This file is a FY25 projected dredge schedule presentation from the U.S. Army Corps of Engineers New York District, containing detailed information about planned dredging projects for fiscal year 2025. The document outlines the New York District's portfolio of 82 federally authorized navigation projects, which includes 727 miles of navigation channels, 26 navigation structures, 1 lock and dam, 21 deep draft and 61 shallow draft projects, and 187 miles of re-nourishable shoreline.
The schedule presents multiple dredging projects planned for FY25, including: Fire Island Inlet to Montauk Point (1,160,000 CY, December 2024-March 2025), Bronx River (150,000 CY, December 2024-January 2025), Jones Inlet to East Rockaway Inlet (1.1M CY, February-September 2025), Newark Bay (375,000 CY, August 2025-January 2026), Arthur Kill 50' Reach (100,000 CY, September-December 2025), East Rockaway Inlet (450,000 CY, October-December 2025), Sandy Hook Channel (200,000 CY, October-November 2025), and Long Island Intracoastal Waterway (50,000 CY, October-December 2025). Each project includes specific details about dredge type (bucket, hopper, or pipeline), placement areas, depths, and work restriction windows.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. ARMY CORPS OF ENGINEERS
NEW YORK DISTRICT
FY25 Projected Dredge Schedule
Information as of
October 2024
Maintenance Dredging of Newark Bay
Maintenance Dredging of
Long Island Intracoastal Waterway
82 Federally authorized navigation projects
▪ 727 miles of Navigation Channels
▪ 26 Navigation Structures
▪ 1 Lock and Dam
▪ 21 Deep Draft (=>14 Ft.)
▪ 61 Shallow Draft (<14 Ft.)
▪ 187 miles of Re-nourishable Shoreline
OVERVIEW OF THE
NEW YORK DISTRICT
PORTFOLIO
NEW YORK DISTRICT SCHEDULE (FROM DIS)
FY25
Project Manager: Mark Lulka
Location: Suffolk County, NY
Dredge Type: Hopper
Placement Area: Shoreline
Quantity: 1,160,000 CY
Depth: -55ft MLLW + 2ft OD
Business Type: Unrestricted
Advertisement Date: August 2024
Bid Opening Date: September 2024
Commence Dredging: December 2024
Dredging Complete: March 2025
Work Restrictions / Window:
01 April –
30 September
FIRE ISLAND INLET TO MONTAUK POINT (FIMP), NY
Contract 4 – Cupsogue Beach and Westhampton
Suffolk County
Approximate
Borrow Area
Project Manager: Divyesh Patel
BRONX RIVER, NY
Area to be
Dredged
Legend:
Location: Bronx County, NY
Dredge Type: Bucket
Placement Area: HARS
Quantity: 150,000 CY
Depth: -10ft MLLW + 1ft OD
Business Type: Unrestricted
Advertisement Date: September 2024
Bid Opening Date: October 2024
Commence Dredging: December 2024
Dredging Complete: January 2025
Work Restrictions / Window:
15 January –
01 October
BRONX, NY
HUNTS POINT
CLASON POINT
Project Manager: Frank Verga
JONES INLET TO EAST ROCKAWAY INLET
LONG BEACH, NY
Re-nourishment Contract #1
Location: Nassau County, NY
Dredge Type: Hopper/Pipeline
Placement Area: Shoreline
Quantity: 1.1M CY (Estimated)
Depth: -35 ft to -45ft NAVD88
Business Type: Unrestricted
Advertisement Date: December 2024
Bid Opening: January 2025
Commence Dredging: February 2025
Dredging Complete: September 2025
Work Restrictions / Windows: 01 April - 31 August
Beachfill Borrow
Area
Area to be
Dredged
Legend:
Project Manager: Jun Yan
NEWARK BAY, NJ –
40 FT & 50 FT REACHES
Location:
Hudson/Union/Essex
County, NJ
Dredge Type: Bucket
