Project Manual Paint Shop and Spray Room.pdf
PDF 8 MB Posted
- Attached to
- Paint Shop and Spray Room Construction
- Solicitation number
- 24-350SOS-SOS35-B-37577
- Issued by
- St. Clair County, Illinois
About this file
This document is a project manual for the renovation of an existing pre-engineered metal storage building into a paint shop with a paint booth for the Illinois Secretary of State. The work includes selective demolition and new construction to convert the building into a paint shop with drop off/prep areas, office, storage, toilet, mechanical space, drying/pickup area, and a paint booth. The project also includes new mechanical, electrical, plumbing, and fire protection systems.
The project is located at 315 N. Klein Street in Springfield, Illinois within Sangamon County. The solicitation is being issued by the Illinois Secretary of State, and responses are due by a date not specified in the document. No information is provided about any site visits, bidder's meetings, award dates, or contract term and renewal options.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Limbaugh Notice of Award For BidBuy.pdf | ||
| Paint Shop Addenda No. 1~1.pdf | ||
| Paint Shop and Spray Room Drawings.pdf | ||
| Paint Shop Addenda No. 2.pdf | ||
| Paint Shop and Spray Room IFB.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT MANUAL
PAINT SHOP AND SPRAY ROOM
CAPITOL COMPLEX
315 N. KLEIN STREET
SPRINGFIELD, SANGAMON COUNTY, ILLINOIS 62702
SOS Project #22.09
USING AGENCY:
SECRETARY OF STATE
BY:
100 E. WASHINGTON ST., SUITE 220
BELLEVILLE, ILLINOIS 62220
BRiC/RTM #2043-04H
DATE: April 21, 2023 ssatterlee Stamp
SOS: #22.09 000100-1 PAINT SHOP AND SPRAY ROOM
BRiC/RTM: 2043-04H Capitol Complex
PROJECT MANUAL
TOC - Table of Contents
Illinois Secretary of State
Michael J. Howlett Bldg.
501 S. 2nd Street, Rm. 037
Springfield, IL 62756
Contact Person: Lorre M. Reents
Telephone: 217-558-4787
PROJECT MANUAL FOR
PAINT SHOP AND SPRAY ROOM
Capitol Complex
Springfield, Sangamon County, Illinois 62702
DIVISION SECTION TITLE PAGES
TOC Table of Contents TOC-1-3
01 GENERAL REQUIREMENTS
010600 Regulatory Requirements 010600-1-2
011000 Summary 011000-1-7
012500 Substitution Procedures 012500-1-4
012600 Contract Modification Procedures 012600-1-3
012900 Payment Procedures 012900-1-5
013100 Project Management and Coordination 013100-1-9
013300 Submittal Procedures 013300-1-10
013516 Alternate Project Procedures 013516-1-10
014000 Quality Requirements 014000-1-9
015000 Temporary Facilities and Controls 015000-1-9
015250 Construction Aids 015250-1
016000 Product Requirements 016000-1-7
017200 Project Record Documents 017200-1-2
017300 Execution 017300-1-12
017419 Construction Waste Management and Disposal 017419-1-5
017700 Closeout Procedures 017700-1-7
017823 Operation and Maintenance Data 017823-1-8
017900 Demonstration and Training 017900-1-5
02 EXISTING CONDITIONS
024119 Selective Demolition 024119-1-4
04 MASONRY
042200 Concrete Unit Masonry 042200-1-7
SOS: #22.09 000100-2 PAINT SHOP AND SPRAY ROOM
07 THERMAL AND MOISTURE PROTECTION
079200 Joint Sealants 079200-1-6
08 OPENINGS
081113 Hollow Metal Doors and Frames 081113-1-6
083323 Overhead Coiling Doors 083323-1-7
083613 Electric Door Operators 083613-1-4
087100 Door Hardware 087100-1-11
09 FINISHES
092116.23 Gypsum Board Shaft Wall Assemblies 092116.23-1-4
092216 Non-Structural Metal Framing 092216-1-5
092900 Gypsum Board 092900-1-5
096513 Resilient Base and Accessories 096513-1-4
097813 Metal Interior Wall and Ceiling Paneling 097813-1-7
099123 Interior Painting 099123-1-5
10 SPECIALTIES
101429 Modular Signage 101429-1-3
102800 Toilet, Bath and Laundry Accessories 102800-1-5
21 FIRE PROTECTION
210500 Common Work Results for Fire Suppression 210500-1-7
210553 Identification for Fire Suppression ` 210553-1-5
211313 Wet-Pipe Sprinkler Systems 211313-1-20
22 PLUMBING
220100 Basic Plumbing Requirements 220100-1-5
220500 Common Work Results for Plumbing 220500-1-12
