PAN 038049 W911SD-26-Q-A044 SOLICITATION D.Final DAS Modernization Phs 1.pdf

PDF 3 MB Posted

Attached to
SOLICITATION--U. S. Army West Point Services for Cellular Distributed Antenna System (DAS) Modernization Phase 1
Solicitation number
W911SD-26-Q-A044
Issued by

About this file

This is a Request for Quote (RFQ) for Distributed Antenna System (DAS) modernization services at the United States Military Academy, West Point, New York.

The solicitation W911SD26QA044 seeks a Women-Owned Small Business (WOSB) contractor to upgrade and renovate existing commercial cellular DAS components and equipment at end-of-life technology and replace them with current 5G capability. The primary requirement covers Building 758 (Jefferson Hall Library) with optional work in two additional facilities: the General Instructional Building (GIB) and Building 752 (Mahan Hall). The contractor must provide all labor, equipment, and consumables to perform RF propagation studies, remove obsolete equipment, install new Advanced RF Technologies (ADRF) equipment, conduct testing and certification, and deliver as-built documentation. The work must comply with industry standards including BICSI 006, NFPA 70, IEEE grounding/arc-flash standards, FCC regulations, and ANSI/TIA telecommunications standards. All major equipment must be newly manufactured by ADRF, and systems must achieve specified DAS performance targets including RSRP coverage of -95 dBm for sub-3 GHz and -100 dBm for above-3 GHz frequencies over 95 percent of the coverage area. The contract type is Firm Fixed Price with a 180-day period of performance from June 1, 2026 to May 31, 2027. The offer due date is May 1, 2026 at 12:00 PM. Offerors must hold a GSA contract to perform required DAS services. Quote submissions must include four volumes (General, Experience/Capability, Past Performance, and Price) with specific page limits and technical documentation. The Government will evaluate quotes based on technical compliance, past performance, and price using a lowest-price-technically-acceptable approach without discussions unless deemed necessary.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WOMEN-OWNED SMALL

BUSINESS (WOSB)

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES

1. REQUISITION NUMBER PAGE 1 OF

2. CONTRACT NUMBER 3. AWARD/EFFECTIVE

DATE

4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE

DATE

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME b. TELEPHONE NUMBER (No collect 8. OFFER DUE DATE/

LOCAL TIME

9. ISSUED BY

13b. RATING

14. METHOD OF SOLICITATION

CODE

15. DELIVER TO 16. ADMINISTERED BY CODE

18a. PAYMENT WILL BE MADE BY CODE17a. CONTRACTOR/

OFFEROR

CODE

FACILITY

CODE

CODE

TELEPHONE NUMBER

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN

OFFER

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK

BELOW IS CHECKED

REQUEST

FOR QUOTE

(RFQ)

INVITATION

FOR BID

(IFB)

REQUEST

FOR

PROPOSAL

(RFP)

SEE ADDENDUM

19.

ITEM NUMBER

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

AMOUNT

(Use Reverse and/or Attach Additional Sheets as Necessary)

25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Government Use Only)

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH

AND DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND

ON ANY ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS

SPECIFIED

29. AWARD OF CONTRACT: REFERENCE OFFER

DATED . . YOUR OFFER ON SOLICITATION

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

30a. SIGNATURE OF OFFEROR/CONTRACTOR

30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED

31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)

31b. NAME OF CONTRACTING OFFICER (Type or print) 31c. DATE SIGNED

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 11/2021)

Prescribed by GSA - FAR (48 CFR) 53.212

10. THIS ACQUISITION IS UNRESTRICTED OR

NORTH AMERICAN

INDUSTRY CLASSIFICATION

STANDARD (NAICS):

SIZE STANDARD:

13a. THIS CONTRACT IS A

RATED ORDER UNDER

THE DEFENSE PRIORITIES

AND ALLOCATIONS

SYSTEM - DPAS (15 CFR 700)

SET ASIDE: % FOR:

11. DELIVERY FOR FREE ON

BOARD (FOB) DESTINATION

UNLESS BLOCK IS MARKED

SEE SCHEDULE

12. DISCOUNT TERMS

ARE ARE NOT ATTACHED

ARE ARE NOT ATTACHED

27a. SOLICITATION INCORPORATES BY REFERENCE (FEDERAL ACQUISITION REGULATION) FAR 52.212-1, 52.212-4. FAR 52.212-3

AND 52.212-5 ARE ATTACHED. ADDENDA

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA

8(A)

ECONOMICALLY

DISADVANTAGED

WOMEN-OWNED SMALL

BUSINESS (EDWOSB)

SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

(SDVOSB)

HUBZONE SMALL

BUSINESS

SMALL BUSINESS

NOTE: OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30.

calls)

Continuation of Supplies or Services and Prices/Costs

Additional Information/Notes

Item Supplies/Service Quantity Unit Unit Price

Amount

0001 Product Service Description: Jefferson Hall- DAS Material Universal Product Number: 012345 Product Service Code: R426 North American Industry Classification System (NAICS): 334220 Pricing Arrangement: Firm Fixed Price

1 Operating Unit

0002 Product Service Description: Jefferson Hall- DAS Labor Universal Product Number: 012345 Product Service Code: R426 Pricing Arrangement: Firm Fixed Price

1 Operating Unit

0003 Product Service Description: OPTION- Jefferson Hall- Redundent Power-M Universal Product Number: 012345 Product Service Code: R426 Pricing Arrangement: Firm Fixed Price

