New York District FY25 Projected Dredge Schedule.pdf

PDF 1 MB Posted

Attached to
North Atlantic Division FY25 Dredge Schedule Notification
Solicitation number
W2SD-25-NAD-0001
Issued by

About this file

This file is a FY25 projected dredge schedule presentation from the U.S. Army Corps of Engineers New York District, containing detailed information about planned dredging projects for fiscal year 2025. The document outlines the New York District's portfolio of 82 federally authorized navigation projects, which includes 727 miles of navigation channels, 26 navigation structures, 1 lock and dam, 21 deep draft and 61 shallow draft projects, and 187 miles of re-nourishable shoreline.

The schedule presents multiple dredging projects planned for FY25, including: Fire Island Inlet to Montauk Point (1,160,000 CY, December 2024-March 2025), Bronx River (150,000 CY, December 2024-January 2025), Jones Inlet to East Rockaway Inlet (1.1M CY, February-September 2025), Newark Bay (375,000 CY, August 2025-January 2026), Arthur Kill 50' Reach (100,000 CY, September-December 2025), East Rockaway Inlet (450,000 CY, October-December 2025), Sandy Hook Channel (200,000 CY, October-November 2025), and Long Island Intracoastal Waterway (50,000 CY, October-December 2025). Each project includes specific details about dredge type (bucket, hopper, or pipeline), placement areas, depths, and work restriction windows.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. ARMY CORPS OF ENGINEERS

NEW YORK DISTRICT

FY25 Projected Dredge Schedule

Information as of

October 2024

Maintenance Dredging of Newark Bay

Maintenance Dredging of

Long Island Intracoastal Waterway

82 Federally authorized navigation projects

▪ 727 miles of Navigation Channels

▪ 26 Navigation Structures

▪ 1 Lock and Dam

▪ 21 Deep Draft (=>14 Ft.)

▪ 61 Shallow Draft (<14 Ft.)

▪ 187 miles of Re-nourishable Shoreline

OVERVIEW OF THE

NEW YORK DISTRICT

PORTFOLIO

NEW YORK DISTRICT SCHEDULE (FROM DIS)

FY25

Project Manager: Mark Lulka

Location: Suffolk County, NY

Dredge Type: Hopper

Placement Area: Shoreline

Quantity: 1,160,000 CY

Depth: -55ft MLLW + 2ft OD

Business Type: Unrestricted

Advertisement Date: August 2024

Bid Opening Date: September 2024

Commence Dredging: December 2024

Dredging Complete: March 2025

Work Restrictions / Window:

01 April –

30 September

FIRE ISLAND INLET TO MONTAUK POINT (FIMP), NY

Contract 4 – Cupsogue Beach and Westhampton

Suffolk County

Approximate

Borrow Area

Project Manager: Divyesh Patel

BRONX RIVER, NY

Area to be

Dredged

Legend:

Location: Bronx County, NY

Dredge Type: Bucket

Placement Area: HARS

Quantity: 150,000 CY

Depth: -10ft MLLW + 1ft OD

Business Type: Unrestricted

Advertisement Date: September 2024

Bid Opening Date: October 2024

Commence Dredging: December 2024

Dredging Complete: January 2025

Work Restrictions / Window:

15 January –

01 October

BRONX, NY

HUNTS POINT

CLASON POINT

Project Manager: Frank Verga

JONES INLET TO EAST ROCKAWAY INLET

LONG BEACH, NY

Re-nourishment Contract #1

Location: Nassau County, NY

Dredge Type: Hopper/Pipeline

Placement Area: Shoreline

Quantity: 1.1M CY (Estimated)

Depth: -35 ft to -45ft NAVD88

Business Type: Unrestricted

Advertisement Date: December 2024

Bid Opening: January 2025

Commence Dredging: February 2025

Dredging Complete: September 2025

Work Restrictions / Windows: 01 April - 31 August

Beachfill Borrow

Area

Area to be

Dredged

Legend:

