This is a Pricing Sheet for Crane, Hoist, and Lift Maintenance Services at Joint Base Charleston-Summerville (JBCHS). The spreadsheet requires contractors to provide pricing for Preventive Maintenance Inspection (PMI) services and repair pricing across multiple facilities and equipment types located at the base.

The PMI pricing section includes 93 line items covering various crane and hoist equipment across different buildings and work sections (AB and WS designations). Equipment types span monorails, bridge cranes, jib cranes, dock levelers, and manlift service platforms, with capacities ranging from 250 pounds to 70,000 pounds. PMI periodicity is either annual, semi-annual, monthly, or combinations thereof. Contractors must enter base period pricing and option period pricing (four option periods total) for each line item in the green-highlighted cells. The second sheet addresses repair pricing, with the government noting that under the current contract, approximately $56,000 annually has been spent on service calls and repairs, though this amount is not guaranteed. Contractors must submit a fully burdened hourly rate (80 hours estimated for the base period and each option period) and a mark-up percentage to be applied to material and subcontractor costs. The government anticipates total evaluated pricing of approximately $200,000 across the base period and four option periods. The Contracting Officer has determined adequate price competition exists for this acquisition.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PMI Pricing

Notes:
This tab requires inputs. Please complete green highlighted area only.
The Contracting Officer has determined there is a high probability of adequate price competition for this acquisition.
Price should be based on PMI PERIODICITY identified column L.
BLDG #LocationBLDG InfoREF. IDCAPACITY (lbs)EQUIPMENT TYPECRANE S#HOIST S#CRANE MFRHOIST MFRFund TypePMI PERIODICITYBase PricePeriod I PricePeriod II PricePeriod III PricePeriod IV PriceNotes/Comments - Pricing Purposes
176ABCargo Lift Equipment ShopBldg 176 Monorail10000MONORAIL/EWRHN/A532 07 5924N/AACCO WRIGHTO&MAnnual$0.00$0.00$0.00$0.00$0.00
176ABCargo Lift Equipment ShopBldg 176 Bridge10000TRSG BRIDGE/EWRHME8309176JJA9901811MERCO ENTERPRISESR&MO&MAnnual$0.00$0.00$0.00$0.00$0.00
178AB437th Air Freight TerminalBldg 178 - Outside, Right end of Bldg70000TRDG BRIDGE9469910120532DEMAGSTAHLTWCFAnnual$0.00$0.00$0.00$0.00$0.00
178AB437th Air Freight TerminalLoading Dock/Door-2> 18,000Dock Leveler (Elec-Hyd Operated)N/A09JD 480503MN/ARITE-HITETWCFSemi-Annual & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in half amounts semi-annually; 1 (one) annual and 1 (one) semi-annual inspections required.
178AB437th Air Freight TerminalLoading Dock/Door-3> 18,000Dock Leveler (Elec-Hyd Operated)N/A09JD 480502MN/ARITE-HITETWCFSemi-Annual & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in half amounts semi-annually; 1 (one) annual and 1 (one) semi-annual inspections required.
178AB437th Air Freight TerminalLoading Dock/Door-4> 18,000Dock Leveler (Elec-Hyd Operated)N/A09JD 480453MN/ARITE-HITETWCFSemi-Annual & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in half amounts semi-annually; 1 (one) annual and 1 (one) semi-annual inspections required.
