Norfolk District FY25 Projected Dredge Schedule.pdf

PDF 720 KB Posted

Attached to
North Atlantic Division FY25 Dredge Schedule Notification
Solicitation number
W2SD-25-NAD-0001
Issued by

About this file

This is a FY25 dredging project schedule presentation from the Norfolk District of the U.S. Army Corps of Engineers detailing planned maintenance and new work dredging projects for fiscal year 2025. The district oversees 6 deep draft harbors, 65 shallow draft channels, and 3 locks in Virginia.

The schedule outlines 10 major dredging projects including: Craney Island Eastward Expansion (2.8M CY, $2.8M, Apr 2025-Nov 2026), Norfolk Harbor Southern Branch maintenance (96K CY, May-Aug 2025), Thimble Shoal Channel West maintenance (1.2M CY, Feb-Jul 2025), Craney Island Rehandling Basin maintenance (1M CY, Jul 2025-Apr 2026), James River 3-year IDIQ contract (1M CY per year, Oct 2025-Sep 2028), Winter Harbor maintenance (150K CY, Dec 2025-Mar 2026), Milford Haven maintenance (25K CY, Dec 2025-Dec 2026), Little Machipongo River maintenance (50K CY, Nov 2025-Nov 2026), Quinby Creek maintenance (200K CY, Jun 2025-Jan 2026), and Sandbridge Beach nourishment (1.7M CY, Dec 2025-May 2026). Projects utilize hopper, mechanical, and pipeline dredging methods with material placement including open water, upland, and beach nourishment sites. Several projects are set aside for small businesses while others are unrestricted. The schedule includes two upcoming stakeholder events: Virginia Navigational Summit in November 2024 and James River IDIQ Industry Day in April 2025.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NORFOLK DISTRICT

FY25 Projected Dredge Schedule

Information as of

October 2024

Norfolk District

OVERVIEW OF

NORFOLK DISTRICT

PORTFOLIO

▪ 6 Deep Draft Harbors

▪ 65 Shallow Draft Channels

▪ 3 Locks

NORFOLK DISTRICT ACTIVE DREDGING PROJECTS

NORFOLK DISTRICT UPCOMING DREDGING PROJECTS

CRANEY ISLAND EASTWARD EXPANSION – NEW WORK

LOCATION: Portsmouth, VA

DREDGE TYPE: Mechanical

PLACEMENT: Open-Water (NODS)

QUANTITY: 2,815,500 CY

DEPTH: 25 – 41 feet

BUSINESS TYPE: Unrestricted

ADVERTISE: Nov 2024

BID OPENING: Jan 2025

COMMENCE DREDGING: Apr 2025

DREDGE COMPLETE: Nov 2026

NORFOLK HARBOR SOUTHERN BRANCH – MAINTENANCE

LOCATION: Hampton Roads, VA

DREDGE TYPE: Mechanical

PLACEMENT: Upland – Direct Pump-Out (Craney

Island)

QUANTITY: 96,200 CY

DEPTH: 36 - 41 feet

BUSINESS TYPE: Small Business

ADVERTISE: Jan 2025

BID OPENING: Feb 2025

COMMENCE DREDGING: May 2025

DREDGE COMPLETE: Aug 2025

THIMBLE SHOAL CHANNEL WEST – MAINTENANCE

LOCATION: Hampton Roads, VA

DREDGE TYPE: Hopper

PLACEMENT: Open Water (DNODS)

QUANTITY: 1,238,500 CY

DEPTH: 56 feet

BUSINESS TYPE: Unrestricted

ADVERTISE: Oct 2024

BID OPENING: Nov 2024

COMMENCE DREDGING: Feb 2025

DREDGE COMPLETE: Jul 2025

WORK RESTRICTIONS: No Dredging 1 Sep – 15 Nov

CRANEY ISLAND REHANDLING BASIN – MAINTENANCE

LOCATION: Portsmouth, VA

DREDGE TYPE: Pipeline

PLACEMENT: Upland (Craney Island)