Project Manager: Jun Yan

NEWARK BAY, NJ –

40 FT & 50 FT REACHES

Location:

Hudson/Union/Essex

County, NJ

Dredge Type: Bucket

Placement Area: Upland

Quantity: 375,000 CY

Depth:

-40ft & -50ft MLLW

+ 1ft OD

Business Type: Unrestricted

Advertisement Date: April 2025

Bid Opening Date: May 2025

Commence Dredging: August 2025

Dredging Complete: January 2026

Work Restrictions / Window:

01 March –

30 June

Area to be

Dredged

NEWARK, NJ

Project Manager: Alexander Gregory

NEW YORK & NEW JERSEY HARBOR -

ARTHUR KILL - 50’ REACH

Location: Lower Bay, NY/NJ

Dredge Type: Bucket

Placement Area: Upland

Quantity: 100,000 CY

Depth: -50ft MLLW + 1ft OD

Business Type: Unrestricted

Advertisement Date: May 2025

Bid Opening Date: June 2025

Commence Dredging: September 2025

Dredging Complete: December 2025

Work Restrictions / Window:

15 January –

31 May

Area to be

Dredged

Legend:

New Jersey

Staten Island, NY

EAST ROCKAWAY INLET, NY

Location: Queens County, NY

Dredge Type: Pipeline

Placement Area: Shoreline

Quantity: 450,000 CY

Depth:

-14ft MLLW

+ 2ft OD

Business Type: Unrestricted

Advertisement Date: June 2025

Bid Opening Date: July 2025

Commence Dredging: October 2025

Dredging Complete: December 2025

Work Restrictions / Window:

15 January –

30 September

Area to be

Dredged

Legend:

Far Rockaway, NY

Atlantic Beach, NY

Placement Site

NEW YORK HARBOR

Sandy Hook Channel (FY25)

Location:

Monmouth County, NJ

Dredge Type: Bucket

Placement Area: Ocean

Quantity: 200,000 CY

Depth: -35ft MLLW+ 2ft OD

Business Type: Unrestricted

Advertisement Date: July 2025

Bid Opening Date: August 2025

Commence Dredging: October 2025

Dredging Complete: November 2025

Work Restrictions / Window:

01 March –

31 August

New Jersey

Approximate

Placement Site

Area to be

LONG ISLAND

INTRACOASTAL WATERWAY, NY

Location: Suffolk County, NY

Dredge Type: Pipeline

Placement Area: Shoreline (various)

Quantity: 50,000 CY

Depth:

-6ft MLLW +

2 ft OD

Business Type: Unrestricted

Advertisement Date: June 2025

Bid Opening Date: July 2025

Commence Dredging: October 2025

Dredging Complete: December 2025

Work Restrictions / Window:

01 January –

30 September

Project Manager: Frank Verga

Location: Suffolk County, NY

Dredge Type: Pipeline/Bucket

Placement Area:

Shoreline

West of Jetty

Quantity:

100,000 CY beach, 15,000 CY stone

Depth: -17ft MLLW + 2 ft OD

Business Type: Unrestricted

Advertisement Date: June 2025

Bid Opening Date: August 2025

Commence Dredging: November 2025

Dredging Complete: December 2025

Work Restrictions / Window:

01 January –

31 October

LAKE MONTAUK HARBOR, NY

Continuing Authorities Program (CAP)- Section 107

Approximate

MONTAUK, NY

❖ Arthur Kill Channel (50’ Reach) - Maintenance dredging of approximately 150,000 CY with processing of the dredged material. Dredging commenced August 2023 and was completed in September 2023.

❖ NY/NJ Channels – Seguine/Ward/Outerbridge Reach- Maintenance dredging of approximately 517,000 CY with placement at the HARS. Dredging commenced

September 2023 and was completed in November 2023.

❖ Shoal Harbor Compton Creek, NJ: ~160,000 CY of material to be placed along the shoreline and upland in a Confined Disposal Facility (CDF). Dredging commenced July 2023 and was completed in September 2023.