Placement Area: Upland
Quantity: 375,000 CY
Depth:
-40ft & -50ft MLLW
+ 1ft OD
Business Type: Unrestricted
Advertisement Date: April 2025
Bid Opening Date: May 2025
Commence Dredging: August 2025
Dredging Complete: January 2026
Work Restrictions / Window:
01 March –
30 June
Area to be
Dredged
NEWARK, NJ
Project Manager: Alexander Gregory
NEW YORK & NEW JERSEY HARBOR -
ARTHUR KILL - 50’ REACH
Location: Lower Bay, NY/NJ
Dredge Type: Bucket
Placement Area: Upland
Quantity: 100,000 CY
Depth: -50ft MLLW + 1ft OD
Business Type: Unrestricted
Advertisement Date: May 2025
Bid Opening Date: June 2025
Commence Dredging: September 2025
Dredging Complete: December 2025
Work Restrictions / Window:
15 January –
31 May
Area to be
Dredged
Legend:
New Jersey
Staten Island, NY
EAST ROCKAWAY INLET, NY
Location: Queens County, NY
Dredge Type: Pipeline
Placement Area: Shoreline
Quantity: 450,000 CY
Depth:
-14ft MLLW
+ 2ft OD
Business Type: Unrestricted
Advertisement Date: June 2025
Bid Opening Date: July 2025
Commence Dredging: October 2025
Dredging Complete: December 2025
Work Restrictions / Window:
15 January –
30 September
Area to be
Dredged
Legend:
Far Rockaway, NY
Atlantic Beach, NY
Placement Site
NEW YORK HARBOR
Sandy Hook Channel (FY25)
Location:
Monmouth County, NJ
Dredge Type: Bucket
Placement Area: Ocean
Quantity: 200,000 CY
Depth: -35ft MLLW+ 2ft OD
Business Type: Unrestricted
Advertisement Date: July 2025
Bid Opening Date: August 2025
Commence Dredging: October 2025
Dredging Complete: November 2025
Work Restrictions / Window:
01 March –
31 August
New Jersey
Approximate
Placement Site
Area to be
LONG ISLAND
INTRACOASTAL WATERWAY, NY
Location: Suffolk County, NY
Dredge Type: Pipeline
Placement Area: Shoreline (various)
Quantity: 50,000 CY
Depth:
-6ft MLLW +
2 ft OD
Business Type: Unrestricted
Advertisement Date: June 2025
Bid Opening Date: July 2025
Commence Dredging: October 2025
Dredging Complete: December 2025
Work Restrictions / Window:
01 January –
30 September
Project Manager: Frank Verga
Location: Suffolk County, NY
Dredge Type: Pipeline/Bucket
Placement Area:
Shoreline
West of Jetty
Quantity:
100,000 CY beach, 15,000 CY stone
Depth: -17ft MLLW + 2 ft OD
Business Type: Unrestricted
Advertisement Date: June 2025
Bid Opening Date: August 2025
Commence Dredging: November 2025
Dredging Complete: December 2025
Work Restrictions / Window:
01 January –
31 October
LAKE MONTAUK HARBOR, NY
Continuing Authorities Program (CAP)- Section 107
Approximate
MONTAUK, NY
❖ Arthur Kill Channel (50’ Reach) - Maintenance dredging of approximately 150,000 CY with processing of the dredged material. Dredging commenced August 2023 and was completed in September 2023.
❖ NY/NJ Channels – Seguine/Ward/Outerbridge Reach- Maintenance dredging of approximately 517,000 CY with placement at the HARS. Dredging commenced
September 2023 and was completed in November 2023.
❖ Shoal Harbor Compton Creek, NJ: ~160,000 CY of material to be placed along the shoreline and upland in a Confined Disposal Facility (CDF). Dredging commenced July 2023 and was completed in September 2023.
❖ NY Harbor - Sandy Hook Channel - Maintenance dredging of 200,000 CY with placement offshore at the Sea Bright Offshore Borrow Area (SBOBA). Dredging commenced October 2023 and was completed in December 2023.
