About this file
This document is pre-bid meeting minutes for the State of Hawaii Department of Land and Natural Resources, Division of Boating and Ocean Recreation, regarding the Kikiaola Small Boat Harbor Sand Bypassing project in Kekaha, Kauai. The project requires excavation of approximately 37,600 cubic yards of sand from East Beach and Basin borrow areas, hauling and placement of sand on the eroded west beach, laydown and equipment storage area preparation with best management practices installation, and an optional additive for dredging a portion of the harbor basin pending available funding and permits. The pre-bid meeting was held on May 11, 2026, via Zoom, with a firm bid deadline of May 26, 2026, at 2:00 PM with no extensions granted. All bidders must be registered in HIePRO prior to the deadline. The RFI (Request for Information) submission deadline is May 18, 2026, by 4:00 PM, with responses to be provided by May 21, 2026. The contract duration is 180 consecutive calendar days from the Notice to Proceed, with an estimated construction start date of November 2, 2026, and estimated completion date of May 1, 2027.
The estimated construction cost is $1,800,000, with award based on the lowest responsible bidder's total sum bid for base items. The State of Hawaii has applied for USACE and other permits that are still pending and may delay construction start; contract duration includes time to order, fabricate, and deliver all required materials. Special provisions address labor and material cost escalation allowances for delays in issuing Notice to Proceed. Bidders must hold a valid State of Hawaii Contractor's License Classification "A" and comply with prevailing wage requirements. Performance and payment bonds of 100 percent contract value, proof of tax clearance, Department of Labor and Industrial Relations Certificate of Compliance, and Department of Commerce and Consumer Affairs Certificate of Good Standing are required. Liquidated damages are assessed at $100 per calendar day for delays beyond the completion date. Additional requirements include Commercial General Liability insurance of not less than $1,000,000 per occurrence, Comprehensive Automobile Liability of not less than $1,000,000 combined single limit, and Hawaii Compliance Express annual subscription fees of $12.00 to $15.00. Questions should be directed to finn.d.mccall@hawaii.gov.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JOSH GREEN, M.D.
GOVERNOR | KE KIAʻĀINA
SYLVIA LUKE
LIEUTENANT GOVERNOR | KA HOPE KIAʻĀINA
DAWN N. S. CHANG
CHAIRPERSON
BOARD OF LAND AND NATURAL RESOURCES
COMMISSION ON WATER RESOURCE
MANAGEMENT
MEGHAN L. STATTS
ADMINISTRATOR
BOATING AND OCEAN RECREATION
STATE OF HAWAIʻI | KA MOKUʻĀINA ʻO HAWAIʻI
DEPARTMENT OF LAND AND NATURAL RESOURCES
DIVISION OF BOATING AND OCEAN RECREATION
4 SAND ISLAND ACCESS ROAD
HONOLULU, HAWAII 96819
Job No. B95CK77A / HIePRO Solicitation No. B26002714 Kikiaola Small Boat Harbor Sand Bypassing
Kekaha, Kauai, Hawaii
PRE-BID MEETING MINUTES
Date: May 11, 2026 Time: 11:00 AM Location: Zoom Meeting Bidding Information:
- Bid Deadline: May 26 at 2:00 PM. NO EXTENSIONS WILL BE GRANTED.
- All interested bidders must be registered in HIePRO prior to bid deadline.
- Bidders shall download, fill out, and upload bids on the Proposal From attached to the bid solicitation and all required attachments:
• Apprenticeship Program Participation Form 1 (optional)
• Bid Bond (required)
- RFIs may be submitted through the HIePRO question/answer section of the solicitation or sent directly to: finn.d.mccall@hawaii.gov. All pertinent RFI responses will be responded to via addendum.
- Deadline for submission of RFIs/questions: May 18, 2026 by 4:00 PM.
- Responses to RFIs/questions: May 21, 2026 by 4:00 PM.
Scope of Work:
- Laydown and equipment storage area preparation; install BMPs.
- Excavate sand from beach on east side of harbor, haul and place sand on eroded beach on west site of harbor.
- Bid additive: Dredge a portion of the harbor basin pending available funding and permits.
Construction Items/Additional Work/Time Extensions:
- Staging/stockpiling areas: Coordinate with Engineer and Kauai District staff.
- USACE and other permits applied by the State are still pending; may delay construction start. See bid proposal and Special Provisions for labor and material cost escalation allowance for delay in issuing NTP.
- DOBOR exempt from Building and SMA permits.
- Awarded contractor shall provide submittals/shop drawings as soon as possible after contract award, not Notice to Proceed
- Contract duration noted in bid proposal shall include time require to order, fabricate, and deliver all required materials
- Contract duration: 180 calendar days
- Estimated construction start: November 2, 2026
- Estimated completion date: May 1, 2027
Discussion:
Questions/Answers mailto:finn.d.mccall@hawaii.gov