This is a dredging project schedule presentation from the U.S. Army Corps of Engineers New England District detailing four planned FY2025 navigation dredging projects. The point of contact for the New England District is Jenifer Thalhauser, Navigation Section Chief.

The four projects include: 1) Narraguagus River in Milbridge, ME with 150,000 CY of silt to be dredged between November-March 2025, using mechanical dredging with disposal at Douglas Island Disposal Site; 2) Wareham Harbor, MA with approximately 52,000 CY of silt and 600 CY of sand to be dredged between October-January 2025, disposing silt at Cape Cod Bay Disposal Site and sand at Church's Beach Nearshore Site; 3) Stony Creek in Branford, CT with approximately 54,000 CY of sand to be dredged between October-January 2025, disposing at Central Long Island Sound Disposal Site; and 4) New Haven Harbor O&M project with 780,000 CY of silt to be dredged between October-January 2025, disposing at Central Long Island Sound Disposal Site. All projects require mechanical dredging and have solicitation dates in February 2025, except New Haven Harbor which has an April 2025 solicitation date.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NEW ENGLAND DISTRICT

NAVIGATION SECTION

PROGRAMS AND PROJECT MANAGEMENT

DIVISION

NEW ENGLAND DISTRICT POC

NORTH ATLANTIC DIVISION

NEW ENGLAND DISTRICT

Jenifer Thalhauser

Navigation Section Chief

Jenifer.E.Thalhauser@usace.army.mil

NARRAGUAGUS RIVER, MILBRIDGE, ME

Re-solicitation date: FEB2025

Quantity: 150,000 CY SILT

Disposal: DOUGLAS ISLAND

DISPOSAL SITE

Mechanical dredge

Dredge Window:

1 NOV – 31 MAR

WAREHAM HARBOR, WAREHAM, MA

Solicitation date: FEB2025

Quantity: ~52,000 CY SILT

AND ~600 CY SAND

Disposal:

SILT: CAPE COD BAY

DISPOSAL SITE (CCBDS)

SAND: CHURCH’S BEACH

NEARSHORE DIPOSAL SITE

Mechanical dredge

ESTIMATED 1 OCT – 15 JAN

STONY CREEK, BRANFORD, CT

Solicitation date: FEB2025

Quantity: ~54,000 CY SAND

Disposal: CENTRAL LONG

ISLAND SOUND DISPOSAL

SITE

Mechanical dredge

ESTIMATED 1 OCT – 15 JAN

NEW HAVEN HARBOR O&M

Solicitation date: APR2025

Quantity: 780,000 CY SILT

Disposal: CENTRAL LONG

ISLAND SOUND DISPOSAL

SITE

Mechanical dredge

ESTIMATED 1 OCT – 31 JAN

Slide 1: New england District
Slide 2: Navigation Section Programs and Project management Division new England district poc NORTH ATLANTIC division NEW ENGLAND DISTRICT Jenifer Thalhauser Navigation Section Chief Jenifer.E.Thalhauser@usace.army.mil
Slide 3: Narraguagus River, milbridge, me
Slide 4: wareham harbor, wareham, ma
Slide 5: Stony creek, BRANFORD, CT
Slide 6: New haven harbor o&m