New England FY25 Projected Dredge Schedule.pdf
PDF 255 KB Posted
- Solicitation number
- W2SD-25-NAD-0001
About this file
This is a dredging project schedule presentation from the U.S. Army Corps of Engineers New England District detailing four planned FY2025 navigation dredging projects. The point of contact for the New England District is Jenifer Thalhauser, Navigation Section Chief.
The four projects include: 1) Narraguagus River in Milbridge, ME with 150,000 CY of silt to be dredged between November-March 2025, using mechanical dredging with disposal at Douglas Island Disposal Site; 2) Wareham Harbor, MA with approximately 52,000 CY of silt and 600 CY of sand to be dredged between October-January 2025, disposing silt at Cape Cod Bay Disposal Site and sand at Church's Beach Nearshore Site; 3) Stony Creek in Branford, CT with approximately 54,000 CY of sand to be dredged between October-January 2025, disposing at Central Long Island Sound Disposal Site; and 4) New Haven Harbor O&M project with 780,000 CY of silt to be dredged between October-January 2025, disposing at Central Long Island Sound Disposal Site. All projects require mechanical dredging and have solicitation dates in February 2025, except New Haven Harbor which has an April 2025 solicitation date.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NEW ENGLAND DISTRICT
NAVIGATION SECTION
PROGRAMS AND PROJECT MANAGEMENT
DIVISION
NEW ENGLAND DISTRICT POC
NORTH ATLANTIC DIVISION
NEW ENGLAND DISTRICT
Jenifer Thalhauser
Navigation Section Chief
Jenifer.E.Thalhauser@usace.army.mil
NARRAGUAGUS RIVER, MILBRIDGE, ME
Re-solicitation date: FEB2025
Quantity: 150,000 CY SILT
Disposal: DOUGLAS ISLAND
DISPOSAL SITE
Mechanical dredge
Dredge Window:
1 NOV – 31 MAR
WAREHAM HARBOR, WAREHAM, MA
Solicitation date: FEB2025
Quantity: ~52,000 CY SILT
AND ~600 CY SAND
Disposal:
SILT: CAPE COD BAY
DISPOSAL SITE (CCBDS)
SAND: CHURCH’S BEACH
NEARSHORE DIPOSAL SITE
Mechanical dredge
ESTIMATED 1 OCT – 15 JAN
STONY CREEK, BRANFORD, CT
Solicitation date: FEB2025
Quantity: ~54,000 CY SAND
Disposal: CENTRAL LONG
ISLAND SOUND DISPOSAL
SITE
Mechanical dredge
ESTIMATED 1 OCT – 15 JAN
NEW HAVEN HARBOR O&M
Solicitation date: APR2025
Quantity: 780,000 CY SILT
Disposal: CENTRAL LONG
ISLAND SOUND DISPOSAL
SITE
Mechanical dredge
ESTIMATED 1 OCT – 31 JAN
| Slide 1: New england District |
| Slide 2: Navigation Section Programs and Project management Division new England district poc NORTH ATLANTIC division NEW ENGLAND DISTRICT Jenifer Thalhauser Navigation Section Chief Jenifer.E.Thalhauser@usace.army.mil |
| Slide 3: Narraguagus River, milbridge, me |
| Slide 4: wareham harbor, wareham, ma |
| Slide 5: Stony creek, BRANFORD, CT |
| Slide 6: New haven harbor o&m |