Propane Standby Inspection Report.pdf
PDF 49 KB Posted
- Solicitation number
- RFQ 171 190000000639 3
- Issued by
- Baraga County, Michigan
About this file
This is a Propane Standby System Inspection Report for Baraga Maximum Correctional Facility located at 301 Wadaga Road, Baraga, Michigan 49908. The inspection was conducted on October 9, 2018, by MI Construction Service 2 and documented the condition and operational status of the facility's propane standby system. The inspection covered a Trinity-manufactured storage tank (Serial #118362) with a 30-gallon capacity, 131-inch diameter, and 561-foot length, along with associated equipment including internal valves, emergency shutdown systems, liquid pumps, bypass valves, and a vaporizer/mixer unit manufactured by Ely Energy (Model Na, Serial Na, Year Built 1990). The system was found to be in generally good working condition with all major components operational.
The inspection identified that the storage tank contained 65 percent propane at the time of inspection and documented specific pressure readings and temperature settings for the vaporizer/mixer unit, including pump pressure at 120 PSI, optimum operating temperature of 160 degrees Fahrenheit, and venturi regulator settings ranging from 35 to 45 PSI. One minor issue was noted: small leaks in the bypass line piping from tank valves to pump inlet. The facility representative present during the inspection was Tyler, and the inspection was conducted by Ken Oswald. The report was submitted by MI Construction Service 2, located at 303 W. Maple Street, PO Box 145, Byron, Michigan 48418, with contact phone number 810-266-4687.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 472_19087.RAA Addendum 1.pdf | ||
| LEIN Request REV 04-2018.pdf | ||
| Design Build Advertisement R10-17).pdf | ||
| Site Photos.pdf | ||
| Ely Energy Vaporizer.pdf | ||
| Design Build Spec Final.pdf | ||
| LPG Equipment Layout.pdf | ||
| Ely Energy Mixer.pdf | ||
| Gas Distribution-Shts.I--6.pdf | ||
| 472_19087.RAA Addendum 2.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JOB INFORMATION
Job # 10990
Customer # M5-053
Customer Name & Billing Address BARAGA MAXIMUM CORRECTIONAL FACILITY [301
WADAGA ROAD BARAGA, MI 49908]
Location Name & Address BARAGA MAXIMUM CORRECTIONAL FACILITY [301
WADAGA ROAD BARAGA, MI 49908]
IPS Job Coordinator Dutch (Olin) Russell
STORAGE TANK INSPECTION
Any leaks at tank fittings? No
Multi-port in proper working condition? Yes
Relief valve stacks in good condition? Yes
Remarks
8d09
Relief valve stacks have their protective caps in place? Yes
Magnetel gauge in good working condition? Yes
Temperature and pressure gauges in good condition? Yes
Piers and tank pads in good condition? Yes
Product in tank at time of inspection? Yes
Remarks
65%
Any combustible materials inside of fenced areas? Yes
Remarks
Small weeds
INTERNAL VALVES & EMERGENCY SHUTDOWN SYSTEM
Internal valves in good working condition? Yes
ESV valves in good working condition? Yes
Emergency shutdown system working correctly? Yes
Emergency shutdown signs or decals in place and in good condition? Yes
TRANSPORT BULKHEAD
Any leaks in piping from bulkhead to tank (liquid and vapor)? No
Liquid and vapor acme adapters in good condition? Yes
Does the system have the required safety features and are they in good working condition?
Yes
Liquid and vapor decals in place? Yes
Emergency shutdown system in place and in good working condition? Yes
Emergency signs or decals in place and in good condition? Yes
LIQUID PUMPS & BYPASS VALVES
Are the pumps in working condition? Yes
Have the pumps been greased? Yes
Did IPS employee need to grease pumps? No
Any leaks in piping from tank valves to pump inlet? Yes
Remarks
Small flex on bypass line
Any leaks in pump assembly or pump flanges? No
Pump pressure checked. Yes
PSI Pump is running at 120
Pump pressure gauge in good condition? Yes
Pump bypass valve was checked for proper working condition? Yes
Checked pump motor wiring
(conduit, flexes, seal-offs)
Yes
Hydrostatic relief valves in required locations? Yes
Checked hydrostatic reliefs for debris, weep hole location & that protective caps are in place.
Yes
LIQUID LINE FROM PUMPS TO VAPORIZER INLET
303 W. Maple St. PO Box 145
Byron, MI 48418
P) 810-266-4687
Date: 10/09/2018Propane Standby System Inspection Report
Submitted by MI Construction Service 2 at 10/09/2018 14:43 EDT Page: 1
Captured at 10/09/2018 14:42 EDT gocanvas.com
Submission ID: C5B5FB8F-4848-44F9-8106-FE307BE6713F https://www.gocanvas.com/?utm_source=canvas_pdf&utm_medium=pdf_link&utm_campaign=canvas_pdf_link
Any leaks in piping from pumps to vaporizer? No
Hydrostatic relief valves in required locations? Yes
Checked hydrostatic reliefs for debris, weep hole location & that protective caps are in place.
Yes
VAPORIZER / MIXER UNIT INFORMATION
Manufacturer Ely energy
Model # Na
Serial # Na
Year Built 1990
Has Pilot Relighter? Yes
Has thermocouple? No
Gas valve Make/Model # Yes
Has power pile? Yes
High Mix (PSI) 6
Low Mix (PSI) 5
Pump PSI 120
Optimum Temp (Degrees F) 160
Low Temp (Degrees F) 150
High Temp (Degrees F) 165
High Propane 1
Low Propane 1
Vaporizer/Mixer Info Surge Tank
Vaporizer/Mixer Info Venturi Regulator (PSI)
#1 45
#2 35
#3 35
Vaporizer/Mixer Info Gas Mix Setting
#1 1.32
#2 1.32
#3 1.32
STORAGE TANK SPECIFICATIONS
Manufacturer Trinity
Serial # 118362
Capacity 30
Diameter (inches) 131
Length (feet) 561
Manway?
Magnetel?
Rotor Gauge?
PSI Gauge 100
Materials Used
Sa615
Inspector Ken Oswald
Facility Representative(s)
Tyler
Date of Inspection 10/09/2018
303 W. Maple St. PO Box 145
Byron, MI 48418
P) 810-266-4687
Date: 10/09/2018Propane Standby System Inspection Report
Submitted by MI Construction Service 2 at 10/09/2018 14:43 EDT Page: 2
Captured at 10/09/2018 14:42 EDT gocanvas.com
Submission ID: C5B5FB8F-4848-44F9-8106-FE307BE6713F