1 Operating Unit

0004 Product Service Description:

OPTIONAL-Jefferson Hall- Redundent Power- Universal Product Number: 012345 Product Service Code: R426 Pricing Arrangement: Firm Fixed Price

1 Operating Unit

0005 Product Service Description:

OPTIONAL- GIB DAS-Material Universal Product Number: 012345 Product Service Code: R426 Pricing Arrangement: Firm Fixed Price

1 Operating Unit

W911SD26QA044

0006 Product Service Description:

OPTIONAL- GIB DAS-Labor Universal Product Number: 012345 Product Service Code: R426 Pricing Arrangement: Firm Fixed Price

1 Operating Unit

0007 Product Service Description:

OPTIONAL- GIB Redundent Power- Material Universal Product Number: 012345 Product Service Code: R426 Pricing Arrangement: Firm Fixed Price

1 Operating Unit

0008 Product Service Description:

OPTIONAL- GIB Redundent Power- Labor Universal Product Number: 012345 Product Service Code: R426 Pricing Arrangement: Firm Fixed Price

1 Operating Unit

0009 Product Service Description:

OPTIONAL- Mahan Hall Active Equip Repl Mat Universal Product Number: 012345 Product Service Code: R426 Pricing Arrangement: Firm Fixed Price

1 Operating Unit

0010 Product Service Description:

OPTIONAL- Mahan Hall Active Equip Repl lab Universal Product Number: 012345 Product Service Code: R426 Pricing Arrangement: Firm Fixed Price

1 Operating Unit

0011 Product Service Description:

OPTIONAL- Mahan Hall Redundent Power- Mate Universal Product Number: 012345 Product Service Code: R426

1 Operating Unit

Pricing Arrangement: Firm Fixed Price

0012 Product Service Description:

OPTIONAL-Mahan Hall Redundent Power- Labor Universal Product Number: 012345 Product Service Code: R426 Pricing Arrangement: Firm Fixed Price

1 Operating Unit

0013 Product Service Description:

OPTIONAL- Mahan Hall Passive Equipment- Ma Universal Product Number: 012345 Product Service Code: R426 Pricing Arrangement: Firm Fixed Price

1 Operating Unit

0014 Product Service Description:

OPTIONAL- Mahan Hall Passive Equipment Lab Universal Product Number: 012345 Product Service Code: R426 Pricing Arrangement: Firm Fixed Price

1 Operating Unit

Continuation of Description

Section C

PWS

GENERAL INFORMATION

C1. General: This is a non-personal service(s) contract under which the personnel rendering the service(s) are not subject, either by the contract's terms or by the manner of its administration, to the supervision and control usually prevailing in relationships between the Government and its employees.

C1.1 Description of Services/Introduction: This is a non-personal service(s) contract to provide the upgrade and renovation of existing commercial cellular Distributed Antenna Systems(DAS) components and equipment that are at end of life technology, and replace them with current 5g capability. The contractor shall provide all labor, equipment and consumables to upgrade capability in support of providing modern capabilities to the Cadet, Staff and Faculty of the United States Military Academy (USMA), Westpoint, New York.

C1.2 Background: The Chief Information Officer, G6(CIO/G6) has identified the need to upgrade the existing cellular distribution systems within key buildings due to the inability to support modern fifth-generation mobile network(5G) enhancements offered by the core carriers. AT&T, T-Mobile, and VERIZON, currently provide signals to the academy to enable cellular service to all Cadet, Faculty and Staff cellular phone subscribers. The carrier signals are distributed within the Academic buildings through a Distributed Antenna System (DAS) installed within each building.

These systems ensure that the cellular service signals are maintained within the buildings since outside antenna signals cannot penetrate walls and indoor barriers. These systems directly support life, safety, and administrative communications.

C1.2.1 The CIO/G6 has identified that the current equipment cannot support new and emerging capabilities of 5G cellular technology since the existing equipment was installed and manufactured before 5G was developed. Currently, the equipment can only support 4G LTE. The enhancement of the equipment to support 5G will provide all mobile subscribers with the following capabilities:

a. Faster Speeds. This enables high-quality streaming, fast downloads, and smooth video conferencing.

b. Greater Capacity. Supports more devices per square mile, ideal for densely populated areas and numerous devices that utilize cellular for internet services- IoT (Internet of Things) deployments.

c. Improved Reliability. Enhanced network stability and better coverage.

C1.3 Scope: The Contractor shall provide non-personal service(s), to Engineer the removal and replacement of existing Distributed Antenna infrastructure and components that are unable to support 5G signal capability to new and emerging cellular technologies. All major equipment provided shall be standardized and be manufactured by Advanced RF Technologies (ADRF). This PWS provides for the upgrade of 3 separate facilities 1 primary, and 2 optional buildings, contingent upon funding.

C1.3.1 The contractor will be required to provide a RF Propagation plot, a.ka. "Heat Map" of all facilities to develop a design plan for antenna and component installations.

