630-CSI-102 Gamma Cam revised 100 drawings.pdf

PDF 22 MB Posted

Attached to
Z1DA--630-CSI-120 NY SPECT CT SITE PREP DESIGN BUILD
Solicitation number
36C24224R0083
Issued by

About this file

This document is a Solicitation for a federal contract opportunity to design and construct site preparation for a new Nuclear Medicine GE SPECT CT system at the Department of Veterans Affairs Medical Center in New York, NY.

The key details are:

  • Solicitation Number: 36C24224R0083
  • Project Name: Z1DA--630-CSI-120 NY SPECT CT SITE PREP DESIGN BUILD
  • Performance Period: 365 Calendar Days
  • Scope of Work: Provide turnkey services to design and construct the site preparation for a new Nuclear Medicine GE SPECT CT system, including demolition, HVAC upgrades, electrical, plumbing, and other renovations to a 1,000 square foot radiology space. Work must meet VA design guidelines, manufacturer specifications, and be completed by August 2025.
  • Government Agency: Department of Veterans Affairs, Veterans Health Administration, Veterans Integrated Service Network 2
  • No security accreditation is required, but contractor employees must complete VA privacy training.
  • The contractor must utilize the VA's Autodesk Build construction management platform for project collaboration and submittals.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GENERAL NOTES

DEMOLITION NOTES

SAFETY NOTES

Drawing Title

Approved: Project Director

Project Title

Date

Location

Checked

Building Number

Project Number

Drawing Number

Drawn

Dwg. ofRevisions: Date

CONSULTANTS: ARCHITECT:

Facilities

Management on e eig ht h inc h on e fo ot th re e inc he s = o ne fo ot

6"

6" on e an d on e ha lf i nc he s = o ne fo ot on e inc h on e fo ot

6" 6" th re e qu ar te rs in ch o ne fo ot on e ha lf i nc h on e fo ot th re e eig ht hs in ch o ne fo ot on e qu ar te r i nc h on e fo ot

VA FORM 08-6231, OCT 1978

1 2 3 4 5 6 87 9

F

E

D

C

B

A

97 8654321

Services

MG PROJECT #

GAMMA CAMERA RM 6503E/F

MANHATTAN, VAMC

MANHATTAN VA MEDICAL CENTER

423 EAST 23RD STREET

NEW YORK, NEW YORK

MANHATTAN

DEPARTMENT OF VETERANS AFFAIRS

421 EAST 23RD STREET

NEW YORK, NEW YORK

NM/CT RM 6503E & 6503F

MEDICAL CENTER

PROJECT # 630-CSI-102

M.E.P. ENGINEER:M.E.P. ENGINEER:

777 SUNRISE HWY, STE 300

LYNBROOK, NY 11563

516 561 5922 WWW.BEPC.US

BECKER ENGINEERING, PC STCETIC HRA

M G NEW YORK

MICHAEL J. GADALETA, R.A. A.I.A. N.Y. LIC.: 17474 N.J. LIC.: 8935

11 BROADWAY, SUITE 860 NEW YORK, N.Y. 10004

212 674 8456 MGNEWYORKARCHITECTS.COM

LANDMARKS & PRESERVATION

DESIGN & PLANNING

ARCHITECTURE, HEALTH CARE,

GENERAL REQUIREMENTS

CODES, STANDARDS, AND EXECUTIVE ORDERS

PURPOSE: THE PUBLIC BUILDINGS AMENDMENT ACT OF 1988, PUBLIC LAW (PUB. L.) 100-678 REQUIRES FEDERAL AGENCIES TO FOLLOW NATIONAL RECOGNIZED "MODEL" BUILDING CODES. THE FEDERAL PARTICIPATION IN THE DEVELOPMENT AND USE OF VOLUNTARY STANDARDS, OFFICE OF MANAGEMENT AND BUDGET (OMB) CIRCULAR A-119, REQUIRES ALL EXECUTIVE AGENCIES TO RELY ON VOLUNTARY STANDARDS, BOTH DOMESTIC AND INTERNATIONAL, WHENEVER FEASIBLE, AND TO

PARTICIPATE IN VOLUNTARY STANDARD BODIES.

GENERAL: VA HAS ADOPTED THE LATEST EDITION OF THE FOLLOWING CODES AND STANDARDS AS A MINIMUM FOR ALL PROJECTS PERFORMED IN THE MODERNIZATION, ALTERATION, ADDITION, OR IMPROVEMENT OF ITS REAL PROPERTY AND THE CONSTRUCTION OF NEW STRUCTURES. VA DESIGN MANUALS AND MASTER SPECIFICATIONS SPECIFY OTHER CODES

AND STANDARDS THAT VA FOLLOWS ON ITS PROJECTS:

· VA DIRECTIVES, DESIGN MANUALS, MASTER SPECIFICATIONS, VA NATIONAL CAD STANDARD APPLICATION GUIDE, AND OTHER GUIDANCE ON THE TECHNICAL INFORMATION LIBRARY (TIL) (HTTP://WWW.CFM.VA.GOV/TIL/).

· INTERNATIONAL BUILDING CODE (IBC) (ONLY WHEN SPECIFICALLY REFERENCED IN VA DESIGN DOCUMENTS, SEE

NOTES BELOW)

· NFPA 101 LIFE SAFETY CODE (SEE NOTES BELOW)

· NFPA NATIONAL FIRE CODES WITH THE EXCEPTION OF NFPA 5000 AND NFPA 900

· OCCUPATIONAL, SAFETY AND HEALTH ADMINISTRATION (OSHA) STANDARDS.

· VA SEISMIC DESIGN REQUIREMENTS, H-18-8

· NATIONAL ELECTRICAL CODE (NEC)

· INTERNATIONAL PLUMBING CODE (IPC)

· SAFETY CODE FOR ELEVATORS AND ESCALATORS, AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME) A 17.1.

· ASME BOILER AND PRESSURE VESSEL CODE

· ASME CODE FOR PRESSURE PIPING

· ARCHITECTURAL BARRIERS ACT ACCESSIBILITY STANDARDS (ABAAS) INCLUDING VA SUPPLEMENT, BARRIER FREE

DESIGN GUIDE (PG-18-13)

· BUILDING CODE REQUIREMENTS FOR REINFORCED CONCRETE, AMERICAN CONCRETE INSTITUTE AND

COMMENTARY (ACI 318)

· MANUAL OF STEEL CONSTRUCTION, LOAD AND RESISTANCE FACTOR DESIGN SPECIFICATIONS FOR STRUCTURAL

STEEL BUILDINGS, AMERICAN INSTITUTE OF STEEL CONSTRUCTION (AISC)

· ENERGY POLICY ACT OF 2005 (EPACT)

· ENERGY STANDARD FOR BUILDINGS EXCEPT LOW-RISE RESIDENTIAL BUILDINGS - ASHRAE 90.1

· DOE INTERIM FINAL RULE: ENERGY CONSERVATION STANDARDS FOR NEW FEDERAL, COMMERCIAL AND MULTI-FAMILY HIGH-RISE RESIDENTIAL BUILDINGS AND NEW LOW-RISE RESIDENTIAL BUILDINGS, 10 CFR PARTS 433, 434 AND 435.

· FEDERAL LEADERSHIP IN HIGH PERFORMANCE AND SUSTAINABLE BUILDINGS: MEMORANDUM OF UNDERSTANDING

(MOU)

· EXECUTIVE ORDER 13423: STRENGTHENING FEDERAL ENVIRONMENTAL, ENERGY, AND TRANSPORTATION

MANAGEMENT.

· THE PROVISIONS FOR CONSTRUCTION AND SAFETY SIGNS. STATED IN THE GENERAL REQUIREMENTS SECTION

01010 OF THE VA MASTER CONSTRUCTION SPECIFICATION.

· VENTILATION FOR ACCEPTABLE INDOOR AIR QUALITY - ASHRAE STANDARD 62.1- 2004.

· SAFETY STANDARD FOR REFRIGERATION SYSTEMS - ASHRAE STANDARD 15 - 2007.

LOCAL CODES: AS AN AGENCY OF THE FEDERAL GOVERNMENT, VA IS NOT SUBJECT TO LOCAL IMPOSITION OF CODE ENFORCEMENT PROCEDURES (DRAWING REVIEWS, BUILDING PERMITS, INSPECTIONS, FEES, ETC.). VA MUST FUNCTION AS THE AUTHORITY HAVING JURISDICTION (AHJ) AND THUS HAS THE RESPONSIBILITY TO GUARD PUBLIC HEALTH AND SAFETY THROUGH ENFORCING ITS ADOPTED CODES. HOWEVER, LOCAL AUTHORITIES SHOULD BE NOTIFIED ABOUT PLANNED PROJECTS AND GIVEN OPPORTUNITY TO REVIEW DRAWINGS PROVIDED THAT VA DOES NOT PAY FOR REVIEW OR

INSPECTION FEES.

NOTES:

1. NFPA 101 PRIMARILY ADDRESSES LIFE SAFETY AND FIRE PROTECTION FEATURES WHILE THE IBC ADDRESSES A WIDE RANGE OF CONSIDERATIONS, INCLUDING, BUT NOT LIMITED TO, STRUCTURAL STRENGTH, SEISMIC STABILITY, SANITATION, ADEQUATE LIGHT AND VENTILATION, AND ENERGY CONSERVATION. VA BUILDINGS MUST MEET THE REQUIREMENTS OF NFPA 101 AND DOCUMENTS REFERENCED BY NFPA 101 IN ORDER TO COMPLY WITH THE ACCREDITATION REQUIREMENTS OF THE JOINT COMMISSION. THEREFORE, DESIGNS SHALL COMPLY WITH THE REQUIREMENTS OF THE LATEST EDITION OF NFPA 101 AND DOCUMENTS REFERENCED THEREIN. DESIGN FEATURES NOT ADDRESSED BY NFPA 101 OR DOCUMENTS REFERENCED THEREIN SHALL COMPLY WITH THE REQUIREMENTS OF THE LATEST EDITION OF THE IBC OR AS OTHERWISE ADDRESSED ABOVE IN THIS PROGRAM GUIDE. FOR DESIGN FEATURES THAT ARE ADDRESSED BY BOTH THE IBC AS WELL AS NFPA 101 OR A DOCUMENT REFERENCED BY NFPA 101, THE REQUIREMENTS OF NFPA 101 OR THE DOCUMENT REFERENCED BY NFPA 101 SHALL BE USED EXCLUSIVELY (THIS

APPLIES EVEN IF THE IBC REQUIREMENTS ARE DIFFERENT).

2. CONFLICTS BETWEEN NATIONALLY RECOGNIZED CODES AND STANDARDS AND VA REQUIREMENTS - SHOULD A CONFLICT EXIST BETWEEN VA REQUIREMENTS AND VA ADOPTED NATIONALLY RECOGNIZED CODES AND STANDARDS, THE CONFLICT SHALL BE BROUGHT TO THE ATTENTION OF VA. THE RESOLUTION OF THE CONFLICT SHALL BE MADE BY THE

AUTHORITY HAVING JURISDICTION FOR VA TO ENSURE A CONSISTENCY SYSTEM WIDE.