220519 Meters and Gages 220519-1-5
220523 General Duty Valves 220523-1-7
220529 Hangers and Supports 220529-1-10
220553 Identification for Plumbing Piping 220553-1-6
220700 Plumbing Insulation 220700-1-14
221116 Domestic Water Piping 221116-1-9
221119 Domestic Water Piping Specialties 221119-1-7
221316 Sanitary Waste and Vent Piping 221316-1-11
221319 Sanitary Waste Piping Specialties 221319-1-6
223300 Electric Domestic Water Heaters 223300-1-7
224300 Plumbing Fixtures 224300-1-12
226113 Compressed-Air Piping 226113-1-9
226119 Compressed-Air Equipment 226119-1-5
SOS: #22.09 000100-3 PAINT SHOP AND SPRAY ROOM
23 MECHANICAL
230529 Hangers and Supports 230529-1-11
230553 Identification for HVAC Piping 230553-1-6
230593 Testing, Adjusting and Balancing 230593-1-17
230713 Duct Insulation 230713-1-14
230993 Sequence of Operations 230993-1-3
232923 Variable-Frequency Motor Controllers 232923-1-11
233113 Metal Ducts 233113-1-18
233300 Air Duct Accessories 233300-1-12
233423 HVAC Power Ventilators 233423-1-6
234100 Particulate Air Filtration 234100-1-7
237423.13 Packaged, Direct-Fired, Outdoor, Heating-Only 237423.13-1-14
Makeup-Air Units
238129 Variable-Refrigerant-Flow HVAC Systems 238129-1-51
26 ELECTRICAL
260523 Building Wire and Cable 260523-1-6
260526 Grounding and Bonding 260526-1-5
260529 Supporting Devices 260529-1-3
260530 Conduit 260530-1-7
260533 Boxes 260533-1-4
260553 Electrical Identification 260553-1-3
260580 Equipment Wiring Systems 260580-1-2
260923 Lighting Control Devices 260923-1-8
262416 Panelboards 262416-1-4
262726 Wiring Devices 262726-1-5
262816 Enclosed Switches 262816-1-3
264313 Surge Protective Devices 264313-1-5
265100 Luminaires 265100-1-4
266100 Electrical Testing 266100-1-3
27 COMMUNICATIONS
271000 Structured Cabling 271000-1-15
271100 Communications Raceway System 271100-1-5
28 ELECTRONIC SAFETY AND SECURITY
281300 Access Control 281300-1-19
283100 Fire Alarm and Smoke Detection System 283100-1-13
END OF TOC
Page intentionally left blank
SOS: #22.09 010600-1 PAINT SHOP AND SPRAY ROOM
DIVISION 1 - GENERAL REQUIREMENTS
Section 010600 - Regulatory Requirements
1. GENERAL
1.1 REQUIREMENTS INCLUDE
A. Contractor comply with all laws, rules and regulations governing the work.
1. When Contractor observes that contract documents are at variance with specified codes, notify Architect/Engineer in writing immediately. Architect/Engineer may process change in accord with General Conditions.
2. When Contractor performs any work knowing or having reason to know that the work is contrary to such laws, rules and regulations and fails to so notify the Architect/Engineer, Contractor shall pay all costs arising therefrom. However, it will not be the Contractor's primary responsibility to make certain that the contract documents are in accord with such laws, rules and regulations.
1.2 DEFINITIONS & ABBREVIATIONS
A. Definitions:
1. Dates: Reference Codes, Regulations and Standards are the issue current at date of bidding documents unless otherwise specified.
2. Code: Codes are rules, regulations or statutory requirements of government agencies.
3. Standards: Standards are requirements set by authorities, custom or general consent and established as accepted criteria.
B. Abbreviations:
1. ANSI American National Standards Institute.
2. ASHRAE American Society of Heating Refrigeration and Air Conditioning
Engineers.
3. ASTM American Society for Testing and Materials.
4. CDB Capital Development Board.
5. FED Federal Agencies.
6. FM Factory Mutual Engineering Corp.
7. IDPH Illinois Department of Public Health.
8. IEPA Illinois Environmental Protection Agency.
9. NFPA National Fire Protection Association.
10. OSFM Office of the State Fire Marshal.
11. UL Underwriters Laboratories, Inc.
SOS: #22.09 010600-2 PAINT SHOP AND SPRAY ROOM
1.3 QUALITY ASSURANCE
A. Architect/Engineer has designed the project with full knowledge of code requirements and has copies of all specified codes available for Contractor's inspection.
