This document is a Solicitation for a federal contract opportunity to design and construct site preparation for a new Nuclear Medicine GE SPECT CT system at the Department of Veterans Affairs Medical Center in New York, NY.
The key details are:
- Solicitation Number: 36C24224R0083
- Project Name: Z1DA--630-CSI-120 NY SPECT CT SITE PREP DESIGN BUILD
- Performance Period: 365 Calendar Days
- Scope of Work: Provide turnkey services to design and construct the site preparation for a new Nuclear Medicine GE SPECT CT system, including demolition, HVAC upgrades, electrical, plumbing, and other renovations to a 1,000 square foot radiology space. Work must meet VA design guidelines, manufacturer specifications, and be completed by August 2025.
- Government Agency: Department of Veterans Affairs, Veterans Health Administration, Veterans Integrated Service Network 2
- No security accreditation is required, but contractor employees must complete VA privacy training.
- The contractor must utilize the VA's Autodesk Build construction management platform for project collaboration and submittals.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24224R0083 0002.pdf | ||
| 36C24224R0083 0001.docx | DOCX document | |
| 013200 Construction Documentation.docx | DOCX document | |
| 237413 Packaged Outdoor Central Station AHU.docx | DOCX document | |
| 01 35 26 Safety Requirements.docx | DOCX document | |
| 134900 Radiation Protection.docx | DOCX document | |
| ProductivityNow Contractors Access Instructions.pdf | ||
| NUC-M037844-FIN-02-A.pdf | ||
| VA 2020 Imaging Services Design Guide.pdf | ||
| P14 EVALUATION FACTORS AND SCORECARD FOR DESIGN-BUILD.pdf | ||
| 233100 HVAC Ducts and Casings.docx | DOCX document | |
| S02 ADDITIONAL INSERTS.pdf | ||
| Attachment A - Privacy Training for Personnel without Access to VA Computer.pdf | ||
| 01 00 00 General Requirements.docx | DOCX document | |
| 36C24224R0083_2.docx | DOCX document | |
| 00 11 21 Design Build Spec 630-CSI-120.docx | DOCX document | |
| S02 VA ID PACKAGE.pdf | ||
| 238400 Humidity Control Equipment.docx | DOCX document | |
| S02 Participation Goals for Minorities and Females.pdf | ||
| S02 DESIGN BUILD RFP SOL.pdf | ||
| VA 2023 HVAC Design Manual.pdf |
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GENERAL NOTES
DEMOLITION NOTES
SAFETY NOTES
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building Number
Project Number
Drawing Number
Drawn
Dwg. ofRevisions: Date
CONSULTANTS: ARCHITECT:
Facilities
Management on e eig ht h inc h on e fo ot th re e inc he s = o ne fo ot
6"
6" on e an d on e ha lf i nc he s = o ne fo ot on e inc h on e fo ot
6" 6" th re e qu ar te rs in ch o ne fo ot on e ha lf i nc h on e fo ot th re e eig ht hs in ch o ne fo ot on e qu ar te r i nc h on e fo ot
VA FORM 08-6231, OCT 1978
1 2 3 4 5 6 87 9
F
E
D
C
B
A
97 8654321
Services
MG PROJECT #
GAMMA CAMERA RM 6503E/F
MANHATTAN, VAMC
MANHATTAN VA MEDICAL CENTER
423 EAST 23RD STREET
NEW YORK, NEW YORK
MANHATTAN
DEPARTMENT OF VETERANS AFFAIRS
421 EAST 23RD STREET
NEW YORK, NEW YORK
NM/CT RM 6503E & 6503F
MEDICAL CENTER
PROJECT # 630-CSI-102
M.E.P. ENGINEER:M.E.P. ENGINEER:
777 SUNRISE HWY, STE 300
LYNBROOK, NY 11563
516 561 5922 WWW.BEPC.US
BECKER ENGINEERING, PC STCETIC HRA
M G NEW YORK
MICHAEL J. GADALETA, R.A. A.I.A. N.Y. LIC.: 17474 N.J. LIC.: 8935
11 BROADWAY, SUITE 860 NEW YORK, N.Y. 10004
212 674 8456 MGNEWYORKARCHITECTS.COM
LANDMARKS & PRESERVATION
DESIGN & PLANNING
ARCHITECTURE, HEALTH CARE,
GENERAL REQUIREMENTS
CODES, STANDARDS, AND EXECUTIVE ORDERS
PURPOSE: THE PUBLIC BUILDINGS AMENDMENT ACT OF 1988, PUBLIC LAW (PUB. L.) 100-678 REQUIRES FEDERAL AGENCIES TO FOLLOW NATIONAL RECOGNIZED "MODEL" BUILDING CODES. THE FEDERAL PARTICIPATION IN THE DEVELOPMENT AND USE OF VOLUNTARY STANDARDS, OFFICE OF MANAGEMENT AND BUDGET (OMB) CIRCULAR A-119, REQUIRES ALL EXECUTIVE AGENCIES TO RELY ON VOLUNTARY STANDARDS, BOTH DOMESTIC AND INTERNATIONAL, WHENEVER FEASIBLE, AND TO
PARTICIPATE IN VOLUNTARY STANDARD BODIES.