178AB437th Air Freight TerminalLoading Dock/Door-5> 18,000Dock Leveler (Elec-Hyd Operated)N/A09JD 480451MN/ARITE-HITETWCFSemi-Annual & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in half amounts semi-annually; 1 (one) annual and 1 (one) semi-annual inspections required.
178AB437th Air Freight TerminalLoading Dock/Door-6> 18,000Dock Leveler (Elec-Hyd Operated)N/A09JD 480506MN/ARITE-HITETWCFSemi-Annual & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in half amounts semi-annually; 1 (one) annual and 1 (one) semi-annual inspections required.
178AB437th Air Freight TerminalLoading Dock/Door-7> 18,000Dock Leveler (Elec-Hyd Operated)N/A09JD 480509MN/ARITE-HITETWCFSemi-Annual & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in half amounts semi-annually; 1 (one) annual and 1 (one) semi-annual inspections required.
178AB437th Air Freight TerminalLoading Dock/Door-9> 18,000Dock Leveler (Elec-Hyd Operated)N/AN/ARITE-HITETWCFSemi-Annual & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in half amounts semi-annually; 1 (one) annual and 1 (one) semi-annual inspections required.
178AB437th Air Freight TerminalLoading Dock/Door-10> 18,000Dock Leveler (Elec-Hyd Operated)N/A09JD 480504MN/ARITE-HITETWCFSemi-Annual & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in half amounts semi-annually; 1 (one) annual and 1 (one) semi-annual inspections required.
178AB437th Air Freight TerminalLoading Dock/Door-11> 18,000Dock Leveler (Elec-Hyd Operated)N/AN/ARITE-HITETWCFSemi-Annual & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in half amounts semi-annually; 1 (one) annual and 1 (one) semi-annual inspections required.
178AB437th Air Freight TerminalLoading Dock/Door-12> 18,000Dock Leveler (Elec-Hyd Operated)N/A09JD 480452MN/ARITE-HITETWCFSemi-Annual & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in half amounts semi-annually; 1 (one) annual and 1 (one) semi-annual inspections required.
178AB437th Air Freight TerminalLoading Dock/Door-13> 18,000Dock Leveler (Elec-Hyd Operated)N/AN/ARITE-HITETWCFSemi-Annual & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in half amounts semi-annually; 1 (one) annual and 1 (one) semi-annual inspections required.
178AB437th Air Freight TerminalLoading Dock/Door-14> 18,000Dock Leveler (Elec-Hyd Operated)N/AN/ARITE-HITETWCFSemi-Annual & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in half amounts semi-annually; 1 (one) annual and 1 (one) semi-annual inspections required.
178AB437th Air Freight TerminalLoading Dock/Door-15> 18,000Dock Leveler (Elec-Hyd Operated)N/AN/ARITE-HITETWCFSemi-Annual & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in half amounts semi-annually; 1 (one) annual and 1 (one) semi-annual inspections required.
178AB437th Air Freight TerminalLoading Dock/Door-17> 18,000Dock Leveler (Elec-Hyd Operated)N/A07JD 481928MN/ARITE-HITETWCFSemi-Annual & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in half amounts semi-annually; 1 (one) annual and 1 (one) semi-annual inspections required.
178AB437th Air Freight TerminalLoading Dock/Door-18> 18,000Dock Leveler (Elec-Hyd Operated)N/A07JD 481935MN/ARITE-HITETWCFSemi-Annual & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in half amounts semi-annually; 1 (one) annual and 1 (one) semi-annual inspections required.
