Pre Award Survey of Prospective Contractor Accounting System Checklist (1).pdf

PDF 130 KB Posted

Attached to
1. 5 Ton Modular Refrigeration System (MRS) Procurement
Solicitation number
N64498-24-R-4057
Issued by

About this file

This document contains a pre-award survey checklist of prospective contractor accounting systems and a related federal contract opportunity for a 1.5 Ton Modular Refrigeration System.

The pre-award survey checklist asks contractors 22 questions regarding their accounting systems and practices, including whether their systems have been audited by the Defense Contract Audit Agency, if they comply with Cost Accounting Standards and Generally Accepted Accounting Principles, and if their systems properly segregate direct and indirect costs. Contractors are asked to provide explanations for their answers.

The related federal contract opportunity is a solicitation from the Department of the Navy Naval Sea Systems Command for a 1.5 Ton Modular Refrigeration System. Responses are due by March 6, 2024. Any questions must be submitted by email to the listed point of contact, as phone calls will not be accepted.

View the file

Other files

File Type Posted
Amendment P00004.pdf PDF
CDRL A014 - Small Business Utilization Report1.pdf PDF
QAs (5 March 2024).docx DOCX document
Amendment 0003.pdf PDF
CDRL A014 - Small Business Utilization Report1.pdf PDF
N6449824R4057 AMENDMENT 0002.pdf PDF
N6449824R4057-0001.pdf PDF
GFI NAVSEA.pdf PDF
GFI NAVSEA.pdf PDF
CDRL A004 - Request for Waivers (RFW)_BH signed.pdf PDF
Attachment 1 -NSWCPD SBPCD August 2018.xlsx XLSX spreadsheet
CDRL A009 - Unauthorized Supplier Purchase Report_BH signed.pdf PDF
CDRL A013 - Electromagnetic (EMI) Test Report.pdf PDF
CDRL A006 - Airborne and Structureborne Noise Test Report_BH signed.pdf PDF
CDRL A012 - Shock and Vibration Test Report.pdf PDF
CDRL A005 - Visual and Operational Test Report_BH signed.pdf PDF
CDRL A002 - Engineering Change Proposal_rev1_BH signed.pdf PDF
CDRL A001 - Product Drawings Models and Associated Lists_rev1_BH signed.pdf PDF
CDRL A010 - Counterfeit Prevention Plan.pdf PDF
CDRL A007 - Diminishing Manufacturing Sources and Material Shortages (DMSMS) Management Plan_BH signed.pdf PDF
CDRL A003 - Request for Variance (RFV)_BH signed.pdf PDF
2_PPD 516-8627963 1.5-ton MRS 20190128.pdf PDF
CDRL A011 - Inclination Test Report.pdf PDF
Solicitation N6449824R4057..pdf PDF
CDRL A008 - Obsolescence Alert Notice_BH signed.pdf PDF
GFI NAVSEA 4340_2 (MRS PPD).pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRE-AWARD SURVEY OF PROSPECTIVE CONTRACTOR ACCOUNTING SYSTEM CHECKLIST

PRE-AWARD SURVEY OF PROSPECTIVE CONTRACTOR ACCOUNTING SYSTEM

Date:

Company Name, Contract Number, and Full Address:

Commercial and Government Agency (CAGE) Code Number: (Found at http://www.dlis.dla.mil/ cage_welcome.asp)

Cognizant Defense Contract Audit Agency (DCAA) office info (Address/phone number/E-mail) - (Found at http://dcaa.mil/office_locator.html)

Company Point of Contact:

(Name, Title, Phone Number, and E-mail address

If the accounting books and records are located at a physical address other than the address provided above, please indicate address here:

Name, Title, and signature of Company Principal (President/VP/Controller, etc) responsible for the design of the Accounting System.

NAME

TITLE

E-MAIL ADDRESS

SIGNATURE DATE

PLEASE ANSWER THE QUESTIONS BELOW:

HAVE YOU READ THE REQUIREMENTS IN THE SF1408? (YES/NO)

HAVE YOU READ THE DCAA PUBLICATION DCAAM 7641.90 - "Information for Contractors" ON

DCAA'S WEBSITE at http:www.dcaa.mil/? (YES/NO)

For each question, check only one box. ALL questions must have explanatory narrative text entered in the boxes. Please provide sufficient detail to describe the process (Including Account Numbers/Process Flow etc.) Each Question must be complete. Do NOT refer to previous answers, (i.e. "See Question 3 Above").

http://www.dlis.dla.mil/ http://dcaa.mil/office_locator.html) http://www.dcaa.mil/

Pre-award Survey of Prospective Contractor Accounting System Checklist

1. Has your organization's Accounting System ever been audited by DCAA?

YES (if Yes, the Offeror should attach a copy of their most recent DCAA audit report to this Modified Pre-Award Survey) or provide the DCAA Report number or DCAA POC info.

