Attachment 1 Specifications

View the file

Other files

File Type Posted
B09_Amendment_Three_P17PS00436_20170524.pdf PDF
Amendment_Two_P17PS00436.pdf PDF
P17PS00436_Amendment_One.pdf PDF
Attach_2_Drawings_11_E.pdf PDF
Attach_8_Geotechnical_Evaluation_Proposed_PI_Annex_Improvements,_Nov_11,_2015.pdf PDF
Attach_5_Asbestos,_Lead-Based_Paint,_and_PCB_Surveys_at_Paradise_Inn_and_Annex_Dec_8,_2004.pdf PDF
Attach_2_Drawings_9_M.pdf PDF
Attach_6_Discovery_Demolition_Observation_Reports_May_2016.pdf PDF
Attach_2_Drawings_7_S0_thru_S3.pdf PDF
Attach_3_Abatement_Closeout_Report_from_FS_&_GS_Jun,_2016.pdf PDF
Attach_12_Subsurface_Exploration_and_Geotech_Engr_Report,_Sept_30,_2011.pdf PDF
Attach_2_Drawings_3_A0_thru_A1.pdf PDF
Attach_2_Drawings_2_C_and_L.pdf PDF
Attach_2_Drawings_4_A2_thru_A4.pdf PDF
Attach_2_Drawings_5_A5.pdf PDF
Attach_10_Memorandum,_Paradise_Inn_Annex_Preliminary_Geotechnical_Review,_Dec_22,_2010.pdf PDF
Attach_13_Supplemental_Hazardous_Material_Inspection_Report,_May_17,_2016.pdf PDF
Attach_11_Radon_test_results_Annex_basement_May_2016.pdf PDF
Attach_2_Drawings_10_F.pdf PDF
Attach_15_DOL_General_Decision_WA38_20170310.docx DOCX document
Attach_7_Furniture_room_list_March_13,_2017_update.xlsx XLSX spreadsheet
Attach_16_Proposal_Submission_Package_MORA.pdf PDF
Attach_14_Wetlands_and_other_Waters_Delineation_Report_Nov_4,_2015.pdf PDF
Attach_9_Geotechnical_Exploration_at_Paradise_Inn,_Nov_22,_2004.pdf PDF
P17PS00436_MORA_152787.pdf PDF
Attach_4_Annex_Fire_Alarm_As-Builts_2008.pdf PDF
Attach_2_Drawings_8_S4_thru_S6.pdf PDF
Attach_2_Drawings_6_A6_thru_A7.pdf PDF
Attach_2_Drawings_1_Cover_and_G.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MOUNT RAINIER NATIONAL PARK

Ashford, Washington

REHABILITATE PARADISE INN ANNEX & CONNECTION

SNOW BRIDGE

MORA

PMIS NO. 152787

FINAL

CONSTRUCTION DOCUMENTS

SPECIFICATIONS: DIVISION 01

VOL. 1 OF 3

NATIONAL PARK SERVICE

DENVER SERVICE CENTER

December 22, 2016

MORA - 152787 00 01 10 – V1-1

TABLE OF CONTENTS

SECTION 00 01 10 - TABLE OF CONTENTS

Division Section Title Pages

SPECIFICATIONS GROUP

VOLUME 1

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00........ Summary of Work 01 26 01........ Contract Modification Procedures 01 27 00........ Definition of Contract Line Items Annex Furniture and Furnishings Inventory 1 01 31 00........ Project Management and Coordination 01 32 16........ Construction Schedule 01 32 33........ Photographic Documentation 01 33 23........ Submittal Procedures Submittal List 01 35 13.22 ... Archeological Protection 01 35 23........ Safety Requirements 01 35 91........ Historic Preservation Treatment Procedures 01 40 00........ Quality Requirements CQC Accessibility Inspection Report Statement of Structural Tests and Special Inspections 01 42 00........ References 01 50 00........ Temporary Facilities and Controls 01 57 19.11 ... Indoor Air Quality Management 01 57 19.12 ... Noise & Acoustics Management 01 57 23........ Under-An-Acre Pollution Prevention 01 67 00........ Product Requirements 01 73 29........ Cutting and Patching 01 73 40........ Execution 01 74 19........ Construction Waste Management and Disposal Appendix A – Project Waste Management Plan Worksheet Appendix B – Standard Solid Waste Conversions 01 77 00........ Closeout Procedures 01 78 23........ Operation and Maintenance Data 01 79 00........ Demonstration and Training 01 81 13........ Sustainable Design Requirements 01 91 14........ Total Building Commissioning

Closeout and Operational Maintenance Requirements Paradise Winter Group Camping Map Winter Recreation Map Annual Snowfall Totals at Paradise Winter Road Closure Status As-Built Floor Survey of Interior Floor Elevations