❖ Long Island Intracoastal Waterway - Maintenance dredging of approximately 70,000 CY with shoreline placement. Dredging commenced October 2023 and was completed in November 2023.
❖ Browns Creek - Maintenance dredging of approximately 33,000 CY with upland placement at a confined disposal facility adjacent to the channel. Dredging commenced November 2023 and was completed in December 2023.
❖ East River – South Brother Island Channel - Maintenance dredging of approximately 150,000 CY with processing of the dredged material and upland placement at a contractor furnished site. Dredging commenced November 2023 and was completed in January 2024.
❖ Shrewsbury River (Upland) - Maintenance dredging of approximately 50,000 CY with placement at a contractor furnished, upland site. Dredging commenced
November 2023 and is anticipated to be completed in November 2024.
❖ Shrewsbury River (Beach) - Maintenance dredging of approximately 50,000 CY with placement along the Monmouth Beach shoreline. Dredging commenced
October 2023 and is anticipated to be complete in November 2024.
❖ Fire Island PL84-99 Contracts (Seaview to Saltaire, Ocean Bay Park to Davis Park) - Maintenance dredging of approximately 2M CY with placement along the Fire
Island shoreline.
SUMMARY OF KEY PROJECTS REVIEW FY 2024
❖ Arthur Kill Channel (50’ Reach) - Maintenance dredging of approximately 90,000 CY with processing of the dredged material and upland placement at a contractor furnished site.
❖ Newark Bay - Maintenance dredging of approximately 150,000 CY with processing of the dredged material and upland placement at a contractor furnished site.
Dredging commenced September 2024 and is anticipated to be complete in November 2024.
❖ Raritan River to Arthur Kill Cut-off - Maintenance dredging of approximately 434,000 CY with placement at the HARS. Dredging commenced August 2024 and is anticipated to be complete in October 2024.
❖ NY & NJ Channels - Raritan Bay Reaches - Maintenance dredging of approximately 517,000 CY with placement at the HARS. Dredging commenced September
2024 and is anticipated to be complete in October 2024.
❖ Great Kills Harbor - Maintenance dredging of approximately 190,000 CY with placement at the HARS. Dredging commenced October 2023 and is anticipated to be complete in November 2023.
❖ Mattituck Harbor - Maintenance dredging of approximately 10,000 CY with processing of the dredged material and upland placement at a contractor furnished site.
Dredging is scheduled to start in October 2024 and is anticipated to be complete in November 2024.
❖ Sandy Hook Channel - Maintenance dredging of 220,000 CY with placement offshore at the Sea Bright Offshore Borrow Area (SBOBA). Dredging scheduled to start October 2024 and is anticipated to be complete in December 2024.
❖ Fire Island Inlet to Shores Westerly - Maintenance dredging of approximately 1.3M CY with placement along the Gilgo Beach shoreline. Dredging is scheduled to start in October 2024 and is anticipated to be complete in March 2025.
❖ Port Jersey - Maintenance dredging of approximately 275,000 CY with placement at the HARS. Dredging scheduled to start in November 2024 and is anticipated to be complete in December 2024.
❖ Long Island Intracoastal Waterway - Maintenance dredging of approximately 50,000 CY with placement at Tiana Bayside Beach, WOSI and Shagwong Marina
Beach. Dredging commenced October 2024 and is anticipated to be complete in November 2024.
