About this file
This is a Pre-Bid Conference Agenda document for the Loma Port of Entry ANS Traffic Rerouting Project, issued by Colorado Parks & Wildlife's Northwest Region Office located in Grand Junction, Colorado. The project involves constructing a new bypass area for watercraft inspections and disinfections at the Port of Entry, with work including earthwork, asphalt paving, concrete, electrical and water services, and drainage line construction. The pre-bid conference was held on October 15, 2026, at 11:00 AM. The question submission deadline is October 19, 2026, at 5:00 PM, with sealed bids due to the Project Manager at 711 Independent Ave, Grand Junction, Colorado 81505, by October 27, 2026, at 11:30 AM for public bid opening. Contractors are required to include a signed bid schedule acknowledging any addendums, a 5% bid bond, contractor qualifications and references, Colorado labor acknowledgement or justification, and SDVOSB certification if applicable. The contractor shall have 90 calendar days to complete the project, with a target completion date of February 23, 2027, and the parking lot will be closed during construction. Contract processing is expected to take 4-6 weeks after the awarded contractor submits all required documents.
Payment will be made at the unit price for each bid item, with pricing required for all bid items as outlined in the Measurement and Payment Section. Required insurance includes Commercial General Liability, Automobile, Workers Compensation, Builder's Risk, and Pollution Liability. The winning bidder must provide Labor and Material, Performance, and Bid bonds prior to contract execution. The project utilizes federal funding and is subject to the Buy Clean Colorado Act (if over $500,000), Build America Buy America requirements, and Davis Bacon wage determinations. Bid tabulation will be posted to the State Vendor Self Serve website following the bid opening, and the lowest responsible bidder will be contacted for award consideration.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Pre-Bid Meeting Attendance_10.15.26.pdf | ||
| SBP-6.14 BidBond.docx | DOCX document | |
| Loma POE Appendices.pdf | ||
| Loma POE ANS - Addendum No. 2.pdf | ||
| Loma POE Bidding Information and Specifications.pdf | ||
| Loma POE ANS - Addendum No. 1.pdf | ||
| 2026 Loma POE Drawings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Northwest Region Office 711 Independent Ave Grand Junction, CO 81505
PRE-BID CONFERENCE AGENDA
Loma Port of Entry ANS Traffic Rerouting Project
10/15/2026 @ 11:00 AM
IFB1 – 2027*042 Page 1 of 2 C26AU5
Colorado Parks & Wildlife Northwest Region Kendal Bergman – Project Manager Cell Phone: (970) 902-7946 E-mail: kendal.bergman@state.co.us
1. General:
a. All questions shall be sent via email to Kendal Bergman at kendal.bergman@state.co.us
b. Any Addendum will be posted on the State VSS website www.colorado.gov/VSS
c. If issued, all addendums must be acknowledged on the bid proposal. It is the bidder’s responsibility to check for addendums. Failure to acknowledge may result in rejection of bid.
d. Amendments are part of the VSS posting system. Anything posted to VSS including Pre-Bid sign-in sheet, addenda, and Q&A will have an accompanying amendment.
These do not need to be acknowledged. However, additional amendments may have addendum associated with them that will require acknowledgement.
e. Pre-bid attendance list, agenda, and Q&A will also be posted on the State Vendor Self Serve website (www.colorado.gov/VSS).
2. Proposed Project Timing:
a. Question Deadline – 5:00PM on Monday, October 19, 2026. Questions sent after the deadline will not be addressed. A Q&A document will be posted to the State VSS website with answers to submitted questions.
b. Bid Opening – Bids are to be sealed and delivered to the Project Manager at 711 Independent Ave, Grand Junction, Colorado 81505 by Tuesday, October 27th, 2026 at 11:30AM at which time a public bid opening will be held. Email submission of bids will not be accepted.
c. Inclusions – Please include with your bid the following:
• Bid Schedule – signed and acknowledging addendums (if any)
• Bid Bond – 5% of the total bid price
• SDVOSB certification through the U.S. Department of Veterans Affairs (if applicable) http://www.colorado.gov/VSS http://www.colorado.gov/VSS
Northwest Region Office 711 Independent Ave Grand Junction, CO 81505
PRE-BID CONFERENCE AGENDA
Loma Port of Entry ANS Traffic Rerouting Project
10/15/2026 @ 11:00 AM
IFB1 – 2027*042 Page 2 of 2 C26AU5
• Colorado Labor acknowledgement or justification if not using 80% Colorado labor
• Contractor’s Qualifications and References
d. Bid Tabulation - Will be sent to bidders and posted to VSS as quickly as possible following the bid opening. The lowest responsible bidder will be contacted.
e. Notice to Proceed – Contracts can take 4-6 weeks to be processed once all required documents (P&P bonds, insurance certificate, W-9, etc.) are received from the awarded contractor. A Notice to Proceed will be sent promptly once a Contract is issued.
f. Project Schedule – The contractor shall have 90 calendar days to complete the project, unless otherwise provided for in the General Conditions for Capital Construction. CPW’s intent is to close the parking lot during construction. The target completion date is February 23, 2027.
3. Project Information:
a. The project will construct a new bypass area for watercraft inspections and disinfections at the Port of Entry.
b. Work includes, but is not limited to, earthwork, asphalt paving, concrete electrical and water services, and construction a drain line.
c. A price must be provided for all bid items.
d. Be sure to read the Measurement and Payment Section to understand the full extent of what each bid item covers.
e. Payment will be made at the unit price for each bid item. The full quantity will not be paid if not installed.
f. Required insurance will include Commercial General Liability, Automobile, Workers Comp, Builder’s Risk, and Pollution Liability.
g. Labor and Material and Performance bonds will be required from the winning bidder prior to execution of a contract.
h. This project is utilizing Federal funding
• Buy Clean Colorado Act if over $500k
• Build America Buy America
• Davis Bacon applies
File details come from the government source that posted it. Updated .