MORA - 152787 00 01 10 – V2-1

VOLUME 2

DIVISION 02 - EXISTING CONDITIONS

02 08 10 ........ Chemical Hazard Removal and Disposal 02 41 19 ........ Selective Demolition 02 42 96 ........ Historic Removal and Dismantling of Exposed Stone Foundation 02 65 00 ........ Underground Storage Tank Removal 02 82 13 ........ Asbestos Abatement and Disposal 02 83 33 ........ Lead Removal and Disturbance

DIVISION 03 – CONCRETE

03 30 00 ........ Cast-In Place Concrete

DIVISION 04 - MASONRY

04 43 13.13 ... Anchored Stone Masonry Veneer

DIVISION 05 - METALS

05 50 00 ........ Metal Fabrications 05 52 13 ........ Pipe and Tube Railings

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 03 12 ........ Historic Wood Repair 06 10 00 ........ Rough Carpentry 06 16 00 ........ Sheathing 06 20 13 ........ Exterior Finish Carpentry 06 20 23 ........ Interior Finish Carpentry 06 64 00 ........ Plastic Paneling

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 13 26 ........ Self-Adhering Sheet Waterproofing 07 21 00 ........ Thermal Insulation 07 25 00 ........ Weather Barriers 07 26 00 ........ Vapor Retarders 07 31 29 ........ Wood Shingles and Shakes 07 41 13.16 ... Standing-Seam Metal Roof Panels 07 46 24 ........ Wood Shingle and Shake Siding 07 62 00 ........ Sheet Metal Flashing and Trim 07 72 00 ........ Roof Accessories 07 84 13 ........ Penetration Firestopping 07 92 00 ........ Joint Sealants

DIVISION 08 - OPENINGS

08 03 52 ........ Historic Treatment of Wood Windows

MORA - 152787 00 01 10 – V2-2

08 11 13 ........ Hollow Metal Doors and Frames 08 14 33 ........ Stile and Rail Wood Doors 08 31 13 ........ Access Doors and Frames 08 71 00 ........ Door Hardware 08 80 00 ........ Glazing 08 83 00 ........ Mirrors

DIVISION 09 - FINISHES

09 21 16.23 ... Gypsum Board Shaft Wall Assemblies 09 22 16 ........ Non-Structural Metal Framing 09 29 00 ........ Gypsum Board 09 30 13 ........ Ceramic Tiling 09 64 00 ........ Wood Flooring 09 65 13 ........ Resilient Base and Accessories 09 65 19 ........ Resilient Tile Flooring 09 68 16 ........ Sheet Carpeting 09 90 00 ........ Painting

DIVISION 10 - SPECIALTIES

10 14 23 ........ Panel Signage 10 28 00 ........ Toilet, Bath, and Laundry Accessories 10 28 19 ........ Tub and Shower Enclosures 10 28 19.16 ... Tub and Shower Doors 10 44 16 ........ Fire Extinguishers

DIVISION 14 - CONVEYING EQUIPMENT

14 91 33 ........ Laundry and Linen Chutes

MORA - 152787 00 01 10 – V3-1

VOLUME 3

DIVISION 21 – FIRE SUPPRESSION

21 05 00 Common Work Results for Fire Suppression

DIVISION 22 – PLUMBING

22 05 00 Common Work Results For Plumbing 22 05 19 Meters and Gages for Plumbing Piping 22 05 29 Hangers and Supports for Plumbing Piping & Equipment 22 05 48 Vibration and Seismic Controls for Plumbing Piping & Equipment 22 05 53 Identification for Plumbing Piping & Equipment 22 07 00 Plumbing Insulation 22 10 00 Plumbing Piping 22 30 00 Plumbing Equipment 22 40 00 Plumbing Fixtures

DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING

23 05 00 Common Work Results for HVAC 23 05 29 Hangers and Supports for HVAC Piping and Equipment 23 05 48 Vibration and Seismic Controls for HVAC Piping, Ductwork and Equipment 23 05 53 Identification for HVAC Piping, Ductwork and Equipment 23 05 93 Testing, Adjusting, and Balancing for HVAC 23 07 00 HVAC Insulation 23 09 33 Instrumentation and Control for HVAC 23 09 93 Sequence of Operations for HVAC Controls 23 31 00 HVAC Ducts and Casings 23 33 00 Air Duct Accessories 23 34 00 HVAC Fans 23 37 00 Air Outlets and Inlets 23 72 00 Air to Air Energy Recovery Equipment 23 82 00 Convection Heating and Cooling Units 23 82 16 Air Coils

