This is a PDF presentation detailing the U.S. Army Corps of Engineers (USACE) Philadelphia District's FY25 coastal dredging projects schedule. The document outlines five major beach nourishment projects along the Delaware and New Jersey coasts planned for FY25.

The projects include: 1) Rehoboth & Dewey Beach, DE (450,000 cy, hopper dredge, Sept 2025-Feb 2026), 2) Indian River Inlet Sand Bypass, DE (500,000 cy, hydraulic cutterhead, Feb-May 2026, with work restrictions), 3) Bethany & South Bethany Beach, DE (500,000 cy, hopper/hydraulic cutterhead, Sept 2025-Feb 2026), 4) Great Egg Harbor Inlet to Peck Beach, NJ (1.2M cy, hydraulic cutterhead, Oct 2025-Mar 2025), and 5) Townsends Inlet to Cape May Inlet, NJ (700,000 cy, hydraulic cutterhead, Oct 2025-Mar 2026). All projects are designated for large businesses, with advertisements beginning between June-November 2025. Three of the five projects are noted as being dependent on receipt of adequate FY25 funding. The point of contact is Frank Master, Chief of Civil Works Programs Branch.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Philadelphia District

Coastal Dredging Projects

FY25

NAP POC

Frank Master, Chief, Civil Works Programs Branch

Frank.R.Master@USACE.Army.Mil

Delaware Coastal Combined Contract

Rehoboth Beach & Dewey Beach, De Portion

Construction - Periodic Nourishment

LOCATION: Rehoboth Beach & Dewey

Beach, DE

DREDGE TYPE: Hopper

PLACEMENT: Shoreline

QUANTITY: 450,000 cy

BORROW AREA: Offshore BA B

BUSINESS TYPE: Large

ADVERTISE: JUN 2025

BID OPENING: AUG 2025

COMMENCE DREDGING: SEP 2025

DREDGE COMPLETE: FEB 2026

WORK RESTRICTIONS/WINDOW:

None

Delaware Coast Protection

Indian River Inlet Sand Bypass Plant, DE

Construction – Emergency Periodic Nourishment

LOCATION: Indian River Inlet, DE North

Shore

DREDGE TYPE: Hydraulic Cutterhead

PLACEMENT: Shoreline

QUANTITY: 500,000 cy

BORROW AREA: Inlet BA

BUSINESS TYPE: Large

ADVERTISE: NOV 2025

BID OPENING: DEC 2025

COMMENCE DREDGING: FEB 2026

DREDGE COMPLETE: MAY 2026

WORK RESTRICTIONS/WINDOW: Yes

– No dredging after 28 FEB. Working to extend due to the emergency situation.

Delaware Coastal Combined Contract

Bethany Beach & S. Bethany Beach, DE Portion

Construction General - Periodic Nourishment

FY25 Capability – Dependent on Receipt of

Adequate Funding in FY25.

LOCATION: Bethany Beach & South

Bethany Beach, DE

DREDGE TYPE: Hopper and/or

Hydraulic Cutterhead

PLACEMENT: Shoreline

QUANTITY: 500,000 cy

BORROW AREA: Offshore BA E

BUSINESS TYPE: Large

ADVERTISE: JUN 2025

BID OPENING: AUG 2025

COMMENCE DREDGING: SEP 2025

DREDGE COMPLETE: FEB 2026

Great Egg Harbor Inlet to Peck Beach, NJ

Construction - Periodic nourishment

FY25 Capability – Dependent on Receipt of

Adequate Funding in FY25.

LOCATION: Ocean City, NJ

DREDGE TYPE: Hydraulic Cuttterhead

PLACEMENT: Ocean City (Between

Seaview Road Groin & 14th St.

QUANTITY: 1,200,000 cy

BORROW AREA: Great Egg Harbor

Inlet

BUSINESS TYPE: Large

ADVERTISE: JUL 2025

BID OPENING: AUG 2025

COMMENCE DREDGING: OCT 2025

DREDGE COMPLETE: MAR 2025

Townsends Inlet to Cape May Inlet, NJ

Construction - Periodic Nourishment

FY25 Capability – Dependent on Receipt of

Adequate Funding in FY25.

LOCATION: Avalon & Stone Harbor, NJ

DREDGE TYPE: Hydraulic Cutterhead

PLACEMENT: Shoreline

QUANTITY: 700,000 cy

BORROW AREA: Townsends Inlet

BUSINESS TYPE: Large

ADVERTISE: JUL 2025

BID OPENING: AUG 2025

COMMENCE DREDGING: OCT 2025

DREDGE COMPLETE: MAR 2026