C1.3.2 Building 758, Jefferson Hall Library. The contractor will perform a preliminary RF Propagation study to be used within the engineering design. The contractor shall remove and replace all active components, passive components, cables, and antennas and replace the system in its entirety to provide for the capability of 5G cellular technology. All new active components will be installed using the existing racks/spaces vacated by the removed systems.

a. The contractor shall be responsible for the disposition of all removed equipment and materials no longer required under 1.3.1

b. The contractor shall install new cable, passive and active equipment to provide for a 100% upgrade to 5G capability, supporting ATT, T-Mobile, Verizon signal distribution within the facility.

c. The contractor shall be responsible for coordination of interruption of services with the CIO/G6 Network Service Branch, DAS Maintenance contractor, and if required the major carrier's.

d. The contractor shall test and certify that the system's performance meets or exceed specified performance levels and provide results to the CIO/G6 Network Service Branch.

e. The contractor shall develop and provide "As Built "drawings which identify locations and inventory of all antenna's, cable routes, and telecom equipment. All drawings and sketches developed under this PWS shall become the property of the CIO/G6 upon final draft at the completion of this project

C1.3.3 OPTION 1. Redundant Power. Building 758, Jefferson Hall Library. Contingent upon funding, the contractor shall provide a back-up power system to all active DAS equipment capable of a 2hour emergency power in the event of an electrical outage.

C1.3.4 OPTION 2. General Instructional Building (GIB). This facility is adjacent to the Jefferson Hall Library and serves as a temporary class and administrative area for displaced academic and staff functions during the academies multiyear Academic Building Upgrade Program (ABUP).

Contingent upon funding, the contractor shall provide the following:

a. The contractor shall perform an RF Propagation study to design the effective placement of antennas and infrastructure.

b. The contractor shall be responsible for the disposition of all removed equipment and materials no longer required under 1.3.3

c. The contractor shall install new cable, passive and active equipment to provide for a 100% upgrade to 5G capability, supporting AT&T, T-Mobile, Verizon signal distribution within the facility.

d. The contractor shall be responsible for coordination of interruption of services with the CIO/G6 Network Service Branch, DAS Maintenance contractor, and if required the major carriers.

e. The contractor shall test and certify that the system's performance meets or exceed specified performance levels and provide results to the CIO/G6 Network Service Branch.

f. The contractor shall develop and provide "As Built "drawings which identify locations and inventory of all antenna's, cable routes, and telecom equipment. All drawings and sketches developed under this PWS shall become the property of the CIO/G6 upon final draft at the completion of this project.

C1.3.5. OPTION 3. General Instructional Building (GIB). Contingent upon funding. The contractor shall provide and install redundant power to all active DAS components installed within 1.3.3.

C1.3.6. OPTION 4. Building 752, Mahan Hall. Contingent upon funding, the contractor shall remove all active DAS equipment and replace the components with newly manufactured Advanced RF Technologies (ADRF) equipment. The equipment shall provide 5G signaling throughout the existing infrastructure. Under this option, all passive components shall remain pending funding for replacement.

a. The contractor shall be responsible for the disposition of all replaced equipment

b. The contractor shall coordinate service outages with the CIO/G6 Network Service Branch.

c. The contractor shall test and certify that the system's performance meets or exceed specified performance levels and provide results to the CIO/G6 Network Service Branch.

d. The contractor shall ensure that the system provides for a 100% upgrade to 5G capability, supporting AT&T, T-Mobile, Verizon signal distribution within the facility.

e. The contractor shall be responsible for coordination of interruption of services with the CIO/G6 Network Service Branch, DAS Maintenance contractor, and if required the major carrier's.

f. The contractor shall develop and provide "As Built "drawings which identify locations and inventory of all telecom equipment and rack elevations. All drawings and sketches developed under this PWS shall become the property of the CIO/G6 upon final draft at the completion of this project.

C1.3.7. OPTION 5. Building 752, Mahan Hall. Contingent upon funding, the contractor shall provide and install Redundant Power to all active DAS Components installed under 1.3.4.

C1.3.8 OPTION 6. Building 752, Mahan Hall. Contingent upon funding, the contractor shall remove and replace all passive equipment, including cabling, and antennas and replace the DAS Infrastructure in its entirety.

a. The contractor shall perform an RF Propagation Study for the efficient placement of antennas and passive components.

b. The contractor is responsible for the disposition of all cabling and components removed under this option.

c. The contractor shall be responsible for coordination of interruption of services with the CIO/G6 Network Service Branch, DAS Maintenance contractor, and if required the major carriers.

d. The contractor shall install newly manufactured material and components that are rated for cellular 5G performance.

e. The contractor shall test and certify that the system's performance meets or exceed specified performance levels and provide results to the CIO/G6 Network Service Branch.

f. The contractor shall ensure that the system provides for a 100% upgrade to 5G capability, supporting AT&T, T-Mobile, Verizon signal distribution within the facility.

g. The contractor shall develop and provide "As Built "drawings which identify locations and inventory of all antenna's, cable routes, and telecom equipment. All drawings and sketches developed under this PWS shall become the property of the CIO/G6 upon final draft at the completion of this project.

C1.4 Objectives: The objective of this contract is to provide:

a. Removal of equipment which cannot support 5G cellular services.

b. Install new ADRF DAS Systems which will provide 100% coverage and 5g signal capability for all major cellular carriers within the building(s).

c. Upgrade DAS Infrastructure to include cable, antennas and associated components to enhance 5G performance, based upon RF Propagation studies.

1.5 Type of Contract: FIRM FIXED PRICE

1.6 Period of Performance: 180 Days from award of contract.

1.7 Place of Performance: The work to be performed under this contract will be performed

Building 758, Jefferson Hall Library.

OPTION 1. Redundant Power, Building 758, Jefferson Hall Library. Contingent on funding.

OPTION 2. General Instructional Building(GIB). OPTION 2, Contingent on funding.

OPTION 3. General Instructional Building (GIB). Contingent upon funding. OPTION 4. Building 752, Mahan Hall, Contingent on funding.

OPTION 5. Building 752, Mahan Hall. Contingent upon funding OPTION 6. Building 752, Mahan Hall. Contingent upon funding. United States Military Academy, Westpoint, NY, 10996.

