Baltimore District FY25 Projected Dredge Schedule.pdf

PDF 890 KB Posted

Attached to
North Atlantic Division FY25 Dredge Schedule Notification
Solicitation number
W2SD-25-NAD-0001
Issued by

About this file

This file is a detailed dredging schedule presentation from the U.S. Army Corps of Engineers Baltimore District for Fiscal Year 2025, dated October 15, 2024. The schedule outlines multiple dredging projects across Maryland and Virginia waterways, with the Baltimore District responsible for maintaining 87 miles of deep draft 50-foot channels, 90 shallow draft projects covering over 200 miles of channels, and 37 navigational structures, removing approximately 3.2 million cubic yards from federal channels annually.

Key projects include the Baltimore Harbor MD Approach (2,292,000 CY, bucket dredge, October 2024-March 2025), York Spit VA Approach (2,600,000 CY, hopper dredge, November 2024-April 2025), Cape Henry VA Approach (2,300,000 CY, hopper dredge, November 2025-April 2026), and Ocean City Beach Renourishment (1,000,000 CY, hopper dredge, October 2025-May 2026). Smaller projects include the North East River (50,000 CY), Honga River (330,000 CY), and Rock Hall Harbor (30,000 CY). The schedule provides specific details for each project including dredge types, placement locations, depths, and precise timeline milestones from advertisement through completion dates.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FY25 PROJECTED DREDGE

SCHEDULE

INFORMATION AS OF

OCTOBER 2024

Eric Lindheimer, P.E.

Navigation Branch Chief

North Atlantic Division

Baltimore District

Date: 15 October 2024

NORTH ATLANTIC DIVISION

BALTIMORE DISTRICT

Eric Lindheimer, P.E.

Navigation Branch Chief

Eric.M.Lindheimer@usace.army.mil

Andrew Payson

Survey/Debris Section Chief

Andrew.W.Payson@usace.army.mil

BALTIMORE DISTRICT POINTS OF CONTACT

mailto:Eric.M.Lindheimer@usace.army.mil mailto:Andrew.W.Payson@usace.army.mil

NAVIGATION AREA OF RESPONSIBILITY

Baltimore District Channel Maintenance

87 miles of Deep Draft 50 ft channels

90 Shallow Draft projects consisting of over 200 miles of channels to maintain

37 navigational structures to maintain

Remove approx. 3.2 million CY from federal channels each year

Masonville

DMCF

Baltimore Harbor & Channels

BALTIMORE HARBOR, FY25, MD APPROACH

LOCATION: Maryland

DREDGE TYPE: Bucket

PLACEMENT: Poplar Island, Cox Creek

QUANTITY: 2,292,000 CY

DEPTH: 50 FT, 22 FT (Curtis Creek)

ADVERTISE: AUG 2024

BID OPENING: SEP 2024

COMMENCE DREDGING: OCT 2024

DREDGE COMPLETE: MAR 2025

BALTIMORE HARBOR, FY24, VA APPROACH

YORK SPIT

LOCATION: Virginia

DREDGE TYPE: Hopper

PLACEMENT: Wolf Trap Alternate Northern

Extension

QUANTITY: 2,600,000 CY

DEPTH: 50 FT

ADVERTISE: JUL 2024

BID OPENING: AUG 2024

COMMENCE DREDGING: NOV 2024

DREDGE COMPLETE: APR 2025

NORTH EAST RIVER

LOCATION: Maryland

DREDGE TYPE: Pipeline

PLACEMENT: North East DMP

QUANTITY: 50,000 CY

DEPTH: 7 FT

ADVERTISE: JUL 2025

BID OPENING: AUG 2025

COMMENCE DREDGING: NOV 2025

DREDGE COMPLETE: FEB 2026

BALTIMORE HARBOR, FY25, VA APPROACH

CAPE HENRY

LOCATION: Virginia

DREDGE TYPE: Hopper

PLACEMENT: Dam Neck Ocean Disposal

QUANTITY: 2,300,000 CY

DEPTH: 50 FT

ADVERTISE: JUL 2025

BID OPENING: AUG 2025

DREDGE COMPLETE: APR 2026

ATLANTIC COAST OF MARYLAND

BEACH RENOURISHMENT

LOCATION: Ocean City, MD

DREDGE TYPE: Hopper

PLACEMENT: Ocean City, MD

QUANTITY: 1,000,000 CY

WATER DEPTH: 30 – 40 FT (at borrow area)