GENERAL: VA HAS ADOPTED THE LATEST EDITION OF THE FOLLOWING CODES AND STANDARDS AS A MINIMUM FOR ALL PROJECTS PERFORMED IN THE MODERNIZATION, ALTERATION, ADDITION, OR IMPROVEMENT OF ITS REAL PROPERTY AND THE CONSTRUCTION OF NEW STRUCTURES. VA DESIGN MANUALS AND MASTER SPECIFICATIONS SPECIFY OTHER CODES
AND STANDARDS THAT VA FOLLOWS ON ITS PROJECTS:
· VA DIRECTIVES, DESIGN MANUALS, MASTER SPECIFICATIONS, VA NATIONAL CAD STANDARD APPLICATION GUIDE, AND OTHER GUIDANCE ON THE TECHNICAL INFORMATION LIBRARY (TIL) (HTTP://WWW.CFM.VA.GOV/TIL/).
· INTERNATIONAL BUILDING CODE (IBC) (ONLY WHEN SPECIFICALLY REFERENCED IN VA DESIGN DOCUMENTS, SEE
NOTES BELOW)
· NFPA 101 LIFE SAFETY CODE (SEE NOTES BELOW)
· NFPA NATIONAL FIRE CODES WITH THE EXCEPTION OF NFPA 5000 AND NFPA 900
· OCCUPATIONAL, SAFETY AND HEALTH ADMINISTRATION (OSHA) STANDARDS.
· VA SEISMIC DESIGN REQUIREMENTS, H-18-8
· NATIONAL ELECTRICAL CODE (NEC)
· INTERNATIONAL PLUMBING CODE (IPC)
· SAFETY CODE FOR ELEVATORS AND ESCALATORS, AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME) A 17.1.
· ASME BOILER AND PRESSURE VESSEL CODE
· ASME CODE FOR PRESSURE PIPING
· ARCHITECTURAL BARRIERS ACT ACCESSIBILITY STANDARDS (ABAAS) INCLUDING VA SUPPLEMENT, BARRIER FREE
DESIGN GUIDE (PG-18-13)
· BUILDING CODE REQUIREMENTS FOR REINFORCED CONCRETE, AMERICAN CONCRETE INSTITUTE AND
COMMENTARY (ACI 318)
· MANUAL OF STEEL CONSTRUCTION, LOAD AND RESISTANCE FACTOR DESIGN SPECIFICATIONS FOR STRUCTURAL
STEEL BUILDINGS, AMERICAN INSTITUTE OF STEEL CONSTRUCTION (AISC)
· ENERGY POLICY ACT OF 2005 (EPACT)
· ENERGY STANDARD FOR BUILDINGS EXCEPT LOW-RISE RESIDENTIAL BUILDINGS - ASHRAE 90.1
· DOE INTERIM FINAL RULE: ENERGY CONSERVATION STANDARDS FOR NEW FEDERAL, COMMERCIAL AND MULTI-FAMILY HIGH-RISE RESIDENTIAL BUILDINGS AND NEW LOW-RISE RESIDENTIAL BUILDINGS, 10 CFR PARTS 433, 434 AND 435.
· FEDERAL LEADERSHIP IN HIGH PERFORMANCE AND SUSTAINABLE BUILDINGS: MEMORANDUM OF UNDERSTANDING
(MOU)
· EXECUTIVE ORDER 13423: STRENGTHENING FEDERAL ENVIRONMENTAL, ENERGY, AND TRANSPORTATION
MANAGEMENT.
· THE PROVISIONS FOR CONSTRUCTION AND SAFETY SIGNS. STATED IN THE GENERAL REQUIREMENTS SECTION
01010 OF THE VA MASTER CONSTRUCTION SPECIFICATION.
· VENTILATION FOR ACCEPTABLE INDOOR AIR QUALITY - ASHRAE STANDARD 62.1- 2004.
· SAFETY STANDARD FOR REFRIGERATION SYSTEMS - ASHRAE STANDARD 15 - 2007.
LOCAL CODES: AS AN AGENCY OF THE FEDERAL GOVERNMENT, VA IS NOT SUBJECT TO LOCAL IMPOSITION OF CODE ENFORCEMENT PROCEDURES (DRAWING REVIEWS, BUILDING PERMITS, INSPECTIONS, FEES, ETC.). VA MUST FUNCTION AS THE AUTHORITY HAVING JURISDICTION (AHJ) AND THUS HAS THE RESPONSIBILITY TO GUARD PUBLIC HEALTH AND SAFETY THROUGH ENFORCING ITS ADOPTED CODES. HOWEVER, LOCAL AUTHORITIES SHOULD BE NOTIFIED ABOUT PLANNED PROJECTS AND GIVEN OPPORTUNITY TO REVIEW DRAWINGS PROVIDED THAT VA DOES NOT PAY FOR REVIEW OR
INSPECTION FEES.