COVER SHEET

02 22 2023 AMG 1

A-000.00

SIXTH FLOOR PLAN

AREA OF WORK

NOT TO SCALE

630-CSI-102

2019-63

ARCHITECTURAL

A-000.00 COVER

A-001.00 LIFE SAFETY PLAN - 6TH FLOOR

A-002.00 INFECTION CONTROL PLAN

A-100.00 EXISTING PLANS AT ROOMS 6503E & 6503F

A-101.00 DEMO PLAN AT AREA OF WORK

A-102.00 DEMO R.C.P. AT AREA OF WORK

A-103.00 PROPOSED PLANS AT NEW GAMMA CAMERA AND AREA OF WORK

A-104.00 PROPOSED R.C.P.

A-200.00 PROPOSED FINISH PLAN

A-201.00 PROPOSED SECTIONS AT NEW UNISTRUT

A-202.00 INTERIOR ELEVATIONS AND DOOR SCHEDULE

MEP DRAWINGS

T-001.00 TITLE SHEET

G-001.00 GENERAL DESIGN NOTES

G-002.00 MECHANICAL DESIGN NOTES

G-003.00 ELECTRICAL DESIGN NOTES

G-004.00 PLUMBING DESIGN NOTES

G-005.00 SPRINKLER DESIGN NOTES

M-001.00 PLOT PLAN, MECHANICAL SYMBOL & ABBREVIATION LIST

M-002.00 ROOM 6503E/F MECHANICAL PLAN & MECHANICAL DETAILS

E-001.00 ELECTRICAL SYMBOLS & ABBREVIATION LIST, LIGHTING FIXTURE SCHEDULE

E-002.00 ROOM 6503E/F LIGHTING & POWER PLAN AND ELECTRICAL DETAILS

P-001.00 PLUMBING SYMBOL & ABBREVIATION LIST

P-002.00 ROOM 6503E/F PLUMBING & SPRINKLER PLAN AND SPRINKLER DETAILS

X-001.00 ELECTRICAL SPECIFICATIONS

GE DRAWINGS

01-C1 COVER SHEET

02-C2 DISCLAIMER - SITE READINESS

03-A1 GENERAL NOTES

04-A2 EQUIPMENT LAYOUT

05-A3 RADIATION PROTECTION

06-A4 EQUIPMENT DETAILS (1)

07-A5 EQUIPMENT DETAILS (2)

08-A6 DELIVERY

09-S1 STRUCTURAL NOTES

10-S2 STRUCTURAL LAYOUT

11-S3 STRUCTURAL DETAILS (1)

12-M1 HVAC

13-E1 ELECTRICAL NOTES

14-E2 ELECTRICAL LAYOUT

15-E3 ELECTRICAL ELEVATIONS

16-E4 POWER REQUIREMENTS

17-E5 ELECTRICAL DETAILS - INTERCONNECTIONS

STRUCTURAL DRAWINGS

S-001.00 STRUCTURAL DETAILS

100% SUBMISSION

(RESUBMITTED 2 22 2023)

60% SUBMISSION 11 24 2020

100% SUBMISSION 02 04 2021

100% RE-SUBMISSION 03 15 2021

100% RE-SUBMISSION 02 22 2023

AutoCAD SHX Text

ACTS AND FROM ANY OTHER CLAIMS FROM DAMAGES.

AutoCAD SHX Text

4.8 ANY SUBSTITUTION THE GENERAL CONTRACTOR WISHES TO MAKE OTHER

AutoCAD SHX Text

4.9 THE GENERAL CONTRACTOR, AT HIS OWN EXPENSE, SHALL EMPLOY A

AutoCAD SHX Text

WRITING WITH THE COST DIFFERENCE BEFORE IT IS ACCEPTED.

AutoCAD SHX Text

THAN THOSE STATED IN THIS PROPOSAL, SHALL BE SUBMITTED IN

AutoCAD SHX Text

IMMEDIATELY.

AutoCAD SHX Text

AFTERWARDS; THIS WORK MUST BE REMOVED AND MADE CORRECT

AutoCAD SHX Text

WHETHER THEY ARE DISCOVERED AT THE TIME OF INSTALLATION OR

AutoCAD SHX Text

4.7 NO INTERIOR WORK OR MATERIAL SHALL BE ACCEPTED ON THIS PROJECT,

AutoCAD SHX Text

WORKMAN SHALL BE EMPLOYED ON THE PROJECT.

AutoCAD SHX Text

4.6 THE GENERAL CONTRACTOR WARRANTS THAT NONE BUT EXPERIENCED

AutoCAD SHX Text

ACCORDANCE WITH BEST PRACTICES WITH FIRST CLASS MATERIALS.

AutoCAD SHX Text

4.5 ALL WORK SHALL BE PERFORMED IN A FIRST CLASS MANNER AND IN

AutoCAD SHX Text

SPECIFICATIONS.

AutoCAD SHX Text

FOR PAINTING OR WALL COVERING AS PER MANUFACTURER'S

AutoCAD SHX Text

4.4 ALL WALL SHALL BE PROPERLY PREPARED (SPACKLED, SANDED, ETC.)

AutoCAD SHX Text

INVOLVED IN THE PROJECT.

AutoCAD SHX Text

AND DUST FROM LEAVING THE JOB SITE AND INFILTRATING AREAS NOT

AutoCAD SHX Text

4.3 THE GENERAL CONTRACTOR SHALL CONTROL CLEANING TO PREVENT DIRT

AutoCAD SHX Text

SCOPE OF THE WORK.

AutoCAD SHX Text

CALLED OUT ON THESE DRAWINGS, IS CONSIDERED TO BE WITHIN THE

AutoCAD SHX Text

4.2 ANY PATCHING AND FINISHING NECESSARY TO FINISH ANY WORK, BUT

AutoCAD SHX Text

GUARANTEED.

AutoCAD SHX Text

AND MAKE GOOD ALL SUCH DEFECTS APPEARING DURING THIS PERIOD

AutoCAD SHX Text

WORKMANSHIP AGAINST DEFECTS FOR ONE YEAR FROM FINAL PAYMENT

AutoCAD SHX Text

4.1 THE GENERAL CONTRACTOR SHALL GUARANTEE ALL MATERIALS AND

AutoCAD SHX Text

SECTION 4 - WORKMANSHIP

AutoCAD SHX Text

OWNER AND DEPARTMENT OF BUILDINGS.

AutoCAD SHX Text

AS REQUIRED BY THE GOVERNING JURISDICTION ARE SUBMITTED TO THE

AutoCAD SHX Text

3.1 NO WORK SHALL COMMENCE UNTIL PROPER CERTIFICATES OF INSURANCE

AutoCAD SHX Text

SECTION 3 - INSURANCES

AutoCAD SHX Text

AGAINST ANY DAMAGES WHICH MAY RESULT FROM SUCH VIOLATIONS.

AutoCAD SHX Text

PENALTIES AND CORRECTIVE MEASURES, AND HOLD HARMLESS THE OWNER

AutoCAD SHX Text

REGULATIONS, HE SHALL AT HIS OWN EXPENSES BEAR THE COSTS OF ALL

AutoCAD SHX Text

2.5 IF THE CONTRACTORS VIOLATE ANY BUILDING DEPARTMENT CODES OR

AutoCAD SHX Text

2.4 ALL WOOD SHALL BE FIRE-PROOFED AS REQUIRED BY THE BUILDING CODE.

AutoCAD SHX Text

LOCAL AND SHALL CONFORM TO GENERALLY ACCEPTED STANDARDS.

AutoCAD SHX Text

CONFORM TO ALL GOVERNING BUILDING CODES; FEDERAL, STATE, AND

AutoCAD SHX Text

2.3 ALL MATERIALS, ASSEMBLIES, CONSTRUCTION AND EQUIPMENT SHALL

AutoCAD SHX Text

MUNICIPAL AND REGULATORY AGENCIES' CODES HAVING JURISDICTION.

AutoCAD SHX Text

2.2 THE GENERAL CONTRACTOR SHALL COMPLY WITH ALL APPROPRIATE

AutoCAD SHX Text

ALLOWING MAXIMUM ACCESS, NOT IMPEDING TRAFFIC AND PROVIDE REQUIRED

AutoCAD SHX Text

9. CONTRACTOR TO RETAIN STORED ITEMS IN AN ORDERLY ARRANGEMENT

AutoCAD SHX Text

TO ARCHITECT'S ATTENTION IMMEDIATELY.

AutoCAD SHX Text

AT THE JOB SITE. IN THE EVENT OF CONFLICTS, THEY SHALL BE BROUGHT

AutoCAD SHX Text

8. CONTRACTORS SHALL CHECK AND VERIFY ALL DIMENSIONS AND CONDITIONS

AutoCAD SHX Text

CODES FOR BUILDING CONSTRUCTION; TO LIFE SAFETY CODE NFPA 101 AND

AutoCAD SHX Text

7. ALL WORK SHALL CONFORM TO MINIMUM REQUIREMENTS OF NEW YORK CITY

AutoCAD SHX Text

THE OWNER AND CONTRACTOR FROM CLAIMS UNDER WORKMEN'S COMPENSATION

AutoCAD SHX Text

6. THE CONTRACTOR SHALL MAINTAIN SUCH INSURANCE AND WILL PROTECT BOTH

AutoCAD SHX Text

REMOVE FROM PREMISES ALL RUBBISH AND DEBRIS FOR WHICH HE IS

AutoCAD SHX Text

AWAY FROM THE PREMISES. UPON COMPLETION OF WORK CONTRACTORS SHALL

AutoCAD SHX Text

OF THIS CONTRACT SHALL BE PROMPTLY REMOVED DAILY AND DISPOSED OF

AutoCAD SHX Text

ARE NOT REQUIRED OR APPROVED FOR USE IN CONNECTION WITH THE WORK

AutoCAD SHX Text

5. EXCESS MATERIALS AND DEBRIS RESULTING FROM THE ALTERATION WHICH

AutoCAD SHX Text

ARCHITECT, AT NO ADDITIONAL COST TO THE OWNER.

AutoCAD SHX Text

PROMPTLY RESTORED, REPAIRED, OR REPLACED TO THE SATISFACTION OF THE

AutoCAD SHX Text

RESULTING DIRECTLY FROM THE CONTRACTOR'S OPERATIONS SHALL BE

AutoCAD SHX Text

EXISTING BUILDING AND IMPROVEMENTS, OR ANY IMPAIRMENTS OF FACILITIES

AutoCAD SHX Text

UNDER THIS CONTRACT. ANY DISTURBANCE OR DAMAGE TO THE WORK, THE

AutoCAD SHX Text

BUILDING, FACILITIES AND IMPROVEMENT WITHIN THE AREAS OF HIS OPERATIONS

AutoCAD SHX Text

4. THE CONTRACTOR SHALL PROTECT AND BE RESPONSIBLE FOR THE EXISTING

AutoCAD SHX Text

EXISTING WORK IN EVERY RESPECT AS APPROVED.

