pre-bid questions and answers B-54660 11.4.26.docx

DOCX document 16 KB Posted

Attached to
TDF - PIF Rooftop Walkway SP
Solicitation number
27-444DHS-MENTH-B-54660
Issued by
Shelby County, Illinois

About this file

This document is a pre-bid questions and answers record for the Illinois Department of Human Services' rooftop walkway pad installation project at the Rushville Transitional Day Facility. The project involves installing anti-slip walkway pads across approximately 2,000 linear feet of rooftop, with 1,600 feet on existing tan TPO VersiFleece roofing and 400 feet on existing white EPDM roofing. The mandatory pre-bid conference was held on November 4, 2026, with bids due November 18, 2026. The contract term extends from execution through June 30, 2027. Vendors must enter through Sally Port gates with facility security protocols including background checks, valid Illinois-issued identification, and foreman-only cell phone access. Work is restricted to normal facility business hours of 7:00 a.m. to 3:30 p.m., unless coordinated with the facility Chief Engineer. Foremen are permitted to schedule preliminary walk-throughs for final measurements and instructions.

Key operational requirements include walkway pad installation in straight paths following current foot traffic patterns, maintaining a minimum 10-foot distance from roof edges and avoiding placement near roof drains. Pads must include yellow borders on VersiFleece roofing areas; Firestone pavers without yellow borders are the only manufacturer-approved option for existing Firestone roofing. Facility staff can lift palletized supplies via forklift, or vendors may bring their own crane. Vendors may store tools in adjacent mechanical rooms and bring portable generators, provided generators are not placed near roof air intakes. Bathroom facilities are not available inside the facility, though vendors may bring port-a-potties. The contract requires 51% self-performance by the prime vendor using permanent, full-time W-2 employees employed for at least 30 consecutive days prior to bid submission, with compliance verified through Department of Labor certified payroll reports and facility visitor logs.

View the file

Other files

File Type Posted
roof map.pdf PDF
Self-Performance Requirements~15.docx DOCX document
RMU150~52.docx DOCX document
Rooftop Walkway standard terms and conditions .pdf PDF
rooftop walkway scope of services B-54660~1.docx DOCX document
Rooftop Walkway standard illinois certifications .pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11/4/26 Pre-bid Conference Questions/Answers B-54660 PIF Rooftop Walkway

Question #1 – Will there be access to power on the roof?

Answer #1 – Yes.

Question #2 – Does the walkway pad need to be installed in a certain pattern?

Answer #2 – Walkway pad needs to be laid in a straight path, where possible, but cannot be installed directly next to the roof drains or roof edge. Pad should be laid to follow the path of current foot traffic. Pad must be installed a minimum of 10 feet from the roof edge.

Question #3 – Can vendor tools be stored inside the facility at the end of the workday?

Answer #3 – Yes, vendor tools can be stored in the mechanical rooms adjacent to the roof.

Question #4 – How will vendor get supplies and tools on the roof?

Answer #4 – Facility staff can lift all supplies onto the roof using a forklift, if loaded on a pallet. Vendor can also bring their own crane to lift supplies.

Question #5 – Can vendor bring their own generator?

Answer #5 – Yes. Generator cannot be placed near the air intakes on roof.

Question #6 – Is smoking allowed on facility grounds?

Answer #6 – Yes, but only in designated smoking areas outside the perimeter fence.

Question #7 – Does pad need to be installed on the wooden ramps and stairs?

Answer #7 – No.Question #8 – Do all walkways need the yellow border?

Answer #8 – Yes, for coverage on all existing VersiFleece roofing. For the existing Firestone roofing, the only option available per manufacturer specs, is Firestone pavers. Firestone pavers do not come equipped with a yellow border.

Question #9 – How will vendor enter facility?

Answer #9 – Vendor will enter through the Sally Port gates. Only the foreman’s truck will be allowed inside the perimeter gates. Vendor’s truck and all vendor staff will be searched prior to entry. All vendor personnel must have a valid IL State issued ID to enter. All vendor personnel must agree to a background check prior to entering facility.

Question #10 – Are cell phones allowed by vendor personnel?

Answer #10 – Only the foreman will be allowed to have a cell phone.

Question #11 – Does path need to be laid up to and on top of the dietary roof?

Answer #11 – Yes. Path must be laid leading up the access stairs to the dietary roof. On top of the dietary roof, path must be laid from stairs to each of the two (2) make up air units.

Question #12 – Will there be access to a bathroom for vendor personnel?

Answer #12 – No access to bathrooms inside facility. Vendor can bring a port-a-potty.

Question #13 – Will vendor be allowed to do a walk-thru prior to construction?

Answer #13 – Yes. The foreman can schedule a walk-thru to get final measurements and instructions.

Question #14 – What days and hours will vendor be allowed to work at facility?

Answer #14 – Work days should be during normal facility business hours of 7a – 330p. However, days and times can be coordinated with the facility Chief Engineer if work needs to be done outside of these hours.