B. Contractor:
1. Ensure that copies of specified codes and standards are readily available to contractor's personnel. Copies are available at Contractor's expense from source or publisher.
2. Ensure that Contractor's personnel are familiar with workmanship and installation requirements of specified codes and standards.
1.4 REGULATORY REQUIREMENTS
A. Source and requirements:
1. State of Illinois:
a. Illinois Steel Products Procurement Act, as amended (Illinois Revised Statutes, ch. 48, par. 1801 et seq.).
b. Illinois Purchasing Act, as amended (Illinois Revised Statutes, Ch 127, Par.
132.1 et seq.)
B. The Architect/Engineer may reference other codes or standards throughout the Project Manual when deemed appropriate for proper compliance with regulatory requirements.
END OF SECTION
SOS: #22.09 011000-1 PAINT SHOP AND SPRAY ROOM
DIVISION 1 - GENERAL REQUIREMENTS
Section 011000 - Summary
1. GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by Contract Documents.
3. Work performed by Owner.
4. Work under Owner's separate contracts.
5. Owner-furnished/Contractor-installed (OFCI) products.
6. Owner-furnished/Owner-installed (OFOI) products.
7. Contractor-furnished/Owner-installed (CFOI) products.
8. Contractor's use of site and premises.
9. Coordination with occupants.
10. Work restrictions.
11. Specification and Drawing conventions.
12. Miscellaneous provisions.
B. Related Requirements:
1. Section 015000 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.
2. Section 017300 "Execution" for coordination of Owner-installed products.
1.3 DEFINITIONS
A. Work Package: A group of specifications, drawings, and schedules prepared by the design team to describe a portion of the Project Work for pricing, permitting, and construction.
B. Fabricated: “Fabricated” pertains to items specifically assembled or made of selected materials or components to meet individual design requirements.
C. Manufactured: “Manufactured” means standard units, usually mass produced by an established manufacturer of the respective item.
D. Provide: “Provide” means to furnish and install.
SOS: #22.09 011000-2 PAINT SHOP AND SPRAY ROOM
E. Shop fabricated or shop made: “Shop fabricated or shop made” refers to items made by the Contractor in his own shop.
F. Using Agency or Owner: Office of the Illinois Secretary of State.
1.4 PROJECT INFORMATION
A. Project Identification: Secretary of State Paint Shop and Spray Room.
1. Project Location: 316 North Klein Street Springfield Illinois 62702.
B. Owner: Illinois Secretary of State.
1. Owner's Representative: Lorre M. Reents, Project Manager; Department of Physical Services, Planning and Development Division.
C. Engineer: RTM Engineering Consultants.
1. Engineer's Representative: Jim LaBlance; 100 E. Washington Street, Suite 220, Belleville, IL 62220.
D. Engineer's Consultants: Engineer has retained the following design professionals, who have prepared designated portions of the Contract Documents:
1. Architect: White & Borgognoni Architects.
a. Architect Representative: Van V. Voyles, AIA; 212 North Illinois Avenue, Carbondale, IL 62901
b. Scope of Service: Architectural Design
1.5 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of Project is defined by the Contract Documents and includes, but is not limited to, the following:
1. Selective demolition and new construction to convert an existing pre-engineered metal storage building into a paint shop with paint booth. The new paint shop will contain drop off/prep areas, office, storage, toilet, mechanical space drying\pickup area and paint booth. Mechanical, Electrical, Plumbing and Fire Protection work will include new HVAC, A new combined water service and new sewer service, new electrical service, fire alarm, fire sprinkler system and other Work indicated in the Contract Documents.
SOS: #22.09 011000-3 PAINT SHOP AND SPRAY ROOM
B. Type of Contract:
1. Project will be constructed under a single prime contract.
1.6 WORK PERFORMED BY OWNER
A. Cooperate fully with Owner, so work may be carried out smoothly, without interfering with or delaying Work under this Contract or work by Owner. Coordinate the Work of this Contract with work performed by Owner.
B. Preceding Work: Owner will perform the following construction operations at Project site. Those operations are scheduled to be substantially complete before Work under this Contract begins.
1. Drying tables, Fire Extinguishers, and Flammable Storage Cabinets by Owner.
C. Concurrent Work: Owner will perform the following construction operations at Project site. Those operations will be conducted simultaneously with Work under this Contract.
1. A separate plumbing project may be ongoing at the site during the time of this project but will not have any scope inside the Paint Shop Building.
D. Subsequent Work: Owner will perform the following additional work at site after Substantial Completion. Completion of that work will depend on successful completion of preparatory Work under this Contract.