NOTES:
1. NFPA 101 PRIMARILY ADDRESSES LIFE SAFETY AND FIRE PROTECTION FEATURES WHILE THE IBC ADDRESSES A WIDE RANGE OF CONSIDERATIONS, INCLUDING, BUT NOT LIMITED TO, STRUCTURAL STRENGTH, SEISMIC STABILITY, SANITATION, ADEQUATE LIGHT AND VENTILATION, AND ENERGY CONSERVATION. VA BUILDINGS MUST MEET THE REQUIREMENTS OF NFPA 101 AND DOCUMENTS REFERENCED BY NFPA 101 IN ORDER TO COMPLY WITH THE ACCREDITATION REQUIREMENTS OF THE JOINT COMMISSION. THEREFORE, DESIGNS SHALL COMPLY WITH THE REQUIREMENTS OF THE LATEST EDITION OF NFPA 101 AND DOCUMENTS REFERENCED THEREIN. DESIGN FEATURES NOT ADDRESSED BY NFPA 101 OR DOCUMENTS REFERENCED THEREIN SHALL COMPLY WITH THE REQUIREMENTS OF THE LATEST EDITION OF THE IBC OR AS OTHERWISE ADDRESSED ABOVE IN THIS PROGRAM GUIDE. FOR DESIGN FEATURES THAT ARE ADDRESSED BY BOTH THE IBC AS WELL AS NFPA 101 OR A DOCUMENT REFERENCED BY NFPA 101, THE REQUIREMENTS OF NFPA 101 OR THE DOCUMENT REFERENCED BY NFPA 101 SHALL BE USED EXCLUSIVELY (THIS
APPLIES EVEN IF THE IBC REQUIREMENTS ARE DIFFERENT).
2. CONFLICTS BETWEEN NATIONALLY RECOGNIZED CODES AND STANDARDS AND VA REQUIREMENTS - SHOULD A CONFLICT EXIST BETWEEN VA REQUIREMENTS AND VA ADOPTED NATIONALLY RECOGNIZED CODES AND STANDARDS, THE CONFLICT SHALL BE BROUGHT TO THE ATTENTION OF VA. THE RESOLUTION OF THE CONFLICT SHALL BE MADE BY THE
AUTHORITY HAVING JURISDICTION FOR VA TO ENSURE A CONSISTENCY SYSTEM WIDE.
COVER SHEET
02 22 2023 AMG 1
A-000.00
SIXTH FLOOR PLAN
AREA OF WORK
NOT TO SCALE
630-CSI-102
2019-63
ARCHITECTURAL
A-000.00 COVER
A-001.00 LIFE SAFETY PLAN - 6TH FLOOR
A-002.00 INFECTION CONTROL PLAN
A-100.00 EXISTING PLANS AT ROOMS 6503E & 6503F
A-101.00 DEMO PLAN AT AREA OF WORK
A-102.00 DEMO R.C.P. AT AREA OF WORK
A-103.00 PROPOSED PLANS AT NEW GAMMA CAMERA AND AREA OF WORK
A-104.00 PROPOSED R.C.P.
A-200.00 PROPOSED FINISH PLAN
A-201.00 PROPOSED SECTIONS AT NEW UNISTRUT
A-202.00 INTERIOR ELEVATIONS AND DOOR SCHEDULE
MEP DRAWINGS
T-001.00 TITLE SHEET
G-001.00 GENERAL DESIGN NOTES
G-002.00 MECHANICAL DESIGN NOTES
G-003.00 ELECTRICAL DESIGN NOTES
G-004.00 PLUMBING DESIGN NOTES
G-005.00 SPRINKLER DESIGN NOTES
M-001.00 PLOT PLAN, MECHANICAL SYMBOL & ABBREVIATION LIST
M-002.00 ROOM 6503E/F MECHANICAL PLAN & MECHANICAL DETAILS
E-001.00 ELECTRICAL SYMBOLS & ABBREVIATION LIST, LIGHTING FIXTURE SCHEDULE
E-002.00 ROOM 6503E/F LIGHTING & POWER PLAN AND ELECTRICAL DETAILS
P-001.00 PLUMBING SYMBOL & ABBREVIATION LIST
P-002.00 ROOM 6503E/F PLUMBING & SPRINKLER PLAN AND SPRINKLER DETAILS
X-001.00 ELECTRICAL SPECIFICATIONS
GE DRAWINGS
01-C1 COVER SHEET
02-C2 DISCLAIMER - SITE READINESS
03-A1 GENERAL NOTES
04-A2 EQUIPMENT LAYOUT
05-A3 RADIATION PROTECTION
06-A4 EQUIPMENT DETAILS (1)
07-A5 EQUIPMENT DETAILS (2)
08-A6 DELIVERY
09-S1 STRUCTURAL NOTES
10-S2 STRUCTURAL LAYOUT
11-S3 STRUCTURAL DETAILS (1)
12-M1 HVAC
13-E1 ELECTRICAL NOTES
14-E2 ELECTRICAL LAYOUT
15-E3 ELECTRICAL ELEVATIONS
16-E4 POWER REQUIREMENTS
17-E5 ELECTRICAL DETAILS - INTERCONNECTIONS
STRUCTURAL DRAWINGS
S-001.00 STRUCTURAL DETAILS
100% SUBMISSION
(RESUBMITTED 2 22 2023)
60% SUBMISSION 11 24 2020
100% SUBMISSION 02 04 2021
100% RE-SUBMISSION 03 15 2021
100% RE-SUBMISSION 02 22 2023
AutoCAD SHX Text
ACTS AND FROM ANY OTHER CLAIMS FROM DAMAGES.