SUMMARY OF KEY PROJECTS REVIEW FY 2024
BACK-UP SLIDES – FY24 PROJECTS
RARITAN RIVER TO ARTHUR KILL
CUTOFF
Location:
Middlesex County, NJ
Dredge Type: Bucket
Placement Area: HARS
Quantity: 360,000 CY
Depth:
-20ft MLLW +
1ft or 2ft OD
Business Type: Unrestricted
Advertisement Date: April 2024
Bid Opening Date: JUNE 2024
Commence Dredging: July 2024
Dredging Complete: September 2024
Work Restrictions / Window:
01 December –
30 June
Area to be
Dredged
Legend:
Perth Amboy, NJ
South Amboy, NJ
GREAT KILLS HARBOR, NY
Location:
Richmond County, NY
Dredge Type: Bucket
Placement Area: HARS
Quantity: 200,000 CY
Depth:
-10 ft MLLW + 2ft
OD
Business Type: Unrestricted
Advertisement Date: May 2024
Bid Opening Date: JUNE 2024
Commence Dredging: September 2024
Dredging Complete: November 2024
Work Restrictions / Window:
15 January –
31 August Area to be
Dredged
Staten Island, New York, NY
NEW YORK & NEW JERSEY HARBOR
Arthur Kill Channel (FY24)
Location: Lower Bay, NY/NJ
Dredge Type: Bucket
Placement Area: Upland
Quantity: 175,000 CY
Depth:
-48 ft & -50ft MLLW
+ 1ft OD
Business Type: Unrestricted
Advertisement Date: May 2024
Bid Opening Date: JUNE 2024
Commence Dredging: September 2024
Dredging Complete: December 2024
Work Restrictions / Window:
15 January –
31 May
Area to be
Dredged
Legend:
NEWARK BAY, NJ –
40 FT, 45 FT, & 50 FT PROJECT (FY24)
Location:
Hudson/Union/Essex
County, NJ
Dredge Type: Bucket
Placement Area: Processing/Upland
Quantity: 258,000 CY
Depth:
-40ft & -50ft MLLW +
1ft OD
Business Type: Unrestricted
Advertisement Date: May 2024
Bid Opening Date: JUNE 2024
Commence Dredging: September 2024
Dredging Complete: February 2025
Work Restrictions / Window:
01 March –
30 June
Newark, NJ
Bayonne, NJ
Area to be
Project Manager: William T. Bruno
FIRE ISLAND INLET AND SHORES WESTERLY
TO JONES INLET, NY
Location: Suffolk County, NY
Dredge Type: Pipeline
Placement Area: Shoreline
Quantity: 1,000,000 CY
Depth:
-14ft MLLW
+ 2ft OD
Business Type: Unrestricted
Advertisement Date: March 2024
Bid Opening Date: MAY 2024
Commence Dredging: October 2024
Dredging Complete: March 2025
Work Restrictions / Window:
01 April –
30 September
Area to be
NEW YORK & NEW JERSEY CHANNELS
Vicinity of Raritan Bay
Sandy Hook
Keansburg
Location: Lower Bay, NY/NJ
Dredge Type: Bucket
Placement Area: HARS
Quantity: 450,000 CY
Depth: -35ft MLLW + 2ft OD
Business Type: Unrestricted
Advertisement Date: May 2024
Bid Opening Date: JUNE 2024
Commence Dredging: October 2024
Dredging Complete: December 2024
Work Restrictions / Window:
01 December –
31 July
Area to be
Dredged
Legend:
Staten Island, NY
Sandy Hook, NJ
Keansburg, NJ
MATTITUCK HARBOR, NY
Location: Suffolk County, NY
Dredge Type: Bucket
Placement Area: Upland
Quantity: 14,000 CY
Depth: -7ft MLLW + 1 ft OD
Business Type: Restricted
Advertisement Date: May 2024
Bid Opening Date: JUNE 2024
Commence Dredging: October 2024
Dredging Complete: December 2024
Work Restrictions / Window:
01 January –
30 September
Area to be
Dredged
Legend:
Bailie Beach Park
Breakwater Beach
Mattituck, NY
Project Manager: Kristin Irwin
Location: Hudson River, NY
Dredge Type: Bucket
Placement Area: Upland
Quantity: 34,000 CY
Depth: -12ft MLLW + 1ft OD
Business Type: Unrestricted
Advertisement Date: June 2024
Bid Opening Date: July 2024
Commence Dredging: August 2024
Dredging Complete: October 2024
Work Restrictions / Window:
01 January –
15 August
SAUGERTIES
HOUGHTALING ISLAND
UPLAND PLACEMENT SITE
Area to be
Dredged
Legend:
HUDSON RIVER , NY
SAUGERTIES HARBOR (ESOPUS CREEK)
NEW YORK AND NEW JERSEY HARBOR
Port Jersey Channel
Area to be
Dredged
Legend:
Location: Hudson County, NJ
Dredge Type: Bucket
Placement Area: HARS
Quantity: 450,000 CY
Depth: -50ft MLLW + 2ft OD
Business Type: Unrestricted
Advertisement Date: June 2024
Bid Opening Date: July 2024
Commence Dredging: September 2024
Dredging Complete: November 2024
Work Restrictions / Window:
15 January –
01 June
Jersey City, NJ
NEW YORK HARBOR
Sandy Hook Channel (FY24)
New Jersey
Approximate
Placement Site
Area to be
Dredged
Legend:
Location: Monmouth County, NJ
Dredge Type: Bucket
Placement Area: Ocean
Quantity: 200,000 CY
Depth: -35ft MLLW+ 2ft OD
Business Type: Unrestricted
Advertisement Date: July 2024
Bid Opening Date: August 2024
Commence Dredging: October 2024
Dredging Complete: December 2024
Work Restrictions / Window:
01 March –
31 August
LONG ISLAND
INTRACOASTAL WATERWAY, NY (FY24)
Location: Suffolk County, NY
Dredge Type: Pipeline
Placement Area: Shoreline (various)
Quantity: 50,000 CY
Depth:
-6ft MLLW +
2 ft OD
Business Type: Unrestricted
Advertisement Date: June 2024
Bid Opening Date: July 2024
Commence Dredging: October 2024
Dredging Complete: December 2024
Work Restrictions / Window:
01 January –
30 September
Approximate
Placement Site
NEW YORK DISTRICT SCHEDULE (FROM DIS)
FY26
NEW YORK & NEW JERSEY CHANNELS -
ARTHUR KILL – 35’ REACH
Location: Lower Bay, NY/NJ
Dredge Type: Bucket
Placement Area: Upland
Quantity: 100,000 CY
Depth: -35ft MLLW + 1ft OD
Business Type: Unrestricted
Advertisement Date: May 2026
Bid Opening Date: June 2026
Commence Dredging: August 2026
Dredging Complete: September 2026
Work Restrictions / Window: TBD
Area to be
Dredged
Legend:
NEWARK BAY, NJ –
40 FT & 50 FT REACHES (FY26)
Location:
Hudson/Union/Essex
County, NJ
Dredge Type: Bucket
Placement Area: Upland
Quantity: 200,000 CY
Depth:
-40ft & -50ft MLLW
+ 1ft OD
Business Type: Unrestricted
Advertisement Date: April 2026
Bid Opening Date: May 2026
Commence Dredging: August 2026
Dredging Complete: January 2027
Work Restrictions / Window:
01 March –
30 June
Area to be
Dredged
NEWARK, NJ
Project Manager: Kristin Irwin
HUDSON RIVER , NY
HAVERSTRAW BAY
Location: Hudson River, NY
Dredge Type: Hopper
Placement Area:
TBD (Upland or
HARS)
Quantity: 530,000 CY
Depth: -32ft MLLW+ 1ft OD
Business Type: Unrestricted
Advertisement Date: June 2026
Bid Opening Date: July 2026
Commence Dredging: August 2026
Dredging Complete: November 2026
Work Restrictions / Window:
01 January –