AutoCAD SHX Text

REPAIRS AND REPLACEMENTS TO SUCH DAMAGED WORK AT HIS COST AND

AutoCAD SHX Text

AND CIRCUMSTANCES TO THE ARCHITECT AND SHALL MAKE ANY NECESSARY

AutoCAD SHX Text

WORK OF THIS CONTRACT, THE CONTRACTOR SHALL REPORT THE CONDITIONS

AutoCAD SHX Text

3. SHOULD ANY PORTION OF THE EXISTING BUILDING BE DAMAGED DUE TO THE

AutoCAD SHX Text

SPECIFIED AND AS REQUIRED BY CONDITIONS ENCOUNTERED.

AutoCAD SHX Text

2. ALTERATIONS ARE TO BE PERFORMED AS REQUIRED BY DRAWINGS AND/OR

AutoCAD SHX Text

COMMENCING WORK, HE SHALL EXAMINE ALL EXISTING WORK.

AutoCAD SHX Text

SO THAT ALL WORK WILL PROPERLY JOIN THE EXISTING WORK. BEFORE

AutoCAD SHX Text

1. THE CONTRACTOR SHALL VERIFY DIMENSIONS AND CONDITIONS ON THE JOB

AutoCAD SHX Text

GENERAL REQUIREMENTS FOR ALTERATION:

AutoCAD SHX Text

TO THE NATIONAL ELECTRIC CODE.

AutoCAD SHX Text

RESPONSIBLE.

AutoCAD SHX Text

RESPECT AS APPROVED. EXPENSE WITH NEW MATERIALS TO MATCH THE

AutoCAD SHX Text

BEEN MADE.

AutoCAD SHX Text

DISTURB THE ASBESTOS UNTIL PROPER MEASURES FOR ITS REMOVAL HAVE

AutoCAD SHX Text

OWNER'S PROJECT MANAGER IMMEDIATELY AND TAKE PRECAUTIONS TO NOT

AutoCAD SHX Text

10.1 IF THE CONTRACTOR ENCOUNTERS ASBESTOS HE SHALL NOTIFY THE

AutoCAD SHX Text

SECTION 10 - ASBESTOS

AutoCAD SHX Text

- ELECTRICAL PANELS TAGGED AND LABELED.

AutoCAD SHX Text

- MANUALS AND INSTRUCTIONS.

AutoCAD SHX Text

- ALL WARRANTIES AND GUARANTEES.

AutoCAD SHX Text

- WAIVER OF LIENS.

AutoCAD SHX Text

SUBMITTED BUT NOT LIMITED TO THESE ITEMS:

AutoCAD SHX Text

9.3 BEFORE FINAL PAYMENT IS ISSUED THE FOLLOWING ITEMS MUST BE

AutoCAD SHX Text

1.16 DRAWINGS SHALL NOT BE SCALED, LARGER SCALE DRAWINGS SHALL ALWAYS

AutoCAD SHX Text

FURNISH A LIST OF SUB-CONTRACTORS AND MANUFACTURERS HE INTENDS

AutoCAD SHX Text

MANUFACTURERS OR SUBCONTRACTORS. THE GENERAL CONTRACTORS SHALL

AutoCAD SHX Text

1.15 WHERE DRAWINGS CALL FOR A SPECIFIC MANUFACTURER TO SUBCONTRACTOR,

AutoCAD SHX Text

1.13 THE GENERAL CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATION OF

AutoCAD SHX Text

1.10 THE GENERAL CONTRACTOR IS RESPONSIBLE FOR PROTECTION OF WORKMEN,

AutoCAD SHX Text

AND INSTALLED BY THE GENERAL CONTRACTOR UNLESS NOTED OTHERWISE.

AutoCAD SHX Text

1.9 ALL WORK SHOWN ON THE CONSTRUCTION DOCUMENTS SHALL BE FURNISHED

AutoCAD SHX Text

TERMS ARE USED, IT SHALL BE BASED UPON THE REVIEW AND APPROVAL

AutoCAD SHX Text

COORDINATION WITH ALL SUBCONTRACTORS, WHETHER UNDER CONTRACT

AutoCAD SHX Text

ENCOUNTERED WHICH COULD HAVE BEEN AVERTED HAD SUCH AN

AutoCAD SHX Text

THE GENERAL CONTRACTOR SHALL BE OBLIGATED TO USE THESE

AutoCAD SHX Text

2.1 (REMOVED)

AutoCAD SHX Text

SECTION 2 - GOVERNING AGENCIES AND PERMITS

AutoCAD SHX Text

ON THE WORK.

AutoCAD SHX Text

1.17 THE A.I.A. GENERAL CONDITIONS, LATEST EDITION, SHALL BE BINDING

AutoCAD SHX Text

GOVERN OVER SMALLER SCALE DRAWINGS.

AutoCAD SHX Text

TO USE BEFORE WORK COMMENCES.

AutoCAD SHX Text

1.14 BEFORE WORK COMMENCES THE ARCHITECT IS TO APPROVE ALL LAYOUTS.

AutoCAD SHX Text

BACKBOXES, ETC. SHALL BE CONCEALED WITHIN BUILDING CONSTRUCTION.

AutoCAD SHX Text

CHOPPING AND PATCHING FOR ALL TRADES. ALL CONDUITS, PIPING,

AutoCAD SHX Text

MAINTAINED.

AutoCAD SHX Text

FIRE PROTECTION DEVICES AND ALARMS SHALL BE CONTINUOUSLY

AutoCAD SHX Text

1.12 DURING THE ENTIRE CONSTRUCTION PERIOD, ALL EXISTING LIGHTING,

AutoCAD SHX Text

MAINTAINED FREE OF OBSTRUCTIONS THROUGHOUT THE CONSTRUCTION.

AutoCAD SHX Text

1.11 ALL REQUIRED EXITS AND EXIT APPROACHES SHALL BE CONTINUOUSLY

AutoCAD SHX Text

PUBLIC AND PROPERTY.

AutoCAD SHX Text

COMMENCEMENTS OF WORK.

AutoCAD SHX Text

SPECIFICATIONS AND SAMPLES FOR APPROVAL, IN WRITING, PRIOR TO

AutoCAD SHX Text

FIRST INFORMING THE ARCHITECT. SUBMIT SUBSTITUTE MATERIAL

AutoCAD SHX Text

BY THE ARCHITECT NO MATERIAL SUBSTITUTION SHALL BE MADE WITHOUT

AutoCAD SHX Text

1.8 WHEN "APPROVAL EQUAL", "EQUAL TO" OR OTHER GENERAL QUALIFYING

AutoCAD SHX Text

TO HIM OR NOT.

AutoCAD SHX Text

1.7 THE GENERAL CONTRACTOR SHALL BE RESPONSIBLE FOR THE OVERALL

AutoCAD SHX Text

CONDITIONS AT THE JOB SITE.

AutoCAD SHX Text

1.6 THE CONTRACTOR SHALL CHECK AND VERIFY ALL DIMENSIONS AND

AutoCAD SHX Text

AT ONCE.

AutoCAD SHX Text

THE CONTRACTOR SHALL STOP IMMEDIATELY AND NOTIFY THE ARCHITECT

AutoCAD SHX Text

1.5 IF ANY UNFORESEEN CONDITIONS ARISE DURING ANY PORTION OF WORK,

AutoCAD SHX Text

ITEMS.

AutoCAD SHX Text

MANAGER SHALL BE AVAILABLE TO REVIEW AND CLARIFY ANY UNCLEAR

AutoCAD SHX Text

UNDERSTANDING OF THE SCOPE OF WORK. THE ARCHITECT OR PROJECT

AutoCAD SHX Text

1.4 THE CONTRACTOR SHALL REVIEW THESE DOCUMENTS TO INSURE A FULL

AutoCAD SHX Text

CLARIFICATION.

AutoCAD SHX Text

COMMENCING ANY WORK OR ORDERING MATERIALS, AND REQUEST

AutoCAD SHX Text

BETWEEN THESE DRAWINGS, THESE NOTES, AND CONDITIONS BEFORE

AutoCAD SHX Text

1.3 THE CONTRACTOR SHALL NOTIFY THE ARCHITECT OF ANY DISCREPANCIES

AutoCAD SHX Text

EXAMINATION BEEN MADE, WILL NOT BE RECOGNIZED.

AutoCAD SHX Text

LABOR, EQUIPMENT OR MATERIALS REQUIRED FOR DIFFICULTIES

AutoCAD SHX Text

THAT SUCH AN EXAMINATION HAS BEEN MADE, AND LATER CLAIMS FOR

AutoCAD SHX Text

1.2 THE SUBMISSION OF THE PROPOSAL WILL BE CONSTRUCTED AS EVIDENCE

AutoCAD SHX Text

OF THE WORK AND DIFFICULTIES THAT ATTEND ITS EXECUTION.

AutoCAD SHX Text

THE PREMISES FAMILIARIZING HIMSELF AS THE NATURE AND SCOPE

AutoCAD SHX Text

1.1 THE CONTRACTOR, BEFORE SUBMITTING A PROPOSAL, SHALL VISIT

AutoCAD SHX Text

SECTION 1 - EXECUTION AND INTENT OF DRAWINGS

AutoCAD SHX Text

THAT THE WORK IS SUBSTANTIALLY COMPLETE.

AutoCAD SHX Text

NOTIFY THE ARCHITECT TO CONDUCT A PUNCH LIST. UPON VERIFICATION

AutoCAD SHX Text

9.2 WHEN THE G.C. CONSIDERS THAT THE WORK IS ACCEPTABLE HE SHOULD

AutoCAD SHX Text

INTENDED.

AutoCAD SHX Text

THE OWNER CAN OCCUPY THE AREA FOR THE PURPOSE FOR WHICH IT WAS

AutoCAD SHX Text

COMPLETE, IN ACCORDANCE WITH THE CONTRACT DOCUMENTS, SO THAT

AutoCAD SHX Text

CERTIFIED BY THE OWNER WHEN CONSTRUCTION IS SUFFICIENTLY

AutoCAD SHX Text

9.1 SUBSTANTIAL COMPLETION OF THE WORK IS DEFINED AS THE DATE

AutoCAD SHX Text

SECTION 9 - SUBSTANTIAL COMPLETION

AutoCAD SHX Text

HIS EMPLOYEE AND OTHER SUBCONTRACTORS.

AutoCAD SHX Text

8.3 THE G.C. SHALL REMOVE ALL RUBBISH AND WASTE MATERIALS FROM BOTH

AutoCAD SHX Text

AREAS UNTIL THE SPACE IS TURNED OVER TO THE OWNER.