AutoCAD SHX Text
4.8 ANY SUBSTITUTION THE GENERAL CONTRACTOR WISHES TO MAKE OTHER
AutoCAD SHX Text
4.9 THE GENERAL CONTRACTOR, AT HIS OWN EXPENSE, SHALL EMPLOY A
AutoCAD SHX Text
WRITING WITH THE COST DIFFERENCE BEFORE IT IS ACCEPTED.
AutoCAD SHX Text
THAN THOSE STATED IN THIS PROPOSAL, SHALL BE SUBMITTED IN
AutoCAD SHX Text
IMMEDIATELY.
AutoCAD SHX Text
AFTERWARDS; THIS WORK MUST BE REMOVED AND MADE CORRECT
AutoCAD SHX Text
WHETHER THEY ARE DISCOVERED AT THE TIME OF INSTALLATION OR
AutoCAD SHX Text
4.7 NO INTERIOR WORK OR MATERIAL SHALL BE ACCEPTED ON THIS PROJECT,
AutoCAD SHX Text
WORKMAN SHALL BE EMPLOYED ON THE PROJECT.
AutoCAD SHX Text
4.6 THE GENERAL CONTRACTOR WARRANTS THAT NONE BUT EXPERIENCED
AutoCAD SHX Text
ACCORDANCE WITH BEST PRACTICES WITH FIRST CLASS MATERIALS.
AutoCAD SHX Text
4.5 ALL WORK SHALL BE PERFORMED IN A FIRST CLASS MANNER AND IN
AutoCAD SHX Text
SPECIFICATIONS.
AutoCAD SHX Text
FOR PAINTING OR WALL COVERING AS PER MANUFACTURER'S
AutoCAD SHX Text
4.4 ALL WALL SHALL BE PROPERLY PREPARED (SPACKLED, SANDED, ETC.)
AutoCAD SHX Text
INVOLVED IN THE PROJECT.
AutoCAD SHX Text
AND DUST FROM LEAVING THE JOB SITE AND INFILTRATING AREAS NOT
AutoCAD SHX Text
4.3 THE GENERAL CONTRACTOR SHALL CONTROL CLEANING TO PREVENT DIRT
AutoCAD SHX Text
SCOPE OF THE WORK.
AutoCAD SHX Text
CALLED OUT ON THESE DRAWINGS, IS CONSIDERED TO BE WITHIN THE
AutoCAD SHX Text
4.2 ANY PATCHING AND FINISHING NECESSARY TO FINISH ANY WORK, BUT
AutoCAD SHX Text
GUARANTEED.
AutoCAD SHX Text
AND MAKE GOOD ALL SUCH DEFECTS APPEARING DURING THIS PERIOD
AutoCAD SHX Text
WORKMANSHIP AGAINST DEFECTS FOR ONE YEAR FROM FINAL PAYMENT
AutoCAD SHX Text
4.1 THE GENERAL CONTRACTOR SHALL GUARANTEE ALL MATERIALS AND
AutoCAD SHX Text
SECTION 4 - WORKMANSHIP
AutoCAD SHX Text
OWNER AND DEPARTMENT OF BUILDINGS.
AutoCAD SHX Text
AS REQUIRED BY THE GOVERNING JURISDICTION ARE SUBMITTED TO THE
AutoCAD SHX Text
3.1 NO WORK SHALL COMMENCE UNTIL PROPER CERTIFICATES OF INSURANCE
AutoCAD SHX Text
SECTION 3 - INSURANCES
AutoCAD SHX Text
AGAINST ANY DAMAGES WHICH MAY RESULT FROM SUCH VIOLATIONS.
AutoCAD SHX Text
PENALTIES AND CORRECTIVE MEASURES, AND HOLD HARMLESS THE OWNER
AutoCAD SHX Text
REGULATIONS, HE SHALL AT HIS OWN EXPENSES BEAR THE COSTS OF ALL
AutoCAD SHX Text
2.5 IF THE CONTRACTORS VIOLATE ANY BUILDING DEPARTMENT CODES OR
AutoCAD SHX Text
2.4 ALL WOOD SHALL BE FIRE-PROOFED AS REQUIRED BY THE BUILDING CODE.
AutoCAD SHX Text
LOCAL AND SHALL CONFORM TO GENERALLY ACCEPTED STANDARDS.
AutoCAD SHX Text
CONFORM TO ALL GOVERNING BUILDING CODES; FEDERAL, STATE, AND
AutoCAD SHX Text
2.3 ALL MATERIALS, ASSEMBLIES, CONSTRUCTION AND EQUIPMENT SHALL
AutoCAD SHX Text
MUNICIPAL AND REGULATORY AGENCIES' CODES HAVING JURISDICTION.