C1.8 Site Survey. All prospective contractors will be offered a site survey to review the requirement of this PWS. All site surveys will be coordinated through the Contracting Officer.

C1.9 Contractor Travel: Reserved

C1.10 Other Direct Costs (ODCs): Special Equipment rental, Hi Reach scaffolding.

PART 2 SPECIFIC REQUIREMENTS

C2.1 Basic Services: The Contractor shall provide services for the upgrade and renovation of existing commercial cellular Distributed Antenna Systems (DAS) components and equipment that are at end of life technology and replace them with current 5g capability. The contractor shall provide all labor, equipment and consumables to upgrade capability in support of providing modern capabilities to the Cadet, Staff and Faculty of the United States Military Academy (USMA), Westpoint, New York. The work performed under this PWS shall conform to the following standards

Standard Purpose

BICSI 006 DAS design and implementation

NFPA 70 (NEC) Electrical safety and installation

IEEE 1100, 1584,

3007.1

Grounding, arc-flash, ESD safety

IFC Section 510 Fire code compliance for public safety DAS

FCC Regulations Frequency and interference control

47 CFR 1.1310 Radiofrequency Radiation Exposure Limits

47 CFR 90.219, Use of Signal Boosters

ANSI/TIA-569, Telecommunications Pathways and Spaces

ANSI/TIA-606 Administration Standard for Telecommunications Infrastructure

TIA TSB- 5018 Structured Cabling Infrastructure Guidelines to Support Distributed Antenna Systems

Manufacturers Guidelines

Major Equipment Manufacturers Installation Guidance

ANSI/TIA-607-E Telecommunications Bonding and Grounding

Standard Purpose

ANSI/TIA-568.3-E Optical Fiber Cabling and Components

ANSI/TIA-756-B Customer Owned Outside Plant Telecommunications Infrastructures

BICSI TDMM 15th Ed.

a. All network enabled hardware and software must support Internet Protocol version 6 (IPv6).

b. All hardware and software must meet all federal Section 508 requirements.

C2.1.1. Major Active Equipment. All active equipment must be newly manufactured provided by Advanced RF Technologies (ADRF).

C2.1.2 DAS Performance Specifications. All Distributed Antenna Systems shall be certified and perform to the below specifications.

Category Target Value

Area Comments

RSRP < 3

GHz

-95 dBm

>95% -95dBm or better RSRP design target is required for all systems over 95% of the Coverage Area

RSRP > 3

GHz)

-100 dBm

>95% -100 dBm or better RSRP design target is required for all systems over 95% of the Coverage Area.

SINR > 4 dB > 95%

The SINR is greater than 4 dB with a loading of 100% for 95%+ of coverage area.

Dominance Over Macro

6 dB 100% The design should be at a minimum 6 dB stronger than the peak macro benchmark data at any point in the entire coverage area.

C2.1.3 Spectrum Requirements. The following Spectrum Requirements support the objective of this requirement.

Table 3 Spectrum Requirements

C2.1.4 Contractor Work Plan: The Contractor shall prepare and maintain a Work Plan. The plan, as a minimum, shall identify regularly scheduled work (to include location, work to be completed, timeline, etc.) The Contractor's proposed Work Plan shall be submitted to the Contracting Officer via the COR for review within 10DAYS after date of contract award (Deliverable 1). The workplan can be Microsoft Project or Excell spreadsheet which would define milestones. Any proposed change to the accepted Final Work Plan is required to be resubmitted via the COR for review and acceptance by the Contracting Officer at a minimum 5 calendar days prior to implementation.

C2.2 Tasks: Building 758, Jefferson Hall Library. Task requirements for Building 758, Jefferson Hall consist of the following:

C2.2.1. The contractor shall perform an RF Propagation Study to establish the optimal placement of passive antennas and components. The contractor shall identify and remove all active DAS components from the facility and dispose of the equipment in accordance with environmental and regulatory guidelines and local regulations.

a. STANDARD(STD). The equipment will be removed and disposed of in accordance with environmental and regulatory guidelines and local regulations.

b. STD. The Contractor shall ensure that all personnel involved in the removal and transportation of removed equipment follows OSHA Standard 1910.176- Handling Materials.

c. STD. The contractor shall coordinate downtime of sectors to the CIO/G6 Network Service Branch and Major Carriers as appropriate.

d. STD. The contractor shall not use Government facilities for disposal of any equipment/materials removed under this PWS.

e. STD. All areas impacted by removal of infrastructure shall be cleaned and clear of debris. Floors and office areas which may have been impacted by dust, falling debris shall be cleaned and remedied before the end of every workday.

C2.2.2. The contractor shall perform a RF Propagation study to assess the building layout for optimal antenna placement, validate cable routes, and passive components.

a. STD. Provide floor plan with antenna locations and cable route to the COR before implementation. (Deliverable # 11)

b. No work will be performed pending the acceptance of the plan as communicated by the COR.

C2.2.3. The contractor shall install active equipment within the assigned telecommunications area within the racks and spaces vacated by the equipment removed in section 2.2.1.

a. STD. All equipment shall be installed in accordance with the manufacturer's specifications.

b. STD. All personnel assigned for the installation of equipment shall be experienced and certified to perform this task, in addition to certifications required by ADRF.

C2.2.4 Infrastructure Installation. The contractor will install all passive equipment to include antennas, cabling, connectors, taps, splitters ect.. from the active equipment throughout its respective zone.

a. STD. All infrastructure installation practices will be installed in accordance with references in Table 1.

b. STD. All cables will be dressed and secure with a neat appearance.

c. STD. All personnel assigned to this task will be qualified and or certified in the installation of DAS Infrastructure.

