perfect Pleat |
| 10 |
| Main Tower B |
| SF-1 |
| 12 x 24 x 15 - 3P/DriPak2000 - 90-95% |
| 5 |
| Main Tower B |
| SF-1 |
| 24 x 24 x 15 - 6P/DriPak2000 - 90-95% |
| 10 |
| Main Tower B |
| RF-1 |
| 24 x 24 x 2/2" Perfect Pleat |
| 9 |
| Main Tower B |
| RF-1 |
| 24 x 24 x 15 - 6P/DriPak2000 - 90-95% |
| 9 |
| Main Tower C |
| SF-2 |
| 12 x 24 x 2/2" Perfect Pleat |
| 5 |
| Main Tower C |
| SF-2 |
| 24 x 24 x 2/2" Perfect Pleat |
| 10 |
| Main Tower C |
| SF-2 |
| 12 x 24 x 15 - 3P/DriPak2000 - 90-95% |
| 5 |
| Main Tower C |
| SF-2 |
| 24 x 24 x 15 - 6P/DriPak2000 - 90-95% |
| 10 |
| Main Tower C |
| RF-2 |
| 24 x 24 x 2/2" Perfect Pleat |
| 9 |
| Main Tower C |
| RF-2 |
| 24 x 24 x 15 - 6P/DriPak2000 - 90-95% |
| 9 |
| Building 9 |
| police station |
| AHU-1 |
| 16 x 24 x 2/2" Perfect Pleat |
| 4 |
| police station |
| AHU-1 |
| 24 x 24 x 2/2" Perfect Pleat |
| 2 |
| police station |
| AHU-1 |
| 12 x 24 x 2/2" Perfect Pleat |
| 2 |
| Building 1 |
| SPD |
| AHU -1 |
| 16 x 25 x 2/2" Perfect Pleat |
| 2 |
| SPD |
| AHU -1 |
| 20 x 25 x 2/2" Perfect Pleat |
| 4 |
| SPD |
| AHU -1 |
| 20 x 24 x 15 - 6P/DriPak2000 - 90-95% |
| 3 |
| SPD |
| AHU -2 |
| 16 x 25 x 2/2" Perfect Pleat |
| 6 |
| SPD |
| AHU -2 |
| 20 x 25 x 2/2" Perfect Pleat |
| 4 |
Blood Bank Package Unit
| 20 x 20 x 2/2" Perfect Pleat |
| 4 |
| Employee Health AC 1 |
| AHU-1 above ceiling |
| 16 x 25 x 2/2" Perfect Pleat |
| 4 |
| Building 6 |
| Dental |
| AHU -1 |
| 16 x 20 x 2/2" Perfect Pleat |
| 9 |
| Dental |
| AHU- 2 |
| 16 x 20 x 1/1" Perfect Pleat |
| 6 |
| Building 2 |
| Morgue |
| AHU-1 |
| 16 x 20 x 4/4" Perfect Pleat |
| 1 |
| Morgue |
| AHU-1 |
| 16 x 16 x 4/4" Perfect Pleat |
| 1 |
| Record Room |
| AHU-1 |
| 16 x 25 x 1/1" Perfect Pleat |
| 2 |
| Record Room |
| AHU-1 |
| 20 x 25 x 1/1" Perfect Pleat |
| 1 |
| Building 5 |
| Gym |
| AHU -1 |
| 16 x 20 x 1/1" Perfect Pleat |
| 6 |
| Gym |
| AHU -2 |
| 16 x 20 x 1/1" Perfect Pleat |
| 6 |
| Building 1 |
| Xray |
| AHU - 1 |
| 16 x 16 x 1/1" Perfect Pleat |
| 6 |
| Xray |
| AHU - 2 |
| 20 x 25 x 1/1" Perfect Pleat |
| 1 |
A.3.2.2 QUARTERLY PREVENTATIVE MAINTENANCE SERVICES
A) The contractor shall provide the facility with a schedule detailing which pieces of equipment shall be serviced on what days at least one week before commencing quarterly preventative maintenance services. Changes to the schedules shall coordinated with the facility at least one business day in advance.
B) Before commencing work on a given day, VA personnel shall turn of the power to units being serviced using proper lock-out and tag-out procedures of the power supply will apply for V.A. and contractor personnel in accordance with NFPA 70E Standard for Electrical Safety in the Workplace.
C) The contractor shall perform the following tasks on the equipment listed in Table 4.
1. Remove and dispose of all pre-filters on all Air Handling Units, Package Units, Air conditioning units and HEPA exhaust units.
2. Remove, wash, air dry and re-install washable air filters when applicable.
3. Remove and dispose of after-filters where applicable excluding HEPA Filters.
4. Inspect coils for cleanliness.
5. Wash or vacuum coils as needed.
6. Install new pre filters.
7. Install new after filters.
8. Lubricate bearings on motors and squirrel cage shaft bearings.
9. Clean grease fittings.
10. Inspect condition of belts and replace or adjust belts as necessary.
11. Install drain pan treatment and conditioner (Anti clog ATC or equivalent, Anti clog FTC or equivalent, Neutronic deodorant or equivalent and Slime Buster or equivalent)
12. Coordinate with VA personnel to remove lock-out tag-out and turn equipment back on.
D) The following Air Handlers (AHU-34, 35, SPS and AHU-1D) cannot be serviced during normal working hours. Special arrangements through the COR/Utility Shop Foreman shall be made to service these units after normal working hours or on weekends.
A.3.2.2 ANNUAL PREVENTATIVE MAINTENANCE SERVICES
A) Provide all services listed in section A.3.1.2 QUARTERLY PREVENTATIVE MAINTENANCE SERVICES in addition to the following tasks:
1. Remove and dispose of all HEPA filters on the third quarter of the government fiscal year.
2. Install new HEPA filters.
3. Winterize all water filled chill water coils. The COR will determine the timing for the winterization based on the weather forecast and also which coils will be exempt from winterizing. To winterize coils, the following guideline will generally apply:
a. Close chilled water supply and return valves to the coil.
b. Open drain line and vent and drain the water to the nearest drain.
c. Connect hoses to drain line, vent, container of glycol and a pump in order to circulate Propylene Glycol throughout the coil. Freeze protection of glycol must be at least -20° F. Circulate the glycol through the coil for at least ten minutes to ensure all areas of the coil are saturated.
d. When circulation of the glycol is completed, drain the coil by reclaiming the glycol for use on the next coil.
e. Leave drain and vent valves in the open position.
f. Test the reclaimed glycol before using on the next coil to ensure protection against freezing to at least -40 F. Adjust concentration of glycol as necessary.
g. Clean up any spill that occurred during winterization.
h. Report to COR/Utility Shop Foreman if any valve does not positively stop the flow of chilled water to the coil being winterized.
1) Utility shop personnel shall reactivate the coil if and when needed and re-winterize if necessary
i. Replace all belts, regardless of condition.