AutoCAD SHX Text
2.2 THE GENERAL CONTRACTOR SHALL COMPLY WITH ALL APPROPRIATE
AutoCAD SHX Text
ALLOWING MAXIMUM ACCESS, NOT IMPEDING TRAFFIC AND PROVIDE REQUIRED
AutoCAD SHX Text
9. CONTRACTOR TO RETAIN STORED ITEMS IN AN ORDERLY ARRANGEMENT
AutoCAD SHX Text
TO ARCHITECT'S ATTENTION IMMEDIATELY.
AutoCAD SHX Text
AT THE JOB SITE. IN THE EVENT OF CONFLICTS, THEY SHALL BE BROUGHT
AutoCAD SHX Text
8. CONTRACTORS SHALL CHECK AND VERIFY ALL DIMENSIONS AND CONDITIONS
AutoCAD SHX Text
CODES FOR BUILDING CONSTRUCTION; TO LIFE SAFETY CODE NFPA 101 AND
AutoCAD SHX Text
7. ALL WORK SHALL CONFORM TO MINIMUM REQUIREMENTS OF NEW YORK CITY
AutoCAD SHX Text
THE OWNER AND CONTRACTOR FROM CLAIMS UNDER WORKMEN'S COMPENSATION
AutoCAD SHX Text
6. THE CONTRACTOR SHALL MAINTAIN SUCH INSURANCE AND WILL PROTECT BOTH
AutoCAD SHX Text
REMOVE FROM PREMISES ALL RUBBISH AND DEBRIS FOR WHICH HE IS
AutoCAD SHX Text
AWAY FROM THE PREMISES. UPON COMPLETION OF WORK CONTRACTORS SHALL
AutoCAD SHX Text
OF THIS CONTRACT SHALL BE PROMPTLY REMOVED DAILY AND DISPOSED OF
AutoCAD SHX Text
ARE NOT REQUIRED OR APPROVED FOR USE IN CONNECTION WITH THE WORK
AutoCAD SHX Text
5. EXCESS MATERIALS AND DEBRIS RESULTING FROM THE ALTERATION WHICH
AutoCAD SHX Text
ARCHITECT, AT NO ADDITIONAL COST TO THE OWNER.
AutoCAD SHX Text
PROMPTLY RESTORED, REPAIRED, OR REPLACED TO THE SATISFACTION OF THE
AutoCAD SHX Text
RESULTING DIRECTLY FROM THE CONTRACTOR'S OPERATIONS SHALL BE
AutoCAD SHX Text
EXISTING BUILDING AND IMPROVEMENTS, OR ANY IMPAIRMENTS OF FACILITIES
AutoCAD SHX Text
UNDER THIS CONTRACT. ANY DISTURBANCE OR DAMAGE TO THE WORK, THE
AutoCAD SHX Text
BUILDING, FACILITIES AND IMPROVEMENT WITHIN THE AREAS OF HIS OPERATIONS
AutoCAD SHX Text
4. THE CONTRACTOR SHALL PROTECT AND BE RESPONSIBLE FOR THE EXISTING
AutoCAD SHX Text
EXISTING WORK IN EVERY RESPECT AS APPROVED.
AutoCAD SHX Text
REPAIRS AND REPLACEMENTS TO SUCH DAMAGED WORK AT HIS COST AND
AutoCAD SHX Text
AND CIRCUMSTANCES TO THE ARCHITECT AND SHALL MAKE ANY NECESSARY
AutoCAD SHX Text
WORK OF THIS CONTRACT, THE CONTRACTOR SHALL REPORT THE CONDITIONS
AutoCAD SHX Text
3. SHOULD ANY PORTION OF THE EXISTING BUILDING BE DAMAGED DUE TO THE
AutoCAD SHX Text
SPECIFIED AND AS REQUIRED BY CONDITIONS ENCOUNTERED.
AutoCAD SHX Text
2. ALTERATIONS ARE TO BE PERFORMED AS REQUIRED BY DRAWINGS AND/OR
AutoCAD SHX Text
COMMENCING WORK, HE SHALL EXAMINE ALL EXISTING WORK.
AutoCAD SHX Text
SO THAT ALL WORK WILL PROPERLY JOIN THE EXISTING WORK. BEFORE
AutoCAD SHX Text
1. THE CONTRACTOR SHALL VERIFY DIMENSIONS AND CONDITIONS ON THE JOB
AutoCAD SHX Text
GENERAL REQUIREMENTS FOR ALTERATION:
AutoCAD SHX Text
TO THE NATIONAL ELECTRIC CODE.
AutoCAD SHX Text
RESPONSIBLE.
AutoCAD SHX Text
RESPECT AS APPROVED. EXPENSE WITH NEW MATERIALS TO MATCH THE
AutoCAD SHX Text
BEEN MADE.
AutoCAD SHX Text
DISTURB THE ASBESTOS UNTIL PROPER MEASURES FOR ITS REMOVAL HAVE
AutoCAD SHX Text
OWNER'S PROJECT MANAGER IMMEDIATELY AND TAKE PRECAUTIONS TO NOT
AutoCAD SHX Text
10.1 IF THE CONTRACTOR ENCOUNTERS ASBESTOS HE SHALL NOTIFY THE
AutoCAD SHX Text
SECTION 10 - ASBESTOS
AutoCAD SHX Text
- ELECTRICAL PANELS TAGGED AND LABELED.