178AB437th Air Freight TerminalLoading Dock/Door-19> 18,000Dock Leveler (Elec-Hyd Operated)N/A09JD 480512MN/ARITE-HITETWCFSemi-Annual & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in half amounts semi-annually; 1 (one) annual and 1 (one) semi-annual inspections required.
178AB437th Air Freight TerminalLoading Dock/Door-20> 18,000Dock Leveler (Elec-Hyd Operated)N/A07JD 481930MN/ARITE-HITETWCFSemi-Annual & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in half amounts semi-annually; 1 (one) annual and 1 (one) semi-annual inspections required.
178AB437th Air Freight TerminalLoading Dock/Door-21> 18,000Dock Leveler (Elec-Hyd Operated)N/A09JD 480513MN/ARITE-HITETWCFSemi-Annual & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in half amounts semi-annually; 1 (one) annual and 1 (one) semi-annual inspections required.
178AB437th Air Freight TerminalLoading Dock/Door-22> 18,000Dock Leveler (Elec-Hyd Operated)N/A07JD 481929MN/ARITE-HITETWCFSemi-Annual & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in half amounts semi-annually; 1 (one) annual and 1 (one) semi-annual inspections required.
178AB437th Air Freight TerminalLoading Dock/Door-23> 18,000Dock Leveler (Elec-Hyd Operated)N/A09JD 480516MN/ARITE-HITETWCFSemi-Annual & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in half amounts semi-annually; 1 (one) annual and 1 (one) semi-annual inspections required.
178AB437th Air Freight TerminalLoading Dock/Door-24> 18,000Dock Leveler (Elec-Hyd Operated)N/A07JD 481933MN/ARITE-HITETWCFSemi-Annual & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in half amounts semi-annually; 1 (one) annual and 1 (one) semi-annual inspections required.
178AB437th Air Freight TerminalLoading Dock/Door-25> 18,000Dock Leveler (Elec-Hyd Operated)N/AN/ARITE-HITETWCFSemi-Annual & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in half amounts semi-annually; 1 (one) annual and 1 (one) semi-annual inspections required.
178AB437th Air Freight TerminalLoading Dock/Door-26> 18,000Dock Leveler (Elec-Hyd Operated)N/A07JD 481932MN/ARITE-HITETWCFSemi-Annual & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in half amounts semi-annually; 1 (one) annual and 1 (one) semi-annual inspections required.
178AB437th Air Freight TerminalLoading Dock/Door-27> 18,000Dock Leveler (Elec-Hyd Operated)N/A09JD 480516MN/ARITE-HITETWCFSemi-Annual & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in half amounts semi-annually; 1 (one) annual and 1 (one) semi-annual inspections required.
178AB437th Air Freight TerminalLoading Dock/Door-28> 18,000Dock Leveler (Elec-Hyd Operated)N/A07JD 481927MN/ARITE-HITETWCFSemi-Annual & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in half amounts semi-annually; 1 (one) annual and 1 (one) semi-annual inspections required.
178AB437th Air Freight TerminalLoading Dock/Door-29> 18,000Dock Leveler (Elec-Hyd Operated)N/A09JD 480511MN/ARITE-HITETWCFSemi-Annual & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in half amounts semi-annually; 1 (one) annual and 1 (one) semi-annual inspections required.
178AB437th Air Freight TerminalLoading Dock/Door-30> 18,000Dock Leveler (Elec-Hyd Operated)N/A07JD 481923MN/ARITE-HITETWCFSemi-Annual & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in half amounts semi-annually; 1 (one) annual and 1 (one) semi-annual inspections required.
