Pricing Schedule.pdf
PDF 123 KB Posted
- Attached to
- Demo B5276 & B8129 Amendment 0001
- Solicitation number
- FA466126Q0065
About this file
This is a Pricing Schedule for demolition work on two federal buildings.
The document specifies two separate demolition line items for Buildings 5276 and 8129, each priced as a lump sum (LS). Item 1 (FNWZ 15-0059) covers the complete demolition of Building 5276, while Item 2 (FNWZ 25-0129) covers the complete demolition of Building 8129. Both items are comprehensive, encompassing all design, survey, layout, plant, labor, supplies, equipment, hauling, permits, abatement, materials, supervision, and incidentals necessary to complete the demolition work in compliance with respective drawings and specifications. Bidders are required to provide pricing for each line item, with a total construction cost calculated by summing both items.
The contract performance period is 60 calendar days total, inclusive of all project phases: mobilization, submittal approval, abatement, actual demolition work, system testing, and closeout documentation. The performance schedule includes 5 working days of anticipated weather delays as part of the 60-day period. No additional weather-related time extensions will be granted until the 5 anticipated weather days have been exceeded and approved by the Contracting Officer.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment FA466126Q00650001 SF 30.pdf | ||
| Wage Determination.pdf | ||
| Pricing Worksheet.xlsx | XLSX spreadsheet | |
| AF Form 3065.xlsx | XLSX spreadsheet | |
| Statement of Work.pdf | ||
| Solicitation - FA466126Q0065.pdf | ||
| AF Form 3064.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment D Pricing Schedule: Demo Buildings 5276 & 8129
0001 Base Bid - Item 1 – FNWZ 15-0059 – Demo Building 5276
This Item includes all design, survey, layout, plant, labor, supplies, equipment, hauling, permits, abatement, materials, supervision and incidentals required to complete all work to demolish the existing Building 5276, in compliance with the drawings & specifications for FNWZ 15-0059.
1 LS: $___________________
0002 Base Bid - Item 2 – FNWZ 25-0129 – Demo Building 8129
This Item includes all design, survey, layout, plant, labor, supplies, equipment, hauling, permits, abatement, materials, supervision and incidentals required to complete all work to demolish the existing Building 8129, in compliance with the drawings & specifications for FNWZ 25-0129.
1 LS: $___________________
Total Construction Cost: $________ _______
CONTRACT PERFORMANCE TIME:
1. Total of 60 calendar days to complete the work.
2. Performance time includes 5 working days of anticipated weather. No additional time weather related delays will be granted until these 5 anticipated weather days have been exceeded and approved by the Contracting Officer.
3. Performance time includes mobilization, submittal approval, abatement, actual demolition work, perform system testing, and close out documents.
END NARRATIVE