1. Not Applicable.
1.7 OWNER-FURNISHED/CONTRACTOR-INSTALLED (OFCI) PRODUCTS (Not Applicable)
1.8 OWNER-FURNISHED/OWNER-INSTALLED (OFOI) PRODUCTS
A. The Owner will furnish and install products indicated.
B. Owner-Furnished/Owner-Installed (OFOI) Products:
1. Flammable Storage Cabinets installed in Storage/Compressor Room.
2. Drying Racks in Drying\Pickup Room
3. Workbench in Dropoff\Prep Room and Drying\Pickup Room.
4. Upper Wall Cabinets Dropoff\Prep Room
1.9 CONTRACTOR'S USE OF SITE AND PREMISES
SOS: #22.09 011000-4 PAINT SHOP AND SPRAY ROOM
A. Unrestricted Use of Site: Contractor shall have full use of Project site for construction operations during construction period. Contractor's use of Project site is limited only by Owner's right to perform work or to retain other contractors on portions of Project.
B. Restricted Use of Site: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.
C. Limits on Use of Site: Limit use of Project site to Work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limits on Use of Site: Confine construction operations to building and area between the south side of building to the drive through gate.
2. Driveways, Walkways and Entrances: Keep driveways loading areas, and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or for storage of materials.
a. Schedule deliveries to minimize use of driveways and entrances by construction operations.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
D. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period.
Repair damage caused by construction operations.
E. Condition of Existing Grounds: Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period. Repair damage caused by construction operations.
1.10 COORDINATION WITH OCCUPANTS
A. Full Owner Occupancy: Owner will occupy Project site and existing adjacent building(s) during entire construction period. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's day-to-day operations. Maintain existing exits unless otherwise indicated.
1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and approval of authorities having jurisdiction.
2. Notify Owner not less than 72 hours in advance of activities that will affect Owner's operations.
SOS: #22.09 011000-5 PAINT SHOP AND SPRAY ROOM
1.11 WORK RESTRICTIONS
A. Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets, work on public streets, rights of way, and other requirements of authorities having jurisdiction.
B. On-Site Work Hours: Limit work to between 7 a.m. to 5 p.m., Monday through Friday, unless otherwise indicated. Work hours may be modified to meet Project requirements if approved by Owner and authorities having jurisdiction.
1. Work in Existing Building: Contractor to provide fire protection in building during construction.
2. Hours for Utility Shutdowns: Requires approval of owner with minimum 72-hour notice.
C. On-Site Work Day Restrictions: Do not perform work resulting in utility shutdowns on-site during work black-out days indicated in Document 003113 "Preliminary Schedules."
D. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging for temporary utility services according to requirements indicated:
1. Notify Engineer and Owner not less than two days in advance of proposed utility interruptions.
2. Obtain Engineer's Owner's written permission before proceeding with utility interruptions.
E. Noise, Vibration, Dust, and Odors: Coordinate operations that may result in high levels of noise and vibration, dust, odors, or other disruption to Owner occupancy with Owner.
1. Notify Owner not less than two days in advance of proposed disruptive operations.
2. Obtain Owner's written permission before proceeding with disruptive operations.
F. Smoking and Controlled Substance Restrictions: Use of tobacco products, alcoholic beverages, and other controlled substances within the existing building is not permitted. Smoking is allowed in designated outside areas only.
G. Employee Identification: Owner will provide identification tags for Contractor personnel working on Project site. Require personnel to use identification tags at all times.
SOS: #22.09 011000-6 PAINT SHOP AND SPRAY ROOM
1.12 SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:
1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
2. Text Color: Text used in the Specifications, including units of measure, manufacturer and product names, and other text may appear in multiple colors or underlined as part of a hyperlink; no emphasis is implied by text with these characteristics.
3. Hypertext: Text used in the Specifications may contain hyperlinks. Hyperlinks may allow for access to linked information that is not residing in the Specifications. Unless otherwise indicated, linked information is not part of the Contract Documents.
4. Specification requirements are to be performed by Contractor unless specifically stated otherwise.
B. Division 00 Contracting Requirements: General provisions of the Contract, including General and Supplementary Conditions, apply to all Sections of the Specifications.
C. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.
D. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:
1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.
2. Abbreviations: Materials and products are identified by abbreviations scheduled on Drawings and published as part of the U.S. National CAD Standard.
3. Keynoting: Materials and products are identified by reference keynotes referencing Specification Section numbers found in this Project Manual.