15 August
NEW YORK & NEW JERSEY CHANNELS -
WARD’S POINT BEND
Location: Lower Bay, NY/NJ
Dredge Type: Bucket
Placement Area: HARS
Quantity: 250,000 CY
Depth: -35ft MLLW + 1ft OD
Business Type: Unrestricted
Advertisement Date: May 2026
Bid Opening Date: June 2026
Commence Dredging: September 2026
Dredging Complete: October 2026
Work Restrictions / Window:
01 February –
31 July
Area to be
Dredged
Legend:
NEW YORK HARBOR
Sandy Hook Channel (FY26)
Location:
Monmouth County, NJ
Dredge Type: Bucket
Placement Area: Ocean
Quantity: 150,000 CY
Depth: -35ft MLLW+ 2ft OD
Business Type: Unrestricted
Advertisement Date: July 2026
Bid Opening Date: August 2026
Commence Dredging: October 2026
Dredging Complete: November 2026
Work Restrictions / Window:
01 March –
31 August
New Jersey
Approximate
Placement Site
Area to be
JONES INLET, NY
Location: Nassau County, NY
Dredge Type: Pipeline
Placement Area: Shoreline
Quantity: 300,000 CY
Depth: -14ft MLLW + 2ft OD
Business Type: Unrestricted
Advertisement Date: June 2026
Bid Opening Date: July 2026
Commence Dredging: November 2026
Dredging Complete: December 2026
Work Restrictions / Window:
15 January –
30 September
Area to be
Dredged
Approximate
Placement Site
Area to be
Dredged
Legend:
POINT LOOK OUT, NY
JONES BEACH, NY
| Slide 1: U.S. Army Corps of Engineers New York District |
| Slide 2: Overview of THE NEW YORK District portfolio |
| Slide 3: NEW YORK district schedule (From DIS) FY25 |
| Slide 4: FIRE ISLAND INLET TO MONTAUK POINT (FIMP), NY Contract 4 – Cupsogue Beach and Westhampton |
| Slide 5: BRONX RIVER, NY |
| Slide 6 |
| Slide 7: Newark bay, NJ – 40 ft & 50 FT reaches |
| Slide 8: NEW YORK & NEW JERSEY HARBOR - ARTHUR KILL - 50’ REACH |
| Slide 9: EAST ROCKAWAY INLET, NY |
| Slide 10: NEW YORK HARBOR Sandy Hook Channel (FY25) |
| Slide 11: Long island intracoastal waterway, ny |
| Slide 12 |
| Slide 13: Summary of Key Projects Review FY 2024 |
| Slide 14: Summary of Key Projects Review FY 2024 |
| Slide 15: BACK-UP SLIDES – FY24 Projects |
| Slide 16: RARITAN RIVER TO ARTHUR KILL CUTOFF |
| Slide 17: Great kills harbor, ny |
| Slide 18: NEW YORK & NEW JERSEY HARBOR Arthur Kill Channel (FY24) |
| Slide 19: Newark bay, NJ – 40 ft, 45 FT, & 50 FT PROJECT (FY24) |
| Slide 20: FIRE ISLAND INLET AND SHORES WESTERLY TO JONES INLET, NY |
| Slide 21: NEW YORK & NEW JERSEY CHANNELS Vicinity of Raritan Bay |
| Slide 22: Mattituck Harbor, ny |
| Slide 23 |
| Slide 24: New York and New Jersey Harbor Port Jersey Channel |
| Slide 25: NEW YORK HARBOR Sandy Hook Channel (FY24) |
| Slide 26: Long island intracoastal waterway, ny (FY24) |
| Slide 27: NEW YORK district schedule (From DIS) FY26 |
| Slide 28: NEW YORK & NEW JERSEY CHANNELS - ARTHUR KILL – 35’ REACH |
| Slide 29: Newark bay, NJ – 40 ft & 50 FT reaches (FY26) |
| Slide 30: HUDSON RIVER , NY HAVERSTRAW BAY |
| Slide 31: NEW YORK & NEW JERSEY CHANNELS - WARD’s POINT BEND |
| Slide 32: NEW YORK HARBOR Sandy Hook Channel (FY26) |
| Slide 33: JONES INLET, NY |