Pricing_Proposal(reference_only).pdf

PDF 194 KB Posted

Attached to
County Wide Parks and Conservation Resources (PCR) Roof Replacement Contract STEP 2
Solicitation number
23-0653-ITB-C STEP 2
Issued by
Pinellas County, Clewiston City, Florida

About this file

This document is a Pricing Proposal for the County Wide Parks and Conservation Resources (PCR) Roof Replacement Contract, issued by a Florida government entity through Invitation to Bid - Construction (ITB-C) #23-0653-ITB-C. The contract covers a comprehensive roof replacement project for multiple structures, with an estimated 36-month duration. The scope includes reroof work using 3 Tab 30-year GFA shingles (Owens Corning TruDefinition Duration Shingles in Desert Tan), with detailed line items for various replacement components such as sheathing, underlayment, fascia, shadow board, drip edges, and skylights. The project encompasses 38,636 square feet of roofing, with additional quantities for specific replacement elements like 3,220 square feet of sheathing and 10 units each of different skylight sizes.

The pricing proposal provides a detailed breakdown of labor and material costs, including hourly rates for specialized workers like Journeyman Roofers, Roofer Helpers, Carpenters, and their respective helpers. The bid includes provisions for equipment usage such as trucks, dump trucks, and crane operations, with 50 hourly rates specified for various vehicles. Additional cost considerations include 2,000 pounds of construction debris disposal. The contract is structured for standard working hours (Monday through Friday, 8 AM to 5 PM), with line items allowing for transparent pricing of different project components. While the total contract value is not explicitly calculated in the document, the comprehensive pricing structure suggests a thorough approach to budgeting and cost management for the roof replacement project.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Invitation to Bid - Construction (ITB-C) #23-0653-ITB-C Title: County Wide Parks and Conservation Resources (PCR) Roof Replacement Contract

9. PRICING PROPOSAL

TABLE 1

Estimated Quantity (36 month)

Line Item Description Quantity Unit of

Measure Unit Cost Total

1 Reroof project: 3 Tab 30-year GFA shingles, Owens Corning TruDefinition

Duration Shingles in Desert Tan, including labor, material, overhead and profit during standard working hours. (8:00 AM to 5:00 PM)

38,636 sq. ft.

2 Replacement of 3/4 sheathing, including all labor and materials.

3,220 sq. ft.

3 Replacement of Self Adhesive

Underlayment, including all labor and materials

38,635 sq. ft.

4 Replacement of Fascia, including all labor and materials (2 x 6 and 2 x 8) 500 Linear Foot

5 Replacement of Shadow Board including labor and materials 800 Linear Foot

6 Cooper replacement of drip edge, including labor and materials.

350 Linear Foot

7 Aluminum replacement of drip edge, including labor and materials.

2,500 Linear Foot

8 Galvanized replacement of drip edge, including labor and materials 830 Linear Foot

9 4' x 4' Replacement of Skylights, including labor and materials.

10 Unit

10 3' x 3' Replacement of Skylights, including labor and materials.

10 Unit

11 2' x 2' Replacement of Skylights, including labor and materials.

10 Unit

Invitation to Bid - Construction (ITB-C) #23-0653-ITB-C Title: County Wide Parks and Conservation Resources (PCR) Roof Replacement Contract

Line Item Description Quantity Unit of

Measure Unit Cost Total

12 Journeyman Roofer, standard working hours (Monday through Friday 8 AM to

5 PM)

800 Hourly

13 Roofer Helper, standard working hours

(Monday through Friday 8 AM to 5

PM)

800 Hourly

14 Carpenter, standard working hours

(Monday through Friday, 8 AM to 5

PM)

400 Hourly

15 Carpenter helper, standard working hours (Monday through Friday, 8 AM to 5 PM)

400 Hourly

17 Truck 50 Hourly

18 Dump Truck 50 Hourly

19 Disposal of all construction debris 2,000 pound

20 Crane and Operator 50 Hourly

TOTAL