1.13 MISCELLANEOUS PROVISIONS (Not Applicable)
2. PRODUCTS (Not Used)
3. EXECUTION (Not Used)
SOS: #22.09 011000-7 PAINT SHOP AND SPRAY ROOM
SOS: #22.09 012500-1 PAINT SHOP AND SPRAY ROOM
DIVISION 1 - GENERAL REQUIREMENTS
Section 012500 - Substitution Procedures
1. GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for substitutions.
B. Related Requirements:
1. Document 002600 "Procurement Substitution Procedures" for requirements for substitution requests prior to award of Contract.
2. Section 016000 "Product Requirements" for requirements for submitting comparable product submittals for products by listed manufacturers.
1.3 DEFINITIONS
A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents.
1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms.
2. Substitutions for Convenience: Changes proposed by Contractor or Owner that are not required to meet other Project requirements but may offer advantage to Contractor or Owner.
1.4 ACTION SUBMITTALS
A. Substitution Requests: Submit documentation identifying product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.
1. Substitution Request Form: Use form acceptable to Architect.
2. Documentation: Show compliance with requirements for substitutions and the following, as applicable:
SOS: #22.09 012500-2 PAINT SHOP AND SPRAY ROOM
a. Statement indicating why specified product or fabrication or installation method cannot be provided, if applicable.
b. Coordination of information, including a list of changes or revisions needed to other parts of the Work and to construction performed by Owner and separate contractors that will be necessary to accommodate proposed substitution.
c. Detailed comparison of significant qualities of proposed substitutions with those of the Work specified. Include annotated copy of applicable Specification Section. Significant qualities may include attributes, such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified.
d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.
e. Samples, where applicable or requested.
f. Certificates and qualification data, where applicable or requested.
g. List of similar installations for completed projects, with project names and addresses as well as names and addresses of architects and owners.
h. Material test reports from a qualified testing agency, indicating and interpreting test results for compliance with requirements indicated.
i. Research reports evidencing compliance with building code in effect for
Project.
j. Detailed comparison of Contractor's construction schedule using proposed substitutions with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery.
k. Cost information, including a proposal of change, if any, in the Contract Sum.
l. Contractor's certification that proposed substitution complies with requirements in the Contract Documents, except as indicated in substitution request, is compatible with related materials and is appropriate for applications indicated.
m. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.
3. Architect's Action: If necessary, Architect will request additional information or documentation for evaluation within seven days of receipt of a request for substitution. Architect will notify Contractor of acceptance or rejection of proposed substitution within 15 days of receipt of request, or seven days of receipt of additional information or documentation, whichever is later.
SOS: #22.09 012500-3 PAINT SHOP AND SPRAY ROOM
a. Forms of Acceptance: Change Order, Construction Change Directive, or Architect's Supplemental Instructions for minor changes in the Work.
b. Use product specified if Architect does not issue a decision on use of a proposed substitution within time allocated.
1.5 QUALITY ASSURANCE
A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers.
1.6 PROCEDURES
A. Coordination: Revise or adjust affected work as necessary to integrate work of the approved substitutions.
1.7 SUBSTITUTIONS
A. Substitutions for Cause: Submit requests for substitution immediately on discovery of need for change, but not later than 15 days prior to time required for preparation and review of related submittals.
1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements:
a. Requested substitution is consistent with the Contract Documents and will produce indicated results.
b. Substitution request is fully documented and properly submitted.
c. Requested substitution will not adversely affect Contractor's construction schedule.
d. Requested substitution has received necessary approvals of authorities having jurisdiction.
e. Requested substitution is compatible with other portions of the Work.
f. Requested substitution has been coordinated with other portions of the
Work.
g. Requested substitution provides specified warranty.
h. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.
SOS: #22.09 012500-4 PAINT SHOP AND SPRAY ROOM
B. Substitutions for Convenience: Architect will consider requests for substitution if received within 60 days after the Notice of Award. Requests received after that time may be considered or rejected at discretion of Architect.
1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements:
a. Requested substitution offers Owner a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional responsibilities Owner must assume. Owner's additional responsibilities may include compensation to Architect for redesign and evaluation services, increased cost of other construction by Owner, and similar considerations.
b. Requested substitution does not require extensive revisions to the Contract Documents.
c. Requested substitution is consistent with the Contract Documents and will produce indicated results.
d. Substitution request is fully documented and properly submitted.
e. Requested substitution will not adversely affect Contractor's construction schedule.
f. Requested substitution has received necessary approvals of authorities having jurisdiction.
g. Requested substitution is compatible with other portions of the Work.
h. Requested substitution has been coordinated with other portions of the
Work.
i. Requested substitution provides specified warranty.
j. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.