178AB437th Air Freight TerminalLoading Dock/Door-31> 18,000Dock Leveler (Elec-Hyd Operated)N/A07JD 481936MN/ARITE-HITETWCFSemi-Annual & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in half amounts semi-annually; 1 (one) annual and 1 (one) semi-annual inspections required.
178AB437th Air Freight TerminalLoading Dock/Door-32> 18,000Dock Leveler (Elec-Hyd Operated)N/A07JD 481934MN/ARITE-HITETWCFSemi-Annual & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in half amounts semi-annually; 1 (one) annual and 1 (one) semi-annual inspections required.
512AB437th Maint. Lox Cart Maint ShopBldg 512 Mono ECH2000MONORAIL/ECHN/AL-0606PZN/ACMTWCFAnnual$0.00$0.00$0.00$0.00$0.00
515AB437th Maint. Corrosion Control Shop#1 Telescoping Mast on West End1000UHDG Manlift Service PlatformN/ACRANE #1AERO SYSTEMS CORPAERO SYSTEMS CORPTWCFAnnual$0.00$0.00$0.00$0.00$0.00
515AB437th Maint. Corrosion Control Shop#2 Telescoping Mast on East End1000UHDG Manlift Service PlatformN/ACRANE #2AERO SYSTEMS CORPAERO SYSTEMS CORPTWCFAnnual$0.00$0.00$0.00$0.00$0.00
515AB437th Maint. Corrosion Control ShopBoiler Room Monorail2000MONORAIL/ECHN/A693670N/AHARRINGTONTWCFAnnual$0.00$0.00$0.00$0.00$0.00
532AB437th Maint. / Boeing / Pneudraulics ShopBldg 532 Jib1000MAST JIB/ECHQG7306LA 306 VLUNKNOWNCOFFINGTWCFAnnual$0.00$0.00$0.00$0.00$0.00
532AB437th Maint. / Boeing / Pneudraulics ShopBldg 532 Bridge1000UH PUSH BRIDGE/ECHQG7242L4957XNGORBELCMTWCFAnnual$0.00$0.00$0.00$0.00$0.00
536AB437th Maint. Sheet Metal/Metals Tech/NDI ShopsBldg 536-Mono-110000MONORAIL/EWRHN/A1828719801N/AR&MTWCFAnnual$0.00$0.00$0.00$0.00$0.00
536AB437th Maint. Sheet Metal/Metals Tech/NDI ShopsBldg 536-Mono-210000MONORAIL/EWRHN/A1828729801N/AR&MTWCFAnnual$0.00$0.00$0.00$0.00$0.00
536AB437th Maint. Sheet Metal/Metals Tech/NDI ShopsBldg 536-Mono-310000MONORAIL/EWRHN/AQGA729N/AP&H HEVI-LIFTTWCFAnnual$0.00$0.00$0.00$0.00$0.00
536AB437th Maint. Sheet Metal/Metals Tech/NDI ShopsBldg 536-Mono-42000MONORAIL/EWRHN/A203674N/AP&HTWCFAnnual$0.00$0.00$0.00$0.00$0.00
536AB437th Maint. Sheet Metal/Metals Tech/NDI ShopsBldg 536-Bridge-120000TRDG BRIDGE/EWRH973012011822329701GAFFEYR&MTWCFAnnual$0.00$0.00$0.00$0.00$0.00
543AB437th Maint. / Boeing/ NASA/ Tire ShopBldg 543 Bay 148000UHSG BRIDGE/ECHx4 (2x4K + 2x20K)N/A(20K) 1E: H-015LLSOUTHERN CRANE ENGINEERINGCMTWCFMonthly & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in equal amounts monthly; 1 (one) annual and 12 monthly inspections required.
543(20K) 1W: H-016LL
543(4K) 2E: L-0020LL
543(4K) 2W: L-0016LL
543AB437th Maint. / Boeing/ NASA/ Tire ShopBldg 543 Bay 238000UHSG BRIDGE/ECHx4 (2x4K + 2x15K)N/A(15K) 1E: H-008LLSOUTHERN CRANE ENGINEERINGCMTWCFMonthly & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in equal amounts monthly; 1 (one) annual and 12 monthly inspections required.
543(15K) 1W: H-016LL
543(4K) 2E: L-0017LL
543(4K) 2W: L-0024LL
543AB437th Maint. / Boeing/ NASA/ Tire ShopBldg 543 Bay 338000UHSG BRIDGE/ECHx4 (2x4K + 2x15K)N/A(15K) 1E: H-010LLSOUTHERN CRANE ENGINEERINGCMTWCFMonthly & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in equal amounts monthly; 1 (one) annual and 12 monthly inspections required.
543(15K) 1W: H-011LL
543(4K) 2E: L-0021LL
543(4K) 2W: L-0013LL
543AB437th Maint. / Boeing/ NASA/ Tire ShopBldg 543 Bay 438000UHSG BRIDGE/ECHx4 (2x4K + 2x15K)N/A(15K) 1E: H-004LLSOUTHERN CRANE ENGINEERINGCMTWCFMonthly & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in equal amounts monthly; 1 (one) annual and 12 monthly inspections required.