QUANTITY: 1,000,000 CY

DEPTH: 9 - 28 feet

BUSINESS TYPE: TBD

ADVERTISE: Mar 2025

BID OPENING: Apr 2025

COMMENCE DREDGING: Jul 2025

DREDGE COMPLETE: Apr 2026

JAMES RIVER FY 2026 3 YEAR IDIQ CONTRACT

LOCATION: James River

DREDGE TYPE: Pipeline

PLACEMENT: Open Water, Upland

QUANTITY: 1,000,000 CY per Year

DEPTH: 18 - 26 feet

BUSINESS TYPE: TBD

ADVERTISE: Jul 2025

BID OPENING: Aug 2025

COMMENCE DREDGING: Oct 2025

DREDGE COMPLETE: Sep 2028

MILFORD HAVEN – JETTY AND CHANNEL MAINTENANCE

LOCATION: Mathews County, VA

DREDGE TYPE: Pipeline

PLACEMENT: Beach Nourishment

QUANTITY: 25,000 CY

DEPTH: 10 feet

BUSINESS TYPE: Small Business

ADVERTISE: Jun 2025

BID OPENING: Jul 2025

COMMENCE DREDGING: Dec 2025

DREDGE COMPLETE: Dec 2026

Beneficial Use

WINTER HARBOR – MAINTENANCE

LOCATION: Mathews County, VA

DREDGE TYPE: Pipeline

PLACEMENT: Beach Nourishment

QUANTITY: 150,000 CY

DEPTH: 7 feet

BUSINESS TYPE: Small Business

ADVERTISE: Apr 2025

BID OPENING: Jun 2025

COMMENCE DREDGING: Dec 2025

DREDGE COMPLETE: Mar 2026

LITTLE MACHIPONGO RIVER – MAINTENANCE

LOCATION: Accomack County, VA

DREDGE TYPE: Pipeline

PLACEMENT: Upland

QUANTITY: 50,000 CY

DEPTH: 8 feet

BUSINESS TYPE: Small Business

ADVERTISE: Jun 2025

BID OPENING: Aug 2025

COMMENCE DREDGING: Nov 2025

DREDGE COMPLETE: Nov 2026

QUINBY CREEK – MAINTENANCE

LOCATION: Accomack County, VA

DREDGE TYPE: Pipeline

PLACEMENT: Open-water (Marsh protection)

QUANTITY: 200,000 CY

DEPTH: 6 feet

BUSINESS TYPE: Small Business

ADVERTISE: Jan 2025

BID OPENING: Apr 2025

COMMENCE DREDGING: Jun 2025

DREDGE COMPLETE: Jan 2026

SANDBRIDGE BEACH – BEACH NOURISHMENT

LOCATION: Virginia Beach, VA

DREDGE TYPE: Hopper

PLACEMENT: Shoreline

QUANTITY: 1,700,000 CY

DEPTH: 56 feet

BUSINESS TYPE: Unrestricted

ADVERTISE: Sep 2025

BID OPENING: Oct 2025

COMMENCE DREDGING: Dec 2025

DREDGE COMPLETE: May 2026

Beneficial Use

Borrow Site B

Borrow Site A

UPCOMING STAKEHOLDER ENGAGEMENTS

Virginia Navigational Summit

1 November 2024

Norfolk Yacht and Country Club

James River New IDIQ Contract Industry Day

April 2025 - TBD

Virtual

All slides
Slide 1: NORfolk District
Slide 2: Overview of Norfolk District portfolio
Slide 3: Norfolk district active dredging projects
Slide 4: Norfolk district Upcoming dredging projects
Slide 5: Craney island eastward expansion – new work
Slide 6: Norfolk harbor southern branch – maintenance
Slide 7: Thimble shoal Channel West – maintenance
Slide 8: Craney island rehandling basin – maintenance
Slide 9: James River Fy 2026 3 Year IDIQ contract
Slide 10: Milford haven – Jetty and channel maintenance
Slide 11: Winter Harbor – maintenance
Slide 12: Little machipongo River – maintenance
Slide 13: Quinby Creek – maintenance
Slide 14: Sandbridge beach – beach nourishment
Slide 15: Upcoming stakeholder engagements