C2.2.5. Testing and certification. The contractor shall provide certification and performance measures for both passive and active systems.

a. STD. All cable will be tested end to end

b. STD. The contractor shall coordinate active operation with the COR and or CIO/G6 Network Service branch.

c. STD. Active test results will meet the requirements in Table 2 and Table 3.

C2.2.6. Closeout Documentation. The contractor shall provide final design plan, RF Propagation studies, test results, As Built.

a. STD. Final documentation shall be in electronic format. All drawings shall be in ADOBE PDF format.

b. Final documentation shall be provided to the COR within 15 days of close-out.(Deliverable #12)

C2.2.7. OPTION 1. Contingent upon funding. The contractor shall provide and install a redundant back-up power system to the active DAS equipment installed within building 758, Jefferson Hall Library.

a. STD. The systems will be rated for 2hrs.

b. STD. The contractor will perform a service test along with the COR to validate the performance of the system.

C2.3. OPTION 2. General Instructional Building(GIB). The contractor shall provide the assessment and replacement of existing DAS equipment with newly manufactured ADRF equipment to support 5G cellular technologies. The contractor shall perform a RF Propagation study to determine the optimal placement of antenna and passive components.

C2.3.1 The contractor shall perform an RF Propagation Study to establish the optimal placement of passive antennas and components. The contractor shall identify and remove all active DAS components from the facility and dispose of the equipment in accordance with environmental and regulatory guidelines and local regulations.

a. STANDARD(STD). The equipment will be removed and disposed of in accordance with environmental and regulatory guidelines and local regulations.

b. STD. The Contractor shall ensure that all personnel involved in the removal and transportation of removed equipment follows OSHA Standard 1910.176- Handling Materials.

c. STD. The contractor shall coordinate downtime of sectors to the CIO/G6 Network Service Branch and Major Carriers as appropriate.

d. STD. The contractor shall not use Government facilities for disposal of any equipment/materials removed under this PWS.

e. STD. All areas impacted by removal of infrastructure shall be cleaned and clear of debris. Floors and office areas which may have been impacted by dust, falling debris shall be cleaned and remedied before the end of every workday.

C2.3.2. The contractor shall perform a RF Propagation study to assess the building layout for optimal antenna placement, validate cable routes, and passive components.

a. STD. Provide floor plan with antenna locations and cable route to the COR before implementation. (Deliverable # 11)

b. No work will be performed pending the acceptance of the plan as communicated by the COR.

C2.3.3. The contractor shall install active equipment within the assigned telecommunications area within the racks and spaces vacated by the equipment removed in section 2.2.1.

a. STD. All equipment shall be installed in accordance with the manufacturer's specifications.

b. STD. All personnel assigned for the installation of equipment shall be experienced and certified to perform this task.(CERTIFICATION)

C2.3.4 Infrastructure Installation. The contractor will install all passive equipment to include antennas, cabling, connectors, taps, splitters ect.. from the active equipment throughout its respective zone.

a. STD. All infrastructure installation practices will be installed in accordance with references in Table 1.

b. STD. All cables will be dressed and secure with a neat appearance.

c. STD. All personnel assigned to this task will be qualified and or certified in the installation of DAS Infrastructure.

C2.3.5. Testing and certification. The contractor shall provide certification and performance measures for both passive and active systems.

a. STD. All cable will be tested end to end

b. STD. The contractor shall coordinate active operation with the COR and or CIO/G6 Network Service branch.

c. STD. Active test results will meet the requirements in Table 2 and Table 3.

C2.3.6. Closeout Documentation. The contractor shall provide final design plan, RF Propagation studies, test results, As Builts.

a. STD. Final documentation shall be in electronic format. All drawings shall be in ADOBE PDF format.

b. Final documentation shall be provided to the COR within 15 days of close-out.

(Deliverable #12)

C2.3.7. OPTION 3. Contingent upon funding. The contractor shall provide and install a redundant back-up power system to the active DAS equipment installed within building GIB Facility adjacent to building 758, Jefferson Hall Library.

C2.4. OPTION 4. Contingent upon funding. The contractor shall remove all active components and replace and install new ADRF equipment to support 5G cellular technologies within Building 752, Mahan Hall. Existing passive equipment and cabling shall be reused.

C2.4.1. The contractor shall identify and remove all active DAS components from the facility. and dispose of the equipment in accordance with environmental and regulatory guidelines and local regulations.

a. STD. The contractor shall not use Government facilities for disposal of any equipment/materials removed under this PWS.

b. STD. The equipment will be removed and disposed of in accordance with environmental and regulatory guidelines and local regulations.

c. STD. The Contractor shall ensure that all personnel involved in the removal and transportation of removed equipment follows OSHA Standard 1910.176- Handling Materials.

d. STD. The contractor shall coordinate downtime of sectors to the CIO/G6 Network Service Branch and Major Carriers as appropriate.

C2.4.2. The contractor shall install active equipment within the assigned telecommunications area within the racks and spaces vacated by the equipment removed in section 2.4.1.

a. STD. All equipment shall be installed in accordance with the manufacturer's specifications.

b. STD. All personnel assigned for the installation of equipment shall be experienced and certified to perform this task.