543(15K) 1W: H-015LL
543(4K) 2E: L-0022LL
543(4K) 2W: L-0014LL
543AB437th Maint. / Boeing/ NASA/ Tire ShopBldg 543 Bay 548000UHSG BRIDGE/ECHx4 (2x4K + 2x20K)N/A(20K) 1E: H-017LL
This Hoist is O.O.C.SOUTHERN CRANE ENGINEERINGCMTWCFMonthly & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in equal amounts monthly; 1 (one) annual and 12 monthly inspections required.
543(20K) 1W:H-014LL
543(4K) 2E: L-0009LL
543(4K) 2W: L-0018LL
543AB437th Maint. / Boeing/ NASA/ Tire ShopBldg 543 Bay 638000UHSG BRIDGE/ECHx4 (2x4K + 2x15K)N/A(15K) 1E: H-005LLSOUTHERN CRANE ENGINEERINGCMTWCFMonthly & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in equal amounts monthly; 1 (one) annual and 12 monthly inspections required.
543(15K) 1W: H-002LL
543(4K) 2E: L-0010LL
543(4K) 2W: L-0011LL
543AB437th Maint. / Boeing/ NASA/ Tire ShopBldg 543 Bay 738000UHSG BRIDGE/ECHx4 (2x4K + 2x15K)N/A(15K) 1E: H-005LLSOUTHERN CRANE ENGINEERINGCMTWCFMonthly & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in equal amounts monthly; 1 (one) annual and 12 monthly inspections required.
543(15K) 1W: H-009LL
543(4K) 2E: L-0019LL
543(4K) 2W: L-0012LL
543AB437th Maint. / Boeing/ NASA/ Tire ShopBldg 543 Bay 838000UHSG BRIDGE/ECHx4 (2x4K + 2x15K)N/A(15K) 1E: H-008LLSOUTHERN CRANE ENGINEERINGCMTWCFMonthly & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in equal amounts monthly; 1 (one) annual and 12 monthly inspections required.
543(15K) 1W: H-0012LL
543(4K) 2E: L-0015LL
543(4K) 2W: L-0023LL
543AB437th Maint., "Wash Bay Room"543-9 Wash Bay Rm1000JIB/CHAINFALLN/A543-9 CFSOUTHERN CRANE ENGINEERINGYALETWCFMonthly & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in equal amounts monthly; 1 (one) annual and 12 monthly inspections required.
543AB437th Maint., "Supply/Kit Room"543-10 Supply/Kit Rm20000TRSG BRIDGE/EWRH7731W313125ADESHAZOYALETWCFMonthly & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in equal amounts monthly; 1 (one) annual and 12 monthly inspections required.
543AB437th Maint., "Tire Shop Area"543-11-J1 Parts Washer1000JIB/ECHN/AHHC006N/ADAYTONTWCFMonthly & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in equal amounts monthly; 1 (one) annual and 12 monthly inspections required.
543AB437th Maint., "Tire Shop Area"543-11-J2 Parts Washer1000JIB/ECHN/AHHC003N/ADAYTONTWCFMonthly & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in equal amounts monthly; 1 (one) annual and 12 monthly inspections required.
543AB437th Maint., "Tire Shop Area"543-11-J3 Tire Torque Machine300JIB/PNEUMATIC/CHAINFALL616276SS6937YVN/ACMTWCFMonthly & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in equal amounts monthly; 1 (one) annual and 12 monthly inspections required.
544ABBoeing Eng Trailer Maint Shop, "Main Bay"BLDG 544 MAIN BAY28000UHSG BRIDGE/EWRHx3 (1x20K + 2x4K)1134690-1(4K) N: 532-20-11918ACCOACCOTWCFMonthly & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in equal amounts monthly; 1 (one) annual and 12 monthly inspections required.
544(20K) C: 533-20-8931
544(4K) S: 532-20-11919
544ABBoeing Eng Trailer Maint Shop, "Supply Room"BLDG 544 SUPPLY AREA24000UHSG BRIDGE/EWRHx2 (1x4K + 1x20K)1134690-18(20K) N: 533-20-8932ACCOACCOTWCFMonthly & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in equal amounts monthly; 1 (one) annual and 12 monthly inspections required.
544(4k) S: 532-20-11920