MORA - 152787 00 01 10 – V3-2

DIVISION 26 – ELECTRICAL

26 01 26 Maintenance Testing of Electrical Systems 26 05 00 Common Work Results for Electrical 26 05 05 Selective Demolition for Electrical 26 05 19 Low-Voltage Electrical Power Conductors and Cables 26 05 26 Grounding and Bonding for Electrical Systems 26 05 29 Hangers and Supports for Electrical Systems 26 05 33 Raceway and Boxes for Electrical Systems 26 05 48 Vibration and Seismic Controls for Electrical Systems 26 05 53 Identification for Electrical Systems 26 09 23 Lighting Control Devices 26 24 16 Panelboards 26 27 26 Wiring Devices 26 28 16.13 Enclosed Circuit Breakers 26 29 13 Enclosed Controllers 26 33 23 Central Battery Inverter Equipment 26 41 00 Lightning Protection System 26 51 00 Interior Lighting 26 52 00 Emergency Lighting 26 56 00 Exterior Lighting 27 10 00 Structured Cabling

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 31 00 Fire Detection and Alarm

DIVISION 31 – EARTHWORK

31 14 13 Soil Stripping and Stockpiling 31 22 13 Site and Roadway Excavation and Grading 31 23 16 Structure Excavation 31 23 19 Dewatering 31 23 33 Utility Trenching and Backfilling 31 37 16 Riprap

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 19 Engineering Fabric 32 12 13 Bituminous Prime Coat and Tack Coat 32 12 16 Asphalt Paving 32 90 00 Topsoil

MORA - 152787 00 01 10 – V3-3

DIVISION 33 – UTILITIES

33 11 00 Water Utility Distribution Piping 33 41 00 Storm Utility Drainage Piping 33 44 13 Concrete Drop Inlets and Catch Basins 33 46 19 Underdrains

END OF TABLE OF CONTENTS

MORA - 152787 01 11 00 - 1

031414 SUMMARY OF WORK

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Project Information

2. Work covered by the Contract Documents.

3. Work under other contracts

4. Government-Furnished Materials.

5. Contractor use of site.

6. Public use of site.

7. Occupancy requirements for buildings.

8. Conduct of operations.

9. Work Restrictions.

10. Special Construction Requirements.

11. Soils Investigation Reports.

12. Additional Reports.

1.2 DEFINITIONS

A. Annex: The southeastern four story building.

B. Normal Season: Mid-April to early October.

C. Paradise Inn: The main two story building west of the snow bridge including the East Wing.

D. Snow Bridge: The connecting three story link between the Paradise Inn and the Annex.

1.3 PROJECT INFORMATION

A. Project Location: Mount Rainier National Park, Ashford, Washington.

1. Paradise is the name of an area at approximately 5,400 feet (1,600 m) on the south slope of Mount Rainier. It is the most popular destination for visitors to Mount Rainier National Park. The historic Paradise Inn was built in 1916 and is listed on the National Register of Historic Places.

2. The Annex was built in 1920, is on the National Register of Historic Places.

3. The annex consists of 79 guest rooms.

4. Weather patterns at Mount Rainier are strongly influenced by the Pacific Ocean, elevation, and latitude. The climate is generally cool and rainy, with summer highs in the 60s and 70s. While July and August are the sunniest months of the year, rain is possible any day, and very likely in spring, fall, and winter.

MORA - 152787 01 11 00 - 2

5. Mountain weather is very changeable. Wet, cold weather can occur anytime of the year.

Although late-July and August are generally the driest and warmest time of the year, summer can also be wet and cool. Snow will remain at the 5,000 to 8,000 feet elevation well into mid-July.

6. Average Monthly Temperatures at Mount Rainier:

Paradise

(5400 ft/1647 m) High Low °F/°C °F/°C January 33 / 0.5 21 / -6 February 35 / 2 22 / -6 March 37 / 3 22 / -6 April 44 / 7 27 / -3 May 50 / 10 32 / 0 June 56 / 14 44 / 7 July 64 / 18 44 / 7 August 63 / 17 43 / 6 September 57 / 14 39 / 4 October 48 / 9 33 / 0.5 November 41 / 5 37 / 3 December 34 / 1 22 / -6

7. The Paradise Inn area receives between 40 and 90 feet of annual snowfall. 80 percent of the annual precipitation occurs from mid-October through April. In addition, the Paradise area receives approximately 900,000 visitors annually with the peak months being July and August at approximately 300,000 visitors per month.

1.4 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work consists of the following:

1. The foundation of the Annex has been compressed, deformed, and shifted, leaving the building susceptible to failure under a heavy snow load or as the result of a seismic event. Failure would likely take the form of damage severe enough to render the Annex and Snow Bridge unfit for human habitation, although complete collapse of the Annex and Snow Bridge buildings also could occur. Inadequate drainage around the foundation is contributing to the undermining of the foundation. Degradation of exterior walls caused by constant moisture also is contributing to accelerated deterioration of the foundation. Building upgrades are needed to bring the Annex and Snow Bridge into compliance with International Building Code and National Fire Protection Act standards.