C2.4.3. Testing and certification. The contractor shall provide certification and performance measures for both passive and active systems.

a. STD. All cable will be tested end to end.

b. STD. Any defective components shall be identified and replaced by the contractor

c. STD. The contractor shall coordinate outages and disruptions of active operation with the COR, CIO/G6 Network Service branch and major carriers.

d. STD. Active test results will meet the requirements in Table 2.

e. STD. The contractor shall coordinate downtime of sectors to the CIO/G6 Network Service Branch and Major Carriers as appropriate.

C2.4.4. Closeout Documentation. The contractor shall provide final design plan, RF Propagation studies, test results, As Builds.

a. STD. Final documentation shall be in electronic format. All drawings shall be in ADOBE PDF format

b. Final documentation shall be provided to the COR within 15 days of close-out. (Deliverable #12)

C2.5. OPTION 5. Contingent upon funding, the contractor shall remove and replace all passives equipment including antennas and cable and replace the DAS infrastructure with a new infrastructure which is rated for 5G performance.

a. STD. The contractor shall not use Government facilities for disposal of any equipment/materials removed under this PWS.

b. STD. The equipment will be removed and disposed of in accordance with environmental and regulatory guidelines and local regulations.

c. STD. The Contractor shall ensure that all personnel involved in the removal and transportation of removed equipment follows OSHA Standard 1910.176- Handling Materials.

d. STD. The contractor shall coordinate downtime of sectors to the CIO/G6 Network Service Branch and Major Carriers as appropriate.

C2.5.1. The contractor shall perform a RF Propagation study to assess the building layout for optimal antenna placement, validate cable routes, and passive components.

a. STD. Provide floor plan with antenna locations and cable route to the COR before implementation. (Deliverable # 11)

b. No work will be performed pending the acceptance of the plan as communicated by the COR.

C2.5.2. Infrastructure Installation. The contractor will install all passive equipment to include antennas, cabling, connectors, taps, splitters ect.. from the active equipment throughout its respective zone.

a. STD. All infrastructure installation practices will be installed in accordance with references in Table 1.

b. STD. All cables will be dressed and secure with a neat appearance

c. STD. All personnel assigned to this task will be qualified and certified in the installation of DAS Infrastructure.

C2.5.3. Testing and certification. The contractor shall provide certification and performance measures for both passive and active systems.

a. STD. All cable will be tested end to end.

b. STD. Any defective components shall be identified and replaced by the contractor.

c. STD. The contractor shall coordinate outages and disruptions of active operation with the COR and or CIO/G6 Network Service branch.

d. STD. Active test results will meet the requirements in Table 2.

e. STD. The contractor shall coordinate downtime of sectors to the CIO/G6 Network Service Branch and Major Carriers as appropriate.

C2.5.4. Closeout Documentation. The contractor shall provide final design plan, RF Propagation studies, test results, As Builts.

a. STD. Final documentation shall be in electronic format. All drawings shall be in ADOBE PDF format.

b. Final documentation shall be provided to the COR within 15 days of close-out.

(Deliverable #12)

C2.5.5. OPTION 6. Contingent upon funding Contingent upon funding. The contractor shall provide and install a redundant back-up power system to the active DAS equipment installed within building 752, Mahan Hall.

QUALITY ASSURANCE

C4.1 Quality Control Plan (QCP):. The Contractor shall develop and maintain a QCP to ensure services are performed in accordance with (IAW) this PWS. The Contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The Contractor's QCP is the means by which it assures that the work provided complies with the requirements of the contract.

The Contractor's Proposed QCP shall be submitted to the Contracting Officer (KO) through the Contracting Officer's Representative (COR) for review within 10DAYS after date of contract award (Deliverable #2)

The Government will review and either notify the Contractor in writing of acceptance of the plan or return their comments to the Contractor within 5 working days If the Government has provided comments, the Contractor shall then have 5 working days to submit a Final QCP. After receipt of the Final QCP, the Contractor may receive the Contracting Officer's acceptance in writing. Any proposed changes to the accepted QCP are required to be resubmitted for acceptance by the Contracting Officer no later than 5 working days prior to the anticipated change and before implementation by the Contractor. The timeline noted above will apply for review and acceptance for proposed changes. At a minimum, the QCP must include and answer the following to be acceptable:

a. A chart showing the organizational structure and lines of authority, the names, qualifications, duties, responsibilities, and classification of each member of the Contractor's Quality Control Team.

b. How the Contractor will monitor work to ensure performance complies with all deliverables (etc.

timelines, deadlines, and goals);

c. How the Contractor will monitor work to ensure performance complies with all specifications and requirements of the contract, including the contract's clauses;

d. How the Contractor will monitor and ensure staff qualifications remain current and valid including Department of Defense (DoD) Contractor Personnel Office (DOCPER) processes /approvals throughout contract performance;

f. How the Contractor will inventory and track maintenance of all Government Provided Equipment / Materials;

g. How the Contractor will identify, investigate, and correct any non-conforming performance and prevent similar deficiencies in the future; and

h. How the Contractor will file and save all Quality Control related documents for the life of the contract plus 5 years.

C4.1.1 The Contractor shall inform the COR of issues or potential issues that might affect the performance within 2 hours of identifying those issues. Verbal reports shall be followed by written reports within 1DAY.

C4.2 Quality Assurance: The Government will evaluate the Contractor's performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government must do to ensure that the Contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the acceptable quality levels (performance thresholds).

