Philadelphia District FY25 Projected Dredge Schedule.pdf
PDF 364 KB Posted
- Solicitation number
- W2SD-25-NAD-0001
About this file
This is a PDF presentation detailing the U.S. Army Corps of Engineers (USACE) Philadelphia District's FY25 coastal dredging projects schedule. The document outlines five major beach nourishment projects along the Delaware and New Jersey coasts planned for FY25.
The projects include: 1) Rehoboth & Dewey Beach, DE (450,000 cy, hopper dredge, Sept 2025-Feb 2026), 2) Indian River Inlet Sand Bypass, DE (500,000 cy, hydraulic cutterhead, Feb-May 2026, with work restrictions), 3) Bethany & South Bethany Beach, DE (500,000 cy, hopper/hydraulic cutterhead, Sept 2025-Feb 2026), 4) Great Egg Harbor Inlet to Peck Beach, NJ (1.2M cy, hydraulic cutterhead, Oct 2025-Mar 2025), and 5) Townsends Inlet to Cape May Inlet, NJ (700,000 cy, hydraulic cutterhead, Oct 2025-Mar 2026). All projects are designated for large businesses, with advertisements beginning between June-November 2025. Three of the five projects are noted as being dependent on receipt of adequate FY25 funding. The point of contact is Frank Master, Chief of Civil Works Programs Branch.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Philadelphia District
Coastal Dredging Projects
FY25
NAP POC
Frank Master, Chief, Civil Works Programs Branch
Frank.R.Master@USACE.Army.Mil
Delaware Coastal Combined Contract
Rehoboth Beach & Dewey Beach, De Portion
Construction - Periodic Nourishment
LOCATION: Rehoboth Beach & Dewey
Beach, DE
DREDGE TYPE: Hopper
PLACEMENT: Shoreline
QUANTITY: 450,000 cy
BORROW AREA: Offshore BA B
BUSINESS TYPE: Large
ADVERTISE: JUN 2025
BID OPENING: AUG 2025
COMMENCE DREDGING: SEP 2025
DREDGE COMPLETE: FEB 2026
WORK RESTRICTIONS/WINDOW:
None
Delaware Coast Protection
Indian River Inlet Sand Bypass Plant, DE
Construction – Emergency Periodic Nourishment
LOCATION: Indian River Inlet, DE North
Shore
DREDGE TYPE: Hydraulic Cutterhead
PLACEMENT: Shoreline
QUANTITY: 500,000 cy
BORROW AREA: Inlet BA
BUSINESS TYPE: Large
ADVERTISE: NOV 2025
BID OPENING: DEC 2025
COMMENCE DREDGING: FEB 2026
DREDGE COMPLETE: MAY 2026
WORK RESTRICTIONS/WINDOW: Yes
– No dredging after 28 FEB. Working to extend due to the emergency situation.
Delaware Coastal Combined Contract
Bethany Beach & S. Bethany Beach, DE Portion
Construction General - Periodic Nourishment
FY25 Capability – Dependent on Receipt of
Adequate Funding in FY25.
LOCATION: Bethany Beach & South
Bethany Beach, DE
DREDGE TYPE: Hopper and/or
Hydraulic Cutterhead
PLACEMENT: Shoreline
QUANTITY: 500,000 cy
BORROW AREA: Offshore BA E
BUSINESS TYPE: Large
ADVERTISE: JUN 2025
BID OPENING: AUG 2025
COMMENCE DREDGING: SEP 2025
DREDGE COMPLETE: FEB 2026
Great Egg Harbor Inlet to Peck Beach, NJ
Construction - Periodic nourishment
FY25 Capability – Dependent on Receipt of
Adequate Funding in FY25.
LOCATION: Ocean City, NJ
DREDGE TYPE: Hydraulic Cuttterhead
PLACEMENT: Ocean City (Between
Seaview Road Groin & 14th St.
QUANTITY: 1,200,000 cy
BORROW AREA: Great Egg Harbor
Inlet
BUSINESS TYPE: Large
ADVERTISE: JUL 2025
BID OPENING: AUG 2025
COMMENCE DREDGING: OCT 2025
DREDGE COMPLETE: MAR 2025
Townsends Inlet to Cape May Inlet, NJ
Construction - Periodic Nourishment
FY25 Capability – Dependent on Receipt of
Adequate Funding in FY25.
LOCATION: Avalon & Stone Harbor, NJ
DREDGE TYPE: Hydraulic Cutterhead
PLACEMENT: Shoreline
QUANTITY: 700,000 cy
BORROW AREA: Townsends Inlet
BUSINESS TYPE: Large
ADVERTISE: JUL 2025
BID OPENING: AUG 2025
COMMENCE DREDGING: OCT 2025
DREDGE COMPLETE: MAR 2026