PWS_636-26-305 Correct Parking Garage Safety Deficiencies.docx
DOCX document 255 KB Posted
- Attached to
- Y1DZ--PN: 636-26-305 Correct Parking Garage Safety Deficiencies (OM) 2237: 636-26-3-5297-0001
- Solicitation number
- 36C26326R0030
About this file
This is a Performance Work Statement (PWS) for Project 636-26-305, which requires a Design-Build Team to develop and install a dry-pipe fire suppression system and jump prevention barriers in the parking garage at the Omaha Veterans Affairs Medical Center under the Nebraska-Western Iowa Health Care System.
The Design-Build Contractor must provide an integrated team including licensed architects, engineers, and construction professionals with expertise in architectural, civil, structural, mechanical/plumbing, electrical, fire protection, and environmental design. Key objectives include: (1) installation of nitrogen-filled standpipe and dry-pipe fire sprinkler systems providing 100% coverage of the existing parking structure (designed to accommodate approximately 900 vehicles and expandable for future project 636-508), compliant with NFPA 1, 13, 14, 24, 25, 72, 101, and 88A standards; (2) connection to the fire main located east of the structure with necessary control systems, valves, pumps, and a fire alarm system compatible with the new SIEMENS system on the Omaha campus; (3) installation of a nitrogen generator system minimizing inspection and maintenance burden; (4) connection to domestic water supply with a new outlet on the northeast side; and (5) installation of jump deterrence barriers on the top level utilizing existing structures without significant aesthetic changes. The design phase shall be completed within 100 calendar days from Notice of Award with deliverables including Schematic Design (35%, day 44), Design Development (65%, day 79), and Construction Documents. Construction shall commence 115 days after Notice of Award and be completed within 120 days of the Notice to Proceed (day 235 total). The Design Team must conduct independent Life Safety/Fire Protection peer review and provide four minimum construction observation site visits. As-Built documents are due 45 days following project completion (day 280). The total contract period of performance is 280 calendar days from contract award. The proposal must include a detailed fee breakdown for schematic design, design documentation, construction documentation, as-built record drawings, and site visits.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance of Work Statement Project Number: 636-26-305 Correct Parking Garage Safety Deficiencies Nebraska-Western Iowa Health Care System Omaha VA Medical Center
1.
1. Background.
This project will require a Design-Build Team to develop and install a dry-pipe fire suppression system and jump prevention barriers in the parking garage at the Omaha Veterans Affairs Medical Center. The design shall incorporate best practices and methods and comply with Veterans Health Administration design guidelines. Barriers shall be consistent with the architecture of the parking garage and shall be mounted to and removable from existing barriers for reinstallation following potential future modifications to the garage.
Successful offeror will be an integrated Design-Build team including Licensed Architects, Engineers, and Construction specialties to complete the scope of work. At minimum, the Design Team will include experienced Architectural, Civil, Structural, Mechanical/Plumbing, Electrical, Fire Protection, and Environmental design professionals. All architects and engineers must be professionally licensed in their field of practice. The fire protection engineer must be qualified and provide all services in accordance with the VA Project Fire Protection Engineer “Qualifications and Scope of Services” document. Separate independent peer review is required for the Life-Safety and Fire Protection elements of this project and shall be provided by the Design-Build Contractor as within the scope of this Performance of Work Statement (PWS).
NOTE:
This Performance of Work Statement (PWS) will refer to the collective Design-Build Team, which includes both Design and Construction, for performance requirements pertaining to the entire scope of work. Where appropriate, Design Team or Construction Team may be used for specificity. All elements of design, construction, and post-construction are included in this PWS.
VA Design Guides, Specifications, and References (current versions).
A complete listing of all VA technical documents can be found on the VA website at https://www.cfm.va.gov/TIL/. These documents shall be referenced as a guide for the completion of this design project. Deviations from these guides must be submitted for review by the VA Office of Healthcare Engineering (OHE). At each submittal, address deviations from guidance with COR/CO to coordinate OHE review process.
All document packages, including the final design/construction documents from a resultant task order will be subject to review and approval (by signature) of all members of an Integrated Project Team (IPT) consisting of individuals identified by the medical center. These individuals will be identified by the VA Contracting Officer’s Representative (COR) at the first design meeting. All document packages, including the final design/construction documents moving forward for construction will be subjected to technical reviews, including third party technical reviews and/or legal reviews. The Design Team is responsible for revising documents to incorporate comments provided by those reviews.