AutoCAD SHX Text
- MANUALS AND INSTRUCTIONS.
AutoCAD SHX Text
- ALL WARRANTIES AND GUARANTEES.
AutoCAD SHX Text
- WAIVER OF LIENS.
AutoCAD SHX Text
SUBMITTED BUT NOT LIMITED TO THESE ITEMS:
AutoCAD SHX Text
9.3 BEFORE FINAL PAYMENT IS ISSUED THE FOLLOWING ITEMS MUST BE
AutoCAD SHX Text
1.16 DRAWINGS SHALL NOT BE SCALED, LARGER SCALE DRAWINGS SHALL ALWAYS
AutoCAD SHX Text
FURNISH A LIST OF SUB-CONTRACTORS AND MANUFACTURERS HE INTENDS
AutoCAD SHX Text
MANUFACTURERS OR SUBCONTRACTORS. THE GENERAL CONTRACTORS SHALL
AutoCAD SHX Text
1.15 WHERE DRAWINGS CALL FOR A SPECIFIC MANUFACTURER TO SUBCONTRACTOR,
AutoCAD SHX Text
1.13 THE GENERAL CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATION OF
AutoCAD SHX Text
1.10 THE GENERAL CONTRACTOR IS RESPONSIBLE FOR PROTECTION OF WORKMEN,
AutoCAD SHX Text
AND INSTALLED BY THE GENERAL CONTRACTOR UNLESS NOTED OTHERWISE.
AutoCAD SHX Text
1.9 ALL WORK SHOWN ON THE CONSTRUCTION DOCUMENTS SHALL BE FURNISHED
AutoCAD SHX Text
TERMS ARE USED, IT SHALL BE BASED UPON THE REVIEW AND APPROVAL
AutoCAD SHX Text
COORDINATION WITH ALL SUBCONTRACTORS, WHETHER UNDER CONTRACT
AutoCAD SHX Text
ENCOUNTERED WHICH COULD HAVE BEEN AVERTED HAD SUCH AN
AutoCAD SHX Text
THE GENERAL CONTRACTOR SHALL BE OBLIGATED TO USE THESE
AutoCAD SHX Text
2.1 (REMOVED)
AutoCAD SHX Text
SECTION 2 - GOVERNING AGENCIES AND PERMITS
AutoCAD SHX Text
ON THE WORK.
AutoCAD SHX Text
1.17 THE A.I.A. GENERAL CONDITIONS, LATEST EDITION, SHALL BE BINDING
AutoCAD SHX Text
GOVERN OVER SMALLER SCALE DRAWINGS.
AutoCAD SHX Text
TO USE BEFORE WORK COMMENCES.
AutoCAD SHX Text
1.14 BEFORE WORK COMMENCES THE ARCHITECT IS TO APPROVE ALL LAYOUTS.
AutoCAD SHX Text
BACKBOXES, ETC. SHALL BE CONCEALED WITHIN BUILDING CONSTRUCTION.
AutoCAD SHX Text
CHOPPING AND PATCHING FOR ALL TRADES. ALL CONDUITS, PIPING,
AutoCAD SHX Text
MAINTAINED.
AutoCAD SHX Text
FIRE PROTECTION DEVICES AND ALARMS SHALL BE CONTINUOUSLY
AutoCAD SHX Text
1.12 DURING THE ENTIRE CONSTRUCTION PERIOD, ALL EXISTING LIGHTING,
AutoCAD SHX Text
MAINTAINED FREE OF OBSTRUCTIONS THROUGHOUT THE CONSTRUCTION.
AutoCAD SHX Text
1.11 ALL REQUIRED EXITS AND EXIT APPROACHES SHALL BE CONTINUOUSLY
AutoCAD SHX Text
PUBLIC AND PROPERTY.
AutoCAD SHX Text
COMMENCEMENTS OF WORK.
AutoCAD SHX Text
SPECIFICATIONS AND SAMPLES FOR APPROVAL, IN WRITING, PRIOR TO
AutoCAD SHX Text
FIRST INFORMING THE ARCHITECT. SUBMIT SUBSTITUTE MATERIAL
AutoCAD SHX Text
BY THE ARCHITECT NO MATERIAL SUBSTITUTION SHALL BE MADE WITHOUT
AutoCAD SHX Text
1.8 WHEN "APPROVAL EQUAL", "EQUAL TO" OR OTHER GENERAL QUALIFYING
AutoCAD SHX Text
TO HIM OR NOT.
AutoCAD SHX Text
1.7 THE GENERAL CONTRACTOR SHALL BE RESPONSIBLE FOR THE OVERALL
AutoCAD SHX Text
CONDITIONS AT THE JOB SITE.
AutoCAD SHX Text
1.6 THE CONTRACTOR SHALL CHECK AND VERIFY ALL DIMENSIONS AND
AutoCAD SHX Text
AT ONCE.
AutoCAD SHX Text
THE CONTRACTOR SHALL STOP IMMEDIATELY AND NOTIFY THE ARCHITECT
AutoCAD SHX Text
1.5 IF ANY UNFORESEEN CONDITIONS ARISE DURING ANY PORTION OF WORK,
AutoCAD SHX Text
ITEMS.
AutoCAD SHX Text
MANAGER SHALL BE AVAILABLE TO REVIEW AND CLARIFY ANY UNCLEAR
AutoCAD SHX Text
UNDERSTANDING OF THE SCOPE OF WORK. THE ARCHITECT OR PROJECT
AutoCAD SHX Text
1.4 THE CONTRACTOR SHALL REVIEW THESE DOCUMENTS TO INSURE A FULL
AutoCAD SHX Text
CLARIFICATION.
AutoCAD SHX Text
COMMENCING ANY WORK OR ORDERING MATERIALS, AND REQUEST
AutoCAD SHX Text
BETWEEN THESE DRAWINGS, THESE NOTES, AND CONDITIONS BEFORE
AutoCAD SHX Text
1.3 THE CONTRACTOR SHALL NOTIFY THE ARCHITECT OF ANY DISCREPANCIES
AutoCAD SHX Text
EXAMINATION BEEN MADE, WILL NOT BE RECOGNIZED.
AutoCAD SHX Text
LABOR, EQUIPMENT OR MATERIALS REQUIRED FOR DIFFICULTIES
AutoCAD SHX Text
THAT SUCH AN EXAMINATION HAS BEEN MADE, AND LATER CLAIMS FOR
AutoCAD SHX Text
1.2 THE SUBMISSION OF THE PROPOSAL WILL BE CONSTRUCTED AS EVIDENCE
AutoCAD SHX Text
OF THE WORK AND DIFFICULTIES THAT ATTEND ITS EXECUTION.
AutoCAD SHX Text
THE PREMISES FAMILIARIZING HIMSELF AS THE NATURE AND SCOPE
AutoCAD SHX Text
1.1 THE CONTRACTOR, BEFORE SUBMITTING A PROPOSAL, SHALL VISIT
AutoCAD SHX Text
SECTION 1 - EXECUTION AND INTENT OF DRAWINGS
AutoCAD SHX Text
THAT THE WORK IS SUBSTANTIALLY COMPLETE.
AutoCAD SHX Text
NOTIFY THE ARCHITECT TO CONDUCT A PUNCH LIST. UPON VERIFICATION
AutoCAD SHX Text
9.2 WHEN THE G.C. CONSIDERS THAT THE WORK IS ACCEPTABLE HE SHOULD
AutoCAD SHX Text
INTENDED.
AutoCAD SHX Text
THE OWNER CAN OCCUPY THE AREA FOR THE PURPOSE FOR WHICH IT WAS
AutoCAD SHX Text
COMPLETE, IN ACCORDANCE WITH THE CONTRACT DOCUMENTS, SO THAT
AutoCAD SHX Text
CERTIFIED BY THE OWNER WHEN CONSTRUCTION IS SUFFICIENTLY
AutoCAD SHX Text
9.1 SUBSTANTIAL COMPLETION OF THE WORK IS DEFINED AS THE DATE
AutoCAD SHX Text
SECTION 9 - SUBSTANTIAL COMPLETION
AutoCAD SHX Text
HIS EMPLOYEE AND OTHER SUBCONTRACTORS.
AutoCAD SHX Text
8.3 THE G.C. SHALL REMOVE ALL RUBBISH AND WASTE MATERIALS FROM BOTH
AutoCAD SHX Text
AREAS UNTIL THE SPACE IS TURNED OVER TO THE OWNER.
AutoCAD SHX Text
8.2 THE G.C. SHALL BE RESPONSIBLE FOR THE SECURITY OF THE CONSTRUCTION
AutoCAD SHX Text
SHALL BE PROMPTLY RESTORED.
AutoCAD SHX Text
UNDER THIS CONTRACT. ANY DISTURBANCES FROM THE G.C.'S OPERATIONS
AutoCAD SHX Text
EXISTING STRUCTURES, FACILITIES AND IMPROVEMENT ADJOINING THE AREA
AutoCAD SHX Text
8.1 THE GENERAL CONTRACTOR SHALL PROTECT AND BE RESPONSIBLE FOR THE
AutoCAD SHX Text
SECTION 8 - PROTECTION OF WORK AND PROPERTY
AutoCAD SHX Text
ATTENTION OF M/G.
AutoCAD SHX Text
INTERFERENCE THAT WOULD PREVENT ACCESS IS TO BE BROUGHT TO THE
AutoCAD SHX Text
BE KEPT CLEAN AND READY FOR ACCESS. ANY POSSIBLE CONSTRUCTION
AutoCAD SHX Text
7.3 ALL EXISTING VALVES AND CONTROLS FOR MECHANICAL EQUIPMENT ARE TO
AutoCAD SHX Text
PERMITTED AS INSULATION OF FILL.
AutoCAD SHX Text
FLAME, SMOKE, FUMES AND HOT GASSES. FLAMMABLE MATERIALS ARE NOT
AutoCAD SHX Text
FILLED WITH NONCOMBUSTIBLE MATERIALS TO PREVENT THE PASSAGE OF
AutoCAD SHX Text
7.2 ALL PENETRATION THROUGH FIRE PARTITIONS SHALL BE FIRESTOPPED OR
AutoCAD SHX Text
FOR ALL SUBCONTRACTORS TO COMPLETE THEIR WORK.
