P14 Specifications - 437-23-165 - Prevent Legionella 2.17.26 - 294 pages.pdf
PDF 2 MB Posted
- Solicitation number
- 36C26326B0012
About this file
This file contains 100% construction document specifications for a repair project to the domestic water system at Fargo VA Health Care System in Fargo, North Dakota (Project No. 437-23-165), issued February 14, 2025, by architect-engineer FourFront Design, Inc. The specifications are organized by CSI divisions and cover general requirements, safety, quality control, plumbing systems, HVAC controls, electrical installations, and interior finishes necessary to prevent Legionella disease transmission through the facility's water distribution systems.
The project scope requires the contractor to install approximately 175 thermostatic mixing valves (TMVs) on plumbing fixtures, upgrade seven existing water monitoring stations with new controllers and BACnet-compliant direct digital control integration to the facility's existing building automation system, replace certain sink and faucet fixtures with low-lead compliant materials, provide complete plumbing piping modifications, install insulation per Section 22 07 11, perform all testing and commissioning, and deliver operation and maintenance documentation. Key technical requirements include water monitoring stations designed to operate in stand-alone mode with network integration capability, thermostatic mixing valves with manual temperature controls and integral check valves rated for disinfection procedures, ceramic tile finishes in specified areas, resilient sheet flooring with heat-welded seams, painting per MPI standards, and a direct digital control system using native BACnet devices with Ethernet communication and HTML 5 web browser access. The contract mandates compliance with the International Plumbing Code, NFPA standards, ASHRAE 135 BACnet protocols, NSF 61 and NSF 372 certification for potable water components, and includes comprehensive safety requirements per OSHA 1926 standards, infection control risk assessments, activity hazard analyses, and warranty obligations extending one year from project acceptance.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REPAIR DOMESTIC WATER SYSTEM
TO PREVENT LEGIONELLA
FARGO VA HEALTH CARE SYSTEM
100% CONSTRUCTION DOCUMENTS
SPECIFICATIONS
CONTRACT NO.: 36C26319D0045
PROJECT NO.: 437-23-165
February 14 , 2025
Fargo VA MEDICAL CENTER
DEPARTMENT OF VETERANS AFFAIRS
Fargo, ND
REPAIR DOMESTIC WATER SYSTEM TO PREVENT LEGIONELLA
February 14, 2025
ARCHITECT
FourFront Design, Inc.
517 Seventh Street Rapid City, SD 57701
(605) 342-9470
MECHANICAL ENGINEER
FourFront Design, Inc.
1211 Echelon Place, Suite B Helena, MT 59602
(605) 342-9470
ELECTRICAL ENGINEER
FourFront Design, Inc.
1211 Echelon Place, Suite B Helena, MT 59602
(605) 342-9470 02/14/25
02/14/25
Repair Domestic Water System to Prevent Legionella 06-01-24
VA Project: 437-23-165
00 01 10-1
Table of Contents
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets 05-20
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-21
01 33 23 Shop Drawings, Product Data, and Samples 02-23 01 35 26 Safety Requirements for Major Projects 05-24
01 42 19 Reference Standards 11-20
01 45 00 Quality Control 02-21
01 57 19 Temporary Environmental Controls 01-21
01 74 19 Construction Waste Management 04-22
01 91 00 General Commissioning Requirements 04-21
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 84 00 Firestopping 01-21
07 92 00 Joint Sealants 04-22
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 01-21
09 06 00 Schedule for Finishes 01-21
09 30 13 Ceramic/Porcelain Tiling 01-21
09 65 13 Resilient Base and Accessories 01-21
09 65 16 Resilient Sheet Flooring 06-22
09 91 00 Painting 01-21
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 01-23
22 05 23 General-Duty Valves for Plumbing Piping 09-20
22 07 11 Plumbing Insulation 09-19
22 11 00 Facility Water Distribution 05-21
22 40 00 Plumbing Fixtures 05-24
Repair Domestic Water System to Prevent Legionella 06-01-24
00 01 10-2
Table of Contents
SECTION NO DIVISION AND SECTION TITLES DATE
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 09 23 Direct-Digital Control System for HVAC 03-23
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 11-22
26 05 19 Low-Voltage Electrical Power Conductors and Cables 11-22
26 05 26 Grounding and Bonding for Electrical Systems 11-22
26 05 33 Raceway and Boxes for Electrical Systems 11-22
26 27 26 Wiring Devices 11-22
Repair Domestic Water System to Prevent Legionella 05-01-20