AutoCAD SHX Text

8.2 THE G.C. SHALL BE RESPONSIBLE FOR THE SECURITY OF THE CONSTRUCTION

AutoCAD SHX Text

SHALL BE PROMPTLY RESTORED.

AutoCAD SHX Text

UNDER THIS CONTRACT. ANY DISTURBANCES FROM THE G.C.'S OPERATIONS

AutoCAD SHX Text

EXISTING STRUCTURES, FACILITIES AND IMPROVEMENT ADJOINING THE AREA

AutoCAD SHX Text

8.1 THE GENERAL CONTRACTOR SHALL PROTECT AND BE RESPONSIBLE FOR THE

AutoCAD SHX Text

SECTION 8 - PROTECTION OF WORK AND PROPERTY

AutoCAD SHX Text

ATTENTION OF M/G.

AutoCAD SHX Text

INTERFERENCE THAT WOULD PREVENT ACCESS IS TO BE BROUGHT TO THE

AutoCAD SHX Text

BE KEPT CLEAN AND READY FOR ACCESS. ANY POSSIBLE CONSTRUCTION

AutoCAD SHX Text

7.3 ALL EXISTING VALVES AND CONTROLS FOR MECHANICAL EQUIPMENT ARE TO

AutoCAD SHX Text

PERMITTED AS INSULATION OF FILL.

AutoCAD SHX Text

FLAME, SMOKE, FUMES AND HOT GASSES. FLAMMABLE MATERIALS ARE NOT

AutoCAD SHX Text

FILLED WITH NONCOMBUSTIBLE MATERIALS TO PREVENT THE PASSAGE OF

AutoCAD SHX Text

7.2 ALL PENETRATION THROUGH FIRE PARTITIONS SHALL BE FIRESTOPPED OR

AutoCAD SHX Text

FOR ALL SUBCONTRACTORS TO COMPLETE THEIR WORK.

AutoCAD SHX Text

7.1 THE GENERAL CONTRACTOR SHALL DO ALL CUTTING AND PATCHING REQUIRED

AutoCAD SHX Text

SECTION 7 - CUTTING AND PATCHING

AutoCAD SHX Text

SECTION 6 - (REMOVED)

AutoCAD SHX Text

CUTS OR SAMPLE.

AutoCAD SHX Text

THE CONTRACT DOCUMENTS BY THE APPROVAL OF SHOP DRAWINGS OR

AutoCAD SHX Text

FOR ANY DEVIATIONS, ERRORS OR OMISSIONS FROM THE REQUIREMENTS OF

AutoCAD SHX Text

5.4 THE GENERAL CONTRACTOR SHALL NOT BE RELIEVED OF RESPONSIBILITY

AutoCAD SHX Text

CONDITIONS RELATED TO THE CONSTRUCTION OF THAT SUBMISSION.

AutoCAD SHX Text

CONTRACTOR REPRESENTS THAT HE HAS VERIFIED FIELD MEASUREMENTS AND

AutoCAD SHX Text

5.3 BY APPROVING AND SUBMITTING SHOP DRAWINGS AND SAMPLES THE GENERAL

AutoCAD SHX Text

EQUIPMENT AND FINISHES FOR APPROVAL.

AutoCAD SHX Text

5.2 THE GENERAL CONTRACTOR SHALL SUBMIT CUTS OF ALL FIXTURES,

AutoCAD SHX Text

FABRICATED ITEMS AND ALL OTHER ITEMS REQUIRED FOR APPROVAL.

AutoCAD SHX Text

REPRODUCIBLE AND THREE BLACK AND WHITE PRINTS FOR ALL SHOP

AutoCAD SHX Text

5.1 THE GENERAL CONTRACTOR SHALL SUBMIT SHOP DRAWINGS OF ONE

AutoCAD SHX Text

SECTION 5 - SHOP DRAWINGS

AutoCAD SHX Text

COMPETENT, FULLTIME SUPERINTENDENT TO SUPERVISE AND

AutoCAD SHX Text

COORDINATE THE WORK OF HIS OWN MEN AND SUBCONTRACTORS.

AutoCAD SHX Text

1. THE GENERAL CONTRACTOR RESPONSIBLE FOR THE DEMOLITION PORTION OF THIS WORK SHALL AS PART OF THIS WORK SURVEY AND/OR INVESTIGATE ALL REQUIRED SHUT-OFFS FOR ELECTRICAL, MECHANICAL, AND PLUMBING WORK, PRIOR TO DEMO OF THESE AREAS. 2. THE GENERAL CONTRACTOR SHALL IDENTIFY SOURCES OF ALL ELECTRICAL POWER REQUIRED TO BE RELOCATED AS PART OF THIS WORK OR FUTURE 3. THE GENERAL CONTRACTOR SHALL PROVIDE AND MAKE AVAILABLE TO THE ARCHITECT THE RECORD DRAWINGS OF ALL SUCH INVESTIGATIONS 4. CONTRACTOR SHALL OBTAIN ALL REQUIRED APPROVALS PRIOR TO BEGINNING WORK. 5. ALL WORK SHALL BE IN STRICT COMPLIANCE WITH THE TERMS AND CONDITIONS OF ALL APPROVALS. 6. CONTRACTOR SHALL OBTAIN ALL NECESSARY PERMITS AND SHALL MAINTAIN THEM ON THE JOB SITE IN ACCORDANCE WITH APPLICABLE REGULATIONS 7. THE CONTRACTOR SHALL MAINTAIN A COPY OF THE APPROVED PLANS ON THE JOB SITE AT ALL TIMES. 8. CONSTRUCTION WORK SHALL NOT BLOCK HALLWAYS OR OBSTRUCT SAFE EGRESS FROM ANY SPACE WITHIN THE PREMISE OF BUILDING 9. REMOVE EXISTING FINISHED FLOOR, BRING DOWN TO SOUND STRUCTURE, PATCH AND REPAIR AS REQUIRED IN ORDER TO RECEIVE FINISHED FLOOR. 10. ALL WORK SHALL BE PERFORMED AS PER CODE AND AS PER ALL GOVERNING AGENCIES HAVING JURISDICTION 11. THE CONTRACTOR SHALL OBTAIN PERMITS WHERE REQUIRED FOR CONTAINERS, SHEDS, AND OTHER ELEMENTS OF THE DEMOLITION. 12. THE CONTRACTOR SHALL MAINTAIN ALL INSURANCES REQUIRED BY THE BUILDING OWNER AND BY REGULATORY AUTHORITIES 13. THE CONTRACTOR SHALL BE RESPONSIBLE FOR PROTECTING ALL BUILDING ELEMENTS WHICH ARE NOT DESIGNATED FOR REMOVAL, AND REPLACE ANY BUILDING ELEMENTS DAMAGED DURING DEMOLITION. 14. CONTRACTOR SHALL PROTECT THE SITE AND THE REBUILDING FROM UN-AUTHORIZED ENTRY AT ALL TIMES.

AutoCAD SHX Text

1. REQUIRED EGRESS SHALL NOT BE IMPEDED DURING COURSE OF CONSTRUCTION 2. SECURITY AND FIRE SAFETY SHALL BE MAINTAINED DURING COURSE OF CONSTRUCTION WORK 3. WHERE STRUCTURAL WORK IS TO BE DONE, THE SAFETY OF OCCUPANTS SHALL BE MAINTAINED 4. DUST CREATED DURING THE COURSE OF CONSTRUCTION SHALL BE CONTAINED AND KEPT UNDER CONTROL 5. NOISE TO BE CONTROLLED DURING ALL WORKING HOURS 6. THE WORK SHALL BE SO PERFORMED, AND SUCH TEMPORARY FACILITIES AND UTILITIES FURNISHED, AS NOT TO INTERFERE WITH ACCESS TO ANY OCCUPIED PARTS OF THE EXISTING BUILDING AND SO AS TO CAUSE THE LEAST POSSIBLE INTERFERENCE WITH THE OPERATION OF THE BUILDING OF ESSENTIAL SERVICES THEREOF. THE CONTRACTOR SHALL WORK OUT A TIME SCHEDULE WITH THE OWNER AND OBTAIN WRITTEN APPROVAL OF THE OWNER TWO WEEKS IN ADVANCE OF WORK WHICH MAY OR WILL CAUSE INTERFERENCE. 7. WHEN INSTALLATION OF PARTIAL OR NEW SYSTEM SHALL BE PERFORMED ONLY AFTER WRITTEN NOTIFICATION OF ESTIMATED SHUTDOWN PERIOD HAS BEEN APPROVED BY OWNER. 8. THE CONTRACTOR SHALL PROVIDE ADEQUATE PROTECTION FOR ALL PARTS OF THE EXISTING BUILDING, ITS CONTENTS AND OCCUPANTS. 9. PROPER PROTECTION SHALL BE PROVIDED AROUND ALL AREAS IN WHICH DEMOLITION OR NEW WORK IS TO BE CARRIED SO AS TO PREVENT DIRT, OR DUST, FROM ENTERING ACTIVE PORTIONS OF THE BUILDING. PROTECTIVE MEASURES SHALL CONSIST OF DUST-TIGHT STUD AND PLYWOOD PARTITIONS. 10. ALL RUBBISH AND DEBRIS SHALL BE COLLECTED AND REMOVED FROM THE SITE BY THE CONTRACTOR.

AutoCAD SHX Text 1, COORDINATE A KICKOFF MEETING AT THE SITE TO REVIEW THE WORK CONTENT, DESIGN FOR THE WORK, DRAWING APPROVAL PROCESS, IF ANY, AND FINALIZE THE SCHEDULE FOR THE DESIGN AND PRODUCTION OF THE WORK. 2. COORDINATE AND ATTEND A PRE-CONSTRUCTION MEETING AND PERIODIC PROGRESS MEETINGS. COMPILE AND DISTRIBUTE THE MINUTES OF THOSE MEETINGS AND AN UPDATED CONSTRUCTION SCHEDULE FOLLOWING EACH OF THOSE MEETINGS. 3. PROJECT MANAGEMENT AND FULL-TIME CONSTRUCTION SUPERVISION SERVICES AT THE SITE DURING THE PRODUCTION OF THE WORK. 4. SEAL OF APPLICABLE SITE SUPPLY AND RETURN DIFFUSERS AD GRILLES TO MINIMIZE DUST CONTAMINATION OF DUCTWORK AND THE SURROUNDING AREA. 5. FURNISH AND INSTALL (i) TEMPORARY WALK-OFF MATS AT THE ENTRANCES TO THE SITE, AND (ii) A TEMPORARY NEGATIVE AIR UNIT FOR THE SITE WITH HEPA FILTRATION FOR GENERAL DUST CONTROL. 6. MAINTAIN THE SITE IN A REASONABLY CLEAN AND SAFE CONDITION IN COMPLIANCE WITH APPLICABLE OSHA REGULATIONS. 7. COMPLY WITH THE REASONABLE WRITTEN FIRE PREVENTION MEASURES AND OTHER WRITTEN GENERAL CONSTRUCTION RELATED RULES FURNISHED BY FACILITY AND THAT ARE IN EFFECT AT THE SITE. 8. THE WORK WILL BE PRODUCED DURING STANDARD WORK HOURS. 9. POWER AND OTHER UTILITIES SHUT DOWNS WILL OCCUR DURING STANDARD WORK HOURS AND WILL BE COORDINATED WITH A REPRESENTATIVE OF FACILITY ENGINEERING DEPARTMENT. 10. CLEAN THE SITE (BROOM CLEAN) ON A DAILY BASIS. AT THE COMPLETION OF THE WORK, REMOVE ALL TOOLS, EQUIPMENT, SURPLUS MATERIAL, AND TEMPORARY STRUCTURES. 11. FURNISH A DUMPSTER FOR WORK RUBBISH AND DEBRIS NEAR THE SITE IN AN AREA DESIGNATED BY FACILITY. 12. IF AREAS ADJOINING THE SITE ARE OCCUPIED DURING THE PRODUCTION OF THE WORK, COORDINATE THE WORK SO THAT THE USE AND OCCUPANCY OF THOSE AREAS WILL NOT BE UNREASONABLY IMPAIRED FOR EXTENDED PERIODS OF TIME. 13. COORDINATE THE DELIVERY AND STORAGE OF THE WORK MATERIALS WITH FACILITY. 14. THE WORK WILL COMPLY WITH APPLICABLE BUILDING CODES, RULES, AND REGULATIONS ENACTED BY THE STATE WHERE THE SITE IS LOCATED. 15. IF FINISHES (E.G., PLASTIC LAMINATE, FLOOR OR CEILING TILE, CARPET, CERAMIC TILE, PAINT, STAIN, ETC.) ARE INCLUDED IN T HE WORK, SAMPLES OF THOSE FINISH MATERIALS WILL BE FURNISHED TO VA MEDICAL CENTER FOR ITS SELECTION OF THE COLOR/PATTERN OF THOSE FINISHES.

Drawing Title

Approved: Project Director

Project Title

Date

Location

Checked

Building Number

Project Number

Drawing Number

Drawn

Dwg. ofRevisions: Date

CONSULTANTS: ARCHITECT:

Facilities

Management on e eig ht h inc h on e fo ot th re e inc he s = o ne fo ot

6"

6" on e an d on e ha lf i nc he s = o ne fo ot on e inc h on e fo ot

6" 6" th re e qu ar te rs in ch o ne fo ot on e ha lf i nc h on e fo ot th re e eig ht hs in ch o ne fo ot on e qu ar te r i nc h on e fo ot

VA FORM 08-6231, OCT 1978

1 2 3 4 5 6 87 9

F

E

D

C

B

A

97 8654321

Services

MG PROJECT #

GAMMA CAMERA RM 6503E/F

MANHATTAN, VAMC

MANHATTAN VA MEDICAL CENTER

423 EAST 23RD STREET

NEW YORK, NEW YORK 6

M.E.P. ENGINEER:M.E.P. ENGINEER:

777 SUNRISE HWY, STE 300

LYNBROOK, NY 11563

516 561 5922 WWW.BEPC.US

BECKER ENGINEERING, PC STCETIC HRA

M G NEW YORK

MICHAEL J. GADALETA, R.A. A.I.A. N.Y. LIC.: 17474 N.J. LIC.: 8935

11 BROADWAY, SUITE 860 NEW YORK, N.Y. 10004

212 674 8456 MGNEWYORKARCHITECTS.COM

LANDMARKS & PRESERVATION

DESIGN & PLANNING

ARCHITECTURE, HEALTH CARE,

LIFE SAFETY PLAN - 6TH FLOOR

02 22 2023 AMG 2

A-001.00

630-CSI-102

2019-63

A-001

N.T.S.

LIFE SAFETY PLAN - 6TH FLOOR

AREA OF WORK

Project Title

Date

Location

Checked

Building Number

Project Number

Drawing Number

Drawn

Dwg. ofRevisions: Date

CONSULTANTS: ARCHITECT:

Facilities

Management on e eig ht h inc h on e fo ot th re e inc he s = o ne fo ot

6"

6" on e an d on e ha lf i nc he s = o ne fo ot on e inc h on e fo ot

6" 6" th re e qu ar te rs in ch o ne fo ot on e ha lf i nc h on e fo ot th re e eig ht hs in ch o ne fo ot on e qu ar te r i nc h on e fo ot

VA FORM 08-6231, OCT 1978

1 2 3 4 5 6 87 9

F

E

D

C

B

A

97 8654321

Services

MG PROJECT #

GAMMA CAMERA RM 6503E/F

MANHATTAN, VAMC

MANHATTAN VA MEDICAL CENTER

423 EAST 23RD STREET

NEW YORK, NEW YORK 6

M.E.P. ENGINEER:M.E.P. ENGINEER:

777 SUNRISE HWY, STE 300

LYNBROOK, NY 11563

516 561 5922 WWW.BEPC.US

BECKER ENGINEERING, PC STCETIC HRA

M G NEW YORK

MICHAEL J. GADALETA, R.A. A.I.A. N.Y. LIC.: 17474 N.J. LIC.: 8935

11 BROADWAY, SUITE 860 NEW YORK, N.Y. 10004

212 674 8456 MGNEWYORKARCHITECTS.COM

LANDMARKS & PRESERVATION

DESIGN & PLANNING

ARCHITECTURE, HEALTH CARE,

INFECTION CONTROL PLAN

02 22 2023 AMG 3

A-002.00

630-CSI-102

2019-63

A-002

SCALE: 1/2" = 1'-0"

INFECTION CONTROL PLAN AT ROOM 6503E / 6503F

AutoCAD SHX Text

PROJECT AREA LIMIT

AutoCAD SHX Text

WALK-OFF MAT

AutoCAD SHX Text M

AutoCAD SHX Text NOTE: 1. PROVIDE TAPE AND PLASTIC SHEET PROTECTIONS AT ANY WALL OR DOOR PENETRATIONS IN ACTIVE CONSTRUCTION AREAS TO PREVENT CONTAMINATION OF ADJACENT OCCUPIED SPACES AT ALL TIMES. ALL CONSTRUCTION DOORS MUST BE PROVIDED WITH SELF-CLOSING DOOR HARDWARE DURING CONSTRUCTION PROCESS 2. BASED ON THE PROJECT SCHEDULE, OFF-HOUR CONSTRUCTION MAY BE REQUIRED. ANY WORK OCCURRING OFF-HOURS SHALL BE COORDINATED IN ADVANCE WITH THE VA. 3. CONTRACTOR SHALL PROVIDE HEPA EQUIPPED AIR FILTRATION UNITS TO MAINTAIN NEGATIVE PRESSURE AND TO EXHAUST THE WORK SITE DURING CONSTRUCTION. CONTRACTOR SHALL PROVIDE REINFORCED FLEXIBLE DUCT TO EXHAUST THE WORK SITE IN A MANNER WHICH IS SAFE AND APPROVED BY THE RESIDENT ENGINEER.

AutoCAD SHX Text

LEGEND:

AutoCAD SHX Text

TEMPORARY PLASTIC DUST BARRIER

AutoCAD SHX Text

NUCLEAR ROOM 6503E

AutoCAD SHX Text C.H. +8'-11"

AutoCAD SHX Text

INJECTION ROOM 6503F

AutoCAD SHX Text C.H. +8'-11"

AutoCAD SHX Text

APPOINTMENT ROOM 6505A

AutoCAD SHX Text ±10'-2"

AutoCAD SHX Text ±10'-2"

AutoCAD SHX Text

FILM PROJECTION 6517

AutoCAD SHX Text

DEXA ROOM 6503D

AutoCAD SHX Text

CORRIDOR 6503

AutoCAD SHX Text

CORRIDOR 6522

AutoCAD SHX Text

CORRIDOR

AutoCAD SHX Text M

AutoCAD SHX Text SEAL EXIST. DOOR WITH HEAVY DUTY PLASTIC FOR AIR TIGHT SEAL. PROVIDE TEMPORARY DUST BARRIER DURING DOOR REMOVAL

AutoCAD SHX Text PROVIDE DUST MAT (BOTH SIDES) AND ZIPPERED DUST BARRIER FOR CONSTRUCTION DOOR. ALL CONSTRUCTION DOORS NOT SEALED TO BE PROVIDED WITH SELF-CLOSING HARDWARE AND STOREROOM LOCK FUNCTION DURING THE CONSTRUCTION PROCESS

AutoCAD SHX Text

EXIST. 30 MIN RATED SMOKE BARRIER

AutoCAD SHX Text PROVIDE TEMPORARY DUST PARTITION TO WORK AREA AND NEW 3'-0"x7'-0" CONSTRUCTION DOOR; 3-5/8" METAL STUD TIGHT TO UNDERSIDE OF EXISTING CEILING, TAPE AND SPACKLE ONE SIDE.

AutoCAD SHX Text M

AutoCAD SHX Text

TEMPORARY CONSTRUCTION WALL

AutoCAD SHX Text

EXISTING MED GAS

AutoCAD SHX Text

EXISTING MED GAS

AutoCAD SHX Text

PROVIDE NEGATIVE PRESSURE MONITOR AT NEW CONSTRUCTION DOOR - SEE NOTE 3

AutoCAD SHX Text EXISTING SMOKE BARRIER WALL TO REMAIN SEALED AT ALL TIMES. DAILY CHECKS MUST BE CONDUCTED AND ANY UNSEALED PENETRATIONS MUST BE FIRE STOPPED

AutoCAD SHX Text N.I.C.

AutoCAD SHX Text N.I.C.

AutoCAD SHX Text 5'-0"

AutoCAD SHX Text 5'-0"

AutoCAD SHX Text CONTRACTOR TO INSTALL 1-HR RATED CEILING BETWEEN TEMPORARY PARTITION AND AREA OF WORK

AutoCAD SHX Text

TYPE

AutoCAD SHX Text "A"

AutoCAD SHX Text

INFECTION CONTROL RISK ASSESSMENT

AutoCAD SHX Text

MIXED OF PRECAUTIONS FOR CONSTRUCTION & RENOVATION

AutoCAD SHX Text

TYPE

AutoCAD SHX Text "B"

AutoCAD SHX Text

TYPE

AutoCAD SHX Text "C"

AutoCAD SHX Text

TYPE

AutoCAD SHX Text "D"

AutoCAD SHX Text

GROUP 1:

AutoCAD SHX Text

LOW RISK

AutoCAD SHX Text

PATIENT RISK GROUP

AutoCAD SHX Text

GROUP 2:

AutoCAD SHX Text

MEDIUM RISK

AutoCAD SHX Text

GROUP 3:

AutoCAD SHX Text

HIGH RISK

AutoCAD SHX Text

GROUP 4:

AutoCAD SHX Text

HIGHEST RISK

AutoCAD SHX Text

PATIENT RISK

AutoCAD SHX Text

GROUP

AutoCAD SHX Text

CONSTRUCTION PROJECT TYPE

AutoCAD SHX Text

LOW RISK GROUP

AutoCAD SHX Text

TYPE "A"

AutoCAD SHX Text

MEDIUM RISK GROUP

AutoCAD SHX Text

HIGH RISK GROUP

AutoCAD SHX Text

HIGHEST RISK GROUP

AutoCAD SHX Text I

AutoCAD SHX Text I

AutoCAD SHX Text I

AutoCAD SHX Text

II

AutoCAD SHX Text

TYPE "B"

AutoCAD SHX Text

II

AutoCAD SHX Text

II

AutoCAD SHX Text

II

AutoCAD SHX Text

III / IV

AutoCAD SHX Text

TYPE "C"

AutoCAD SHX Text

II

AutoCAD SHX Text

III

AutoCAD SHX Text

III / IV

AutoCAD SHX Text

III / IV

AutoCAD SHX Text

TYPE "D"

AutoCAD SHX Text

III / IV

AutoCAD SHX Text

IV

AutoCAD SHX Text

IV

AutoCAD SHX Text

IV

AutoCAD SHX Text

%%UNOTE:

AutoCAD SHX Text

CLASS

AutoCAD SHX Text "I"

AutoCAD SHX Text

DESCRIPTION OF REQUIRED INFECTION CONTROL PRECAUTIONS BY CLASS

AutoCAD SHX Text

CLASS "II"

AutoCAD SHX Text

DURING CONSTRUCTION PROJECT

AutoCAD SHX Text

UPON COMPLETION OF PROJECT

AutoCAD SHX Text

CLASS

AutoCAD SHX Text

"III"

AutoCAD SHX Text

CLASS

AutoCAD SHX Text

"IV"

AutoCAD SHX Text

%%UNOTE:

AutoCAD SHX Text

* EMERGENCY ROOM * POST ANESTHESIA CARE UN. * LABOR AND DELIVERY * PEDIATRICS * ADMISSION / DISCHARGE * LABORATORIES (SPECIMEN) * AMBULATORY SURGERY * PHARMACY * RECOVERY ROOM * SURGICAL UNITS * INPATIENT UNITS (NOT OTHERWISE SPECIFIED) AT ALL AEHN LOCATIONS.

AutoCAD SHX Text

* ANY AREA CARING FOR IMMUNOCOMPROMISED PATIENT * ANESTHESIA AND PUMP AREA * CENTRAL EQUIPMENT / STERILE SUPPLY * CARDIAC CATH LAB & ANGIOGRAPHY AREA * INTERVENTIONAL RADIOLOGY * SPD * CRITICAL CARE & INTENSIVE CARE UNITS * MEDICAL UNIT * NEGATIVE PRESSURE ISOLATION ROOMS * RADIOLOGY/ ONCOLOGY(INPATIENT / OUTP.) * OPERATING ROOMS INCL. LABOR & DELIV. * TRANSPLANT - INPATIENT / OUTPATIENT * DIALYSIS * PHARMACY ADMIXTURE * NEWBORN NURSERIES, INCLUDING NICU

AutoCAD SHX Text IT IS THE GENERAL CONTRACTOR RESPONSIBILITY TO PROVIDE THE FOLLOWING INFECTION CONTROL PRECAUTIONS DEPENDING UPON THE AREA CLASS DESIGNATION

AutoCAD SHX Text INFECTION CONTROL APPROVAL WILL BE REQUIRED WHEN THE CONSTRUCTION ACTIVITY AND RISK LEVEL INDICATE THAT [CLASS "III"] OR [CLASS "IV"] CONTROL PROCEDURES ARE NECESSARY

AutoCAD SHX Text 1 - EXECUTE WORK BY METHODS TO MINIMIZE RAISING DUST FROM CONSTRUCTION OPERATIONS. 2 - IMMEDIATELY REPLACE A CEILING TILE DISPLACED FOR VISUAL INSPECTION.

AutoCAD SHX Text 1 - PROVIDE ACTIVE MEANS TO PREVENT AIRBORNE DUST FROM DISPERSING INTO ATMOSPHERE. 2 - WATER MIST WORK SURFACES TO CONTROL DUST WHILE CUTTING 3 - SEAL UNUSED DOORS WITH DUCT TAPE 4 - BLOCK OFF AND SEAL AIR VENTS 5 - PLACE DUST MAT AT ENTRANCE AND EXIT OF WORK AREA 6 - REMOVE OR ISOLATE HVAC SYSTEM IN AREAS WHERE WORK IS BEING PERFORMED

AutoCAD SHX Text 1 - REMOVE OR ISOLATE HVAC SYSTEM IN AREA WHERE WORK IS BEING DONE TO PREVENT CONTAMINATION OF DUCT SYSTEM 2 - COMPLETE ALL CRITICAL BARRIERS I.E. SHEETROCK, PLYWOOD, PLASTIC, TO SEAL AREA FROM NON-WORK AREA OR IMPLEMENT CONTROL CUBE METHOD (CART WITH PLASTIC COVERING AND SEALED CONNECTION TO WORK SITE WITH HEPA VACUUM FOR VACUUMING PRIOR TO EXIT) BEFORE CONSTRUCTION BEGINS. 3 - MAINTAIN NEGATIVE AIR PRESSURE WITHIN WORK SITE UTILIZING HEPA EQUIPPED AIR FILTRATIONS UNITS. 4 - CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT IN TIGHTLY COVERED CONTAINERS. COVER TRANSPORT RECEPTACLES OR CARTS. TAPE COVERING UNLESS SOLID LID.

AutoCAD SHX Text 1 - ISOLATE HVAC SYSTEM IN AREA WHERE WORK IS BEING DONE TO PREVENT CONTAMINATION OF DUCT SYSTEM. 2 - COMPLETE ALL CRITICAL BARRIERS I.E. SHEETROCK, PLYWOOD, PLASTIC, TO SEAL AREA FROM NON-WORK AREA OR IMPLEMENT CONTROL CUBE METHOD (CART WITH PLASTIC COVERING AND SEALED CONNECTION TO WORK SITE WITH HEPA VACUUM FOR VACUUMING PRIOR TO EXIT) BEFORE CONSTRUCTION BEGINS. 3 - MAINTAIN NEGATIVE AIR PRESSURE WITHIN WORK SITE UTILIZING HEPA EQUIPPED AIR FILTRATIONS UNITS. 4 - SEAL HOLES, PIPES, CONDUITS, AND PUNCTURES APPROPRIATELY. 5 - CONSTRUCTION ANTEROOM AND REQUIRE ALL PERSONNEL TO PASS THROUGH THIS ROOM SO THEY CAN BE VACUUMED USING A HEPA VACUUM CLEANER BEFORE LEAVING WORK SITE OR THEY CAN WEAR CLOTHES OR PAPER COVERALLS THAT ARE REMOVED EACH TIME THEY LEAVE THE WORK SITE. 6 - ALL PERSONNEL ENTERING WORK SITE ARE REQUIRED TO WEAR SHOE COVERS. SHOE COVERS MUST BE CHANGED EACH TIME THE WORKER EXITS THE WORK AREA. 7 - DO NOT REMOVE BARRIERS FROM WORK AREA UNTIL COMPLETED PROJECT IS INSPECTED BY THE OWNER'S SAFETY DEPARTMENT AND INFECTION CONTROL DEPARTMENT AND THOROUGHLY CLEANED BY THE OWNER'S ENVIRONMENTAL SERVICES DEPARTMENT.

AutoCAD SHX Text 1 - WIPE WORK SURFACES WITH DISINFECTANT 2 - CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT IN TIGHTLY COVERED CONTAINERS. 3 - WET MOP AND/ OR VACUUM WITH HEPA FILTER. 4 - REMOVE ISOLATION OF HVAC SYSTEM IN AREAS WHERE WORK IS BEING PERFORMED.

AutoCAD SHX Text 1 - DO NOT REMOVE BARRIERS FROM WORK AREA UNTIL COMPLETED PROJECT IS INSPECTED BY THE OWNER'S SAFETY DEPARTMENT AND INFECTION CONTROL DEPARTMENT AND THOROUGHLY CLEANED BY THE OWNER'S ENVIRONMENTAL SERVICES DEPARTMENT. 2 - REMOVE BARRIER MATERIALS CAREFULLY TO MINIMIZE SPREADING OF DIRT AND DEBRIS ASSOCIATED WITH CONSTRUCTION. 3 - VACUUM WORK AREA WITH HEPA FILTERED VACUUMS. 4 - WET MOP AREA WITH DISINFECTANT. 5 - REMOVE ISOLATION OF HVAC SYSTEM IN AREAS WHERE WORK IS BEING PERFORMED.

AutoCAD SHX Text 1 - REMOVE BARRIER MATERIAL CAREFULLY TO MINIMIZE SPREADING OF DIRT AND DEBRIS ASSOCIATED WITH CONSTRUCTION. 2 - CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT IN TIGHTLY COVERED CONTAINERS. 3 - COVER TRANSPORT RECEPTACLES OR CARTS. TAPE COVERING UNLESS SOLID LID. 4 - VACUUM WORK AREA WITH HEPA FILTERED VACUUMS. 5 - WET MOP AREA WITH DISINFECTANT. 6 - REMOVE ISOLATION OF HVAC SYSTEM IN AREAS WHERE WORK IS BEING PERFORMED.

AutoCAD SHX Text INSPECTION AND NON-INVASIVE ACTIVITIES (INCLUDED, BUT IS NOT LIMITED TO): * REMOVAL OF CEILING TILES FOR VISUAL INSPECTION LIMITED TO 1 TILE PER 50 SQUARE FEET. * PAINTING (BUT NOT SANDING) * WALL COVERING, ELECTRICAL TRIM WORK, MINOR PLUMBING, AND ACTIVITIES WHICH DO NOT GENERATE DUST OR REQUIRE CUTTING OF WALLS OR ACCESS TO CEILING OTHER THAN FOR VISUAL INSPECTION.

AutoCAD SHX Text SMALL SCALE, SHORT DURATION ACTIVITIES WHICH CREATE MINIMAL DUST (INCLUDED, BUT IS NOT LIMITED TO): * INSTALLATION OF TELEPHONE AND COMPUTER CABLING * ACCESS TO CHASE SPACES * CUTTING OF WALLS OR CEILING WHERE DUST MIGRATION CAN BE CONTROLLED

AutoCAD SHX Text WORK THAT GENERATES A MODERATE TO HIGH LEVEL OF DUST OR REQUIRES DEMOLITION OR REMOVAL OF ANY FIXED BUILDING COMPONENTS OR ASSEMBLIES (INCLUDED, BUT IS NOT LIMITED TO): * SANDING OF WALLS FOR PAINTING OR WALL COVERING * REMOVAL OF FLOOR COVERINGS, CEILING TILES AND CASEWORK. * NEW WALL CONSTRUCTION * MINOR DUCT WORK OR ELECTRICAL WORK ABOVE CEILING * MAJOR CABLING ACTIVITIES * ANY ACTIVITY THAT CANNOT BE COMPLETED WITHIN A SINGLE WORK SHIFT

AutoCAD SHX Text MAJOR DEMOLITION AND CONSTRUCTION PROJECTS (INCLUDED, BUT IS NOT LIMITED TO): * ACTIVITIES WHICH REQUIRE CONSECUTIVE WORK SHIFTS * REQUIRES HEAVY DEMOLITION OR REMOVAL OF A COMPLETE CABLING SYSTEM * NEW CONSTRUCTION

AutoCAD SHX Text

* CARDIOLOGY * ECHOCARDIOGRAPHY * ENDOSCOPY - GI * NUCLEAR MEDICINE * PHYSICAL THERAPY * RADIOLOGY / MRI * RESPIRATORY THERAPY * RESPIRATORY CARE (EXCLUDED BRONCHOSCOPY AREA * CAFETERIA * KITCHEN * OUTPATIENT AREAS- CLINICS AND OFFICES (EXCEPTION: TRANSPLANT AND ONCOLOGY)

AutoCAD SHX Text

* OFFICE AREA OFFICE AREA * STORAGE AREA STORAGE AREA * MECHANICAL MECHANICAL SPACES * PUBLIC PUBLIC CORRIDOR

%%USIXTH FLOOR ROOMS 6503D / 6503E / 6503F

CENTRAK CENTRAK

XRAY IN USE

CENTRAK

AP

APT

XRAY IN USE

CENTRAK

T

AP

AP

T

CENTRAK

Drawing Title

Approved: Project Director

Project Title

Date

Location

Checked

Building Number

Project Number

Drawing Number

Drawn

Dwg. ofRevisions: Date

CONSULTANTS: ARCHITECT:

Facilities

Management on e eig ht h inc h on e fo ot th re e inc he s = o ne fo ot

6"

6" on e an d on e ha lf i nc he s = o ne fo ot on e inc h on e fo ot

6" 6" th re e qu ar te rs in ch o ne fo ot on e ha lf i nc h on e fo ot th re e eig ht hs in ch o ne fo ot on e qu ar te r i nc h on e fo ot

VA FORM 08-6231, OCT 1978

1 2 3 4 5 6 87 9

F

E

D

C

B

A

97 8654321

Services

MG PROJECT #

GAMMA CAMERA RM 6503E/F

MANHATTAN, VAMC

MANHATTAN VA MEDICAL CENTER

423 EAST 23RD STREET

NEW YORK, NEW YORK 6

M.E.P. ENGINEER:M.E.P. ENGINEER:

777 SUNRISE HWY, STE 300

LYNBROOK, NY 11563

516 561 5922 WWW.BEPC.US

BECKER ENGINEERING, PC STCETIC HRA

M G NEW YORK

MICHAEL J. GADALETA, R.A. A.I.A. N.Y. LIC.: 17474 N.J. LIC.: 8935

11 BROADWAY, SUITE 860 NEW YORK, N.Y. 10004

212 674 8456 MGNEWYORKARCHITECTS.COM

LANDMARKS & PRESERVATION

DESIGN & PLANNING

ARCHITECTURE, HEALTH CARE,

EXISTING PLANS AT ROOMS 6503E & 6503F

02 22 2023 AMG 4

A-100.00

630-CSI-102

2019-63

A-100

SCALE: 1/2" = 1'-0"

ROOM 6503E / 6503F EXISTING PLAN

A-100

SCALE: 1/2" = 1'-0"

ROOM 6503E / 6503F EXISTING R.C.P.

AutoCAD SHX Text

NUCLEAR ROOM 6503E

AutoCAD SHX Text C.H. +9'-0"

AutoCAD SHX Text

INJECTION ROOM 6503F

AutoCAD SHX Text C.H. +9'-0"

AutoCAD SHX Text

APPOINTMENT ROOM 6505A

AutoCAD SHX Text

EXISTING MED GAS

AutoCAD SHX Text

CORRIDOR

AutoCAD SHX Text ±10'-2"

AutoCAD SHX Text ±10'-2"

AutoCAD SHX Text

FILM PROJECTION 6517

AutoCAD SHX Text

DEXA ROOM 6503D

AutoCAD SHX Text

EXISTING ELECTRICAL CONDUIT

AutoCAD SHX Text C.H. +9'-0"

AutoCAD SHX Text C.H. +8'-0"

AutoCAD SHX Text C.H. +8'-0"

AutoCAD SHX Text

EXISTING 30 MIN-RATED SMOKE BARRIER

AutoCAD SHX Text

EXISTING MED GAS

AutoCAD SHX Text N.I.C.

AutoCAD SHX Text N.I.C.

AutoCAD SHX Text S

AutoCAD SHX Text S

AutoCAD SHX Text S

AutoCAD SHX Text

EXISTING XRAY IN USE SIGN

AutoCAD SHX Text

EXISTING XRAY IN USE SIGN

AutoCAD SHX Text

EXISTING ELECTRICAL CONDUIT

AutoCAD SHX Text

EXISTING MEDICAL AIR, OXYGEN, AND VACUUM

AutoCAD SHX Text

EXISTING SYSTEM MAIN DISCONNECT PANEL

AutoCAD SHX Text S

AutoCAD SHX Text S

AutoCAD SHX Text N.I.C.

AutoCAD SHX Text N.I.C.

AutoCAD SHX Text

SINGLE POLE LIGHT SWITCH

AutoCAD SHX Text

TELEPHONE AND DATA OUTLET

AutoCAD SHX Text

DUPLEX RECEPTACLE

AutoCAD SHX Text

CEILING DIFFUSER

AutoCAD SHX Text

SPRINKLER HEAD

AutoCAD SHX Text

THERMOSTAT

AutoCAD SHX Text

LIGHT FIXTURE

AutoCAD SHX Text

CIRCUIT BREAKER PANEL

AutoCAD SHX Text

ELECTRICAL LEGEND

AutoCAD SHX Text

CEILING MTD CENTRAK SYSTEM

S

FD

Approved: Project Director

Project Title

Date

Location

Checked

Building Number

Project Number

Drawing Number

Drawn

Dwg. ofRevisions: Date

CONSULTANTS: ARCHITECT:

Facilities

Management on e eig ht h inc h on e fo ot th re e inc he s = o ne fo ot

6"

6" on e an d on e ha lf i nc he s = o ne fo ot on e inc h on e fo ot

6" 6" th re e qu ar te rs in ch o ne fo ot on e ha lf i nc h on e fo ot th re e eig ht hs in ch o ne fo ot on e qu ar te r i nc h on e fo ot

VA FORM 08-6231, OCT 1978

1 2 3 4 5 6 87 9

F

E

D

C

B

A

97 8654321

Services

MG PROJECT #

GAMMA CAMERA RM 6503E/F

MANHATTAN, VAMC

MANHATTAN VA MEDICAL CENTER

423 EAST 23RD STREET

NEW YORK, NEW YORK 6

M.E.P. ENGINEER:M.E.P. ENGINEER:

777 SUNRISE HWY, STE 300

LYNBROOK, NY 11563

516 561 5922 WWW.BEPC.US

BECKER ENGINEERING, PC STCETIC HRA

M G NEW YORK

MICHAEL J. GADALETA, R.A. A.I.A. N.Y. LIC.: 17474 N.J. LIC.: 8935

11 BROADWAY, SUITE 860 NEW YORK, N.Y. 10004

212 674 8456 MGNEWYORKARCHITECTS.COM

LANDMARKS & PRESERVATION

DESIGN & PLANNING

ARCHITECTURE, HEALTH CARE,

DEMO PLAN AT ROOMS 6503E & 6503F

02 22 2023 AMG 5

A-101.00

630-CSI-102

2019-63

A-101

SCALE: 1/2" = 1'-0"

ROOM 6503E / 6503F DEMO PLAN

AutoCAD SHX Text CONTRACTOR TO INSPECT ALL AREAS OF ROOM UPON COMPLETION OF DEMOLITION. ALL AREAS OF MISSING FIRE PROTECTION, FLOOR SLAB, OR WALL PENETRATIONS TO BE BROUGHT TO THE ATTENTION OF THE VA

AutoCAD SHX Text CONTRACTOR SHALL PROVIDE HEPA EQUIPPED AIR FILTRATION UNITS TO MAINTAIN NEGATIVE PRESSURE AND TO EXHAUST THE WORK SITE DURING CONSTRUCTION. CONTRACTOR SHALL PROVIDE REINFORCED FLEXIBLE DUCT TO EXHAUST THE WORK SITE IN A MANNER WHICH IS SAFE AND APPROVED BY THE RESIDENT ENGINEER.

AutoCAD SHX Text NO CHOPPING OR CHIPPING OF THE CONCRETE SLAB WILL BE PERMITTED; CORE DRILL ONLY. CONTRACTOR TO X-RAY FLOOR SLAB PRIOR TO ANY SLAB PENETRATION OR CORE DRILLING

AutoCAD SHX Text

APPOINTMENT ROOM 6505A

AutoCAD SHX Text

EXISTING MED GAS TO REMAIN

AutoCAD SHX Text ±10'-2"

AutoCAD SHX Text ±10'-2"

AutoCAD SHX Text

FILM PROJECTION 6517

AutoCAD SHX Text

CORRIDOR 6522

AutoCAD SHX Text

DEXA ROOM 6503D

AutoCAD SHX Text

NUCLEAR ROOM 6503E

AutoCAD SHX Text C.H. +9'-0"

AutoCAD SHX Text

INJECTION ROOM 6503F

AutoCAD SHX Text C.H. +8'-11"

AutoCAD SHX Text EXIST. DIAGNOSTIC EQUIPMENT TO BE REMOVED AS DIRECTED BY THE VA. REMOVE EXISTING SLAB-EMBEDDED FLOOR ANCHORS AS REQUIRED.

AutoCAD SHX Text

REMOVE EXIST. SLAB-EMBEDDED FLOOR ANCHORS

AutoCAD SHX Text EXIST. VCT FLOOR AND BASE TO BE REMOVED. PREP FLOOR IN ACCORDANCE WITH PRE- INSTALLATION MANUAL SPECS

AutoCAD SHX Text EXIST. NON-LOAD BEARING PARTITION TO BE REMOVED. PATCH WALL AS REQUIRED. RETURN WALL-MOUNTED CASEWORK TO VA

AutoCAD SHX Text

EXISTING FLOOR RAIL TO BE REMOVED

AutoCAD SHX Text

EXIST DOOR AND FRAME TO BE REMOVED

AutoCAD SHX Text

EXISTING SINK TO BE REMOVED. CAP PLUMBING AT SOURCE

AutoCAD SHX Text

REMOVE EXIST. STORAGE CABINET AND RETURN TO VA

AutoCAD SHX Text UPON REMOVAL OF EXIST. EQUIPMENT, BASE PLATES, ANCHORS, FILL ALL REMAINING DEPRESSIONS WITH SELF-LEVELING CEMENTITIOUS NDERLAYMENT (ARDEX K15 OR EQUAL)

AutoCAD SHX Text EXIST. COUNTERTOP, BASE AND WALL CABINETS, AND STORAGE TO BE REMOVED AND RETURNED TO VA

AutoCAD SHX Text

EXISTING SINK TO REMAIN

AutoCAD SHX Text

EXIST. DOOR AND FRAME TO BE REMOVED.