The Paradise area is the most heavily visited area of the park, with approximately 70 percent of visitors to the park spending a portion of their stay in the area. Rehabilitation of the Annex and Snow Bridge would need to efficiently implement construction activities while minimizing impacts on park visitors.

2. Rehabilitation work is to be completed as specified in Division 01 Section "Historic Preservation Treatment Procedures.”

3. The Work includes building foundation replacement, building structural and life safety upgrades, replacement of building systems, roofing and siding, repair and replacement of windows, and modifications to site drainage, for the Annex and Snow Bridge portions of the Paradise Inn.

MORA - 152787 01 11 00 - 3

4. Project is designed to comply with a Certification Level according to the U.S. Green Building Council's Leadership in Energy & Environmental Design (LEED) Rating System, as specified in Division 01 Section "Sustainable Design Requirements for Non- LEED Projects."

B. Project will be constructed under a single prime contract.

1.5 WORK UNDER OTHER CONTRACTS

A. The Work is defined by separate Contract Documents and consists of the following:

1. Nisqually to Paradise resurfacing project during summer of 2017.

1.6 GOVERNMENT-FURNISHED MATERIALS

A. Government will furnish products indicated.

B. Government will arrange and pay for delivery of Government-furnished items according to Contractor's Construction Schedule.

1. After delivery, Government will inspect delivered items for damage. Contractor shall be present for and assist in Government's inspection.

2. Contractor is responsible for receiving, unloading, and handling Government-furnished items at Project site.

3. Contractor is responsible for protecting Government-furnished items from damage during storage and handling, including damage from exposure to the elements.

4. Contractor shall install and otherwise incorporate Government-furnished items into the Work.

C. Government-Furnished Products:

1. Local seed for seeding of vegetated swale on west side of Annex. Quantity dependent upon availability of local harvested seed. Contractor to spread available seed provided and shall not provide additional seed if quantity is insufficient.

1.7 CONTRACTOR USE OF SITE

A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Confine construction operations to areas indicated on Drawings and the Contracting Officer.

2. Maintain clearance at right side of parking area at Fourth crossing (located along Paradise Valley road). Area shall be kept open to allow for park use for search and rescue operations (SAR) and helicopter staging.

3. Maintain access to transformer located between Inn and Annex to allow vehicles moving large equipment to access transformer.

MORA - 152787 01 11 00 - 4

4. Snow avalanches off the roof. Contractor to avoid occupancy immediately adjacent to the Annex and Snow Bridge during winter. Contractor is responsible for snow removal from driveway near the southwest corner to the building southwest entrance, Contractor use parking areas, and Contractor use staging areas.

5. If a construction area is unworked for more than seven days during the dry summer season, or two days during the wet summer season, it shall be covered with certified weed-free mulch. All finished construction areas would be stabilized within seven days after final grading.

6. Concessionaire vehicles will require access to Paradise Inn year round. Contractor shall not restrict Concessionaire access.

a. November through March: access to the snow tunnel/entry into the lobby is required for maintenance and management.

b. April 1st thru November 30th (dates may vary according to the type of vehicle): A refrigerated transport truck delivers Monday/Wednesday/Friday to the front doors of the Inn and to the boiler room (directly beneath the kitchen); hourly van service at the front door of the Inn and to the boiler room door for shuttling employees and product delivery (5:30 am to 10 pm); maintenance and management vehicles will require access as well.

c. Concessionaire will require year round access to all of Paradise Inn including concessionaire parking from April thru November.

d. Managers living in the Inn from the end of April through mid-October park their vehicles behind the inn. Contractor shall not restrict Managers access.

e. There is a large recycling dumpster that is placed directly across from the kitchen boiler room doors for the Inns use. Two dumpsters (garbage and composting) are located next to the fuel bunker across from the kitchen for the Inns use. Contractor shall not restrict dumpster access.

f. Since the Inn will be open to the public mid-May through the first week in October, ADA designated parking exists across from the front door of Paradise Inn. Contractor shall not restrict ADA designated parking access during normal season.

B. Storage of Materials: Confine storage of materials to areas indicated on Drawings.

C. Preservation of Natural Features:

1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

2. Provide temporary barriers to protect existing trees and plants and root zones.

3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer and remove agreed-on roots and branches that interfere with construction.

4. Do not fasten ropes, cables, or guys to existing trees.

5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

MORA - 152787 01 11 00 - 5

D. Driveways and Entrances: Keep driveways, entrances, delivery areas, and mechanical access rooms serving premises and adjacent inn clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

E. Construction Camp: Establishment of a camp within the park will not be permitted.

F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment. Road closure and restriction notices may be permitted Monday through Thursday, with one week notice to Park and acceptance at least 72 hours prior to road closure.

