KATM_148250-Combined_Specifications_2016_0628.pdf
PDF 4 MB Posted
- Attached to
- Replace Floating Bridge and Access Trails with Elevated Bridge and Walkway Federal contract opportunity
- Solicitation number
- P16PS00287
About this file
Specifications
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_No._6.pdf | ||
| Q A_Amendment_5.pdf | ||
| Q-A-Spec_Chgs-Drwgs_chgs-Amend4.pdf | ||
| Amendment_3SubKPlanForm.pdf | ||
| KATM_148250_Pre-Bid_Attendance_List_2016_0901.pdf | ||
| KATM_148250_Pre-bid_Site_Visit_Notes_2016_0906.pdf | ||
| SubContracting_Form_1_-_Amendment_2.htm | HTM file | |
| Amendment_No._1_P16PS00287.pdf | ||
| KATM_Brooks_Camp_100__Final_Drawings-22x34_Signed_160616.pdf | ||
| Proposal_Submission_Pkg.pdf | ||
| Solicitation-P16PS00287.pdf | ||
| DB_wage_rates.txt | TXT text file |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
KATMAI BAY NATIONAL PARK AND
PRESERVE
REPLACE FLOATING BRIDGE AND ACCESS TRAIL WITH
ELEVATED BRIDGE AND BOARDWALK
PMIS NO. 148250
CONSTRUCTION SPECIFICATIONS
VOL. 1 OF 1
NATIONAL PARK SERVICE
ALASKA REGIONAL OFFICE
June 28, 2016
KATM – 148250 131065 - 1
050611
Division Section Title Pages
SPECIFICATIONS GROUP
General Requirements Subgroup
DIVISION 01 – GENERAL REQUIREMENTS
01 11 00 ......... SUMMARY OF WORK
01 26 01 ......... CONTRACT MODIFICATION PROCEDURES
01 31 00 ......... PROJECT MANAGEMENT AND COORDINATION
01 31 00 ......... SAMPLE AGENDA ITEMS
01 32 16 ......... CONSTRUCTION SCHEDULE
01 32 23 ......... SUBMITTAL PROCEDURES
01 35 23 ......... SAFETY REQUIREMENTS
01 40 00 ......... QUALITY REQUIREMENTS
01 42 00 ......... REFERENCES
01 50 00 ......... TEMPORARY FACILITIES AND CONTROLS
01 52 00 ......... FIELD OFFICES AND SHEDS
01 57 23 ......... TEMPORARY STORM WATER POLLUTION PREVENTION
01 67 00 ......... PRODUCT REQUIREMENTS
01 71 23 ......... CONSTRUCTION SURVEYING
01 73 40 ......... EXECUTION
01 77 00 ......... CLOSEOUT PROCEDURES
....................... GEOTECHNICAL REPORT
Facility Construction Subgroup
DIVISION 05 - METALS
05 12 00 ........ STRUCTURAL STEEL FRAMING
05 50 00 ........ METAL FABRICATIONS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ........ ROUGH CARPENTRY
06 15 00 ........ WOOD DECKING
06 18 00 ........ GLUED-LAMINATED CONSTRUCTION
06 20 13 ........ EXTERIOR FINISH CARPENTRY
06 73 00 ........ PLASTIC LUMBER
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 41 13 ........ STANDING-SEAM METAL ROOF PANELS
KATM – 148250 131065 - 2
DIVISION 08 - OPENINGS
08 71 11 ........ DOOR HARDWARE (DESCRIPTIVE SPECIFICATION)
Facility Services Subgroup
DIVISION 22 - PLUMBING
22 05 00 ........ COMMON WORK RESULTS FOR PLUMBING
22 05 03 ........ PIPES AND TUBES FOR PLUMBING PIPING AND EQUIPMENT
22 05 23 ........ GENERAL-DUTY VALVES FOR PLUMBING PIPING
22 07 00 ........ PLUMBING INSULATION
22 21 16 ........ PLUMBING PIPING SPECIALTIES
22 30 00 ........ PLUMBING EQUIPMENT
DIVISION 23 - HEATING VENTILATING AND AIR CONDITIONING
23 05 00 ........ COMMON WORK RESULTS FOR HVAC
23 05 03 ........ PIPES AND TUBES FOR HVAC PIPING AND EQUIPMENT
23 05 23 ........ GENERAL-DUTY VALVES FOR HVAC PIPING
23 05 93 ........ TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 ........ HVAC INSULATION