548AB437th AGE Equip Maint ShopBC116000UHSG BRIDGE/EWRHN/A140608SHEPHARD NILESSHEPHARD NILESTWCFMonthly & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in equal amounts monthly; 1 (one) annual and 12 monthly inspections required.
548AB437th AGE Equip Maint ShopH018000MONORAIL/EWRHN/A2080695ETRAN RAILYALETWCFMonthly & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in equal amounts monthly; 1 (one) annual and 12 monthly inspections required.
548AB437th AGE Equip Maint ShopH028000MONORAIL/EWRHN/A2080695CTRAM RAILYALETWCFMonthly & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in equal amounts monthly; 1 (one) annual and 12 monthly inspections required.
548AB437th AGE Equip Maint ShopH038000MONORAIL/EWRHN/A2080695GTRAM RAILYALETWCFMonthly & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in equal amounts monthly; 1 (one) annual and 12 monthly inspections required.
548AB437th AGE Equip Maint ShopH048000MONORAIL/EWRHN/A2080695ATRAM RAILYALETWCFMonthly & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in equal amounts monthly; 1 (one) annual and 12 monthly inspections required.
548AB437th AGE Equip Maint ShopJT024000JACK TEST STAND/ECHN/AL1929XFJACK TEST STANDCMTWCFMonthly & Annual$0.00$0.00$0.00$0.00$0.00Provide one price, which can be billed in equal amounts monthly; 1 (one) annual and 12 monthly inspections required.
551AB315th Contengency Reserve Flight (CRF) Maint Shop/StorageBldg 551 Main Bay7000UHSG BRIDGE/EWRHN/AH29596N/AROBBINS & MYERSO&MAnnual$0.00$0.00$0.00$0.00$0.00
551AB315th Contengency Reserve Flight (CRF) Maint Shop/StorageBldg 551 Tool Room2000MONORAIL/CHAINFALLN/A460949N/AHARRINGTONO&MAnnual$0.00$0.00$0.00$0.00$0.00
570AB437th Maint Fuel Cell ShopBldg 570 Main Bay250MONORAIL/ECHN/A00117687N/ATWCFAnnual$0.00$0.00$0.00$0.00$0.00Hoist downrated to 250 lbs
610ABBase Supply Warehouse (LRS)Roll-Up Door-145000Dock Leveler (Manual Operated)N/AN/AN/AMcGUIREO&MAnnual$0.00$0.00$0.00$0.00$0.00
610ABBase Supply Warehouse (LRS)Roll-Up Door-845000Dock Leveler (Manual Operated)N/AN/AN/AMcGUIREO&MAnnual$0.00$0.00$0.00$0.00$0.00
610ABBase Supply Warehouse (LRS)Roll-Up Door-945000Dock Leveler (Manual Operated)N/AN/AN/AMcGUIREO&MAnnual$0.00$0.00$0.00$0.00$0.00
610ABBase Supply Warehouse (LRS)Roll-Up Door-1245000Dock Leveler (Manual Operated)N/AN/AN/AMcGUIREO&MAnnual$0.00$0.00$0.00$0.00$0.00
610ABBase Supply Warehouse (LRS)Roll-Up Door-1345000Dock Leveler (Manual Operated)N/AN/AN/AMcGUIREO&MAnnual$0.00$0.00$0.00$0.00$0.00
610ABBase Supply Warehouse (LRS)Roll-Up Door-1445000Dock Leveler (Manual Operated)N/AN/AN/AMcGUIREO&MAnnual$0.00$0.00$0.00$0.00$0.00
688ABFuel Truck AreaShop Area2000MONORAIL/CHAINFALLN/AS3856PWN/ACMO&MAnnual$0.00$0.00$0.00$0.00$0.00
700AB437th Maint HSC Aircraft Insp HangarRear of Hangar, Flt Line side10000UHSG BRIDGE/EWRH70 09770 097GRAND TRAVERSE CRANEGRAND TRAVERSE CRANETWCFAnnual$0.00$0.00$0.00$0.00$0.00
731ABRed Horse Maint ShopVehicle Maint. Area10000TRSG BRIDGE/EWRH215-5237WR5B2753RFSYSTEM SPECIALTIES, INCCOFFINGO&MAnnual$0.00$0.00$0.00$0.00$0.00
1990ABAAFES - BXS/N 1Dock Leveler (Manual Operated)N/AN/AN/ADOCK LEVELERO&MAnnual$0.00$0.00$0.00$0.00$0.00
1990ABAAFES - BXS/N 2Dock Leveler (Manual Operated)N/AN/AN/ADOCK LEVELERO&MAnnual$0.00$0.00$0.00$0.00$0.00
328WSAFSBnVehicle Maint. Area20000TRDG BRIDGE/EWRH1720TBDMILWAUKEE CRANEACCO-WRIGHTO&MAnnual$0.00$0.00$0.00$0.00$0.00Hoist downrated to 20,000 lbs