2. Objectives and Technical Requirements.
Design-Build Contractor (Design Team) shall provide stamped/sealed construction documents in accordance with the requirements of Department of Veterans Affairs Program Guide PG-18-15 prior to the construction phase of this project.
Design Services include site visit(s), field investigation, and user interviews to prepare complete construction drawings and specifications to meet the following objectives:
a. Installation of nitrogen-filled standpipe systems and nitrogen-filled dry-pipe fire sprinkler system providing 100% coverage of the exiting parking structure. The sprinkler system shall be designed for expansion during an upcoming minor project, 636-508 – Construct Additional Floor Parking Garage. The completed parking structure will accommodate approximately 900 vehicles.
· The fire suppression system will comply with all requirements listed in the most recent editions of NFPA 1, 13, 14, 24, 25, 72, 101, and 88A, and all other applicable codes and standards.
· Currently, a stand-pipe exists in the parking structure. This project installs a dry-pipe system connected to the fire main located to the east of the parking structure. Connections to the fire main and necessary control systems, valves, and pumps are required for this project. Project shall be phased so that traffic flow is maintained to all levels of the parking garage and no more than 20 spaces are closed at any time.
· Installation of nitrogen generator systems is required, with a focus on minimizing the inspection, testing, and maintenance burden of the nitrogen generation systems.
· The sprinkler system will require a fire pump due to building height. The fire pump and any associated electrical system improvements shall be considered in scope for this project. Fire pump shall be installed at a location and sized to accommodate future planned expansion.
· A new fire alarm system will be required for the parking garage. Alarm equipment shall be compatible with new SIEMENS system installed throughout the Omaha campus.
b. Connection to domestic water supply and installation of a domestic water outlet on the northeast side of the current parking garage structure.
c. Installation of jump deterrence on the top level of the existing structure. Deterrence method shall utilize the existing structure and not significantly change the existing structure, fencing, and architectural aesthetic. Extensions of the existing fencing are an acceptable option, as are the installation of deterrent methods on the existing fencing.
3. Design Services The Design Team shall produce Construction Documents, including drawings and specifications, in accordance with professional architectural/engineering practices, the Performance of Work Statement (PWS) and, where identified, VA criteria. The Design Team is responsible for obtaining the NCS.
The Design Team shall also provide any additional design criteria necessary for project development (supporting calculations, equipment guide list, Design and Construction Procedures, design manuals, signage design, etc.), so that the DB Team can provide construction drawings and specifications.
During design and construction of the project, the Design Team will be required to participate in construction inspections and assist in the review of:
a. Construction Document submittals including specifications and design calculations.
b. Shop Drawings, Product Data, and Samples
c. Test Results, Certificates, and Other Submittals
d. Operation and Maintenance Manuals, Training, Project Record Documents, and Warranties.
Utilize appropriate and/or edited sections of the following VA documents:
a. VA Master Construction Specifications (PG-18-1);
b. VA Design and Construction Procedures (PG-18-3)
c. VA National CAD Standards Details (PG-18-4);
d. VA Seismic Requirements (H-18-8);
e. VHA National CAD Standard Application Guide
Provide design criteria from VA Design Manuals where appropriate and as determined during design, including but not limited to the following:
a. Architectural Design Manual;
b. CPM Design Manual;
c. Electrical Design Manual;
d. Plumbing Design Manual;
e. Site Development Design Manual; and
f. Structural Design Manual.
g. Fire Protection Design Manual
Independent Life Safety/Fire Protection review is required for this project. The Design-Build Contractor shall contract with an independent qualified and registered Professional Fire Protection Engineer or Design Firm not associated with the design of this project to conduct independent peer review of the 65% design submission and the 100% Construction/As-Built Documents. Completion of this review and resolution of any deficiencies identified shall be required for construction notice to proceed and final acceptance of the completed project.
4. Design Deliverables: At each submission, the A/E shall date all material and present the designs on VA standard size drawings that are appropriately labeled, "SCHEMATIC SUBMISSION", “DESIGN DEVELOPMENT SUBMISSION”, OR “CONSTRUCTION DOCUMENT SUBMISSION”, in large block letters above or beside the VA standard drawing title block. In each submission, the A/E shall incorporate the corrections, adjustments, and changes made by VA at the previous review.