23 09 05 ........ INSTRUMENTATION FOR HVAC
23 09 93 ........ SEQUENCE OF OPERATIONS FOR HVAC CONTROLS
23 21 16 ........ HYDRONIC PIPING SPECIALTIES
23 21 23 ........ HYDRONIC PUMPS
23 51 00 ........ BREECHINGS, CHIMNEYS, AND STACKS
23 52 23 ........ CAST-IRON BOILERS
23 52 24 ........ WOOD-FIRED BOILERS
23 57 00 ........ HEAT EXCHANGERS
DIVISION 26 - ELECTRICAL
26 01 26 ........ TESTING AND MAINTENANCE OF ELECTRICAL SYSTEMS
26 05 00 ........ COMMON WORK RESULTS FOR ELECTRICAL
26 05 03 ........ EQUIPEMENT WIRING CONNECTIONS
26 05 13 ........ MEDIUM-VOLTAGE CABLE
26 05 19 ........ LOW VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
26 05 26 ........ GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
26 05 29 ........ HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
26 05 33 ........ RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS
KATM – 148250 131065 - 3
26 05 53 ........ IDENTIFICATION FOR ELECTRICAL SYSTEMS
26 29 13 ........ ENCLOSED CONTROLLERS
Site and Infrastructure Subgroup
DIVISION 31 - EARTHWORK
31 10 00 ........ SITE CLEARING
31 22 00 ........ GRADING
31 23 16.13 ... TRENCHING
31 23 23 ........ FILL
31 62 16 ........ STEEL PILES
DIVISION 33 - UTILITIES
33 31 11 ........ INSULATED SANITARY SEWER
33 31 12 ........ UNINSULATED SANITARY SEWER
END OF TABLE OF CONTENTS
KATM – 148250 01 11 00 - 1
090915 SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work Covered by the Contract Documents.
2. Access
3. Contractor Use of Site.
4. Public Use of Site.
5. Work Restrictions.
6. Special Construction Requirements.
7. Environmental Protection
8. Government Furnished Materials
9. Geotechnical Report
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Brooks River Area, Katmai National Park and Preserve, King Salmon, Alaska.
B. The Work consists of the following:
1. Construction of an elevated boardwalk and bridge including viewing platforms, pullouts, electrical distribution and a septic pump out system.
2. Bid Options for the construction and rehabilitation of viewing platforms and utility work at the Housing Loop.
C. Project will be constructed under a single prime contract.
1.3 ACCESS
A. Contractor shall be responsible for transportation of all materials, equipment and manpower to the project site, from the site and around the site. Common access to Brooks Camp is by water from the Lake Camp boat landing near King Salmon or by small aircraft from King Salmon as lake levels allow.
1. Access by boat, barge, or fixed-wing aircraft does not require a permit.
2. Access via rotary-wing/helicopter will only be allowed between October 1 and June 1 and will require a Special Use Permit issued by Katmai National Park & Preserve.
B. Contractor Access via Water
1. Procedures for Contractor Barge and Boat Access to Project Site:
KATM – 148250 01 11 00 - 2
a. Contractor must provide a satellite phone for use on any Contractor operated vessels capable of communication with the National Park Service.
b. Sailing Requirements
1) Landings at Brooks Camp must be scheduled and approved by the
Contracting Officer. Contractor shall provide a minimum of 48 hours’ notice prior to sailing.