455WSAFSBnBay-210000TRDG BRIDGE/EWRHT35318T35318-HPHILIDELPHIA CRANEP&HO&MAnnual$0.00$0.00$0.00$0.00$0.00
455WSAFSBnBay-16000TRDG BRIDGE/EWRH455-1455-1 HOISTUNKNOWNP&HO&MAnnual$0.00$0.00$0.00$0.00$0.00
850WSAFSBnMain Bay Area2000UHSG BRIDGE/EWRH850.1.1WAW217003HECOYALEO&MAnnual$0.00$0.00$0.00$0.00$0.00Hoist downrated to 2,000 lbs
1660WSAFSBnVehicle Maint. Area70000TRDG BRIDGE/EWRHUNKNOWN303323 58728950 L/97HYDRO POWERHYDRO POWERO&MAnnual$0.00$0.00$0.00$0.00$0.00
1660WSAFSBnVehicle Maint. Area20000TRDG BRIDGE/EWRHUNKNOWNHYDRO POWERHYDRO POWERO&MAnnual$0.00$0.00$0.00$0.00$0.00
1681WSAFSBn1681-1 Veh Maint Area15000UHSG BRIDGE/EWRHCD-32923BB1938524AP&HYALEO&MAnnual$0.00$0.00$0.00$0.00$0.00
1681WSAFSBn1681-2 Veh Maint Area15000UHSG BRIDGE/EWRHCD-33110BB2008157AP&HYALEO&MAnnual$0.00$0.00$0.00$0.00$0.00
79WSOrdnanceOutside Covered Area4000UHSG BRIDGE/ECH489-07A52299503ENGINEERED SYSTEMSR&MO&MAnnual$0.00$0.00$0.00$0.00$0.00Hoist downrated to 4,000 lbs
79WSOrdnanceInside Shop Area1000JIB/ECH91 28426 2235156ABELL-HOWEBUDGITO&MAnnual$0.00$0.00$0.00$0.00$0.00
274WSOrdnance274-137-B17600UHSG BRIDGE/EWRH8288ECIWR5A-103-UDDSOUTHERN CRANECOFFINGO&MAnnual$0.00$0.00$0.00$0.00$0.00
274WSOrdnance274-137-E12000MONORAIL/EWRHN/AWR1C-113-LCDN/ACOFFINGO&MAnnual$0.00$0.00$0.00$0.00$0.00
274WSOrdnance274-137-E22000MONORAIL/EWRHN/AWR1C-112-LCDN/ACOFFINGO&MAnnual$0.00$0.00$0.00$0.00$0.00
274WSOrdnance274-137-E32000MONORAIL/EWRHN/AWR1C-110-LCDN/ACOFFINGO&MAnnual$0.00$0.00$0.00$0.00$0.00
274WSOrdnance274-137-E42000MONORAIL/EWRHN/AWR1C-109-LCDN/ACOFFINGO&MAnnual$0.00$0.00$0.00$0.00$0.00
274WSOrdnance274-137-W12000MONORAIL/EWRHN/AWR1C-108-LCDN/ACOFFINGO&MAnnual$0.00$0.00$0.00$0.00$0.00
274WSOrdnance274-137-W22000MONORAIL/EWRHN/AWR1C-115-LCDN/ACOFFINGO&MAnnual$0.00$0.00$0.00$0.00$0.00
274WSOrdnance274-137-W32000MONORAIL/EWRHN/AWR1C-111-LCDN/ACOFFINGO&MAnnual$0.00$0.00$0.00$0.00$0.00
274WSOrdnance274-137-W42000MONORAIL/EWRHN/AWR1C-114-LCDN/ACOFFINGO&MAnnual$0.00$0.00$0.00$0.00$0.00
274WSOrdnance274-124-12000MONORAIL/EWRHN/A274-124-1HN/AYALEO&MAnnual$0.00$0.00$0.00$0.00$0.00
274WSOrdnance Powder Coating Area274-6K-M6000MONORAIL /CHAINFALLx3 (3x2K)N/A136-10-1057 (2K)N/AACCOO&MAnnual$0.00$0.00$0.00$0.00$0.00
274136-10-1083 (2K)N/AACCO
2745184 (2K)N/AJET
2314WSNPTU "RSA Crane"2314-110000TRDG BRIDGE/EWRHVC92-5282314VIRGINIA CRANEDETROITO&MAnnual$0.00$0.00$0.00$0.00$0.00NAVFAC P-307. Weight test every 4 years. Additional certs required.
2701WSNPTU "Support Sys Process Rm"2701-11000MONORAIL/CHAINFALLN/AUSA3190XJN/ABUDGITO&MAnnual$0.00$0.00$0.00$0.00$0.00NAVFAC P-307. Weight test every 4 years. Additional certs required.
37WS628th LRS Fork Lift Shed37-24000MONORAIL/EWRHN/A9932-LTN/ACOFFINGO&MAnnual$0.00$0.00$0.00$0.00$0.00
900WS628th LRS Vehicle MaintBldg 900 Bay-14000MONORAIL/ECHN/A246298N/ABUDGITO&MAnnual$0.00$0.00$0.00$0.00$0.00
900WS628th LRS Vehicle MaintBldg 900 Bay-24000MONORAIL/ECHN/A246299N/ABUDGITO&MAnnual$0.00$0.00$0.00$0.00$0.00
900WS628th LRS Vehicle MaintBldg 900 Bay-34000MONORAIL/ECHN/A246300N/ABUDGITO&MAnnual$0.00$0.00$0.00$0.00$0.00
3125WSCoastal Riverine SQD (CRS) Vehicle MaintMain Shop Area30000VEHICLE LIFTN/ASM300 / RFL25N/AROTARY LIFTO&MAnnual$0.00$0.00$0.00$0.00$0.00
Total$0.00$0.00$0.00$0.00$0.00
O&M$0.00$0.00$0.00$0.00$0.00
TWCF$0.00$0.00$0.00$0.00$0.00
Totals$0.00$0.00$0.00$0.00$0.00