2. PRODUCTS (Not Used)
SOS: #22.09 012600-1 PAINT SHOP AND SPRAY ROOM
DIVISION 1 - GENERAL REQUIREMENTS
Section 012600 - Contract Modification Procedures
1. GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for handling and processing Contract modifications.
B. Related Requirements:
1. Section 012500 "Substitution Procedures" for administrative procedures for handling requests for substitutions made after the Contract award.
2. Section 013100 "Project Management and Coordination" for requirements for forms for contract modifications provided as part of web-based Project management software.
1.3 MINOR CHANGES IN THE WORK
A. Architect will issue supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or the Contract Time, on AIA Document G710.
1.4 PROPOSAL REQUESTS
A. Owner-Initiated Proposal Requests: Architect will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.
1. Work Change Proposal Requests issued by Architect are not instructions either to stop work in progress or to execute the proposed change.
2. Within time specified in Proposal Request or 10 days, when not otherwise specified, after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.
a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
SOS: #22.09 012600-2 PAINT SHOP AND SPRAY ROOM
b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
c. Include costs of labor and supervision directly attributable to the change.
d. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
e. Quotation Form: Use forms acceptable to Architect.
B. Contractor-Initiated Proposals: If latent or changed conditions require modifications to the Contract, Contractor may initiate a claim by submitting a request for a change to Architect.
1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change.
Indicate the effect of the proposed change on the Contract Sum and the Contract Time.
2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
4. Include costs of labor and supervision directly attributable to the change.
5. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
6. Comply with requirements in Section 012500 "Substitution Procedures" if the proposed change requires substitution of one product or system for product or system specified.
7. Proposal Request Form: Use form acceptable to Architect.
1.5 CHANGE ORDER PROCEDURES
A. On Owner's approval of a Work Change Proposal Request, Architect will issue a Change Order for signatures of Owner and Contractor on AIA Document G701.
1.6 CONSTRUCTION CHANGE DIRECTIVE
A. Construction Change Directive: Architect may issue a Construction Change Directive on AIA Document G714. Construction Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.
SOS: #22.09 012600-3 PAINT SHOP AND SPRAY ROOM
1. Construction Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the Contract Time.
B. Documentation: Maintain detailed records on a time and material basis of work required by the Construction Change Directive.
1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.
2. PRODUCTS (Not Used)
SOS: #22.09 012900-1 PAINT SHOP AND SPRAY ROOM
DIVISION 1 - GENERAL REQUIREMENTS
Section 012900 - Payment Procedures
1. GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements necessary to prepare and process Applications for Payment.
B. Related Requirements:
1. Document 004373 "Proposed Schedule of Values Form" for requirements for furnishing proposed schedule of values with bid.
2. Section 012600 "Contract Modification Procedures" for administrative procedures for handling changes to the Contract.
1.3 DEFINITIONS
A. Schedule of Values: A statement furnished by Contractor allocating portions of the Contract Sum to various portions of the Work and used as the basis for reviewing Contractor's Applications for Payment.
1.4 SCHEDULE OF VALUES
A. Coordination: Coordinate preparation of the schedule of values with preparation of Contractor's construction schedule.
1. Coordinate line items in the schedule of values with items required to be indicated as separate activities in Contractor's construction schedule.
2. Submit the schedule of values to Architect at earliest possible date, but no later than seven days before the date scheduled for submittal of initial Applications for Payment.
B. Format and Content: Use Project Manual table of contents as a guide to establish line items for the schedule of values. Provide at least one line item for each Specification Section.
1. Identification: Include the following Project identification on the schedule of values:
SOS: #22.09 012900-2 PAINT SHOP AND SPRAY ROOM
a. Project name and location.
b. Owner's name.
c. Owner's Project number.
d. Name of Architect.
e. Architect's Project number.
f. Contractor's name and address.
g. Date of submittal.
2. Arrange schedule of values consistent with format of AIA Document G703.
3. Arrange the schedule of values in tabular form, with separate columns to indicate the following for each item listed:
a. Related Specification Section or division.
b. Description of the Work.
c. Name of subcontractor.
d. Name of manufacturer or fabricator.
e. Name of supplier.
f. Change Orders (numbers) that affect value.
g. Dollar value of the following, as a percentage of the Contract Sum to nearest one-hundredth percent, adjusted to total 100 percent. Round dollar amounts to whole dollars, with total equal to Contract Sum.
1) Labor.
2) Materials.
3) Equipment.
4. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports.
Provide multiple line items for principal subcontract amounts in excess of five percent of the Contract Sum.
5. Provide a separate line item in the schedule of values for each part of the Work where Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.
a. Differentiate between items stored on-site and items stored off-site.
6. Overhead Costs, Proportional Distribution: Include total cost and proportionate share of general overhead and profit for each line item.