NO (if NO, answer N/A to Questions 1.A., 1.B., and 1.C. below)

1.A. If the answer is "Yes" to Question 1 above, when was the audit performed?

Within the past Year

Within the past 3 Years

Greater than 3 Years (PROVIDE THE YEAR THE AUDIT WAS PERFORMED HERE - ).

N/A (Answer to Question 1 is NO)

1.B. If the answer is "Yes" to Question 1 above, did DCAA determine the Accounting System acceptable for award of prospective contracts?

YES

NO (If NO provide an explanation in the box below)

1.C. If the answer is "Yes" to Question 1 above, have there been any changes to the Accounting System since the DCAA audit?

YES (If YES, describe the changes in the box below

NO

2. Is your organization subject to CAS (48 CFR Chapter 99)?

YES (If YES, is it FULL or MODIFIED CAS?) FULL MODIFIED

(If YES (FULL or MODIFIED), the Offeror MUST attach a copy of their most recent audit reports/documentation regarding all CAS compliance or non-compliance issues to this Modified Pre-Award Survey)

NO (If NO provide an explanation in the box below why your organization is exempt and answer N/A to Questions 2.A., 2.B., and 2.C. below)

2.A. Has your organization submitted a CASB disclosure statement (CASB DS-1) to DCAA and has it been determined adequate?

YES (If YES, provide an explanation that validates your answer in the box below)

N/A (Answer to Question 2 is NO)

2.B. Has your organization been notified by DCAA that it is (or may be in) non-compliance with its disclosure statement or CAS?

N/A (N/A, if the answer to Question 2 is NO)

2.c. Is any aspect of this proposal inconsistent with your organization’s disclosed practices or applicable CAS?

N/A (N/A, if the answer to Question 2 is NO or if you have no current, active proposal being considered)

Instruction: If the Contractor is planning on bidding on Cost Type Contracts, the contractor MUST provide explanatory narrative for all of the following questions:

3. Has your organization's Accounting System been audited by an outside Certified Public Accountant/Consultant or other Cognizant Federal Agency other than DCAA?

YES (If YES, the Offeror MUST attach a copy of their most recent audit report to this Modified Pre-Award Survey) NOTE: Do not submit your Annual Financial Audit.

4. Is your organization's Accounting System currently in full operation?

YES (If YES, provide an explanation that validates your answer in the box below).

NO (If NO, provide an explanation in the box below which portions are (1) in operation, (2) set up, but not yet in operation, (3) anticipated, or (4) non-existent)

N/A (If N/A, provide an explanation in the box below)

5. Is your organization's Accounting System in accord with Generally Accepted Accounting Principles (GAAP) Applicable in the Circumstances?

YES (If YES, provide an explanation that validates your answer in the box below)

N/A (N/A, provide an explanation in the box below)

6. Is your organization's Accounting System ready for a DCAA audit?

NO (If NO provide an explanation in the box below as to when you will be ready for an audit)

7. Are the loaded hourly labor rates proposed consistent with your established estimating and accounting principles and procedures and FAR Part 31, Cost Principles? (Answer this Questions "N/A" if you do not have an active proposal)

8. Does the Accounting System provide for the proper segregation of Direct Costs from Indirect Costs?

9. Does the Accounting System provide for the identification and accumulation of Direct Costs by contract?

10. Does the Accounting System provide for a logical and consistent method for the allocation of Indirect Costs to intermediate and final cost objectives? (A contract is a final cost objective.)

YES (If YES, provide an explanation that validates your answer in the box below)

11. Does the Accounting System Provide for the accumulation of costs under general ledger control?

12. Does the Accounting System provide for a timekeeping system that identifies employees' labor by intermediate or final cost objectives?

13. Does the Accounting System provide for a labor distribution system that charges Direct and Indirect labor to the appropriate cost objectives?