2) For Sailings to Brooks Camp: Contractor must contact Katmai NP&P Dispatch immediately upon departure from Lake Camp and 30 minutes prior to arrival at Brooks Camp.
3) For Sailings from Brooks Camp: Contractor must contact Katmai NP&P Dispatch immediately prior to departure from Brooks Camp.
2. Boat & Barge Loading/Offloading Requirements:
a. All barge/boat landings shall occur at the Spit or the Barge Landing area southeast of the mouth of the Brooks River. Contractor is advised to expect delays in landings due to the presence of wildlife during peak periods of bear activity in July, September and October.
b. All equipment, vehicles, and materials must be immediately off-loaded and moved to the Contractor’s staging areas as shown on the drawings.
3. The lake levels as shown on the drawings are average lake levels for the identified time of year. Lake levels may be higher and lower than these levels, based on climatic conditions.
1.4 CONTRACTOR USE OF SITE
A. General: Contractor shall at all times conduct their operations to ensure the least inconvenience to the public.
B. Work Hours: Between June 1 and September 19, Work Hours shall generally be limited to 8am to 8pm, unless otherwise authorized by Contracting Officer. Between September 18 and June 1, there are no limitations on work hours.
Access to and Use of Staging Areas and Work Sites: Access to and use of Staging Areas and Work Sites is restricted to the periods identified as follows:
1. Staging Areas:
a. Spit: August 1 through July 1
b. Barge Landing Pad: after August 1
c. Barge Landing Access Road: November 1 through June 1
d. Spit Road: November 1 through June 1
e. Brooks Camp Beach: November 1 through May 1
f. Housing Loop Maintenance Building and Yard: November 1 through May 1
g. Housing Loop: No time restrictions
2. Work Sites: On-site construction activities outside designated staging areas shall be performed as follows:
a. Work within the Fish Freezing Building and at the Housing Loop: No restrictions.
b. Underground Utility Work: August 1 through June 1
c. At Grade Boardwalk Work (grids 1-2 and grids 83-84): August 1 through June 1.
d. Clearing work within construction limits: between August 1 and August 31 or between October 1 and June 1.
KATM – 148250 01 11 00 - 3
e. All other work: October 1 through June 1
C. Storage of Materials & Equipment: The available space at the staging areas will be affected by the lake levels. Materials shall be confined to the designated Contractor’s staging areas as shown on the Drawings within designated time periods. Between September 19 and June 1 materials may also be stored within the construction limits.
D. Mobilization, construction and/or assembly within the designated staging areas may be performed as access permits, except as follows:
1. Spit: No construction or assembly will be permitted within the Contractor’s staging area at the Spit between June 1 and September 19. Due to the frequent presence of bears only “hard sided” material or equipment shall be stored at the Spit.
E. Construction Camp:
1. NPS housing consisting of two duplex units with a total of 8 bedrooms is available for Contractor’s use at the Contractor’s housing area during the contract period. An additional duplex unit with 4 bedrooms will be available between October 1 and June 1.
Each housing unit will be furnished with one twin mattress in each bedroom, a table and 2 chairs in the living area, a range, and a refrigerator. Contractor shall provide all cookware, dinnerware and kitchen utensils. Power, heat, water and wastewater will be provided at no cost to the Contractor. One wash machine and 2 dryers will be available for Contractor’s use within the Housing Loop area.
2. Contractor is responsible for the cleaning and maintenance of all existing facilities in their use at the Housing Loop. The Government will be responsible for the operation and maintenance of utilities such as power, heat, water, and burnable trash disposal. The Contractor shall be responsible for collection and disposal of non-burnable garbage and/or trash.
3. Contractor shall keep the construction camp housing neat and clean and restore site to its original or better condition.
4. Contractor may provide a Contractor provided construction camp and tie into existing NPS utilities (water, sewer and power) at the Contractor’s housing area. If a construction camp is provided the Contractor shall be responsible for installation and maintenance of all connections to existing NPS utilities.
F. Government Representative Housing:
1. Government Representative will be housed in Government-provided housing at the Housing Loop.
G. PUBLIC USE OF SITE
1. The immediate construction limits will be closed to the public during construction, except as otherwise noted within these Specifications, however, maintain access for National Park Service administrative and other official business throughout the construction phase.
2. Between June 1 and October 15, Contractor shall be responsible for restricting public access to the immediate construction area by installing signs, barricades or other approved means.
KATM – 148250 01 11 00 - 4
3. Between June 1 and October 15, Contractor shall at all times allow for pedestrian access on existing trails, walks and roads.
4. Contractor shall at all times allow for pedestrian and wildlife access along the beach. This shall include maintaining a minimum of 5’ clear area, free of stored materials.
1.5 WORK RESTRICTIONS
A. Seasonal Hauling Restrictions & Road Use Restrictions:
1. The roads in the Brooks River area are narrow, generally operable only for one-way traffic, and have limited (or no) opportunities for pull-offs or turning vehicles around.
2. Procedures for use of the roads between June 1 and September 19: Road closures may be permitted, when required, upon specific approval of Contracting Officer. Additionally;
a. Contractor shall coordinate travel on roads with Contracting Officer, or their designee, to minimize impact to public and to NPS operations.
b. Contractor is advised that, at a minimum, one visitor bus travels from the Brooks
Camp area to the Valley of 10,000 Smokes daily between June 1 and September
17. It typically departs at approximately 9:00 AM and returns at approximately 4:00PM, but the schedule may vary. The immediate area on the Valley Road through which the bus is traveling must be clear of all personnel and equipment during transit times.
c. Vehicles may not be used for personal use within the Park (i.e. travel on Valley Road for recreational purposes or along the beach).
d. Confine parking of construction equipment and vehicles to designated staging areas or within the Project Limits after start up dates identified in these Specifications.
3. The Government will provide snow plowing on existing roads as required for Contractor’s access on the roads between the Housing Loop, Contractor’s staging areas and Project limits. Snow plowing within the Contractor’s staging areas and Project limits is the responsibility of the Contractor.
1.6 SPECIAL CONSTRUCTION REQUIREMENTS
A. Bear & Regulatory Orientation:
1. All contractor employees working on site between April 1 and December 1 must attend a bear orientation prior to working on-site. Orientation may be held in either King Salmon or at Brooks Camp, at the Contracting Officer’s discretion.
2. Orientation is valid for the calendar year in which it is given and must be repeated the following season.
3. Orientations will be held during normal business hours. Contractor shall request, in writing, any orientations a minimum of 2 working days in advance of the required date.
4. An additional “refresher course” may be required for Contractor employees at the discretion of the Contracting Officer.
5. Employees SHALL NOT be permitted to commence work on-site prior to receiving bear orientation.
B. Vehicle & Equipment Cleaning and Inspection:
KATM – 148250 01 11 00 - 5
1. All vehicles and equipment shall be inspected by the Contracting Officer and Park Natural Resources staff prior to their entry into the Park for invasive species, seeds, mud, weeds, and other unwanted substances. This inspection will occur in King Salmon, Alaska immediately prior to mobilization to the Project.
2. Steam clean all earth-moving equipment and vehicles before entering Lake Camp.
3. Correct all oil and fluid leaks in vehicles and equipment before entering Lake Camp and immediately upon occurrence.
4. Notify the Contracting Officer a minimum of 2 working days prior to entry of vehicles into the Park to schedule inspection.
5. Vehicles failing inspection will require repair, re-cleaning and re-inspection prior to being allowed entry into the Park.
C. Superintendent’s Compendium: Contractor must comply with all rules and regulations within the Park. For additional guidance refer to the Katmai National Park and Preserve Compendium (Available at http://www.nps.gov/akso/management/compendiums.cfm and clicking “Current Compendiums”)
1.7 ENVIRONMENTAL PROTECTION
A. Wildlife Protection:
1. Unless working within a fenced, protected area or otherwise directed by the Contracting Officer, stop work whenever bears are detected within 50 yards of Construction activity.
Work may only resume once bears have moved at least 50 yards from the construction activity. Even when working within a fenced, protected area it may be necessary to stop work when bears are detected in close proximity of the protected area.
2. Contractor is advised to expect delays due to wildlife movement during peak periods of bear activity in July, September and October. It may be necessary to provide portable electric fencing to protect equipment and/or materials at any time.
3. Contractor shall comply with direction of NPS uniformed personnel in regards to protection of wildlife. Contractor shall notify Contracting Officer in event of all bear disturbances.
B. Preservation of Natural Features:
1. Carefully supervise excavating, grading, filling, pile driving and other construction operations to minimize damage to natural surroundings. Restore damaged areas at no additional expense to the Government.
2. Ground conditions within the construction limits are not expected to support heavy equipment without excessive rutting and tracking. Minimize damage from equipment and vehicles by performing pile driving and related construction activities when the ground is frozen and/or snow covered. If ground conditions cannot support equipment without creating ruts or tracks less than 6” in depth, Contractor shall use methods such as equipment mats or pads to minimize damage.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer and remove agreed-on and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
C. Hazardous Spill Plan:
http://www.nps.gov/akso/management/compendiums.cfm
KATM – 148250 01 11 00 - 6
1. Submit a Hazardous Spill Plan one week prior to the Preconstruction Conference, stating what precautions will be taken to prevent a spill and what actions will be taken if a spill occurs.
2. The Plan shall show placement of refueling facilities, storage and handling of hazardous materials, inventory and storage of spill response materials, etc. The Plan shall also include best management practices in operating procedures that will be implemented.
3. Notify the Contracting Officer immediately of any hazardous spills. Contractor is responsible for any legally required spill notifications, including but not limited to notifying ADEC.
4. Completely contain all fuel at the work site. Clean up any spills immediately. Dispose of petroleum products outside the Park according to Borough, State, and Federal regulations.
D. Waste Management:
1. Store any food, liquids, and garbage in bear-proof containers or locked vehicles. Dispose of waste in locked or otherwise protected receptacles
2. Any mishandling of garbage, trash, food, and other potential bear attractants will result in the responsible person, or Contractor, receiving a citation subject to a fine and/or court appearance.
3. All non-burnable trash and debris shall be removed by the Contractor and disposed outside the Park in accordance with all applicable regulations.
4. Burnable trash shall be bagged, transported and stockpiled at the Maintenance building adjacent to the Housing Loop for disposal by the Government.
5. Cigarette butts shall not be placed on the ground at any time, in any location. Failure to comply will result in citation subject to fine and/or court appearance.
1.8 GOVERNMENT FURNISHED MATERIAL
A. The government will furnish all fill and bedding material.
1. Contractor shall provide 48 hours’ notice prior to the need for Government-furnished material. The Government will deliver the material to the project site.
2. Contractor shall install and otherwise incorporate Government-furnished items into the Work.
1.9 GEOTECHNICAL REPORT
A. A Geotechnical investigation and report entitled “Geotechnical Foundation Report, October 2011” has been prepared by R&M Consultants, Inc. The report is attached to these specifications.
B. If conflicts occur between the report and the drawings or specifications, the drawings and specifications govern.
KATM – 148250 01 11 00 - 7
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
KATM - 148250 01 10 00 - 1
121212 CONTRACT MODIFICATION PROCEDURES
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. The work of this section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager, Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
KATM - 148250 01 10 00 - 2
6. Scheduling
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: This is the hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:
1) Social Security
2) Medicare
3) Workers Compensation– Policy and company calculation to be made available.
4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.
5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.
KATM - 148250 01 10 00 - 3
6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank http://www.nps.gov/dscw/publicforms.htm#ct
KATM - 148250 01 10 00 - 4
Form, or their own form, provided that it contains the same information and level of detail as the Gov’t provided form.
3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.
Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.
5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS.
All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.
Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. The labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by the NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for the work being performed.
2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.
3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region) http://www.nps.gov/dscw/publicforms.htm#ct
KATM - 148250 01 10 00 - 5
b. Construction Blue Book
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. The estimated rental rates shall include the cost of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major overhaul is not included), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.
6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.
8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. The following percentages establish the maximum allowable markups (OH&P) for contractor self-performed work:
Overhead………………10% Profit………………5%
2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.
http://www.nps.gov/dscw/publicforms.htm#dt
KATM - 148250 01 10 00 - 6
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 011000
KATM – 148250 01 27 00 - 1
050611 DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item No. 10 – Base Bid Item 1 – North Boardwalk, Bridge, South Viewing Platform and Ramp
1. This item consist of the following:
A. Construction of an elevated boardwalk and bridge from Grids 1-43.1, including two pullouts; the south viewing platform; and ramp from Grids 80-85. This Bid Item does not include the work of CLIN 20.
2. No separate measurement of quantities shall be made.
3. Payment will be made at the contract lump sum price.
B. Contract Line Item No. 20 – Base Bid Item 2 - Piles for Contract Line Item 10
1. This item consists of the following:
A. Construction of piling for the work Of CLIN 10; North Boardwalk, Bridge, South Viewing Platform and Ramp.
2. Measurement shall be made based on the total lineal feet of piles installed as measured from tip to cut off to the nearest 12 inches.
3. Payment will be made at the contract unit price.
C. Contract Line Item No. 30 – Base Bid Item 3 - Power Distribution
1. This item consist of the following:
KATM – 148250 01 27 00 - 2
Construction of a power distribution from Sectionalizer Cabinets SP8 to SP9 and electrical work in the existing Brooks Camp Utility building and the Housing Loop Utility building.
D. Contract Line Item No. 40 – Base Bid Item 4 - Septic Pump Out System
1. This item consist of the following:
A. Construction of a septic pump out system from the Fish Freezing Building to the pump out near Grid 83. This Contract Line Item includes all work within the Fish Freezing Building.
E. Contract Line Item No. 50 - Option Item No. 1 – North Viewing Platform and Rehabilitation of Existing Viewing Platform
1. This item consists of the following:
A. Construction of a new viewing platform and connecting boardwalk from the Boardwalk of CLIN 10 and rehabilitation of the existing viewing platform. This Bid Item does not include the work of CLIN 60.
3. Award of this Contract Line Item is contingent upon the award of CLIN 60. Payment will be made at the contract lump sum price.
F. Contract Line Item No. 60- Option Item No. 2 – Piles for Contract Line Item 50
1. This item consists of the following:
A. Construction of piling for the work Of CLIN 50; North Viewing Platform.
2. Measurement shall be made based on the total lineal feet of piles installed as measured from tip to cut off to the nearest 12 inches.
3. Payment will be made at the contract unit price.
G. Contract Line Item No. 70 – Option Bid Item 3 - Housing Loop Utility Improvements
1. This item consist of the following:
A. Construction of utility improvements including tempered domestic water and central heating system.
KATM – 148250 01 27 00 - 3
END OF SECTION 01 27 00
SAMPLE PRE-WORK ON-SITE MEETING AGENDA ITEMS:
A. Roles & Responsibilities/Lines of Authority
B. Teamworking
C. Quality Control Plan and Phase Meetings
D. Park rules and regulations
E. Coordination of Subcontractors
F. Payroll reports
G. Correspondence procedures
H. Environmental requirements
I. As-constructed drawings/operation and maintenance (O&M) manuals
J. Saturday/Sunday/Holiday/Night work
K. Traffic and Pedestrian control
L. Site Specific Accident Prevention and Safety
M. Wildlife reporting requirements and procedures
N. Food and food waste handling requirements and procedures
O. Construction Waste Management Plan. - Waste management and recycling requirements
P. Road use restrictions
Q. Contractor's Housing & Communications Plan
SAMPLE PRECONSTRUCTION CONFERENCE AGENDA ITEMS:
1. Roles & Responsibilities/Lines of Authority
2. Teamworking
3. Park rules and regulations.
4. Resolution of comments on required Division 01 documents
5. Coordination of Subcontractors
6. Labor Law application
7. Correspondence procedures.
8. Payroll reports.
9. Modifications.
10. Payments to Contractor.
11. Contract time
12. Display of Hotline posters
13. Acceptance/rejection.
14. Construction progress meetings.
15. Subcontractors.
16. Cultural resource studies.
17. Documents required under the contract.
18. Submittal of shop drawings, project data, samples, and approved equals.
19. As-constructed drawings/operation and maintenance (O&M) manuals.
20. Saturday, Sunday, holiday and night work.
21. Reference materials.
22. Contractor quality control.
23. Value engineering.
24. Liquidated damages.
25. Notice to proceed.
26. Construction schedule
27. Environmental Requirements & Construction Waste Management Plan
28. Site Specific Accident Prevention and Safety
29. Traffic and Pedestrian Control.
30. Contractor's Housing Plan
KATM – 148250 01 31 00 - 1
050512 PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Construction Coordination.
2. Requests for Information (RFIs).
3. Project meetings.
4. Environmental Coordination.
B. Related Requirements:
1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.
1.2 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
KATM – 148250 01 31 00 - 2
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Quality Control Meetings:
a. Preparatory Phase Meetings
b. Initial Phase Meetings
c. Follow-up Phase Meetings
7. Pre-installation conferences.
8. Project closeout activities.
1.3 SUBMITTALS
A. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.
1. Letter designating Project Superintendent.
2. Construction Schedule.
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention Plan.
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.
7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.
8. Hazardous Spill Plan
9. Quality Control Plan.
10. Storm Water Pollution Prevention Plan.
11. Contractor’s Housing & Communications Plan
B. All items listed under 1.3.A must be provided to the Contracting Officer before the Pre- Construction Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.
1.4 PRECONSTRUCTION CONFERENCE & PREWORK SITE MEETING
A. Before the issuance of Notice-To-Proceed, Contracting Officer will arrange an administrative Pre-Construction Conference meeting with Contractor. The meeting will be held at the National Park Service Alaska Regional Office. The meeting will include the contractor and all major subcontractors.
B. Before start of construction, the Contracting Officer will arrange a Pre-Work Site Meeting at the Project Site. This meeting will include, at a minimum, the Contractor’s Project Manager and Superintendent plus field supervisors from all major subcontractors.
KATM – 148250 01 31 00 - 3
C. Sample agenda topics for these meetings are included at the end of this Specification Section.
1.5 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI.
1. CO will not respond to RFIs submitted by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially.
2. Date.
3. RFI subject.
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution. If Contractor's suggested resolution impacts the
Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
8. Contractor's signature.
9. Requested date for response.
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
1.6 PROJECT MEETINGS
A. Progress Meetings: The Contractor shall schedule weekly meetings with the Contractor Officer.
1. Attendees: In addition to the Contractor and Government Representatives, each Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.
2. Agenda: Contractor shall prepare an agenda for each meeting and minutes of previous progress meeting. Review other items of significance that could affect progress. The meeting agenda will include the following:
a. Approval of minutes of previous meetings.
b. Submittal status.
c. Review of off-site fabrication and delivery schedules.
d. Requests for information (RFI) and other issues.
e. Modifications.
f. Work in progress and projected.