7. Temporary Facilities: Show cost of temporary facilities and other major cost items that are not direct cost of actual work-in-place as separate line items.
8. Closeout Costs. Include separate line items under Contractor and principal subcontracts for Project closeout requirements in an amount totaling five percent of the Contract Sum and subcontract amount.
SOS: #22.09 012900-3 PAINT SHOP AND SPRAY ROOM
9. Schedule of Values Revisions: Revise the schedule of values when Change Orders or Construction Change Directives result in a change in the Contract Sum. Include at least one separate line item for each Change Order and Construction Change Directive.
1.5 APPLICATIONS FOR PAYMENT
A. Each Application for Payment following the initial Application for Payment shall be consistent with previous applications and payments, as certified by Architect and paid for by Owner.
B. Payment Application Times: The date for each progress payment is indicated in the Owner/Contractor Agreement. The period of construction work covered by each Application for Payment is the period indicated in the Agreement.
C. Payment Application Times: Submit Application for Payment to Architect by the 25th of the month. The period covered by each Application for Payment is one month, ending on the last day of the month.
1. Submit draft copy of Application for Payment seven days prior to due date for review by Architect.
D. Application for Payment Forms: Use AIA Document G702 and AIA Document G703 as form for Applications for Payment.
E. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. Architect will return incomplete applications without action.
1. Entries shall match data on the schedule of values and Contractor's construction schedule. Use updated schedules if revisions were made.
2. Include amounts for work completed following previous Application for Payment, whether or not payment has been received. Include only amounts for work completed at time of Application for Payment.
3. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.
F. Stored Materials: Include in Application for Payment amounts applied for materials or equipment purchased or fabricated and stored, but not yet installed. Differentiate between items stored on-site and items stored off-site.
1. Provide certificate of insurance, evidence of transfer of title to Owner, and consent of surety to payment for stored materials.
2. Provide supporting documentation that verifies amount requested, such as paid invoices. Match amount requested with amounts indicated on documentation; do not include overhead and profit on stored materials.
3. Provide summary documentation for stored materials indicating the following:
SOS: #22.09 012900-4 PAINT SHOP AND SPRAY ROOM
a. Value of materials previously stored and remaining stored as of date of previous Applications for Payment.
b. Value of previously stored materials put in place after date of previous Application for Payment and on or before date of current Application for Payment.
c. Value of materials stored since date of previous Application for Payment and remaining stored as of date of current Application for Payment.
G. Transmittal: Submit three signed and notarized original copies of each Application for Payment to Architect by a method ensuring receipt within 24 hours. One copy shall include waivers of lien and similar attachments if required.
1. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application.
H. Waivers of Mechanic's Lien: With each Application for Payment, submit waivers of mechanic's lien from subcontractors, sub-subcontractors, and suppliers for construction period covered by the previous application.
1. Submit partial waivers on each item for amount requested in previous application, after deduction for retainage, on each item.
2. When an application shows completion of an item, submit conditional final or full waivers.
3. Owner reserves the right to designate which entities involved in the Work must submit waivers.
4. Submit final Application for Payment with or preceded by conditional final waivers from every entity involved with performance of the Work covered by the application who is lawfully entitled to a lien.
5. Waiver Forms: Submit executed waivers of lien on forms acceptable to Owner.
I. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:
1. List of subcontractors.
2. Schedule of values.
3. Contractor's construction schedule (preliminary if not final).
4. Products list (preliminary if not final).
5. Submittal schedule (preliminary if not final).
6. List of Contractor's staff assignments.
7. List of Contractor's principal consultants.
8. Copies of building permits.
9. Copies of authorizations and licenses from authorities having jurisdiction for performance of the Work.
10. Initial progress report.
SOS: #22.09 012900-5 PAINT SHOP AND SPRAY ROOM
11. Report of preconstruction conference.
12. Certificates of insurance and insurance policies.
13. Performance and payment bonds.
14. Data needed to acquire Owner's insurance.
J. Application for Payment at Substantial Completion: After Architect issues the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete.
1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.
a. Complete administrative actions, submittals, and Work preceding this application, as described in Section 017700 "Closeout Procedures."
2. This application shall reflect Certificate(s) of Substantial Completion issued previously for Owner occupancy of designated portions of the Work.
K. Final Payment Application: After completing Project closeout requirements, submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:
1. Evidence of completion of Project closeout requirements.
2. Certification of completion of final punch list items.
3. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid.