❖ NY Harbor - Sandy Hook Channel - Maintenance dredging of 200,000 CY with placement offshore at the Sea Bright Offshore Borrow Area (SBOBA). Dredging commenced October 2023 and was completed in December 2023.

❖ Long Island Intracoastal Waterway - Maintenance dredging of approximately 70,000 CY with shoreline placement. Dredging commenced October 2023 and was completed in November 2023.

❖ Browns Creek - Maintenance dredging of approximately 33,000 CY with upland placement at a confined disposal facility adjacent to the channel. Dredging commenced November 2023 and was completed in December 2023.

❖ East River – South Brother Island Channel - Maintenance dredging of approximately 150,000 CY with processing of the dredged material and upland placement at a contractor furnished site. Dredging commenced November 2023 and was completed in January 2024.

❖ Shrewsbury River (Upland) - Maintenance dredging of approximately 50,000 CY with placement at a contractor furnished, upland site. Dredging commenced

November 2023 and is anticipated to be completed in November 2024.

❖ Shrewsbury River (Beach) - Maintenance dredging of approximately 50,000 CY with placement along the Monmouth Beach shoreline. Dredging commenced

October 2023 and is anticipated to be complete in November 2024.

❖ Fire Island PL84-99 Contracts (Seaview to Saltaire, Ocean Bay Park to Davis Park) - Maintenance dredging of approximately 2M CY with placement along the Fire

Island shoreline.

SUMMARY OF KEY PROJECTS REVIEW FY 2024

❖ Arthur Kill Channel (50’ Reach) - Maintenance dredging of approximately 90,000 CY with processing of the dredged material and upland placement at a contractor furnished site.

❖ Newark Bay - Maintenance dredging of approximately 150,000 CY with processing of the dredged material and upland placement at a contractor furnished site.

Dredging commenced September 2024 and is anticipated to be complete in November 2024.

❖ Raritan River to Arthur Kill Cut-off - Maintenance dredging of approximately 434,000 CY with placement at the HARS. Dredging commenced August 2024 and is anticipated to be complete in October 2024.

❖ NY & NJ Channels - Raritan Bay Reaches - Maintenance dredging of approximately 517,000 CY with placement at the HARS. Dredging commenced September

2024 and is anticipated to be complete in October 2024.

❖ Great Kills Harbor - Maintenance dredging of approximately 190,000 CY with placement at the HARS. Dredging commenced October 2023 and is anticipated to be complete in November 2023.

❖ Mattituck Harbor - Maintenance dredging of approximately 10,000 CY with processing of the dredged material and upland placement at a contractor furnished site.

Dredging is scheduled to start in October 2024 and is anticipated to be complete in November 2024.

❖ Sandy Hook Channel - Maintenance dredging of 220,000 CY with placement offshore at the Sea Bright Offshore Borrow Area (SBOBA). Dredging scheduled to start October 2024 and is anticipated to be complete in December 2024.

❖ Fire Island Inlet to Shores Westerly - Maintenance dredging of approximately 1.3M CY with placement along the Gilgo Beach shoreline. Dredging is scheduled to start in October 2024 and is anticipated to be complete in March 2025.

❖ Port Jersey - Maintenance dredging of approximately 275,000 CY with placement at the HARS. Dredging scheduled to start in November 2024 and is anticipated to be complete in December 2024.

❖ Long Island Intracoastal Waterway - Maintenance dredging of approximately 50,000 CY with placement at Tiana Bayside Beach, WOSI and Shagwong Marina

Beach. Dredging commenced October 2024 and is anticipated to be complete in November 2024.