YES (If YES, provide an explanation that validates your answer in the box below)

14. Does the Accounting System provide for an interim (at least monthly) determination of costs charged to a contract through routine posting of books of account?

YES (If YES, provide an explanation that validates your answer in the box below)

15. Does the Accounting System provide for an exclusion of costs charged to government contracts of amounts which are not allowable in terms of FAR 31, Contract Cost Principles and Procedures, or other contract provisions?

YES (If YES, provide an explanation that validates your answer in the box below)

16. Does the Accounting System provide for the identification of costs by contract line item and by units (as if each unit or line item were a separate contract) if required by the proposed contract?

YES (If YES, provide an explanation that validates your answer in the box below)

17. Does the Accounting System provide for the segregation of preproduction costs from production costs?

18. Does the Accounting System provide financial information required by contract clauses concerning limitation of cost (FAR 52.232.20) or limitation on payments (FAR 52.216-16)?

YES (If YES, provide an explanation that validates your answer in the box below)

19. Does the Accounting System provide financial information required to support requests for Progress Payments?

20. Is the Accounting System designed, and are the records maintained, in such manner that adequate, reliable data are developed for use in pricing follow-on acquisitions?

21. Is your organization planning on submitting proposals on Cost-Type (FAR 16.3) contracts/task orders?

22. Is your organization currently performing on Cost-Type (FAR 16.3) contracts/task orders?

N/A

PRE-AWARD SURVEY OF PROSPECTIVE CONTRACTOR ACCOUNTING SYSTEM CHECKLIST
1. Has your organization's Accounting System ever been audited by DCAA?
1.A. If the answer is "Yes" to Question 1 above, when was the audit performed?
1.B. If the answer is "Yes" to Question 1 above, did DCAA determine the Accounting System acceptable for award of prospective contracts?
1.C. If the answer is "Yes" to Question 1 above, have there been any changes to the Accounting System since the DCAA audit?
2. Is your organization subject to CAS (48 CFR Chapter 99)?
2.A. Has your organization submitted a CASB disclosure statement (CASB DS-1) to DCAA and has it been determined adequate?
2.B. Has your organization been notified by DCAA that it is (or may be in) non-compliance with its disclosure statement or CAS?
2.c. Is any aspect of this proposal inconsistent with your organization’s disclosed practices or applicable CAS?
3. Has your organization's Accounting System been audited by an outside Certified Public Accountant/Consultant or other Cognizant Federal Agency other than DCAA?
4. Is your organization's Accounting System currently in full operation?
5. Is your organization's Accounting System in accord with Generally Accepted Accounting Principles (GAAP) Applicable in the Circumstances?
7. Are the loaded hourly labor rates proposed consistent with your established estimating and accounting principles and procedures and FAR Part 31, Cost Principles? (Answer this Questions "N/A" if you do not have an active proposal)
8. Does the Accounting System provide for the proper segregation of Direct Costs from Indirect Costs?
9. Does the Accounting System provide for the identification and accumulation of Direct Costs by contract?
10. Does the Accounting System provide for a logical and consistent method for the allocation of Indirect Costs to intermediate and final cost objectives? (A contract is a final cost objective.)
11. Does the Accounting System Provide for the accumulation of costs under general ledger control?
12. Does the Accounting System provide for a timekeeping system that identifies employees' labor by intermediate or final cost objectives?
13. Does the Accounting System provide for a labor distribution system that charges Direct and Indirect labor to the appropriate cost objectives?
14. Does the Accounting System provide for an interim (at least monthly) determination of costs charged to a contract through routine posting of books of account?
15. Does the Accounting System provide for an exclusion of costs charged to government contracts of amounts which are not allowable in terms of FAR 31, Contract Cost Principles and Procedures, or other contract provisions?
Pre-award Survey of Prospective Contractor Accounting System Checklist
16. Does the Accounting System provide for the identification of costs by contract line item and by units (as if each unit or line item were a separate contract) if required by the proposed contract?
17. Does the Accounting System provide for the segregation of preproduction costs from production costs?
19. Does the Accounting System provide financial information required to support requests for Progress Payments?
pricing follow-on acquisitions?
21. Is your organization planning on submitting proposals on Cost-Type (FAR 16.3) contracts/task orders?
22. Is your organization currently performing on Cost-Type (FAR 16.3) contracts/task orders?

File details come from the government source that posted it. Updated .