4. Updated final statement, accounting for final changes to the Contract Sum.
5. AIA Document G706.
6. AIA Document G706A.
7. AIA Document G707.
8. Evidence that claims have been settled.
9. Proof that taxes, fees, and similar obligations are paid.
10. Waivers and releases.
2. PRODUCTS (Not Used)
SOS: #22.09 013100-1 PAINT SHOP AND SPRAY ROOM
DIVISION 1 - GENERAL REQUIREMENTS
Section 013100 - Project Management and Coordination
1. GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project, including, but not limited to, the following:
1. General coordination procedures.
2. Coordination drawings.
3. RFIs.
4. Digital project management procedures.
5. Project meetings.
B. Related Requirements:
1. Section 017300 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
2. Section 017700 "Closeout Procedures" for coordinating closeout of the Contract.
1.3 DEFINITIONS
A. RFI: Request for Information. Request from Owner, Architect, or Contractor seeking information required by or clarifications of the Contract Documents.
1.4 INFORMATIONAL SUBMITTALS
A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:
1. Name, address, telephone number, and email address of entity performing subcontract or supplying products.
2. Number and title of related Specification Section(s) covered by subcontract.
SOS: #22.09 013100-2 PAINT SHOP AND SPRAY ROOM
3. Drawing number and detail references, as appropriate, covered by subcontract.
B. Key Personnel Names: Within 15 days of starting construction operations, submit a list of key personnel assignments, including superintendent and other personnel in attendance at Project site. Identify individuals and their duties and responsibilities;
list addresses, cellular telephone numbers, and e-mail addresses. Provide names, addresses, and telephone numbers of individuals assigned as alternates in the absence of individuals assigned to Project.
1. Post copies of list in Project meeting room, in temporary field office,and in prominent location inbuilt facility. Keep list current at all times.
1.5 GENERAL COORDINATION PROCEDURES
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations included in different Sections that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results, where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
1. Prepare similar memoranda for Owner and separate contractors if coordination of their Work is required.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's construction schedule.
2. Preparation of the schedule of values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
SOS: #22.09 013100-3 PAINT SHOP AND SPRAY ROOM
6. Preinstallation conferences.
7. Project closeout activities.
8. Startup and adjustment of systems.
1.6 REQUEST FOR INFORMATION (RFI)
A. General: Immediately on discovery of the need for additional information, clarification, or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.
1. Architect will return without response those RFIs submitted to Architect by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in Contractor's work or work of subcontractors.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. Project name.
2. Owner name.
3. Owner's Project number.
4. Name of Architect.
5. Architect's Project number.
6. Date.
7. Name of Contractor.
8. RFI number, numbered sequentially.
9. RFI subject.
10. Specification Section number and title and related paragraphs, as appropriate.
11. Drawing number and detail references, as appropriate.
12. Field dimensions and conditions, as appropriate.
13. Contractor's suggested resolution. If Contractor's suggested resolution impacts the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
14. Contractor's signature.
15. Attachments: Include sketches, descriptions, measurements, photos, Product
Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Forms: AIA Document G716.
1. Attachments shall be electronic files in PDF format.
SOS: #22.09 013100-4 PAINT SHOP AND SPRAY ROOM
D. Architect's Action: Architect will review each RFI, determine action required, and respond. Allow three days for Architect's response for each RFI. RFIs received by Architect after 1:00 p.m. will be considered as received the following working day.
1. The following Contractor-generated RFIs will be returned without action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract
Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. Architect's action may include a request for additional information, in which case Architect's time for response will date from time of receipt by Architect of additional information.
3. Architect's action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal according to Section 012600 "Contract Modification Procedures."
a. If Contractor believes the RFI response warrants change in the Contract Time or the Contract Sum, notify Architect in writing within 5 days of receipt of the RFI response.
E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number. Submit log weekly. Include the following:
1. Project name.
2. Name and address of Contractor.
3. Name and address of Architect.
4. RFI number, including RFIs that were returned without action or withdrawn.
5. RFI description.
6. Date the RFI was submitted.
7. Date Architect's response was received.
8. Identification of related Minor Change in the Work, Construction Change
Directive, and Proposal Request, as appropriate.
F. On receipt of Architect's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Architect within three days if Contractor disagrees with response.
SOS: #22.09 013100-5 PAINT SHOP AND SPRAY ROOM
1.7 DIGITAL PROJECT MANAGEMENT PROCEDURES
A. PDF Document Preparation: Where PDFs are required to be submitted to Architect, prepare as follows:
1. Assemble complete submittal package into a single indexed file, incorporating submittal requirements of a single Specification Section and transmittal form with links enabling navigation to each item.
2. Name file with submittal number or other unique identifier, including revision identifier.
3. Certifications: Where digitally…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .