P14 EVALUATION FACTORS AND SCORECARD FOR DESIGN-BUILD.pdf

PDF 176 KB Posted

Attached to
Z1DA--630-CSI-120 NY SPECT CT SITE PREP DESIGN BUILD
Solicitation number
36C24224R0083
Issued by

About this file

This document is a Request for Proposal (RFP) for design-build services to prepare the site for installing a new GE SPECT CT nuclear medicine equipment at the Department of Veterans Affairs (VA) medical center in New York.

The RFP outlines the required scope of work, which includes providing all labor, materials, and equipment necessary to design and construct the site preparation. Key requirements include demolition of existing HVAC equipment, installation of a new standalone HVAC system with cooling and humidity control, construction of a new radiology space with supporting rooms, and all electrical and plumbing work. The contractor must also provide project management, risk assessment, commissioning, and ensure compliance with VA design guidelines, OSHA regulations, and manufacturer specifications. The government's required completion date is 365 calendar days after the notice to proceed. Offerors must submit technical proposals addressing factors such as qualifications, management approach, schedule, and past experience, as well as a separate pricing volume. The technical proposals will be evaluated using an adjectival rating system. If proposals are technically equal, award will be made to the offeror with the lowest price.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project #630-CSI-120

Project Title: NY SPECT CT Site Prep

- FOR OFFICIAL USE ONLY - 1

SELECTION PLAN

VISN 2 Design-Build Services

The Department of Veterans Affairs Network Contracting Office 2

TABLE OF CONTENTS

- FOR OFFICIAL USE ONLY - 2

1. SOURCE-SELECTION PROCEDURES AND EVALUATION FACTORS

This acquisition will be negotiated under negotiated best value with trade-offs proce-dures outlined in FAR Part.15. All Offerors are instructed to provide information in their proposal Technical Volume 1 regarding their management plan, team composition, proposed schedule, and past performance experience, specifically on site-prep pro-jects. Additional information shall be provided on proposed subcontractors and the per-centage of work to be self-performed. All Offerors are instructed to provide their pricing in a separate Pricing Volume 2.

1.1. CONTRACT TYPE

This is a single award firm fixed-price contract for Design-Build services.

1.2. PROCUREMENT INTEGRITY

All personnel involved in the selection process are considered to be “procurement offi-cials” and will be familiar with and comply with Federal Acquisition Regulation Part 3 and section 27 of the Office of Federal Procurement Policy Act (41 U.S.C. 423).

1.2.1 Conflict of Interest/ Non-Disclosure Statement and Certificate of Confidentiality

All members of the A/E Technical Evaluation Board will complete a “Certifi-cate of Confidentiality” form (ATTACHMENT 8) and provide it to the Contract-ing Officer before commencing their involvement.

1.2.2 Recusal

The Contracting Officer will review all statements of non-disclosure and fi-nancial interest for possible conflicts of interest. If an actual or potential con-flict of interest is found to exist, the Contracting Officer, after consulting with legal counsel, will recuse the person from participation in the selection pro-cess.

1.3 EVALUATION FACTORS

The below technical evaluation criteria (EC) EC-1 through EC-7 are listed in descend-ing order of importance, and combined are significantly more important than non-technical factor EC-6 through EC-7:

- FOR OFFICIAL USE ONLY - 3

EC-1 Professional Qualifications Professional Qualifications necessary for satisfactory performance of required services with a balanced licensed and certified workforce for the disciplines anticipated to be necessary, including:

• Mechanical Engineering

• Electrical Engineering

• Structural Engineering

• Architecture

• Health Facility Design

• Information Technology

• Communications Systems

• Control Systems Engineering

• Systems Integration

• Fire Protection Engineering

• Hazardous Material Abate

• Physical Security

• The construction team’s proposal shall emphasize the team’s expertise in:

o Construction in a Medical Center/DVA facility while maintaining normal operations of the existing adjacent facility.

o Site-Prep High Tech High Cost renovation project.

o Its capacity to devote time to the project.

o The degree to which the contractor has previous project experience with critical team members.

• Identify all key members of the construction team in an organizational chart which demonstrates:

• The specific responsibilities.

• Specific Control of the project.

• Include biographical data of all key project personnel to include the following:

a. Name of individual

b. Company employed by

c. Company position title

d. Years with the company

e. Work experience with projects that were of a similar nature.

- FOR OFFICIAL USE ONLY - 4

EC-2 Management Plan QA/QC, Risk Management

• Demonstrate that they understand and are familiar with local Manhattan VAMC site and its conditions. This includes understanding the various complexities with the specific site.

• Effectively and realistically demonstrate its ability to maintain quality assurance and quality control construction practices. Provide a copy of a Quality Assur-ance/Quality Control Plan from a previous project of similar size and scope that is in compliance with the Contract Clause titled "Inspection of Construction:

o QC consists of plans, procedures, and organization necessary to produce an end product which complies with the contract requirements. Cover all construction operations, both onsite and offsite, and be keyed to the pro-posed construction design and construction sequence. The project super-intendent will be held responsible for the quality of work and is subject to removal by the Contracting Officer for non- compliance with the quality requirements specified in the contract. In this context the highest level manager responsible for the overall construction activities at the site, in-cluding quality and production is the project superintendent. The project superintendent must maintain a physical presence at the site at all times and is responsible for all construction and related activities at the site, ex-cept as otherwise acceptable to the Contracting Officer.

o Submit no later than 10 days after receipt of Notice to Proceed, the Con-tractor Quality Control (CQC) Plan proposed to implement the require-ments of the Contract Clause titled "Inspection of Construction." The Government will consider an interim plan for the first 7 days of operation.

Construction will be permitted to begin only after acceptance of the CQC Plan or acceptance of an interim plan applicable to the particular feature of work to be started. Work outside of the accepted interim plan will not be permitted to begin until acceptance of a CQC Plan or another interim plan containing the additional work.

EC-3 Previous Experience of Proposed Team

• Contractor must show documentation and demonstrate that the contractor and proposed subcontractors have had previous experience in performing work on similar projects. This includes working on High Tech High Cost site renovation.

• Offeror shall demonstrate corporate experience with no less than 4 projects completed within the last five years similar in size and scope to this Project.

• In describing project construction experience, provide the following information:

o Project title, location and brief description including local government agency coordination and contracting method (design-build, design bid

- FOR OFFICIAL USE ONLY - 5

construction, CM at risk, RFP etc.), Project owner, contact name and tel-ephone number and email addresses of owners’ contract person;

o Project Design Architect and Engineers (If Design/Build) and names and telephone number of contact person(s). Note each firm and employee al-so proposed for this solicitation o Project prime contractor and major subcontractors and name and tele-phone number of contact person(s). Note each firm and managing per-sons also proposed for this solicitation.

o Project statistics including start and completion dates (original vs actual) for construction; cost (with brief explanation of what is included in the cost), linear footage, significant traffic control or phasing and any awards received.

o Referenced projects should preferably have dealt with the situation where adjacent areas were required to be protected and all services maintained to keep remaining building occupants in operation.

o The contractor shall respond within 48 hours of attempted contact either by the Contracting Officer or VAMC Engineering staff. Failure to respond within the specified time may result in your technical score being lowered for this area of evaluation.

• Demonstrate successful construction safety management and practices on past projects. Provide a copy of the overall company Construction Safety Policy that is in harmony with the requirements of the Code of Federal Regulations 29, Part 1926.

• Clearly outline utility shutdown needed to perform work and the proposed timeframes for outages in the proposed construction schedule as required by EC-5 below. Also state how you will ensure that the main hospital will continue to maintain normal operating activities throughout the site-prep renovation pro-ject.

EC-4 Schedule, Capacity to accomplish the work in the required time.

• The proposed schedule will be evaluated as to how well it meets the objectives of the project:

o Explain how you would Maintaining Normal Operations of Building 6, Outpatient Clinic and Building 1, Main Building.

• Explain your procedures of Planned outages for Building 6, Outpatient Clinic

• Explain your procedures of fire protection phasing to maintain coverage in the 6th Floor Radiology.

• Discuss the process in scheduling work to be done in Radiology.

• Discuss Testing procedures such as medical gas etc…

- FOR OFFICIAL USE ONLY - 6

• Unless other objectives are stated, the shorter the construction duration that is evaluated to be feasible while maintaining safety and quality in conformance with the RFP is preferred and will receive a higher evaluation.

• The construction team schedule will:

o Describe the project schedule (Gantt or CPM type bar chart) identifying major work items including long lead items with start and stop dates that are realistic. The schedule will show the critical path activities highlighted in red. (i.e., main building utility, medical gas outages, etc.)

o Describe critical suppliers and subcontractors and if they have reviewed and agree to the schedule.

o The Government required finish date for this Project is Four Hundred Fifty

(365) days after NTP for base bid. This includes all design, construction, site work, all contracted modifications, final punch list, site cleanup, com-missioning, and demobilization from the site.

EC-5 Miscellaneous Experience & Capabilities

• Contractor shall provide their philosophy and method of implementing. Contrac-tor shall provide example of specialized experiences or capabilities beneficial to the completion of the project, including:

o Interior Design o CADD & Other Computer Applications. BIM o Value Engineering & Life Cycle Cost Analyses o Energy Conservation & New Energy Resources o CPM & Fast Track Construction o Seismic Design o Alternate Delivery Method – CMc, D/B, etc.

EC-6 Location and Facilities of Working Offices

• Contractor shall provide location of prime firm, consultants, subcontractor loca-tion and their distance to Manhattan VAMC.

EC-7 Price

• All teams must include a firm fixed lump sum price for the Project work with suf-ficient breakdown to assure that the Team understands the types of work in-volved in the project. The proposal will be evaluated for cost/price realism. The price proposal MUST include a breakdown of the lump sum price by all current

- FOR OFFICIAL USE ONLY - 7

CSI Divisions and show discreet quantities and prices for all equipment including but not necessarily limited to HVAC and associated components etc.

• Quantities of labor hours and labor hour rates which are at least equal Davis Bacon Wage Determination for all trades and hourly rates are also required.

Construction teams are encouraged to propose any value added items that they can deliver within the budget under a section titled “Value Engineering”.

• Offerors are advised that if the technical proposals are essentially equal, award will be made on the basis of lowest cost. A proposal that is unrealistic in terms of technical level of effort or unrealistically low in cost and/or price will be consid-ered to reflect a lack of technical competence or inability to comprehend the complexity and risk of contract requirements.

The Government Technical Evaluation Team will use the following adjectival rating sys-tem, rating each proposal’s response to the above evaluation criteria using the follow-ing adjectival rating schemes for both past performance and non-past performance fac-tors:

Past Performance Only (NEUTRAL RATING INCLUDED):

RATING DEFINITION/STANDARD

Excellent (Raw score 1) Based on the offeror’s performance record, no doubt exists that the offeror will successfully perform the required effort. There is a very low performance risk.

Very Good ( Raw score .8) Based on the offeror’s performance record, little doubt exists that the offeror will successfully perform the required effort. There is a low performance risk.

Satisfactory (Raw score .6)

Based on the offeror’s performance record, some doubt exists that the offeror will successfully perform the required effort. Normal contractor emphasis should preclude any problems. There is a moderate performance risk.

Marginal (Raw score .4)

Based on the offeror’s performance record, substan-tial doubt exists that the offeror will successfully per-form the required effort. There is a high performance risk.

Unacceptable (Raw score .2)

Based on the offeror’s performance record, extreme doubt exists that the offeror will successfully perform the required effort. There is a very high performance risk.

Neutral No performance record is identifiable.

- FOR OFFICIAL USE ONLY - 8

Non-past-performance Factors (No NEUTRAL Rating):

RATING DEFINITION/STANDARD

Excellent (Raw score 1)

The proposal demonstrates an excellent understand-ing of requirements and approach that significantly exceeds performance or capability standards. Has exceptional strengths that will significantly benefit the Government.

Good (Raw score .8)

The proposal demonstrates a good understanding of requirements and approach that exceeds perfor-mance or capability standards. Has one or more strengths that will benefit the Government.

Satisfactory (Raw score .6)

The proposal demonstrates an acceptable under-standing of requirements and approach that meets performance or capability standards. Acceptable so-lution. Few or no strengths.

Marginal (Raw score .4)

The proposal demonstrates a shallow understanding of requirements and approach that only marginally meets performance or capability standards necessary for minimal but acceptable performance.

Unacceptable (Raw score .2) Fails to meet performance or capability standards.

Requirements can only be met by major changes to the proposal.

- FOR OFFICIAL USE ONLY - 9