All submittals shall meet requirements listed in VA PG 18-15 and be submitted in the digital format requested unless otherwise noted.
a. SCHEMATIC DESIGN [SD-1] SUBMITTAL (35% Documents):
1. Draft narratives, analyses, studies, calculations, and data. Provide documents in Microsoft word format.
2. Schematic Design Development (SD) Drawings Submittal. Provide set in hardcopy and Adobe PDF format.
3. Draft Project Specification in Microsoft Word format.
4. Allow 21 calendar days for VA Review
b. DESIGN DEVELOPMENT [DD-1] SUBMITTAL (65% Documents):
1. Mark-Ups: Report of disposition of marked-up comments or drawings showing corrective action from prior submittal responding to comments
2. Draft narratives, analyses, studies, calculations, and data. Provide documents in Microsoft word format.
3. Design Development (DD) Drawings Submittal. Provide full-sized (Arch C) set in hardcopy and Adobe PDF format.
4. Final Project Specification in Microsoft Word format.
5. Allow 21 calendar days for VA Review.
6. Notice to Proceed with construction will occur upon acceptance of the 65% DD-1 Submittal.
c. CONSTRUCTION DOCUMENTS:
1. Construction documents shall be updated and maintained throughout construction to show the current status of planned and installed elements of construction. Updated drawings shall be provided monthly in digital PDF format to the COR.
d. POST CONSTRUCTION SUBMITTAL/ RECORD DRAWINGS
1. Obtain information in the form of marked-up prints, drawings, and other data certified by the construction contractor documenting changes made during the performance of the work.
2. Review of general accuracy of information submitted and certified by the Contractor.
3. Prepare As-Built drawings and provide digital copies to the COR in .DWG and .PDF format.
4. Provide manufacturer’s data and warranties for all installed equipment.
5. Construction
Construction shall commence with VA issuance of a Notice to Proceed (NTP) upon acceptance of the 65% DD Submittal. Separate NTPs may be issued for sprinkler and jump-deterrence objectives, if the DB contractor and CO agree to do so.
Design Team Construction Period Services (CPS) shall be provided during the entire construction period of performance. Services to be performed under CPS include, but are not limited to the following:
a. Pre-Construction Meeting: The Design Build Team (design and construction) shall attend a pre-construction meeting prior to the start of work.
b. The Design Team shall review submittals, shop drawings, plans, or any other related documentation submitted by the Construction Team for compliance with the construction documents.
c. Weekly Progress Meetings: The Design Build Team Project Leader will attend and record minutes for all meetings related to the construction contract and other meetings as determined by the Contracting Officer Representative (COR).
d. Requests for Information (RFI) Submittals: RFIs shall be resolved by the Design Build Team and coordinated with the COR for final approval. The COR will respond to requests for RFI approval according to the following:
i. Critical – 2 days (Cost and Schedule delays)
ii. Urgent – 7 days (Schedule Delays)
iii. Normal – 14 days
e. The Design Build Team shall provide change order documents, change order cost estimates, contractor proposal evaluations, recommendations and assist the VA in final price determination.
f. The Design Team shall review and recommend approval of the O&M Manual(s).
g. The Design Team shall coordinate any required training with the General Contractor, manufacturers, etc. to ensure that VA personnel are knowledgeable on equipment or systems.
h. The Design Team shall provide at a minimum four (4) Construction observation site visits; minimum visits to include the following:
i. Rough-In Inspection
ii. Final Inspection (generation of a final punch list)
iii. Punch List Completion Inspection
iv. Contractor’s As-Built Drawing Verification
6. Post Construction Services (Record Drawings):
a. Obtain information in the form of as-built drawings, marked-up prints, and other data certified by the construction contractor documenting changes made during the performance of the work. All information provided or gathered will be verified by the Design Team for accuracy and completeness. These drawings and information will then be incorporated into the construction drawings to produce project record drawings.
b. Create electronic copies in AutoCAD format of all files associated with the project.
c. Create as-built construction documents accordance with the VA National CAD Standards Application Guide. Provide all supplemental files, including fonts, plotter configurations, etc., that are required to open and plot drawings. Where drawings were created with an AutoCAD add-on program, save the files so that they can be used with AutoCAD only. Drawings shall be saved such that one file will produce one plot without manipulation of layers.
d. Create electronic PDF files using the most recent version of Adobe Acrobat.
e. Deliver record drawings to the VA no later than 45 days following beneficial occupancy/final acceptance of the site.