1. Emergency access must be allowed and maintained at all times.

2. When transporting large equipment or heavy loads into the park that will cross center lines (due to turning radii) or other conflicts with vehicular traffic in the park, traffic shall not be stopped longer than 20 minutes in each direction and traffic control shall be provided by the contractor.

G. Housing: Park will provide three residences for Contractor’s rental if desired. Each house has a capacity of up to six occupants.

1. Ohanapecosh: One each three bedroom house, $1,030/mo. including utilities, available from May 2018 to October 2018.

2. Tahoma Woods: Two each, three bedroom house, $800/mo. including utilities, available from November 2017 to May 2019.

1.8 PUBLIC USE OF SITE

A. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public.

1. The Paradise Inn will be fully occupied, and operated by the Concessionaire, over the normal seasonal schedule for the facility.

2. The Jackson Visitor Center is open for public access year round with winter access only on weekends and holidays.

3. During the winter season, since the Paradise area typically has over 100 inches of snow accumulation, the Paradise snow play area is open and heavily used. On sunny weekends and holidays, the lower parking lot is full. Parking lot will not be available to Contractor.

MORA - 152787 01 11 00 - 6

1.9 OCCUPANCY REQUIRMENTS FOR BUILDINGS

A. Existing Buildings

1. Partial Government Occupancy: Government will occupy the adjacent Inn during entire construction period (seasonally), with the exception of areas under construction.

Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government’s operations. Maintain existing exits, unless otherwise indicated.

a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the Contracting Officer (CO).

b. The Annex and Snow Bridge will be closed to the public during construction, anticipated to be from August 2017 through spring 2019.

1.10 CONDUCT OF OPERATIONS

A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.

B. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

1.11 WORK RESTRICTIONS

A. The adjoining Paradise Inn is open to the public from around Memorial Day, till the first week in October. The Inn Concessionaire occupies the building approximately two week before, and two weeks after, this period for start-up and shut-down procedures.

1. The Annex and Snow Bridge will be closed to the public during construction, anticipated to be from August 2017 through spring 2019. The Paradise Inn lobby, dining hall, and East Wing will remain open during construction.

B. On-Site Work Hours: Work shall be generally performed Monday through Saturday, as indicated below:

1. Occupied Inn Season Work Hours:

a. 7 am to 8am: Quiet work hours.

b. 8 am to 7 pm: General work hours.

c. 8 am to 5 pm: Restricted hours for excessively loud work.

2. Non-Occupied Inn Season Work Hours:

a. 7 am to 7 pm: General work hours with no restrictions for excessively loud work.

MORA - 152787 01 11 00 - 7

C. Work on Sundays, Federal holidays, early mornings, or at night may not be performed without prior consent from the Contracting Officer. Submit requests two weeks in advance of the work to the Contracting Officer for approval.

1. Requests may be submitted one week in advance during non-occupied Inn season

D. Existing Utilities

1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.

2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

E. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify Contracting Officer not less than seven days in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without Contracting Officer’s written permission.

F. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes.

1.12 SPECIAL CONSTRUCTION REQUIREMENTS

A. Project Website: A project website administered by the NPS will be used for purposes of managing communication and documents during the construction stage.

1. See Section 01 31 00 “Project Management and Coordination” for requirements on using the Project Website.

MORA - 152787 01 11 00 - 8

B. Site Access Restrictions:

1. Primary Access: The primary access to the project site for construction vehicles is from the Ohanapecosh Entrance along Stevens Canyon Road to the intersection with the Nisqually to Paradise Road, and then northerly on the Nisqually to Paradise Road to the project site. Nisqually to Paradise Road from the Nisqually Entrance to the project site may be used only when hauling materials and equipment to or from one of the staging areas along the Nisqually to Paradise Road, or State Route 706. Contractor vehicles shall provide scale receipts showing the fully loaded weight prior to entering the Park. Park roads include many tight radius curves. As a result, dump trucks with trailers, belly dump trucks, lowboy trucks, truck and trailer combinations, and any other vehicle unable to negotiate these curves without crossing the road centerline are permitted on these roads only after receiving approval of a detailed hauling and traffic control plan. This plan shall be submitted to the Contracting Officer, and shall include locations for offloading trucks, anticipated dates and durations for hauling, including time of day, the number of trucks and anticipated quantity of trips. Provide location specific traffic control plans for all curves where a road closure is needed.