KATM – 148250 01 31 00 - 4
1) Status of required inspections (Special Inspections, Accessibility, etc.)
g. Inspections of work in progress and projected
h. Construction Schedule update (provide updated CPM).
i. Status of Project Record Drawings and O&M manuals.
j. Other business relating to work.
1.7 ENVIRONMENTAL COORDINATION
A. Contractor’s Environmental Manager: Designate an on-site party responsible for overseeing the Contractor’s conformance to environmental goals for the project and implementing procedures for environmental protection.
1. Qualifications: Must be familiar with environmental regulations applicable to construction operations and specific project requirements.
2. Responsibilities: Responsibilities shall include:
a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.
b. Implementation of the Storm Water Pollution Prevention Plan (SWPPP).
c. Present an overview of environmental issues and summarize site specific procedures relating to management plans at the Preconstruction conference, pre-work meetings, and as required (i.e. arrival of new contractor personnel).
d. Training for Contractor personnel in accordance with their position requirements.
e. Monitoring and documentation of environmental procedures.
B. Contractor’s Site Specific Environmental Training Program: Contractor shall provide environmental training for workers performing work on the project site. Training shall include the following:
1. Overview of environmental issues related to the building industry, as required.
2. Overview of environmental issues related to the Project, as required.
3. Review of site specific procedures, requirements, and management plans (including, but not limited to, river crossings and compliance with park bear management policies).
4. Compliance with environmental regulations: As specified in Regulatory Requirements.
Submit Contractor 40 CFR employee training records upon request of Contracting Officer.
C. Provide documentation for environmental procedures as specified herein and in accordance with approved management plans.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 31 00
KATM – 148250 01 32 16 - 1
050611 CONSTRUCTION SCHEDULE
SECTION 01 32 16 – CONSTRUCTION SCHEDULE
PART 1 - GENERAL
1.1 SUMMARY
A. This Section consists of Construction Schedule requirements including but not limited to the following:
1. Schedule of Values
2. Construction Schedule Requirements.
3. Construction Schedule Updates.
4. Time Impact Analysis.
B. Purpose: The purpose of the Construction Schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. The Construction Schedule will assist the Contractor and Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor's monthly progress payment.
1.2 DEFINITIONS
A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. Cost Loading: The allocation of the Schedule of Values for the completion of an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.
C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.
D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.
E. Float: The measure of leeway in starting and completing an activity.
1. Float: Float is not for the exclusive use or benefit of either the Government or the Contractor but is jointly owned.
2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.
KATM – 148250 01 32 16 - 2
3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.
F. Resource Loading: The allocation of manpower and equipment necessary for the completion of an activity as scheduled.
G. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.
1.3 SUBMITTALS
A. Electronic Copies: All schedules and reports submitted shall be submitted via e-mail, provided in the native electronic file format and 11x17 PDF format. PDF files shall be of scale to be legible when printed at 11x17 size.
B. Schedule of Values: After contract award and before the Pre-Construction conference submit a schedule of dollar values based on the Contract Price Schedule, in accordance with requirements in this Specification Section.
C. Look-Ahead Schedules: Submit 3-week "look-ahead" schedules showing work completed in the preceding week, work scheduled for the current week, and work schedule for the two subsequent weeks.
1. Look-Ahead schedules are to be in significantly greater detail than the overall project schedule. No individual work item shall be listed for greater than 3 days.
2. Look-Ahead schedules may be produced in the master scheduling software or in an alternative graphical format, such as a spreadsheet.
D. Construction Baseline Schedule: After contract award and before the Pre-Construction conference, submit the baseline schedule, large enough to show entire schedule for entire construction period.
E. Construction Schedule Updates: Submit electronically with each payment request, showing current status and any required schedule changes. When requested by the CO, or required due to Project changes, submit additional updates.
F. Construction Schedule Revisions and Time Impact Analysis: For each Construction Schedule revision submit a Time Impact Analysis.