7.
8. Period of Performance and Schedule.
Design Phase: The contract Period of Performance for the design phase shall be 100 calendar days from the Notice of Award. Period of Performance for total design and construction is 280 calendar days from Contract Award.
The proposed schedule for Design Build services is as shown below:
| Project Kickoff Meeting |
| Review VA procedures and requirements. |
| Within 14 days of Notice of Award. |
| SD-1 |
| Provide a digital copy |
| 30 days after Initial Design Meeting (44 days after Notice of Award) |
| SD-1 Review Meeting |
| Meeting |
| Within 21 calendar days after VA receipt of SD-1 Submittals (65 days after Notice of Award) |
| DD-1 Submittal (65% Drawings) |
| Provide digital copy along with one full-sized drawing set and one 1/2 -sized drawing set. |
| 14 calendar days after SD-1 Review Meeting (79 days after Notice of Award) |
| DD-1 Review Meeting |
| Meeting |
| 21 calendar days after VA receipt of DD-1 Submittals. (100 days after Notice of Award) |
Notice to Proceed (Construction)
15 calendar days after acceptance of DD1 submittal. (115 days after Notice of Award)
Construction Completion
120 calendar days after Construction Notice to Proceed. (235 days after Notice of Award)
As-Built Documents
45 calendar days after Construction Completion (280 days after Notice of Award)
9. DESIGN FEE SCHEDULE: Proposal Cover Sheet should indicate the breakdown of fees as below:
A/E DESIGN SERVICES
a. Schematic Design
b. Design Documentation
c. Construction documentation
d. Total for Base work under this Contract
e. As-Built Record Drawings
f. Site Visits (each)
10. Additional Information/General Requirements.
The Design Build Contractor(s) shall notify COR of any deviations from this document, referenced guides, manuals, or any other related document used. Approval for deviations requires a review by the Office of Healthcare Engineering. Coordinate submission requirements for deviation requests with CO/COR
a. Confidentiality and Nondisclosure: It is agreed that:
· The preliminary and final deliverables, and all associated working papers, application source code, and other material deemed relevant by VA which have been generated by the contractor in the performance of this task order, are the exclusive property of the U.S. Government and shall be submitted to the CO at the conclusion of the task order.
· The CO will be the sole authorized official to release, verbally or in writing, any data, draft deliverables, final deliverables, or any other written or printed materials pertaining to this task order. No information shall be released by the contractor. Any request for information relating to this task order, presented to the contractor, shall be submitted to the CO for response.
· Press releases, marketing material, or any other printed or electronic documentation related to this project, shall not be publicized without the written approval of the CO.
· Upon request and if available, any existing campus plans, inspections, directives, etc. will be provided by the VA for use in completing the design. The VA does not guarantee the accuracy and completeness of any of the data provided and Design Team shall investigate and verify the accuracy of documents that impact the design in a manner that has a direct bearing on both the design and the cost of construction.
b. Meetings and Conferences: The Design Team shall be responsible for attending and having appropriate representation for all design review meetings and conferences held with the VA during design services and construction period services. At a minimum, during design services, a kick-off meeting will be held virtually and a review session for each design development stage. Design Team is responsible for providing “action-taken” comments to design review comments provided by the VA. During CPS, at a minimum, weekly progress meetings will be held for discussion of the ongoing construction project and the Design Team shall be prepared to provide guidance on construction documents, RFI’s, submittals, etc. The Design Team shall be responsible for recording and distributing all meeting minutes within two (2) calendar days of the meeting or conference. All documentation shall be in PDF format.
c. The Design-Build Team will be required to comply with any training requirements as necessary. Currently, course number TMS 20939—VA Privacy Training for Personnel without Access to VA Computer Systems or Direct Access to or the Use of VA Sensitive Information is required. Employees will be required to sign documentation acknowledging that the training has been completed.