2. Nisqually-to-Paradise Road: This road is heavily traveled. Gate at Longmire is open year-round and generally open from 9 am to 5 pm in winter, dependent on road conditions and avalanche danger. It is closed during snow removal operations and may be closed for multiple days due to avalanche hazards, drifting snow, high winds, or storm warnings. The road shall be re-built and resurfaced during the summers of 2016 and 2017. There is a 20-ton limit on this road to the junction with Stevens Canyon Road and 32/40 ton from this junction to Paradise Inn. Centerline radius dimension for the curves are as low as 60-feet. Provide traffic control flag personnel when truck turning radius will cross road centerline.

3. Valley Road: The one way traffic downhill from Paradise Inn to Stevens Canyon Road is heavily used by public in the summer from mid-June to mid-October. Road is closed in winter. Two staging areas along the road will be made available to the Contractor. Load limit is 32/40 ton.

4. Stevens Canyon Road: Road is closed in winter and open from mid-June to mid-October.

Tunnels and bridges restrict load weight and width. Vertical clearance for the 2 tunnels on Stevens Canyon Road is 12-feet 6-inches. Load restriction from Stevens Canyon/Highway123 junction to Nisqually-to-Paradise junction is 32/40 ton. Centerline radius dimension for the curves are as low as 90-feet.

5. Restrict hauling of heavy loads from dump trucks, concrete transit trucks, belly dumps, and low-boy trailers to road easterly along Stevens Canyon Road from Stevens Canyon Entrance at Highway 123 to connection with Nisqually-to-Paradise Road, and northerly along Nisqually-to-Paradise Road to Paradise. See Hauling Restrictions in Contractors Use of Site for additional requirements.

6. Chains shall be carried from November 1 to May 1 for all roads. Conditions may require their use during unseasonal snowfall events.

7. Report all road kill and wildlife collisions to the Contracting Officer immediately.

C. Staging Restrictions:

1. Many amphibians are present around the Work area. Provide sediment control barriers to prevent amphibians from crawling onto the project site and stored materials.

2. Paradise Inn Site: As shown on Drawings.

MORA - 152787 01 11 00 - 9

3. Cougar Rock Picnic Area: Contractor will have winter staging use of this area from November 2017, to March 14 2018, and from November 2018, to March 14 2019.

Summer staging will not be permitted. Contractor may not use this area from March 15 to October 31. Cougar Rock Picnic Site is located approximately 9 miles from Paradise along the Nisqually to Paradise Road.

4. Tahoma Woods: Staging will be permitted year round.

5. Backbone Ridge Staging Area: Contractor will have summer staging use of this area from late June 2017, to mid October 2017 and from June 2018 to mid-October 2018. The space available is approximately 350 feet long by 35 feet wide and is located approximately 15.5 miles from Paradise along the Stevens Canyon Road.

6. Storage of equipment and materials at designated staging areas within 150 feet of streams and wetlands, appropriate erosion protection measures shall be implemented to protect water resources, travel lanes, or areas designated not to be disturbed.

7. Contractor is responsible for snow removal at staging areas.

8. See Section 01 57 23 “Under-an-Acre Pollution Prevention’ for sediment control requirements.

D. Vehicle Restrictions:

1. Vehicles may not be permitted to idle more than 15 minutes when not in use.

2. All motor vehicles shall be equipped with mufflers in good working order and conforming to original manufacturer’s specifications.

3. Sound attenuation devises such as rubber strips or sheeting shall be installed and maintained on all equipment. Example: Dump truck tail gate dampeners for both opening and closing.

4. Un-muffled air brakes are prohibited within park boundaries.

5. Air horns shall not be used within park boundaries except for safety.

E. Lighting: All lighting required at night must be directed downward.

F. Wildlife Restrictions:

1. Four amphibian federal and state species of concern are known to occur near the project area or staging areas: Cascades frog (Rana cascadae), tailed frog (Ascaphus truei), Van Dyke’s salamander (Plethodon vandykei), and Larch Mountain salamander (Plethodon larselii). Potential impacts on these amphibian species include roadkill, being crushed by machinery, falling into excavated areas during construction, or being crushed or trapped in staging areas.

2. The NPS will inform construction personnel of occurrence and status of special status species near project area, potential impacts construction activities may have on the species, and the potential penalties for taking or harming a special status species.

3. Contractor to notify the NPS two weeks prior to excavation or use of the wetlands east of Annex.

4. Feeding or approaching wildlife is prohibited and is subject to citation.

5. The Contracting Officer shall be notified if bear or fox loiter near the project area.

6. A litter control program shall be implemented during construction to eliminate the accumulation of trash. All food items shall be stored inside vehicles, trailers, or wildlife-resistant receptacles except during actual use to prevent attracting wildlife. Food waste left out is subject to citation.

MORA - 152787 01 11 00 - 10

G. Weed Prevention:

1. All imported erosion control materials that are capable of harboring plant seed would be certified weed-free according to North American Weed Management Association standards. The park will inspect all local material sources prior to use or transport of materials into the park.