AutoCAD SHX Text EXIST. NON-LOAD BEARING PARTITION TO BE REMOVED. PATCH WALL AS REQUIRED. RETURN WALL-MOUNTED CASEWORK AND IMAGING TO VA

AutoCAD SHX Text

EXISTING SINK TO BE REMOVED. CAP PLUMBING BEHIND NEW GYP BD.

AutoCAD SHX Text

EXIST. DOOR AND FRAME TO BE REMOVED

AutoCAD SHX Text PROVIDE OPENING IN EXIST. CORRIDOR WALL FOR NEW 3'-0"x7'-0" DOOR AND FRAME

AutoCAD SHX Text ENLARGE OPENING IN EXIST. CORRIDOR WALL FOR NEW 6'-0" WIDE DOUBLE-DOOR AND NEW FRAME

AutoCAD SHX Text

ALL FURNISHING TO BE RETURNED TO THE VA

AutoCAD SHX Text

ALL DEXA EQUIPMENT TO BE REMOVED BY VA

AutoCAD SHX Text

EXISTING MED GAS TO REMAIN

AutoCAD SHX Text

EXISTING LEAD LINED GYP BD. CORRIDOR WALL TO REMAIN

AutoCAD SHX Text PROVIDE TEMPORARY DUST PARTITION TO WORK AREA AND NEW 3'-0"x7'-0" CONSTRUCTION DOOR; 3-5/8" METAL STUD TIGHT TO UNDERSIDE OF EXISTING CEILING, TAPE AND SPACKLE ONE SIDE.

AutoCAD SHX Text N.I.C.

AutoCAD SHX Text N.I.C.

AutoCAD SHX Text M

AutoCAD SHX Text M

AutoCAD SHX Text

CORRIDOR 6503

AutoCAD SHX Text 5'-0"

AutoCAD SHX Text 5'-0"

AutoCAD SHX Text EXISTING GYP BD. TO BE REMOVED AT ROOM SIDE (TYP.) TO PROVIDE NEW LEAD LINED WALL SEE PROPOSED PLAN

AutoCAD SHX Text

EXISTING LEAD LINED GYP BD. CORRIDOR WALL TO REMAIN

AutoCAD SHX Text

LEGEND:

AutoCAD SHX Text

WALK-OFF MAT

AutoCAD SHX Text M

AutoCAD SHX Text

TEMPORARY PLASTIC DUST BARRIER SEAL

AutoCAD SHX Text

EXISTING TO BE REMOVED

AutoCAD SHX Text

EXISTING WALL TO REMAIN

EXISTING 30 MIN RATED SMOKE BARRIER TO REMAIN UNDISTURBED

CENTRAK CENTRAK

CENTRAK

AP

APT

CENTRAK

T

AP

AP

T

CENTRAK

Drawing Title

Approved: Project Director

Project Title

Date

Location

Checked

Building Number

Project Number

Drawing Number

Drawn

Dwg. ofRevisions: Date

CONSULTANTS: ARCHITECT:

Facilities

Management on e eig ht h inc h on e fo ot th re e inc he s = o ne fo ot

6"

6" on e an d on e ha lf i nc he s = o ne fo ot on e inc h on e fo ot

6" 6" th re e qu ar te rs in ch o ne fo ot on e ha lf i nc h on e fo ot th re e eig ht hs in ch o ne fo ot on e qu ar te r i nc h on e fo ot

VA FORM 08-6231, OCT 1978

1 2 3 4 5 6 87 9

F

E

D

C

B

A

97 8654321

Services

MG PROJECT #

GAMMA CAMERA RM 6503E/F

MANHATTAN, VAMC

MANHATTAN VA MEDICAL CENTER

423 EAST 23RD STREET

NEW YORK, NEW YORK 6

M.E.P. ENGINEER:M.E.P. ENGINEER:

777 SUNRISE HWY, STE 300

LYNBROOK, NY 11563

516 561 5922 WWW.BEPC.US

BECKER ENGINEERING, PC STCETIC HRA

M G NEW YORK

MICHAEL J. GADALETA, R.A. A.I.A. N.Y. LIC.: 17474 N.J. LIC.: 8935

11 BROADWAY, SUITE 860 NEW YORK, N.Y. 10004

212 674 8456 MGNEWYORKARCHITECTS.COM

LANDMARKS & PRESERVATION

DESIGN & PLANNING

ARCHITECTURE, HEALTH CARE,

DEMO R.C.P AT ROOMS 6503E & 6503F

02 22 2023 AMG 6

A-102.00

630-CSI-102

2019-63

A-102

SCALE: 1/2" = 1'-0"

ROOM 6503E / 6503F DEMO R.C.P.

AutoCAD SHX Text S

AutoCAD SHX Text S

AutoCAD SHX Text REMOVE THE EXISTING DIAGNOSTIC IMAGING SYSTEM'S MAIN DISCONNECT PANEL. REMOVE THE EXISTING CONDUCTORS BACK TO PANEL AP-L6BC IN ELECTRICAL CLOSET 6543 ALL EXISTING ELECTRICAL DEVICES AT THIS WALL TO BE REMOVED AND RETURNED BACK TO PANEL

AutoCAD SHX Text

EXISTING XRAY IN USE SIGN TO BE REMOVED AND RETURNED TO THE VA

AutoCAD SHX Text S

AutoCAD SHX Text EXISTING MEDICAL AIR, OXYGEN, AND VACUUM TO BE REMOVED. REMOVE ELECTRICAL DEVICES BACK TO SOURCE

AutoCAD SHX Text

REMOVE ANY ABANDONED SURFACE- MTD OR EXPOSED ELECTRICAL CONDUITS. V.I.F.

AutoCAD SHX Text EXISTING 2'x2' LIGHTS AND DOWNLIGHTS AND ASSOCIATED WIRING TO BE REMOVED THROUGHOUT BACK TO FIRST JUNCTION BOX (TYP.) RESECURE EXISTING ELECTRICAL JUNCTION BOXES

AutoCAD SHX Text EXISTING SPRINKLER HEADS TO BE REMOVED THROUGHOUT AND REPLACED WITH NEW TO ALIGN WITH NEW CEILING GRID AS REQ'D (TYP.)

AutoCAD SHX Text

EXISTING XRAY IN USE SIGN TO BE REMAIN

AutoCAD SHX Text EXIST. CEILING MTD CENTRAK MONITORING SYSTEM TO BE REMOVED AND STORED FOR RE-INSTALLATION. COORDINATE WITH HOSPITAL STAFF (TYP.)

AutoCAD SHX Text

EXISTING CEILING GRID AND TILES TO BE REMOVED

AutoCAD SHX Text

EXISTING DIFFUSERS AND DUCTWORK ABOVE TO BE REMOVED. SEE MECHANICAL DRAWINGS

AutoCAD SHX Text EXISTING CEILING DIFFUSERS AND DUCTWORK ABOVE TO BE REMOVED. SEE MECHANICAL DRAWINGS.

AutoCAD SHX Text EXISTING 2x4 LIGHTS TO BE REMOVED

AutoCAD SHX Text

EXISTING SPRINKLER HEADS TO REMOVED AND REPLACED WITH NEW. SEE PROPOSED PLAN

AutoCAD SHX Text

EXISTING CEILING GRID AND TILES TO BE REMOVED

AutoCAD SHX Text S

AutoCAD SHX Text S

AutoCAD SHX Text

EXISTING RETURN GRILLE TO BE REMOVED AND REPLACED IN NEW ROOM. SEE PROPOSED PLAN

AutoCAD SHX Text EXISTING CEILING DIFFUSERS TO BE REPLACED. SEAL TO MINIMIZE CONTAMINATION AND DUST CONTAINMENT

AutoCAD SHX Text N.I.C.

AutoCAD SHX Text N.I.C.

AutoCAD SHX Text CONTRACTOR TO INSTALL 1-HR RATED CEILING BETWEEN TEMPORARY PARTITION AND AREA OF WORK

AutoCAD SHX Text

EXISTING ELECTRICAL DEVICES AND OUTLETS TO REMAIN UNLESS OTHERWISE NOTED

AutoCAD SHX Text

SINGLE POLE LIGHT SWITCH

AutoCAD SHX Text

TELEPHONE AND DATA OUTLET

AutoCAD SHX Text

DUPLEX RECEPTACLE

AutoCAD SHX Text

CEILING DIFFUSER

AutoCAD SHX Text

SPRINKLER HEAD

AutoCAD SHX Text

THERMOSTAT

AutoCAD SHX Text

LIGHT FIXTURE

AutoCAD SHX Text

CIRCUIT BREAKER PANEL

AutoCAD SHX Text

ELECTRICAL LEGEND

AutoCAD SHX Text

CEILING MTD CENTRAK SYSTEM

S

A-202A-201

A-201

A-202

A-200

A-200

FD

A-200

ITEM DESCRIPTION

(GE SUPPLIED / CONTRACTOR INSTALLED)

CT GANTRY BASEPLATE

NM GANTRY BASEPLATE

TABLE ANCHOR PLATE

COLLIMATOR EXCHANGE PLATE

SWING PLATE

3 5/8" METAL RUNNER

SECURED TO SLAB

PROVIDE 1 LAYER OF 5/8" LEAD

LINED (1/16") GYP. BD. BOTH SIDES

FROM FLOOR TO HEIGHT OF 7'

3 5/8" METAL STUDS

@ 16" O.C.

SOUND ATTENUATION BATT.

1 HR FIRE RATING

ANSI/UL 263 DESIGN NO. U465

43-44 STC SOUND TRANS.

SCALE: 1" = 1'-0"

ACOUSTICAL

CEILING TILE

EXISTING CONCRETE SLAB

NEW METAL STUD WALL

3 5/8" METAL RUNNER

SECURED TO SLAB

3 5/8" METAL STUDS

@ 16" O.C.

SOUND ATTENUATION BATT.

1 HR FIRE RATING

ANSI/UL 263 DESIGN NO. U465

43-44 STC SOUND TRANS.

SCALE: 1" = 1'-0"

PROVIDE 1 LAYER OF

5/8" GYP. BD. BOTH SIDES

ACOUSTICAL

CEILING TILE

EXISTING CONCRETE SLAB

NEW LEAD LINED WALL

3 5/8" METAL RUNNER SECURED TO

SLAB

PROVIDE 1 LAYER OF 5/8" LEAD

LINED (1/16") GYP. BD. AT NUCLEAR

ROOM SIDE FROM FLOOR TO

HEIGHT OF 7'

3 5/8"…