11. Records Management:
a. Contractor shall comply with all applicable records management laws and regulations, as well as National Archives and Records Administration (NARA) records policies, including but not limited to the Federal Records Act (44 U.S.C. chs. 21, 29, 31, 33), NARA regulations at 36 CFR Chapter XII Subchapter B, and those policies associated with the safeguarding of records covered by the Privacy Act of 1974 (5 U.S.C. 552a). These policies include the preservation of all records, regardless of form or characteristics, mode of transmission, or state of completion.
b. In accordance with 36 CFR 1222.32, all data created for Government use and delivered to, or falling under the legal control of, the Government are Federal records subject to the provisions of 44 U.S.C. chapters 21, 29, 31, and 33, the Freedom of Information Act (FOIA) (5 U.S.C. 552), as amended, and the Privacy Act of 1974 (5 U.S.C. 552a), as amended and must be managed and scheduled for disposition only as permitted by statute or regulation.
c. In accordance with 36 CFR 1222.32, Contractor shall maintain all records created for Government use or created in the course of performing the contract and/or delivered to, or under the legal control of the Government and must be managed in accordance with Federal law. Electronic records and associated metadata must be accompanied by sufficient technical documentation to permit understanding and use of the records and data.
d. VA Nebraska-Western Iowa Health Care System and its contractors are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Records may not be removed from the legal custody of VA Nebraska-Western Iowa Health Care System or destroyed except for in accordance with the provisions of the agency records schedules and with the written concurrence of the Head of the Contracting Activity. Willful and unlawful destruction, damage or alienation of Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701.
e. In the event of any unlawful or accidental removal, defacing, alteration, or destruction of records, Contractor must report to VA Nebraska-Western Iowa Health Care System. The agency must report promptly to NARA in accordance with 36 CFR 1230.
f. The Contractor shall immediately notify the appropriate Contracting Officer upon discovery of any inadvertent or unauthorized disclosures of information, data, documentary materials, records or equipment. Disclosure of non-public information is limited to authorized personnel with a need-to-know as described in the [contract vehicle]. The Contractor shall ensure that the appropriate personnel, administrative, technical, and physical safeguards are established to ensure the security and confidentiality of this information, data, documentary material, records and/or equipment is properly protected. The Contractor shall not remove material from Government facilities or systems, or facilities or systems operated or maintained on the Government’s behalf, without the express written permission of the Head of the Contracting Activity. When information, data, documentary material, records and/or equipment is no longer required, it shall be returned to VA Nebraska-Western Iowa Health Care System control or the Contractor must hold it until otherwise directed. Items returned to the Government shall be hand carried, mailed, emailed, or securely electronically transmitted to the Contracting Officer or address prescribed in the contract documents. Destruction of records is EXPRESSLY PROHIBITED unless in accordance with Paragraph (4).
g. The Contractor is required to obtain the Contracting Officer's approval prior to engaging in any contractual relationship (sub-contractor) in support of this contract requiring the disclosure of information, documentary material and/or records generated under, or relating to, contracts. The Contractor (and any sub-contractor) is required to abide by Government and [VA Nebraska-Western Iowa Health Care System] guidance for protecting sensitive, proprietary information, classified, and controlled unclassified information.
h. The Contractor shall only use Government IT equipment for purposes specifically tied to or authorized by the contract and in accordance with [VA Nebraska-Western Iowa Health Care System] policy.
i. The Contractor shall not create or maintain any records containing any non-public VA Nebraska-Western Iowa Health Care System information that are not specifically tied to or authorized by the contract.
j. The Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected from public disclosure by an exemption to the Freedom of Information Act.
k. The [VA Nebraska-Western Iowa Health Care System] owns the rights to all data and records produced as part of this contract. All deliverables under the contract are the property of the U.S. Government for which [VA Nebraska-Western Iowa Health Care System] shall have unlimited rights to use, dispose of, or disclose such data contained therein as it determines to be in the public interest. Any Contractor rights in the data or deliverables must be identified as required by FAR 52.227-11 through FAR 52.227-20.
l. Training. All Contractor employees assigned to this contract who create, work with, or otherwise handle records are required to take VHA-provided records management training. The Contractor is responsible for confirming training has been completed according to agency policies, including initial training and any annual or refresher training.
12. Flowdown of requirements to Subcontractors
a. The Contractor shall incorporate the substance of this clause, its terms and requirements including this paragraph, in all subcontracts under this [contract vehicle], and require written subcontractor acknowledgment of same.
b. Violation by a subcontractor of any provision set forth in this clause will be attributed to the Contractor.
13. Attachments