C4.3 Performance Requirements Summary(PRS). The Contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement

C4.4 Post Award Conference/Periodic Progress Meetings: The Contractor shall attend any post award conference convened by the contracting activity or contract administration office in accordance with FAR Subpart 42.5. The Contracting Officer, COR, and other Government personnel, as appropriate, may meet periodically with the Contractor to review the Contractor's performance. At these meetings the Contracting Officer will apprise the Contractor of how the Government views the Contractor's performance and the Contractor shall apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the Government.

C4.4.1 The Contractor shall attend, participate in, and furnish input to scheduled and unscheduled meetings, conferences, and briefings that relate to the functions and services herein as required by the Government to provide effective communication and impart necessary information. The Contract Manager or designated representative shall attend meetings as requested by the Government. Meeting attendees shall at times include Contractor managerial, supervisory, and other personnel knowledgeable of the subject matter. Meetings may start or end outside of regular duty hours.

PART 5

KEY PERSONNEL

C5.1 Key Personnel- Contractor: The following personnel are considered key personnel by the Government: The Contractor shall provide a Program/Contract Manager who shall be responsible for the performance of the work. Each of these individuals shall be provided in writing to the Contracting Officer no later than 5 DAYS after contract award (Deliverable #4). The Contract Manager and Alternate Contract Manager shall have full authority to act for the Contractor on all contract matters relating to daily operation of this contract. The Contract Manager or Alternate Contract Manager shall be available between 0700 and 1700. Qualifications for all key personnel are listed below:

C6.1 Recognized Holidays: The following provides information on recognized holidays for the purpose of the PWS. If submittal of any documentation (e.g. deliverables, submittals, etc.)

deadlines fall on a holiday, the closest workday prior to the holiday will apply as the deadline for submittal.

C6.1.1 U.S. Holidays: Work shall not be performed on U.S. federally recognized holidays occurring during the normal workweek unless otherwise directed by the Contracting Officer. When a U.S.

holiday occurs on a Saturday or a Sunday, the holiday is observed on the preceding Friday or following Monday, respectively.

New Year's Day January 1st M. L. King Memorial Day 3rd Monday in Jan Presidents' Day 3rd Monday in February Memorial Day last Monday in May Juneteenth June 19th Independence Day July 4th

Labor Day 1st Monday in September Columbus Day 2nd Monday in October Veteran's Day November 11th Thanksgiving Day 4th Thursday in November Christmas Day December 25th

C6.1.2 Should the United States Congress and/or the President of the United States sign into law any new federal holidays not listed above, guidance will be given as to the availability of personnel and the effected hours of operation where the work is being conducted. Contractors will be notified as soon as any new holiday guidance is given to the Department of Defense, Department of the Army and the United States Military Academy at West Point.

C6.2 Operating Hours: The Government facility office hours, facility operating hours, and the Contractor support hour requirements often coincide, however, they may differ. Please refer to the following.

C6.2.1 Government Facility Office Hours: The Government facility office hours are 7:00 am and 5:

00 pm (0700 - 1700 hours) Monday thru Friday except U.S. Holidays identified in paragraph

1.5.3.1 above or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings.

C6.2.2 Government Facility Operating Hours: The Government facility operating hours are 7:00 am and 5:00 pm (0700 - 1700 hours) Monday thru Friday except U.S. Holidays identified in paragraph 6.1.1, above or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings.

C6.2.3 Contractor Support Hours: The Contractor shall provide support between the hours of 7:00 am and 5:00 pm (0700 - 1700 hours) Monday thru Friday except on Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. The Contractor shall maintain an adequate workforce at all times, for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce is essential.

C6.3 Blackout dates: USMA is an educational institution and located at the United States Army Garrison - West Point. Certain Army functions, as well as USMA activities, occur throughout the calendar year where contractors are prohibited from conducting work. Work during these dates is allowed to continue based on mission requirements and coordination between the government and contractor; however, these dates are subject to blackout due to the Academy's mission and operations.

C6.4 Security Requirements: The following information is provided on security related matters.

C6.4.1 Security Program: Contractor personnel performing work under this contract must comply with the standards as defined within this document.

C6.4.1.1 Alien Employment. The contractor shall not employ any alien who does not have a valid US Immigration I-551 or I-94. The contractor shall provide valid social security numbers and citizenship status of all employees to the Government, upon request.

C6.4.1.2 E-Verify. E-Verify is an Internet based system operated by the Department of Homeland Security (DHS) in partnership with the Social Security Administration (SSA) that allows participating employers to electronically verify the employment eligibility of their newly hired employees. E-Verify is currently free to employers and is available in all 50 states. E-Verify provides an automated link to federal databases to help employers determine employment eligibility of new hires and the validity of their Social Security numbers. E-Verify are the best means for determining employment eligibility of new hires and the validity of their Social Security numbers.

(1) Contractors shall use E-Verify on all employees that will be working on this installation, under this contract. This shall be done prior to the employee starting work on the installation.

For E-Verify information: www.dhs.gov/E-Verify 1-888-464-4218

(2) The United States Government has adopted a zero tolerance policy regarding trafficking in persons. Additional information about trafficking in persons may be found at the website for the

Department of State's Office to Monitor and Combat Trafficking in Persons' at http://www.state.gov /g/tip. Government contracts shall :

(a) Prohibit contractors, contractor employees, subcontractors, and subcontractor employees from

(b) Engaging in severe forms of trafficking in persons during the period of performance of the contract;

(c) Procuring commercial sex acts during the period of performance of the contract; or

(d) Using forced labor in the performance of the contract;

(e) Require contractors and subcontractors to notify employees of the prohibited activities described in paragraph (a) of this section and the actions that may be taken against them for violations; and

(f) Impose suitable remedies, including termination, on contractors that fail to comply with the requirements of paragraphs (a) and (b) of this section.

