PRIME-SUB_FORM_for_Contractors_rev._01.15.2025.xls
XLS spreadsheet 38 KB Posted
- Solicitation number
- 25-B-155LL
- Issued by
- Volusia County, Florida
About this file
This is a Prime/Subcontractor Form for Volusia County, Florida's Invitation for Bid (IFB) #25-B-155LL for construction of a pre-engineered metal building (PEMB) canopy structure at the Tomoka Farms Landfill in Port Orange. The project involves constructing a 4,720 square foot open-air covered workspace for fleet vehicle maintenance and repair operations adjacent to an existing facility. The project timeline spans 150 days with 120 days designated for substantial completion, and liquidated damages are assessed at $225 per day for delays beyond the completion date. A non-mandatory pre-bid meeting is scheduled for October 30, 2025, at 3:30 pm, with sealed bids due on November 20, 2025, at 3:01 pm. The scope includes site preparation, civil work, structural construction, plumbing, and electrical systems with specific requirements for a rigid frame structure featuring a 21'-6" eave height, pre-finished metal roof panels, concrete slab, oil/water separator, compressed air system extension, and LED lighting.
The estimated project construction cost is $250,000, with the contract to be awarded on a lump sum basis to a single responsive and responsible bidder. Bidders must hold a Florida Certified General or Building Contractor license and are required to obtain performance and payment bonds due to the project value exceeding $200,000. The form requires bidders to list all proposed prime and subcontractors with corresponding dollar values and percentage of work performed, with anticipated disciplines including electrical and plumbing work. Prime contractors are responsible for ensuring all subcontractors maintain appropriate licenses, and any subcontractor changes during project completion require prior County Project Manager approval. Local businesses with at least six months of operation may receive preference under the local bid preference provision. Contractors must comply with E-verify requirements and provide comprehensive insurance coverage including Workers' Compensation, Commercial General Liability, Auto Liability, and Builder's Risk insurance. Funding will be drawn from county account numbers 513-860-0300-6300 and 450-760-5000-6300.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Contract No. C-2014 | ITB No. 25-B-##XX | ||||
| PRIME/SUBCONTRACTOR FORM | |||||
| FAILURE TO COMPLETE AND RETURN THIS FORM MAY RESULT IN A NON-RESPONSIVE BID | |||||
| Bidders are to list ALL Subcontractors that he/she proposed to perform scope of work for this project. The bidder hereby states that he/she proposes, if awarded the contract to hire the following Subcontractor(s) for this project. Prime Contractor is responsible for ensuring that all Subcontractors hold the appropriate license(s). Any change to the Subcontractors during the completion of this project shall receive prior approval from the County Project Manager. The County reserves the right to seek clarification regarding subcontractors but will not allow change to the total submitted base bid pricing. | |||||
| TOTAL BID | $ - 0 | This number should match the Total Bid Price |
(inclusive of performance/payment bond, if applicable) as listed on Bid Form/Exhibit ?/Attachment ? - Bid Price Sheet
| PRIME CONTRACTOR | Company name and complete address | Dollar Value performed by Prime Contractor | % of Work performed by Contractor |
| $ - 0 | 0.00% | ||
| List appropriate sub contractors to be used for each displine listed below, if prime is self performing note self performing in the box under company name and address and submit $0.00 to equal 0 % as this should be included in the green box above. If additional subcontractors are required and their discipline is not listed below they may be added in the blank rows. This form will also be used to determine local preference in accordance with Section 2.8, D. Local Bid Preference in the solicitation. | |||
| Anticipated Subcontractor Disciplines required for this project. | Company name and complete address | Dollar Value performed by Subcontractor(s) | % of Work performed by Subcontractor |
| Electrical | $ - 0 | 0.00% | |
| Plumbing | $ - 0 | 0.00% | |
| $ - 0 | 0.00% | ||
| $ - 0 | 0.00% | ||
| $ - 0 | 0.00% | ||
| $ - 0 | 0.00% | ||
| $ - 0 | 0.00% | ||
| $ - 0 | 0.00% | ||
| $ - 0 | 0.00% | ||
| $ - 0 | 0.00% | ||
| $ - 0 | 0.00% | ||
| $ - 0 | 0.00% | ||
| $ - 0 | 0.00% | ||
| $ - 0 | 0.00% | ||
| Bidders shall complete the areas shaded in GREEN, which shall be the dollar values assigned to each Contractor (Prime and Subs). All other cells shall be automatically calculated. The total listed in the GREY cell must equal 100% | $ - 0 | 0% |
Sheet2
Sheet3
File details come from the government source that posted it. Updated .