00 01 15 - 1
List of Drawing Sheets
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
G 0.00 COVER PAGE
G 1.00 INFECTION CONTROL RISK ASSESSMENT(ICRA)
ARCHITECTURAL
A 5.00 ROOM FINISH SCEDULE/FINISH PLANS
MECHANICAL
M 0.00 MECHANICAL GENERAL NOTES AND ABBREVIATIONS
M 0.10 MIXING VALVE DETAILS AND SCHEDULES
M 0.20 SINK AND FAUCET REPLACEMENT DETAILS
M 0.30 WATER MONITORING STATION DEMOLITION DETAIL
M 0.40 NEW WATER MONITORING STATION DETAILS
M 1.01 BASEMENT WEST FLOOR PLAN
M 1.02 BASEMENT EAST FLOOR PLAN
M 1.03 BASEMENT SOUTH FLOOR PLAN
M 1.04 BUILDING 10 BOILER PLANT LOWER-LEVEL PLAN
M 1.11 FIRST FLOOR NORTHWEST FLOOR PLAN
M 1.12 FIRST FLOOR SOUTHWEST FLOOR PLAN
M 1.13 FIRST FLOOR EAST FLOOR PLAN
M 1.14 FIRST FLOOR SOUTHEAST FLOOR PLAN
M 1.15 FIRST FLOOR INFUSION CENTER FLOOR PLAN
M 1.21 SECOND FLOOR NORTH FLOOR PLAN
M 1.22 SECOND FLOOR WEST FLOOR PLAN
M 1.23 SECOND FLOOR SOUTHWEST FLOOR PLAN
M 1.24 SECOND FLOOR EAST FLOOR PLAN
M 1.31 THIRD FLOOR FLOOR PLANS
M 1.41 FOURTH FLOOR NORTH FLOOR PLAN
ELECTRICAL
E 0.00 ELECTRICAL LEGEND AND ABBREVIATIONS
E 1.00 BUILDING 1 BASEMENT ELECTRICAL PLANS, WINGS A,C
E 1.10 BUILDING 1 BASEMENT ELECTRICAL PLANS, WINGS D,E
E 2.00 BUILDING 10 LEVEL 1 ELECTRICAL PLANS
- - - END - - -
Repair Domestic Water System to Prevent Legionella 11-01-21
01 00 00 -1
General Requirements
SECTION 01 00 00
GENERAL REQUIREMENTS
GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for repair the systems to prevent legionella. as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the Medical Center Engineering Officer..
C. Offices of FourFront Design, Inc., as Architect-Engineers, will render certain technical services during construction.
Such services shall be considered as advisory to the
Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
D. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL CONSTRUCTION: BASE BID Work includes general construction, alterations, necessary removal of existing piping and equipment and construction and certain other items.
01 00 00 -2
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees.
This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The
01 00 00 -3
General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Document Control:
1. Before starting any work, the General Contractor/Sub
Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or
“Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of
“sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an
Engineering Document Management Software (EDMS).
01 00 00 -4
General Requirements
Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.
“Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
D. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access.
Access shall be restricted to picking up and dropping off materials and supplies.
2. A limited number of (2 to 5) permits shall be issued for
General Contractor and its employees for parking in designated areas only. Contractor to coordinate with VA
Medical Center Facility Manager.
1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The
Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. The Contractor shall, under regulations prescribed by the
Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, 01 00 00 -5
State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
C. Working space and space available for storing materials shall be as determined by the COR .
D. Workers are subject to rules of Medical Center applicable to their conduct.
E. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.
Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by
Department of Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.
01 00 00 -6
General Requirements
G. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR . All such actions shall be coordinated with the COR or Utility Company involved:
H. Utilities Services: Maintain existing utility services for
Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems
(including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR.
Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification
Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL
INSTALLATIONS.
01 00 00 -7
General Requirements
2. Contractor shall submit a request to interrupt any such services to COR, in writing, 21 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical
Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 21 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
I. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions;
so that they are completely behind the finished surfaces.
J. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction
01 00 00 -8 materials, debris and standing construction equipment and vehicles.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
K. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of
VA Supply Service, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the
Contracting Officer. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings
01 00 00 -9 where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR , to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and
"CHANGES" (FAR 52.243-4).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved.
They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by
Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
01 00 00 -10
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the
Government are noted on drawings or in specifications as items to be stored. Items that remain property of the
Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the
Contractor and be removed by Contractor from Medical
Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government.
When rooms and spaces are vacated by the Department of
Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the
01 00 00 -11
Government in advance of work to avoid interfering with
Contractor's operation.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by
Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
01 00 00 -12
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).
1.11 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.12 WARRANTY MANAGEMENT
A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21
Warranty of Construction in at least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by
01 00 00 -13 future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting
Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the
Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:
1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the
Contractor, subcontractors, manufacturers or suppliers involved.
2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.
3. Listing and status of delivery of all Certificates of
Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.
01 00 00 -14
4. A list for each warranted equipment item, feature of construction or system indicating:
a. Name of item.
b. Model and serial numbers.
c. Location where installed.
d. Name and phone numbers of manufacturers and suppliers.
e. Name and phone numbers of manufacturers or suppliers.
f. Names, addresses and phone numbers of sources of spare parts.
g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.
h. Starting point and duration of warranty period.
i. Summary of maintenance procedures required to continue the warranty in force.
j. Cross-reference to specific pertinent Operation and
Maintenance manuals.
k. Organizations, names and phone numbers of persons to call for warranty service.
l. Typical response time and repair time expected for various warranted equipment.
5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.
6. Procedure and status of tagging of all equipment covered by extended warranties.
7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.
01 00 00 -15
B. Performance & Payment Bonds: The Performance & Payment
Bonds must remain effective throughout the construction period.
1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.
2. In the event sufficient funds are not available to cover the construction warranty work performed by the
Government at the contractor’s expenses, the Contracting
Officer will have the right to recoup expenses from the bonding company.
3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the
Contractor.
C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the
Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for
Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for Contractor response, and other details deemed necessary by the Contracting Officer for the
01 00 00 -16 execution of the construction warranty will be established/ reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor. This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the
Contractor of any of its responsibilities in conjunction with other portions of this provision.
D. Contractor’s Response to Construction Warranty Service
Requirements:
E. Following oral or written notification by the Contracting
Officer, the Contractor shall respond to construction warranty service requirements in accordance with the
“Construction Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period. Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.
1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within
4 hours, initiate work within 6 hours and work continuously to completion or relief.
01 00 00 -17
2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within
8 hours, initiate work within 24 hours and work continuously to completion or relief.
3. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.
4. The “Construction Warranty Service Priority List” is as follows:
a) Code 1-Life Safety Systems
Fire suppression systems.
Fire alarm system(s).
b) Code 1-Air Conditioning Systems
Air conditioning leak in part of the building, if causing damage.
Air conditioning system not cooling properly.
c) Code 1 Doors
Overhead doors not operational, causing a security, fire or safety problem.
1) Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.
d) Code 3-Doors
Overhead doors not operational.
Interior/exterior personnel doors or hardware not functioning properly.
e) Code 1-Electrical
Power failure (entire area or any building operational after 1600 hours).
Security lights.
01 00 00 -18
Smoke detectors.
f) Code 2-Electrical
Power failure (no power to a room or part of building). Receptacle and lights not operational (in a room or part of building).
g) Code 3-Electrical
Exterior lights not operational.
h) Code 1-Gas
Leaks and pipeline breaks.
i) Code 1-Heat
Power failure affecting heat.
j) Code 1-Plumbing
Hot water heater failure.
2) Leaking water supply pipes
k) Code 2-Plumbing
Flush valves not operating properly
Fixture drain, supply line or any water pipe leaking.
Toilet leaking at base.
l) Code 3- Plumbing
Leaky faucets.
m) Code 3-Interior
Floors damaged.
Paint chipping or peeling.
Casework damaged.
n) Code 1-Roof Leaks
Damage to property is occurring.
o) Code 2-Water (Exterior)
No water to facility.
p) Code 2-Water (Hot)
No hot water in portion of building listed.
01 00 00 -19
q) Code 3
All work not listed above.
F. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating.
Also submit tworecord copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.
Warranty Tags
Type of product/material
Model number
Serial number
Contract number
Warranty period from/to
Inspector’s signature
Construction Contractor
Address
Telephone number
Warranty Contact
Address
Telephone number
Warranty response time priority code
1.13 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on
Medical Center property and, when authorized by the COR, 01 00 00 -20 such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
1.14 TEMPORARY USE OF EXISTING ELEVATORS
A. Use of existing elevators for handling building materials and Contractor's personnel will be permitted subject to following provisions:
1. Contractor makes all arrangements with the COR for use of elevators. The COR will ascertain that elevators are in proper condition.
2. Contractor covers and provides maximum protection of following elevator components:
a) Entrance jambs, heads soffits and threshold plates.
b) Entrance columns, canopy, return panels and inside surfaces of car enclosure walls.
c) Finish flooring.
3. Place elevator in condition equal, less normal wear, to that existing at time it was placed in service of
Contractor as approved by Contracting Officer.
1.15 TEMPORARY TOILETS
1. *Contractor may have for use of Contractor's workers, such toilet accommodations as may be assigned to
Contractor by the COR. Contractor shall keep such places clean and be responsible for any damage done thereto by
Contractor's workers. Failure to maintain satisfactory
01 00 00 -21
General Requirements condition in toilets will deprive Contractor of the privilege to use such toilets.
1.16 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.
B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the
Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.
1.17 TESTS
A. As per specification section the contractor shall provide a written testing plan complete with component level, equipment level, sub-system level and system level breakdowns. The plan will provide a schedule and a written sequence of what will be tested, how and what the expected
01 00 00 -22 outcome will be. This document will be submitted for approval prior to commencing work. The contractor shall document the results of the approved plan and submit for approval with the as built documentation.
B. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested.
C. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting Officer. Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.
D. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.
1.18 INSTRUCTIONS
A. Contractor shall furnish Maintenance and Operating manuals
(hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.
B. Manuals: Maintenance and operating manuals and one compact disc (four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the
COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall
01 00 00 -23 include an index covering all component parts clearly cross-referenced to diagrams and illustrations.
Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth.
Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.
C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned Department of Veterans
Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system, shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed. This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the COR and shall be considered concluded only when the COR is satisfied in regard to complete and thorough coverage. The contractor shall submit a course outline with associated material to
01 00 00 -24 the COR for review and approval prior to scheduling training to ensure the subject matter covers the expectations of the VA and the contractual requirements.
The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the COR, does not demonstrate sufficient qualifications in accordance with requirements for instructors above.
1.19 RELOCATED EQUIPMENT
A. Contractor shall disconnect, dismantle as necessary, remove and reinstall in new location, all existing equipment and items shown to be relocated by the Contractor.
B. Perform relocation of such equipment or items at such times and in such a manner as directed by the COR.
C. Suitably cap existing service lines, such as steam, condensate return, water, drain, gas, air, vacuum and/or electrical, at the main whenever such lines are disconnected from equipment to be relocated. Remove abandoned lines in finished areas and cap as specified herein before under paragraph "Abandoned Lines".
D. Provide all mechanical and electrical service connections, fittings, fastenings and any other materials necessary for assembly and installation of relocated equipment; and leave such equipment in proper operating condition.
E. All service lines such as noted above for relocated equipment shall be in place at point of relocation ready for use before any existing equipment is disconnected. Make relocated existing equipment ready for operation or use immediately after reinstallation.
01 00 00 -25
1.20 SAFETY SIGN
A. Provide a Safety Sign where directed by COR.
B. Maintain sign and remove it when directed by COR.
C. Drawing details in VA Signage Design Manual, Section 11
Specialty Signs (found on VA TIL) show required legend and other characteristics of sign and are attached hereto and is made a part of this specification.
D. Post the number of accident free days on a daily basis.
- - - E N D - - -
Repair Domestic Water System to Prevent Legionella 02-01-23
01 33 23 - 1
Shop Drawings, Product Data, and Samples
SECTION 01 33 23
SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
PART 1 – GENERAL
1.1 DESCRIPTION
A. This specification defines the general requirements and procedures for submittals. A submittal is information submitted for VA review to establish compliance with the contract documents.
B. Detailed submittal requirements are found in the technical sections of the contract specifications. The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective technical specifications at no additional cost to the government.
C. VA approval of a submittal does not relieve the Contractor of the responsibility for any error which may exist. The Contractor is responsible for fully complying with all contract requirements and the satisfactory construction of all work, including the need to check, confirm, and coordinate the work of all subcontractors for the project.
Non-compliant material incorporated in the work will be removed and replaced at the Contractor’s expense.
1.2 DEFINITIONS
A. Preconstruction Submittals: Submittals which are required prior to issuing contract notice to proceed or starting construction. For example, Certificates of insurance; Surety bonds; Site-specific safety plan; Construction progress schedule; Schedule of values; Submittal register; List of proposed subcontractors.
B. Shop Drawings: Drawings, diagrams, and schedules specifically prepared to illustrate some portion of the work. Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be integrated and coordinated.
C. Product Data: Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions, and brochures, which describe and illustrate size, physical appearance, and other characteristics of materials, systems, or equipment for some portion of the work. Samples of warranty language when the contract requires extended product warranties.
D. Design Data: Calculations, mix designs, analyses, or other data pertaining to a part of work.
01 33 23 - 2
Shop Drawings, Product Data, and Samples
E. Test Reports: Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work. Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
F. Certificates: Document required of Contractor, or of a manufacturer, supplier, installer, or subcontractor through Contractor. The purpose is to document procedures, acceptability of methods, or personnel qualifications for a portion of the work.
G. Manufacturer's Instructions: Pre-printed material describing installation of a product, system, or material, including special notices and MSDS concerning impedances, hazards, and safety precautions.
H. Manufacturer's Field Reports: Documentation of the testing and verification actions taken by manufacturer's representative at the job site on a portion of the work, during or after installation, to confirm compliance with manufacturer's standards or instructions. The documentation must indicate whether the material, product, or system has passed or failed the test.
I. Operation and Maintenance Data: Manufacturer data that is required to operate, maintain, troubleshoot, and repair equipment, including manufacturer's help, parts list, and product line documentation. This data shall be incorporated in an operations and maintenance manual.
J. Closeout Submittals: Documentation necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a phase of construction on a multi-phase contract.
1.3 SUBMITTAL REGISTER
A. The submittal register will list items of equipment and materials for which submittals are required by the specifications. This list may not be all inclusive and additional submittals may be required by the specifications. The Contractor is not relieved from supplying submittals required by the contract documents but which have been omitted from the submittal register.
B. The submittal register will serve as a scheduling document for submittals and will be used to control submittal actions throughout the contract period.
C. The VA will provide the initial submittal register in electronic format. Thereafter, the Contractor shall track all submittals by maintaining a complete list, including completion of all data columns, 01 33 23 - 3 including dates on which submittals are received and returned by the
VA.
ENG_FORM_4288-R.
D. The Contractor shall update the submittal register as submittal actions occur and maintain the submittal register at the project site until final acceptance of all work by Contracting Officer.
E. The Contractor shall submit formal monthly updates to the submittal register in electronic format. Each monthly update shall document actual submission and approval dates for each submittal.
1.4 SUBMITTAL SCHEDULING
A. Submittals are to be scheduled, submitted, reviewed, and approved prior to the acquisition of the material or equipment.
B. Coordinate scheduling, sequencing, preparing, and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow time for potential resubmittal.
C. No delay costs or time extensions will be allowed for time lost in late submittals or resubmittals.
D. All submittals are required to be approved prior to the start of the specified work activity.
1.5 SUBMITTAL PREPARATION
A. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
B. Collect required data for each specific material, product, unit of work, or system into a single submittal. Prominently mark choices, options, and portions applicable to the submittal. Partial submittals will not be accepted for expedition of construction effort. Submittal will be returned without review if incomplete.
C. If available product data is incomplete, provide Contractor-prepared documentation to supplement product data and satisfy submittal requirements.
D. All irrelevant or unnecessary data shall be removed from the submittal to facilitate accuracy and timely processing. Submittals that contain the excessive amount of irrelevant or unnecessary data will be returned without review.
01 33 23 - 4
Shop Drawings, Product Data, and Samples
E. Provide a transmittal form for each submittal with the following information:
1. Project title, location and number.
2. Construction contract number.
3. Date of the drawings and revisions.
4. Name, address, and telephone number of subcontractor, supplier, manufacturer, and any other subcontractor associated with the submittal.
5. List paragraph number of the specification section and sheet number of the contract drawings by which the submittal is required.
6. When a resubmission, add alphabetic suffix on submittal description.
For example, submittal 18 would become 18A, to indicate resubmission.
7. Product identification and location in project.
F. The Contractor is responsible for reviewing and certifying that all submittals are in compliance with contract requirements before submitting for VA review. Proposed deviations from the contract requirements are to be clearly identified. All deviations submitted must include a side by side comparison of item being proposed against item specified. Failure to point out deviations will result in the VA requiring removal and replacement of such work at the Contractor's expense.
G. Stamp, sign, and date each submittal transmittal form indicating action taken.
H. Stamp used by the Contractor on the submittal transmittal form to certify that the submittal meets contract requirements is to be similar to the following:
01 33 23 - 5
| CONTRACTOR |
| (Firm Name) |
| Approved |
| Approved with corrections as noted on submittal data and/or |
| attached sheets(s) |
| SIGNATURE: |
| TITLE: |
| DATE: |
1.6 SUBMITTAL FORMAT AND TRANSMISSION
A. Provide submittals in electronic format, with the exception of material samples. Use PDF as the electronic format, unless otherwise specified or directed by the Contracting Officer.
B. Compile the electronic submittal file as a single, complete document.
Name the electronic submittal file specifically according to its contents.
C. Electronic files must be of sufficient quality that all information is legible. Generate PDF files from original documents so that the text included in the PDF file is both searchable and can be copied. If documents are scanned, Optical Character Resolution (OCR) routines are required.
D. E-mail electronic submittal documents smaller than 5MB in size to e-mail addresses as directed by the Contracting Officer.
01 33 23 - 6
Shop Drawings, Product Data, and Samples
E. Provide electronic documents over 5MB through an electronic FTP file sharing system. Confirm that the electronic FTP file sharing system can be accessed from the VA computer network. The Contractor is responsible for setting up, providing, and maintaining the electronic
FTP file sharing system for the construction contract period of performance.
F. Provide hard copies of submittals when requested by the Contracting
Officer. Up to 3 additional hard copies of any submittal may be requested at the discretion of the Contracting Officer, at no additional cost to the VA.
1.7 OPERATION AND MAINTENANCE DATA
A. Submit data specified for a given item within 30 calendar days after the item is delivered to the contract site.
B. In the event the Contractor fails to deliver O&M Data within the time limits specified, the Contracting Officer may withhold from progress payments 50 percent of the price of the item with which such O&M Data are applicable.
1.9 TEST REPORTS
COR may require specific test after work has been installed or completed which could require contractor to repair test area at no additional cost to contract.
1.10 VA REVIEW OF SUBMITTALS AND RFIS
A. The VA will review all submittals for compliance with the technical requirements of the contract documents. The Architect-Engineer for this project will assist the VA in reviewing all submittals and determining contractual compliance. Review will be only for conformance with the applicable codes, standards and contract requirements.
B. Period of review for submittals begins when the VA COR receives submittal from the Contractor.
C. Period of review for each resubmittal is the same as for initial submittal.
D. VA review period is 15 calendar days for submittals.
E. VA review period is 10 calendar days for RFIs.
F. The VA will return submittals to the Contractor with the following notations:
1. "Approved": authorizes the Contractor to proceed with the work covered.
01 33 23 - 7
2. "Approved as noted": authorizes the Contractor to proceed with the work covered provided the Contractor incorporates the noted comments and makes the noted corrections.
3. "Disapproved, revise and resubmit": indicates noncompliance with the contract requirements or that submittal is incomplete. Resubmit with appropriate changes and corrections. No work shall proceed for this item until resubmittal is approved.
4. "Not reviewed": indicates submittal does not have evidence of being reviewed and approved by Contractor or is not complete.