C6.4.2 Personnel Security Clearance Requirements: The contractor shall be responsible for safeguarding all government equipment, information, and property provided for contractor use. At the close of each work period, government facilities, equipment, and materials shall be secured.

C6.4.3 Installation Access: Access to U.S. installations, buildings and controlled areas is limited to personnel who meet security criteria and are authorized. Failure to submit required information /data and obtain required documentation or clearances will be grounds for denying access to U.S.

installations, buildings and controlled areas. The Contractor shall ensure that any subcontractors used in performance of this contract complies with these requirements and that all employees, of both the Contractor and any subcontractor utilized by the Contractor, are made aware of and comply with these requirements.

The Contractor shall be aware of and comply with the requirements associated with Installation Access Control. The Government is not liable for any costs associated with performance delays due solely to a firm's failure to comply with Installation Access Control System (IACS) processing requirements.

The Contractor shall return installation passes to the issuing IACS office when the contract is completed or when a Contractor employee no longer requires access.

C6.4.3.1 6.4.3.1 Force Protection Conditions (FPCON's).

During higher Force Protection Conditions (FPCON's) Contract personnel are required to comply with all Antiterrorism policies and procedures while on the installation. Contract personnel may be directed to enter the installation through certain access control points where they can best be identified and searched. Contractor personnel may be prohibited from certain portions of the installation during exercises and actual emergencies.

(1) Contractors will comply with parking restrictions and will not park in unauthorized parking areas or within 82 feet of an inhabited building when directed.

(2) Access control roster (personnel and vehicles) must be provided. Names / vehicles verified by the company and received background screening. Substitutes receive same vetting process prior to work.

(3) All contractor personnel and vehicles are subject to search while on the installation

(4) In the event of an identified restricted/exclusion area, the contractor personnel will not be authorized without specific permission or an escort.

(5) Access may be denied during increased readiness or Force Protection Conditions (FPCON's).

C6.4.3.2 Under no circumstances will Contractors Park in Central Parking Area (CPA) Lots. The local general, visitor, and government designated parking areas SHALL NOT be used by the contractor. No general contractor or subcontractor employee parking is available near the immediate site. The contractor will need to identify and locate parking facilities for general and subcontractors on/off of West Point and provide a means for shuttling workers to the site. West Point shuttle services will not be used for transporting workers to the site.

Contractors vehicles can only park in pre-approved designated staging areas or as identified in their contract, but not in contradiction of the CPRA Policy or the Installation Access policy #13 dated 12 December 2022. Central Area Parking is reserved for Staff and Faculty and requires a special pass. In accordance with AR 190-5, persons who operate a motor vehicle on West Point shall be deemed to have given consent for the removal and temporary impoundment of the privately owned vehicle (POV) and equipment when it is:

(1) Parked illegally.

(2) Interfering with operations

(3) Creating a safety hazard

(4) Left unattended in a restricted or controlled area.

(5) Parked in a Central Parking Area (CPA) lot without the proper CPA Pass

(6) Parked in a reserved space authorized by the Installation Commander

The COR overseeing the contract will review and coordinate all contractor pass requests. All contractor vehicles requiring access to the Cadet Area will require a Cadet Area Pass (CAP). The Contractor must coordinate with the COR immediately upon vehicle assignment. The Contractor will need to provide the following information:

Make, Model, Year, Color and Registration (Tag Number)

C6.4.4 Installation Pass Log: The contractor must first stop at the West Point Visitor's Control Center (VCC) and complete a background check to get access to the installation. It is located at 2107 New South Post Rd, Highland Falls, New York 10928, Ph: (845) 938-2638. The Visitor Control Center is open Monday-Sunday from 6 a.m. to 10 p.m. When the Visitor Control Center is closed, visitors will be directed to proceed to Stony Lonesome Gate for a background check and temporary pass. If you do not have a Department of Defense issued identification card, you will be considered one of three categories: Escorted Visitors, Foreign Visitors and Unescorted Visitors. A current driver's license or passport will suffice for identification, but effective October 1, 2020, driver's licenses and identification cards from specific territories and states that do not comply with the REAL ID Act of 2005 are not to be used as the sole source for identity verification to access Federal installations. A listing of the current state-by-state compliance is available at REAL ID Act Status of States & Territories. Additional information can be found at: https://home.army.mil /westpoint/index.php/about/visitor-information

In addition, the Contractor shall provide the Contracting Officer, via the COR, an Initial Installation Pass Log within 5DAYS after the contractor's workforce have satisfied all access requirements (Deliverable #4"). The log must at a minimum contain the following information Last Name, First Name, Company, Supervisor Contact. The log shall be updated as employees are added or removed. The Updated Installation Pass Log shall be current and available at any time upon request by the Government and submitted to the COR within 5DAYS after any changes to the log.

C6.4.5 Individual Termination or Expiration of Employment: The Contractor shall collect the installation access passes the same day employment of an individual has expired or has been terminated and shall return them to the issuing office within 3 days (Deliverable #5).

6.4.5.1 Contract Termination or Cancellation: Upon termination or cancellation of this contract, the Contractor shall collect all outstanding installation access passes and return them to the issuing office within 5 working days (Deliverable #6).

6.6 Common Access Cards (CAC) and CAC Log: Before CAC issuance, the contractor employee requires, at a minimum, a favorably adjudicated National Agency Check with Inquiries (NACI) or an equivalent or higher investigation in accordance with Army Directive 2014-05.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .