Preliminary_Staff_Report_(For_Legistar_only).docx
DOCX document 49 KB Posted
- Solicitation number
- 24-1061-ITB-C
- Issued by
- Pinellas County, Clewiston City, Florida
About this file
This is a Preliminary Staff Report from the Purchasing Department on behalf of the Utilities Department for a county-level water infrastructure contract in Florida. The contract, Bid No. ###-####-X, is for Annual Water and Reclaimed Water Repair and Extensions covering fiscal years 2024-2026, with the intent to repair, rehabilitate, and replace potable and reclaimed water pipes throughout the county. The contract will be awarded to the top-ranked firm for a not-to-exceed amount of $X,XXX,XXX, with a 730-consecutive calendar day completion timeline. The work includes comprehensive water infrastructure services such as directional drilling, excavation, pipe installation, valve replacements, fire hydrant relocations, roadway restoration, and water pipe disinfection.
The project will be funded through the Water/Sewer Fund, with an engineer's estimate of $5,782,277.50. The contract strategy focuses on efficiency by consolidating multiple smaller infrastructure projects into a single work-order contract, which reduces overall construction time and provides cost benefits to the county. The approach also allows flexibility to address unanticipated infrastructure needs, such as emergency failures. Key project managers include Carlos Solis (Project Manager), Misael Munoz (Maintenance Division Director), Jeremy Waugh (Utilities Director), and Merry Celeste (Purchasing Director). The contract aligns with the county's strategic plan objectives of fostering economic growth, investing in infrastructure, and delivering first-class public services.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Preliminary Staff Report
New Bid UTL Contract Subject:
Ranking of firms and Agreement with [Contractor Name] for the Annual Water and Reclaimed Water Repair and Extensions FY24-26;
Recommended Action:
Approval of the ranking of firms and Agreement with [Contractor Name] for the Annual Water and Reclaimed Water Repair and Extensions.
· Award recommendation is to the number one ranked firm, [Contractor Name], in the amount of $X,XXX,XXX.
· Contract No. [TBD], in the amount of $X,XXX,XXX. will be completed within 730 consecutive calander days.
· The contract is to accommodate emergency repairs
Strategic Plan:
Foster Continual Economic Growth and Vitality
4.4 Invest in infrastructure to meet current and future needs Deliver First Class Services to the Public and Our Customers
5.2 Be responsible stewards of the public’s resources
5.3 Ensure effective and efficient delivery of county services and support
5.4 Strive to exceed customer expectations
Summary:
The purpose of this project is to effectuate the repair, rehabilitation, and replacement of potable and reclaimed water pipe at various locations throughout the County. This work order contract is necessary in order to construct individual projects that are typically smaller in cost and are more efficiently managed through a work-order type contract, rather than advertising and bidding each small project individually. This approach reduces the overall contruction time frame and provides cost-benefits to the County by grouping numerous small projects into one work order type contract. It also provides the flexibility to address unanticipated infrastructure needs (i.e., emergency failures)
Background/Explanation:
On ______________, the Purchasing Department, on behalf of the Utilities Department, released an invitation to bid with the intent to establish a contract for Bid No. ###-####-X (XX); Annual Water and Reclaimed Water Repair and Extension; PID 24-1061. This contract was competitively solicited to_____ pre-qualified contractors.
Work pertaining to this contract includes all services and materials required to repair, rehabilitate, and /or replace potable and reclaimed water pipe, including but not limited to: directional drilling, excavation, pipe installation, installation of valves abd valve boxes, relocation and/or replacement of fire hydrants, restoration of roadway and disinfection of potable water pipe prior to placement into service.
Fiscal Impact:
| Estimated expenditure not-to-exceed: | $X,XXX,XXX.XX | |
| Engineer’s estimate: | $5,782,277.50 |
Funding for this project is through the Water/ Sewer Fund for FY24-FY26.
Project Manager/Subject Matter Expert:
Carlos Solis, Project Manager
Staff Member Responsible:
Misael Munoz, Maintenance Division Director, Utilities Jeremy Waugh, Director, Utilities Merry Celeste, Director, Purchasing
Partners:
Attachments:
Approved By:
image1.wmf image2.wmf image3.wmf image4.wmf image5.wmf image6.wmf image7.wmf