Power_Transformer_Maintenance_Checklist_Unit_1.pdf
PDF 78 KB Posted
- Attached to
- Life Extension for Deerhaven Unit 1 Transformers
- Solicitation number
- 2026-093
- Issued by
- Alachua County, Graceville City, Florida
About this file
This Power Transformer Maintenance Checklist is a technical document prepared by GRU (Gainesville Regional Utilities) in Florida for the Life Extension for Deerhaven Unit 1 Transformers project. The checklist establishes the comprehensive maintenance and testing requirements for power transformers as part of GRU's initiative to extend the operational life of Unit 1 transformers at the Deerhaven facility for an additional five years. The scope of work encompasses three transformers (T-61, T-62, and T-65), with T-61 and T-62 requiring procurement and replacement of radiators, wiring between transformer cabinets, transformer components, and full testing, while T-65 is limited to testing only. The checklist outlines specific inspection tasks including physical condition assessment, control cabinet inspection, liquid level verification in tanks and bushings, equipment cleaning, temperature monitoring at ambient, winding, and top oil levels, and calibration of temperature gauges with replacement thresholds established at 20 degrees variance.
The maintenance checklist details comprehensive testing protocols that contractors must complete, including power factor (PF) winding testing, winding resistance testing, PF bushing testing, transformer turns ratio (TTR) testing, and excitation testing. Additional requirements include verification of operational safety systems such as pressure relief devices, liquid level alarms, sudden pressure relays coordinated with GRU relay technicians, loss of AC alarms, and pressurized inert gas system inspection. Contractors must verify fan operation and complete a Testing MxOrder inspection sheet, with final closeout responsibility assigned to GRU. The checklist includes designated areas for documenting personnel involved, providing wraup comments, and recording the completion date, ensuring comprehensive documentation and accountability throughout the maintenance and testing process.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Life_Extension_for_Deerhaven_Unit_1_Transformers.pdf | ||
| T61.JPEG | JPEG file | |
| T61_.JPEG | JPEG file | |
| T61___.JPEG | JPEG file | |
| T62.JPEG | JPEG file | |
| T62_Nameplate.JPG | JPG image | |
| T65.JPEG | JPEG file | |
| T62_.JPEG | JPEG file | |
| T61_Nameplate.JPG | JPG image | |
| T62___.JPEG | JPEG file | |
| T65_.JPEG | JPEG file | |
| T65_Nameplate.JPEG | JPEG file | |
| T61_T62_Outline_Drawing.pdf | ||
| Oil_Analysis_T62_20260105_(1).pdf | ||
| T61_T62_Cabinet_Wiring_Diagram_(1).pdf | ||
| Oil_Analysis_T61_20260105_(1).pdf | ||
| Power_Transformer_Maintenance_Checklist_Unit_1_(2).pdf | ||
| Oil_Analysis_T61_20260105.pdf | ||
| DH_Unit_1_Transformers_Life_Extension_Specification_2026-093.docx | DOCX document | |
| T61_T62_Cabinet_Wiring_Diagram.pdf | ||
| Oil_Analysis_T62_20260105.pdf |
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Power Transformer Maintenance
Checklist
Inspect physical condition
Inspect control cabinet
Verify correct liquid level in tanks and bushings
Main tank Bushings
Clean equipment
Ambient temperature
Winding temperature Top oil temperature
Complete PF winding testing Complete Winding Resistance testing
Complete PF bushing testing Complete TTR testing
Complete exitation testing
Winding temperature gauge
Calibrate gauge ( Replace gauge if > 20° off )
First contact Second contact Third contact
Top oil temperature gauge
Calibrate gauge ( Replace gauge if > 20° off )
First contact Second contact Third contact
Verify operation of pressure relief device
Verify operation of liquid level alarm
Verify operation of sudden pressure relay (coordinate with GRU relay tech)
Inspect the pressurized inert gas system
General Inspection
Transformer Testing
Component Inspection
Power Transformer Maintenance
Checklist
Verify "lose of AC" alarm
Verify fans operate
Verify completion of Testing MxOrder inspection sheet
Close Testing MxOrder (By GRU)
Personnel :
Wrap‐up
Comments
Date :