Bid_Schedule_REVISED_6.19.2015.pdf
PDF 262 KB Posted
- Solicitation number
- P15PS00830
About this file
Revised Bid Schedule
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_004.pdf | ||
| Amendment__004_RFI_Questions.pdf | ||
| Sol_P15PS00830_Amd_000004.pdf | ||
| Sol_P15PS00830_Amd_000003.pdf | ||
| Amendment_0003_RFP.pdf | ||
| Amendment__003_RFI_Questions.pdf | ||
| SAP_Template.pdf | ||
| P15PS00830_Amend_02.pdf | ||
| Sol_P15PS00830_Amd_000002.pdf | ||
| Site_Visit_Questions__2.pdf | ||
| SF_30_Amendment_0001_-_P15PS00830.pdf | ||
| SV_Sign_In_Sheet_Utility_Map.pdf | ||
| Sol_P15PS00830_Amd_000001.pdf | ||
| Site_Visit_Questions.pdf | ||
| SOW_FINAL.pdf | ||
| Past_Performance_Questinnaire.docx | DOCX document | |
| A1_Bid_Schedule__Impacted_Soil_Remediation__-_Copy_(4).pdf | ||
| A5_Bid_Bond_SF_24.pdf | ||
| Lower_Keweah_Solicitation_FINAL_5-20-15_(1).pdf | ||
| Key_Personnel_Qualifications.docx | DOCX document | |
| General_References.docx | DOCX document | |
| Submittal_Instructions.pdf | ||
| A3_EECA_Report_FINAL.pdf | ||
| Sol_P15PS00830.pdf | ||
| A9_Wages_DB.pdf | ||
| Subcontractor_Reference.docx | DOCX document |
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT BID SCHEDULE
Solicitation No. P15PS00830
SOLICITATION NO.
PROJECT AREA: SEQUOIA AND KINGS CANYON NATIONAL PARK
PROJECT TITLE: IMPACTED SOIL REMEDIATION
NOTICE: Refer to FAR clause 52.217-5, Evaluation of Options, as prescribed in FAR 17. Submit pricing for base price and all options.
Failure to do so may render the proposal unacceptable. On lump sum items, provide total price only; on unit price items, provide the unit price and the extended amount.If no item exists for a portion of the work, include the costs in a related item. In case of error in extension prices, unit governs. In case of errors in summations, the total of the corrected amounts govern. Limit amounts to whole dollars. The Government reserves the right to award any or no options at or after the time of award. At the option of the Government, the period for exercise of options at the proposed prices shall extend 180 calendar days from the Notice to Proceed.
Options may be exercised in any combination, order, or grouping deemed in the judgement of the Contracting Officer to offer the best advantage (value) in goods and services for the dollar.
CONTRACT
LINE ITEM
NUMBER
(CLIN)
CONTRACT LINE ITEM
TITLE
QTY UNIT
PRICE
UNIT OF
MEASURE
TOTAL PRICE
Base
Project Mob and Demob 1 Lump Sum N/A
Base
Tasks 1 and 2--Prepare Plans –
Project Plans/Action Plan, Site
Specific Health and Safety Plan, and Sampling and Analysis Plan
HASP, Sampling and Analysis
Plan IAW SOW paragraphs 4.1 &
4.2
1 Lump Sum N/A
Base
Task 3--Removal Actions – Clear and Stockpile, Confirmation
Sample Collection and Analysis, Load Trucks IAW SOW paragraphs 4.3.3, 4.3.4 and 4.3.5.
1 Lump Sum N/A
Base
Task 3 -- Stockpiling and
Sampling IAW paragraphs 4.3.1 to 4.3.5
1 Lump Sum N/A
Base
Task 3 – Transport Hazardous
Regulated Waste Transport to
RCRA Landfill IAW SOW paragraphs 4.3.5 to 4.3.7, maximum 3,300 tons
3,300 Tons
Option
OPTION ITEM: Task 3 --
Transport Hazardous Regulated
Waste Transport to RCRA
Landfill IAW SOW paragraphs
4.3.5 to 4.3.7. This option is for transportation of hazardous waste in excess the quantity in CLIN
0005. Option may be exercised to a maximum 3,300 tons.
1 Tons
N/A
0007 Task 3 -- Disposal Fees for 3,300 Tons $_____________ $_____________
Base Hazardous Regulated Waste transported IAW SOW paragraph
4.3.5 to 4.3.7
Option
Option Item -- Disposal Fees for
Hazardous Regulated Waste transported IAW SOW paragraph
4.3.5 to 4.3.7. This option provides for disposal fees when option item 0006 is awarded and will typically be awarded in the same quanity.
1 Tons
N/A
Base
Task 4 -- Composite Sampling
IAW SOW paragraph 4.4 1 Lump Sum N/A
Base
Task 6 -- Meetings/Conference
Calls IAW SOW paragraph 4.6 1 Lump Sum N/A
Base
Task 7 -- Prepare Reports IAW paragraph 4.7 1 Lump Sum N/A
Base
Task 8 -- Final Inspection &
Closeout IAW SOW paragraph
4.8.1 and 4.8.2.
1 Lump Sum N/A
TOTAL PROPOSED PRICE
(Contract Line Item Numbers 0001 through 0012) $_____________
File details come from the government source that posted it. Updated .