SUMMARY OF KEY PROJECTS REVIEW FY 2024

BACK-UP SLIDES – FY24 PROJECTS

RARITAN RIVER TO ARTHUR KILL

CUTOFF

Location:

Middlesex County, NJ

Dredge Type: Bucket

Placement Area: HARS

Quantity: 360,000 CY

Depth:

-20ft MLLW +

1ft or 2ft OD

Business Type: Unrestricted

Advertisement Date: April 2024

Bid Opening Date: JUNE 2024

Commence Dredging: July 2024

Dredging Complete: September 2024

Work Restrictions / Window:

01 December –

30 June

Area to be

Dredged

Legend:

Perth Amboy, NJ

South Amboy, NJ

GREAT KILLS HARBOR, NY

Location:

Richmond County, NY

Dredge Type: Bucket

Placement Area: HARS

Quantity: 200,000 CY

Depth:

-10 ft MLLW + 2ft

OD

Business Type: Unrestricted

Advertisement Date: May 2024

Bid Opening Date: JUNE 2024

Commence Dredging: September 2024

Dredging Complete: November 2024

Work Restrictions / Window:

15 January –

31 August Area to be

Dredged

Staten Island, New York, NY

NEW YORK & NEW JERSEY HARBOR

Arthur Kill Channel (FY24)

Location: Lower Bay, NY/NJ

Dredge Type: Bucket

Placement Area: Upland

Quantity: 175,000 CY

Depth:

-48 ft & -50ft MLLW

+ 1ft OD

Business Type: Unrestricted

Advertisement Date: May 2024

Bid Opening Date: JUNE 2024

Commence Dredging: September 2024

Dredging Complete: December 2024

Work Restrictions / Window:

15 January –

31 May

Area to be

Dredged

Legend:

NEWARK BAY, NJ –

40 FT, 45 FT, & 50 FT PROJECT (FY24)

Location:

Hudson/Union/Essex

County, NJ

Dredge Type: Bucket

Placement Area: Processing/Upland

Quantity: 258,000 CY

Depth:

-40ft & -50ft MLLW +

1ft OD

Business Type: Unrestricted

Advertisement Date: May 2024

Bid Opening Date: JUNE 2024

Commence Dredging: September 2024

Dredging Complete: February 2025

Work Restrictions / Window:

01 March –

30 June

Newark, NJ

Bayonne, NJ

Area to be

Project Manager: William T. Bruno

FIRE ISLAND INLET AND SHORES WESTERLY

TO JONES INLET, NY

Location: Suffolk County, NY

Dredge Type: Pipeline

Placement Area: Shoreline

Quantity: 1,000,000 CY

Depth:

-14ft MLLW

+ 2ft OD

Business Type: Unrestricted

Advertisement Date: March 2024

Bid Opening Date: MAY 2024

Commence Dredging: October 2024

Dredging Complete: March 2025

Work Restrictions / Window:

01 April –

30 September

Area to be

NEW YORK & NEW JERSEY CHANNELS

Vicinity of Raritan Bay

Sandy Hook

Keansburg

Location: Lower Bay, NY/NJ

Dredge Type: Bucket

Placement Area: HARS

Quantity: 450,000 CY

Depth: -35ft MLLW + 2ft OD

Business Type: Unrestricted

Advertisement Date: May 2024

Bid Opening Date: JUNE 2024

Commence Dredging: October 2024

Dredging Complete: December 2024

Work Restrictions / Window:

01 December –

31 July

Area to be

Dredged

Legend:

Staten Island, NY

Sandy Hook, NJ

Keansburg, NJ

MATTITUCK HARBOR, NY

Location: Suffolk County, NY

Dredge Type: Bucket

Placement Area: Upland

Quantity: 14,000 CY

Depth: -7ft MLLW + 1 ft OD

Business Type: Restricted

Advertisement Date: May 2024

Bid Opening Date: JUNE 2024

Commence Dredging: October 2024

Dredging Complete: December 2024

Work Restrictions / Window:

01 January –

30 September

Area to be

Dredged

Legend:

Bailie Beach Park

Breakwater Beach

Mattituck, NY

Project Manager: Kristin Irwin

Location: Hudson River, NY

Dredge Type: Bucket

Placement Area: Upland

Quantity: 34,000 CY

Depth: -12ft MLLW + 1ft OD

Business Type: Unrestricted

Advertisement Date: June 2024

Bid Opening Date: July 2024

Commence Dredging: August 2024

Dredging Complete: October 2024

Work Restrictions / Window:

01 January –

15 August

SAUGERTIES

HOUGHTALING ISLAND

UPLAND PLACEMENT SITE

Area to be

Dredged

Legend:

HUDSON RIVER , NY

SAUGERTIES HARBOR (ESOPUS CREEK)

NEW YORK AND NEW JERSEY HARBOR

Port Jersey Channel

Area to be

Dredged

Legend:

Location: Hudson County, NJ

Dredge Type: Bucket

Placement Area: HARS

Quantity: 450,000 CY

Depth: -50ft MLLW + 2ft OD

Business Type: Unrestricted

Advertisement Date: June 2024

Bid Opening Date: July 2024

Commence Dredging: September 2024

Dredging Complete: November 2024

Work Restrictions / Window:

15 January –

01 June

Jersey City, NJ

NEW YORK HARBOR

Sandy Hook Channel (FY24)

New Jersey

Approximate

Placement Site

Area to be

Dredged

Legend:

Location: Monmouth County, NJ

Dredge Type: Bucket

Placement Area: Ocean

Quantity: 200,000 CY

Depth: -35ft MLLW+ 2ft OD

Business Type: Unrestricted

Advertisement Date: July 2024

Bid Opening Date: August 2024

Commence Dredging: October 2024

Dredging Complete: December 2024

Work Restrictions / Window:

01 March –

31 August

LONG ISLAND

INTRACOASTAL WATERWAY, NY (FY24)

Location: Suffolk County, NY

Dredge Type: Pipeline

Placement Area: Shoreline (various)

Quantity: 50,000 CY

Depth:

-6ft MLLW +

2 ft OD

Business Type: Unrestricted

Advertisement Date: June 2024

Bid Opening Date: July 2024

Commence Dredging: October 2024

Dredging Complete: December 2024

Work Restrictions / Window:

01 January –

30 September

Approximate

Placement Site

NEW YORK DISTRICT SCHEDULE (FROM DIS)

FY26

NEW YORK & NEW JERSEY CHANNELS -

ARTHUR KILL – 35’ REACH

Location: Lower Bay, NY/NJ

Dredge Type: Bucket

Placement Area: Upland

Quantity: 100,000 CY

Depth: -35ft MLLW + 1ft OD

Business Type: Unrestricted

Advertisement Date: May 2026

Bid Opening Date: June 2026

Commence Dredging: August 2026

Dredging Complete: September 2026

Work Restrictions / Window: TBD

Area to be

Dredged

Legend:

NEWARK BAY, NJ –

40 FT & 50 FT REACHES (FY26)

Location:

Hudson/Union/Essex

County, NJ

Dredge Type: Bucket

Placement Area: Upland

Quantity: 200,000 CY

Depth:

-40ft & -50ft MLLW

+ 1ft OD

Business Type: Unrestricted

Advertisement Date: April 2026

Bid Opening Date: May 2026

Commence Dredging: August 2026

Dredging Complete: January 2027

Work Restrictions / Window:

01 March –

30 June

Area to be

Dredged

NEWARK, NJ

Project Manager: Kristin Irwin

HUDSON RIVER , NY

HAVERSTRAW BAY

Location: Hudson River, NY

Dredge Type: Hopper

Placement Area:

TBD (Upland or

HARS)

Quantity: 530,000 CY

Depth: -32ft MLLW+ 1ft OD

Business Type: Unrestricted

Advertisement Date: June 2026

Bid Opening Date: July 2026

Commence Dredging: August 2026

Dredging Complete: November 2026

Work Restrictions / Window:

