PLA_FAQ24B.pdf

PDF 119 KB Posted

Attached to
Chemical Feed Boiler Replacement
Solicitation number
147625
Issued by
Lucas County, Ohio

About this file

This document is a Project Labor Agreements Fact Sheet issued by the City of Toledo, Ohio, providing guidance on labor agreement requirements for construction projects. The fact sheet applies to all construction projects funded by the City of Toledo or other funding sources that do not exclude Project Labor Agreements, with a threshold of $100,000 or greater. Project Labor Agreements apply to all contractors and subcontractors performing construction work on-site or adjacent to the worksite. The execution timeline requires a pre-job conference to be held within fifteen days of bid award notification between the successful bidder and the Northwest Ohio Building and Construction Trades Council (NWOBTC), with an executed Project Labor Agreement to be delivered to the Division of Purchases and Supplies within fifteen working days from the pre-job conference. The executed agreement must be signed by both the lead contractor and the Executive Secretary of NWOBTC to be deemed valid. No exemptions from the pre-job meeting are granted, even for companies already signatory to collective bargaining agreements.

The fact sheet clarifies that Project Labor Agreements do not affect the City's Minority Business Enterprise Program or override any requirements of the Toledo Municipal Code, which mandates 15 percent minority business enterprise participation for construction projects and 21 percent for HUD-assisted projects. Wages and fringe benefits must be paid according to applicable local collective bargaining agreements. The agreement prohibits strikes, lockouts, slowdowns, picketing, and work stoppages of any nature by the union and its members. The document does not impact manufacturing and fabrication work. Grievances and disputes are addressed through Article VI of the Project Labor Agreement. The fact sheet provides essential procedural information for bidders preparing to submit on the related Chemical Feed Boiler Replacement project.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT LABOR AGREEMENTS

FACT SHEET

When are Project Labor Agreements required?

They are required for all construction projects, $100,000.00 or greater, funded by the City of Toledo or other funding sources that do not exclude Project Labor Agreements.

Who do Project Labor Agreements apply to?

All contractors and sub-contractors performing construction work, within historical definitions, on-site or adjacent to the worksite.

What is the timeframe on execution of a Project Labor Agreement?

Once the successful bidder is notified of bid award, a pre-job conference shall be held within fifteen (15) days of the award notification between the Bidder and the Northwest Ohio Building and Construction Trades Council (“NWOBTC”). An executed Project Labor Agreement must be delivered to the Division of Purchases and Supplies within fifteen (15) working days from pre-job conference with NWOBTC. An executed Project Labor Agreement must have the signature of the lead contractor and the Executive Secretary of the Northwest Ohio Building and Construction Trades Council at a minimum to be deemed valid.

Does the Project Labor Agreement affect the City’s Minority Business Enterprise Program?

No, all successful bidders are required to comply with the Toledo Municipal Code and Toledo Administrative Policy No. 13, which creates a goal-oriented program to meet and/or exceed a level of 15% Minority Business Enterprise participation in construction projects and a level of 21% Minority Business Enterprise participation in HUD-assisted projects.

Can the Project Labor Agreement affect the bidder’s duties under the Toledo Municipal Code?

No, all requirements of the Toledo Municipal Code must be obeyed regardless of any terms in a Project Labor Agreement.

How do I get the Northwest Ohio Building and Construction Trades Council to sign my Project Labor Agreement?

All successful bidders must attend a pre-job meeting with the Northwest Ohio Building and Construction Trades Council in order to gain their signature on a Project Labor Agreement.

If my company is already a signatory to collective bargaining agreement, are we exempt from the pre-job meeting?

No, there are no exemptions from the pre-job meeting.

Does this impact manufacturing and fabrication work?

No.

How will Project Labor Agreements affect wages and fringe benefits?

While under a Project Labor Agreement, wages and fringe benefits shall be paid in accordance with the applicable local collective bargaining agreement.

Will there be any strikes or lockouts?

The Union and its members, agents, representatives and employees shall not allow, incite, encourage, condone or participate in any strike, walkout, slowdown, picketing, sympathy strike or other work stoppage of any nature whatsoever for any cause whatsoever, whether jurisdictional or otherwise, or observe any picket of any nature during the term of a Project Labor Agreement. Any such action by the Union or its members, agents, representatives and employees shall constitute a violation of the Project Labor Agreement.

How will grievances and disputes be handled?

Article VI of the Project Labor Agreement lays out the grievance and dispute process.