ADVERTISE: MAY 2025

BID OPENING: JUNE 2025

COMMENCE DREDGING: OCT 2025

DREDGE COMPLETE: MAY 2026

BALTIMORE HARBOR, FY26, MD APPROACH

LOCATION: Maryland

DREDGE TYPE: Bucket

PLACEMENT: Poplar Island, Cox Creek

QUANTITY: 2,418,500 CY

DEPTH: 50 FT, 35 FT (Tolchester)

ADVERTISE: AUG 2025

BID OPENING: SEP 2025

DREDGE COMPLETE: MAR 2026

HONGA RIVER

LOCATION: Maryland

DREDGE TYPE: Pipeline

PLACEMENT: Barren Island, MD

QUANTITY: 330,000 CY

DEPTH: 7 FT

ADVERTISE: MAY 2024

BID OPENING: JUN 2024

WICOMICO RIVER (UPPER)

LOCATION: Maryland

DREDGE TYPE: Pipeline

PLACEMENT: Sharps Point DMP

QUANTITY: 100,000 CY

DEPTH: 14 FT

ADVERTISE: JUL 2025

BID OPENING: AUG 2025

ROCK HALL HARBOR

LOCATION: Maryland

DREDGE TYPE: Bucket

PLACEMENT: Bramble Inc. (Chestertown, MD)

QUANTITY: 30,000 CY

DEPTH: 8 – 10 FT

ADVERTISE: JULY 2025

BID OPENING: AUG 2025

ST. PATRICKS CREEK

LOCATION: Maryland

DREDGE TYPE: Pipeline

PLACEMENT: New Towne Neck State Park

QUANTITY: 15,000 CY

DEPTH: 7 FT

ADVERTISE: JUL 2025

BID OPENING: AUG 2025

DREDGE COMPLETE: JAN 2026

SEAGIRT LOOP DEEPENING

LOCATION: Maryland

DREDGE TYPE: Bucket

PLACEMENT: Cox Creek

QUANTITY: 2,000,000 CY

DEPTH: 50 FT

ADVERTISE: MAR 2027

BID OPENING: MAY 2027

COMMENCE DREDGING: JUL 2027

DREDGE COMPLETE: DEC 2028

WICOMICO RIVER (LOWER)

LOCATION: Maryland

DREDGE TYPE: Pipeline

PLACEMENT: TBD

QUANTITY: 100,000 CY

DEPTH: 14 FT

ADVERTISE: JUN 2026

BID OPENING: JUL 2026

COMMENCE DREDGING: OCT 2026

DREDGE COMPLETE: FEB 2027

BALTIMORE HARBOR, FY26, VA APPROACH

RAPPAHANNOCK SHOAL

LOCATION: Virginia

DREDGE TYPE: Hopper

PLACEMENT: Deep Alternate

QUANTITY: 1,000,000 CY

DEPTH: 50 FT

ADVERTISE: JUL 2026

BID OPENING: AUG 2026

COMMENCE DREDGING: NOV 2026

DREDGE COMPLETE: MAR 2027

Slide 1: FY25 Projected Dredge Schedule Information as of October 2024
Slide 2: North Atlantic division Baltimore district Eric Lindheimer, P.E. Navigation Branch Chief Eric.M.Lindheimer@usace.army.mil Andrew Payson Survey/Debris Section Chief Andrew.W.Payson@usace.army.mil
Slide 3: Navigation area of responsibility
Slide 4: Baltimore Harbor, FY25, MD APPROACH
Slide 5: Baltimore Harbor, FY24, VA APPROACH York SPIT
Slide 6: North East River
Slide 7: Baltimore Harbor, FY25, VA APPROACH CAPE Henry
Slide 8: Atlantic Coast of Maryland BEACH RENOURISHMENT
Slide 9: Baltimore Harbor, FY26, MD APPROACH
Slide 10: Honga river
Slide 11: Wicomico river (upper)
Slide 12: Rock Hall Harbor
Slide 13: St. Patricks Creek
Slide 14: SEAGIRT LOOP DEEPENING
Slide 15: WICOMICO River (lower)
Slide 16: Baltimore Harbor, FY26, VA APPROACH Rappahannock Shoal