&K000000 &"Arial,Bold"&14&K000000JBCHS MASTER CRANE LIST

Repair Pricing

Notes:
This tab requires inputs. Please complete green highlighted cells only.
The Contracting Officer has determined there is a high probability of adequate price competition for this acquisition.
Under the current contract, on average, $56,000 per year for service calls/repairs. No guarantee this amount will materialize; could be more or less.
Rate, fully burdned, will be utilized for service calls and repairs.
Mark-up will be applied to material/subcontractor costs only.
Base Period
HoursRateTotal
Labor Costs80$0
AmountMark-upTotal
Material/Subcontractor Costs$56,000$56,000

Total Price OP-1 (Base Year) $56,000

Option Period 1
HoursRateTotal
Labor Costs80$0
AmountMark-upTotal
Material/Subcontractor Costs$56,000$56,000

Total Price OP-2 (Option Year-1) $56,000

Option Period II
HoursRateTotal
Labor Costs80$0
AmountMark-upTotal
Material/Subcontractor Costs$56,000$56,000

Total Price OP-3 (Option Year-2) $56,000

Option Period III
HoursRateTotal
Labor Costs80$0
AmountMark-upTotal
Material/Subcontractor Costs$56,000$56,000

Total Price OP-4 (Option Year-3) $56,000

Option Period IV
HoursRateTotal
Labor Costs80$0
AmountMark-upTotal
Material/Subcontractor Costs$56,000$56,000

Total Price OP-5 (Option Year-4) $56,000

Total Price

Notes:
No inputs are required on this tab.
The Contracting Officer has determined there is a high probability of adequate price competition for this acquisition.
Repair pricing are just estimates based on last year's requirements. There is no guarantee that future annual repairs will be issued. Pricing is being used for evaluation purposes.
Price
Base Period (PMI)$0
Ordering Period-1 (Repairs)$40,000
Total Order Period-1$40,000
Option Period I (PMI)$0
Ordering Period-2 (Repairs)$40,000
Total Order Period-2$40,000
Option Period II (PMI)$0
Ordering Period-3 (Repairs)$40,000
Total Order Period-3$40,000
Option Period III (PMI)$0
Ordering Period-4 (Repairs)$40,000
Total Order Period-4$40,000
Option Period IV (PMI)$0
Ordering Period-5 (Repairs)$40,000
Total Order Period-5$40,000

Total Evaluated Price $200,000