2. See material source measures in the Environmental Assessment BMPs/resource protection measures. Sources shall be approved/inspected in advance. Large rock shall be cleaned. The NPS has preferred source(s), but most have weeds. All vehicle loads shall be covered.

H. Pest Management (Excerpt from NPS Management Policies 2006):

1. All park contractors on all lands managed or regulated by the National Park Service will comply with NPS pest management policies.

2. Pests: Pests are living organisms that interfere with the purposes or management objectives of a specific site within a park or that jeopardize human health or safety.

Decisions concerning whether or not to manage a pest or pest population will be influenced by whether the pest is an exotic or a native species. Exotic pests will be managed according to both the policies in this section and the exotic species policies.

Native pests will be allowed to function unimpeded, except as noted below. Many fungi, insects, rodents, disease organisms, and other organisms that may be perceived as pests are, in fact, native organisms existing under natural conditions and are natural elements of the ecosystem. Also, native pests that were evident in pesticide-free times are traditional elements in park cultural settings.

3. Contractor shall control native pests to accomplish the following:

a. Conserve threatened, rare, or endangered species, or unique specimens or communities;

b. Preserve, maintain, or restore the historical integrity of cultural resources;

c. Conserve and protect plants, animals, and facilities in developed areas;

d. Prevent outbreaks of a pest from invading uninfested areas outside the park;

e. Manage a human health hazard when advised to do so by the U. S. Public Health

Service (which includes the Centers for Disease Control and the NPS public health program);

f. o otherwise protect against a significant threat to human safety.

4. Integrated Pest Management Program: Contractor shall conduct an integrated pest management (IPM) program to reduce risks to the public, park resources, and the environment from pests and pest-related management strategies. Integrated pest management is a decision-making process that coordinates knowledge of pest biology, the environment, and available technology to prevent unacceptable levels of pest damage by cost-effective means while posing the least possible risk to people, resources, and the environment.

MORA - 152787 01 11 00 - 11

Contractor and each park unit will use an IPM approach to address pest issues. Proposed pest management activities must be conducted according to the IMP process prescribed in Director’s Order #77-7: Integrated Pest Management. Pest issues will be reviewed on a case-by-case basis. Controversial issues, or those that have potential to negatively impact the environment, must be addressed through established planning procedures and be included in an approved park management or IPM plan. IPM procedures will be used to determine when to implement pest management actions and which combination of strategies will be most effective for each pest situation. Under the Contractor’s IPM program, all pesticide use on lands managed or regulated by the Contractor, whether that use was authorized or unauthorized, must be reported annually.

5. Pesticide Use: A pesticide, as defined by the Federal Insecticide, Fungicide and Rodenticide Act, is any substance or mixture that is used in any manner to destroy, repel, or control the growth of any viral, microbial, plant, or animal pest. Except as identified in the next paragraph, all prospective users of pesticides in parks must submit pesticide use requests, which will be reviewed on a case-by-case basis, taking into account environmental effects, cost and staffing, and other relevant considerations. The decision to incorporate a chemical, biological, or bioengineered pesticide into a management strategy will be based on a determination by a designated IPM specialist that it is necessary and other available options are either not acceptable or not feasible. Pesticide applications will only be performed by or under the supervision of certified or registered applicators licensed under the procedures of a federal or state certification system. Insect repellents, bear deterrent sprays, and insecticides applied to persons or to livestock must conform to NPS policies and approval procedures, except that pesticides used under the following conditions do not require approval:

a. Cleansers and disinfectants used in restrooms and restaurants

b. Personal insect repellents, insecticides, and bear deterrent sprays that employees or park visitors personally obtain and use to meet personal needs

c. Insect repellents and insecticides applied to personally owned pets and pack and saddle stock

6. Biological Control Agents and Bioengineered Products: The application or release of any bio-control agent or bioengineered product relating to pest management activities must be reviewed by designated IPM specialists in accordance with Director’s Order #77-7 and conform to the exotic species policies.

7. Pesticide Purchase and Storage: Pesticides must not be stockpiled. No pesticides may be purchased unless they are authorized and expected to be used within one year from the date of purchase. Pesticide storage, transport, and disposal will comply with procedures established by (1) the Environmental Protection Agency; (2) the individual states in which parks are located; and (3) Director’s Order #13B: Solid and Hazardous Waste Management, Director’s Order #77-1: Wetland Protection, and Director’s Order 77-7:

Integrated Pest Management.

(See NPS Management Policies 2006 Sections Planning for Natural Resource Management 4.1.1; Genetic Resource Management Principles 4.4.1.2; Management of Exotic Species 4.4.4; Maintenance 9.1.4)

MORA - 152787 01 11 00 - 12

1.13 SOILS INVESTIGATION REPORTS

A. A soils investigation report entitled Geotechnical Evaluation, Proposed Paradise Inn Annex Improvements dated November 11, 2015, has been prepared by AECOM.