01 January –

15 August

NEW YORK & NEW JERSEY CHANNELS -

WARD’S POINT BEND

Location: Lower Bay, NY/NJ

Dredge Type: Bucket

Placement Area: HARS

Quantity: 250,000 CY

Depth: -35ft MLLW + 1ft OD

Business Type: Unrestricted

Advertisement Date: May 2026

Bid Opening Date: June 2026

Commence Dredging: September 2026

Dredging Complete: October 2026

Work Restrictions / Window:

01 February –

31 July

Area to be

Dredged

Legend:

NEW YORK HARBOR

Sandy Hook Channel (FY26)

Location:

Monmouth County, NJ

Dredge Type: Bucket

Placement Area: Ocean

Quantity: 150,000 CY

Depth: -35ft MLLW+ 2ft OD

Business Type: Unrestricted

Advertisement Date: July 2026

Bid Opening Date: August 2026

Commence Dredging: October 2026

Dredging Complete: November 2026

Work Restrictions / Window:

01 March –

31 August

New Jersey

Approximate

Placement Site

Area to be

JONES INLET, NY

Location: Nassau County, NY

Dredge Type: Pipeline

Placement Area: Shoreline

Quantity: 300,000 CY

Depth: -14ft MLLW + 2ft OD

Business Type: Unrestricted

Advertisement Date: June 2026

Bid Opening Date: July 2026

Commence Dredging: November 2026

Dredging Complete: December 2026

Work Restrictions / Window:

15 January –

30 September

Area to be

Dredged

Approximate

Placement Site

Area to be

Dredged

Legend:

POINT LOOK OUT, NY

JONES BEACH, NY

Slide 1: U.S. Army Corps of Engineers New York District
Slide 2: Overview of THE NEW YORK District portfolio
Slide 3: NEW YORK district schedule (From DIS) FY25
Slide 4: FIRE ISLAND INLET TO MONTAUK POINT (FIMP), NY Contract 4 – Cupsogue Beach and Westhampton
Slide 5: BRONX RIVER, NY
Slide 6
Slide 7: Newark bay, NJ – 40 ft & 50 FT reaches
Slide 8: NEW YORK & NEW JERSEY HARBOR - ARTHUR KILL - 50’ REACH
Slide 9: EAST ROCKAWAY INLET, NY
Slide 10: NEW YORK HARBOR Sandy Hook Channel (FY25)
Slide 11: Long island intracoastal waterway, ny
Slide 12
Slide 13: Summary of Key Projects Review FY 2024
Slide 14: Summary of Key Projects Review FY 2024
Slide 15: BACK-UP SLIDES – FY24 Projects
Slide 16: RARITAN RIVER TO ARTHUR KILL CUTOFF
Slide 17: Great kills harbor, ny
Slide 18: NEW YORK & NEW JERSEY HARBOR Arthur Kill Channel (FY24)
Slide 19: Newark bay, NJ – 40 ft, 45 FT, & 50 FT PROJECT (FY24)
Slide 20: FIRE ISLAND INLET AND SHORES WESTERLY TO JONES INLET, NY
Slide 21: NEW YORK & NEW JERSEY CHANNELS Vicinity of Raritan Bay
Slide 22: Mattituck Harbor, ny
Slide 23
Slide 24: New York and New Jersey Harbor Port Jersey Channel
Slide 25: NEW YORK HARBOR Sandy Hook Channel (FY24)
Slide 26: Long island intracoastal waterway, ny (FY24)
Slide 27: NEW YORK district schedule (From DIS) FY26
Slide 28: NEW YORK & NEW JERSEY CHANNELS - ARTHUR KILL – 35’ REACH
Slide 29: Newark bay, NJ – 40 ft & 50 FT reaches (FY26)
Slide 30: HUDSON RIVER , NY HAVERSTRAW BAY
Slide 31: NEW YORK & NEW JERSEY CHANNELS - WARD’s POINT BEND
Slide 32: NEW YORK HARBOR Sandy Hook Channel (FY26)
Slide 33: JONES INLET, NY