B. A copy of the report is available to all plan holders with this package.

C. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.

1.14 ADDITIONAL REPORTS

A. A report entitled Geotechnical Exploration at Paradise Inn Mount Rainier National Park dated November 22, 2004, has been prepared by Northwest Geotechnical.

B. A memorandum entitled Paradise Inn Annex Preliminary Geotechnical Review dated December 22, 2010, has been prepared by Ash Creek Associates.

C. A report entitled Subsurface Exploration and Geotechnical Engineering Report Proposed Paradise Inn Annex Improvements Mount Rainier, Washington dated September 30, 2011, has been prepared by Ash Creek Associates.

D. A report entitled Wetlands and Other Waters Delineation Report, Paradise Inn Annex and Snow Bridge Rehabilitation dated November 2015, has been prepared by ERO Resources Corporation.

E. A report entitled Asbestos, Lead-Based Paint, and PCB Surveys at Paradise Inn and Annex dated December 8, 2004, has been prepared by U.S. Public Health Service, Federal Occupational Health.

F. A report titled Supplemental Hazardous Material Inspection Report dated May 17, 2016, has been prepared by White Environmental Consultants, Inc.

G. A copy of these reports are available to all plan holders with this package.

H. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 PARKING AND STAGING AREAS

A. Repair asphalt in parking and staging areas damaged by Contractor’s vehicles and machinery.

END OF SECTION 01 11 00

MORA - 152787 01 26 01 - 1

031414 CONTRACT MODIFICATION PROCEDURES

SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. The work of this section consists of administrative and procedural requirements for contract modifications.

1.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):

1. Rent

2. Utilities

3. Furnishings

4. Office equipment

5. Executive and management staff not exclusively assigned to the project

6. Support, accounting, and administrative staff

7. Preparation of cost proposals, estimating, and schedule analyses connected with

Modifications

8. Estimating and preconstruction services

9. Mortgage costs

10. Real estate and corporate taxes

11. Automobile maintenance and travel costs for home office personnel

12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.

13. Depreciation of equipment and other assets

14. Home office supplies (paper, staples, etc.)

15. Legal services

16. Accounting and data processing

17. Professional fees/registration

B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:

1. Project Manager, Assistant Project Manager

2. Superintendent, Assistant Superintendent

3. Quality Control, Safety Officer, Environmental Manager, etc.

4. Engineers

5. Travel, lodging, and per diem (as established by Federal Travel Regulations)

MORA - 152787 01 26 01 - 2

6. Scheduling

7. Field Office Trailers and associated temporary utilities

8. Field office supplies

a. Mailing and couriers

b. Reproduction costs

c. Storage

d. Phones

e. Computers

f. Copiers

9. Personal vehicles i.e. Superintendent Pickup trucks

C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:

1. Hoisting

2. Material handling

3. Temporary fencing

4. Port-a-lets

5. Trash removal, dumpsters

6. Barricades

7. Small tools

8. Safety supplies

9. Scaffolding

10. Daily cleaning

11. Traffic control

12. Temporary signage

13. Temporary heating and power

D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: This is the hourly rate paid directly to the worker

b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:

1) Social Security

2) Medicare

3) Workers Compensation– Policy and company calculation to be made available.

4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.

5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.

MORA - 152787 01 26 01 - 3

6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.

c. Fringe Benefits: Various non-wage compensations provided to employees such as:

1) Health Care Insurance Premiums

2) Cell Phone

3) Clothing

4) 401K and Pensions

5) Vehicle allowances

6) Gas allowance

7) Life insurance premiums

8) Disability insurance

9) Other Fringe Benefits required under an enforceable collective bargaining agreement

E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.

F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.

G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.

H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS

A. General:

1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.

http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank

MORA - 152787 01 26 01 - 4

2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Gov’t provided form.

3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.

Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.

4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.

5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS.

All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

B. Labor:

1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.

Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. The labor cost for foremen shall only be costs for related work required for the modification.

C. Materials:

1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.

2. No markup shall be applied to any material provided by the NPS.

D. Equipment:

1. Equipment used for the project must be appropriately sized for the work being performed.

http://www.nps.gov/dscw/publicforms.htm#ct http://www.nps.gov/dscw/publicforms.htm#ct

MORA - 152787 01 26 01 - 5

2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.

3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region)

b. Construction Blue Book

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.

6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.

8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

E. Establishment and Application of Overhead and Profit Percentages:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.

Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:

Overhead………………10.0% Profit………………….…8.0%

2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

MORA - 152787 01 26 01 - 6

3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above).