AutoCAD SHX Text
7.1 THE GENERAL CONTRACTOR SHALL DO ALL CUTTING AND PATCHING REQUIRED
AutoCAD SHX Text
SECTION 7 - CUTTING AND PATCHING
AutoCAD SHX Text
SECTION 6 - (REMOVED)
AutoCAD SHX Text
CUTS OR SAMPLE.
AutoCAD SHX Text
THE CONTRACT DOCUMENTS BY THE APPROVAL OF SHOP DRAWINGS OR
AutoCAD SHX Text
FOR ANY DEVIATIONS, ERRORS OR OMISSIONS FROM THE REQUIREMENTS OF
AutoCAD SHX Text
5.4 THE GENERAL CONTRACTOR SHALL NOT BE RELIEVED OF RESPONSIBILITY
AutoCAD SHX Text
CONDITIONS RELATED TO THE CONSTRUCTION OF THAT SUBMISSION.
AutoCAD SHX Text
CONTRACTOR REPRESENTS THAT HE HAS VERIFIED FIELD MEASUREMENTS AND
AutoCAD SHX Text
5.3 BY APPROVING AND SUBMITTING SHOP DRAWINGS AND SAMPLES THE GENERAL
AutoCAD SHX Text
EQUIPMENT AND FINISHES FOR APPROVAL.
AutoCAD SHX Text
5.2 THE GENERAL CONTRACTOR SHALL SUBMIT CUTS OF ALL FIXTURES,
AutoCAD SHX Text
FABRICATED ITEMS AND ALL OTHER ITEMS REQUIRED FOR APPROVAL.
AutoCAD SHX Text
REPRODUCIBLE AND THREE BLACK AND WHITE PRINTS FOR ALL SHOP
AutoCAD SHX Text
5.1 THE GENERAL CONTRACTOR SHALL SUBMIT SHOP DRAWINGS OF ONE
AutoCAD SHX Text
SECTION 5 - SHOP DRAWINGS
AutoCAD SHX Text
COMPETENT, FULLTIME SUPERINTENDENT TO SUPERVISE AND
AutoCAD SHX Text
COORDINATE THE WORK OF HIS OWN MEN AND SUBCONTRACTORS.
AutoCAD SHX Text
1. THE GENERAL CONTRACTOR RESPONSIBLE FOR THE DEMOLITION PORTION OF THIS WORK SHALL AS PART OF THIS WORK SURVEY AND/OR INVESTIGATE ALL REQUIRED SHUT-OFFS FOR ELECTRICAL, MECHANICAL, AND PLUMBING WORK, PRIOR TO DEMO OF THESE AREAS. 2. THE GENERAL CONTRACTOR SHALL IDENTIFY SOURCES OF ALL ELECTRICAL POWER REQUIRED TO BE RELOCATED AS PART OF THIS WORK OR FUTURE 3. THE GENERAL CONTRACTOR SHALL PROVIDE AND MAKE AVAILABLE TO THE ARCHITECT THE RECORD DRAWINGS OF ALL SUCH INVESTIGATIONS 4. CONTRACTOR SHALL OBTAIN ALL REQUIRED APPROVALS PRIOR TO BEGINNING WORK. 5. ALL WORK SHALL BE IN STRICT COMPLIANCE WITH THE TERMS AND CONDITIONS OF ALL APPROVALS. 6. CONTRACTOR SHALL OBTAIN ALL NECESSARY PERMITS AND SHALL MAINTAIN THEM ON THE JOB SITE IN ACCORDANCE WITH APPLICABLE REGULATIONS 7. THE CONTRACTOR SHALL MAINTAIN A COPY OF THE APPROVED PLANS ON THE JOB SITE AT ALL TIMES. 8. CONSTRUCTION WORK SHALL NOT BLOCK HALLWAYS OR OBSTRUCT SAFE EGRESS FROM ANY SPACE WITHIN THE PREMISE OF BUILDING 9. REMOVE EXISTING FINISHED FLOOR, BRING DOWN TO SOUND STRUCTURE, PATCH AND REPAIR AS REQUIRED IN ORDER TO RECEIVE FINISHED FLOOR. 10. ALL WORK SHALL BE PERFORMED AS PER CODE AND AS PER ALL GOVERNING AGENCIES HAVING JURISDICTION 11. THE CONTRACTOR SHALL OBTAIN PERMITS WHERE REQUIRED FOR CONTAINERS, SHEDS, AND OTHER ELEMENTS OF THE DEMOLITION. 12. THE CONTRACTOR SHALL MAINTAIN ALL INSURANCES REQUIRED BY THE BUILDING OWNER AND BY REGULATORY AUTHORITIES 13. THE CONTRACTOR SHALL BE RESPONSIBLE FOR PROTECTING ALL BUILDING ELEMENTS WHICH ARE NOT DESIGNATED FOR REMOVAL, AND REPLACE ANY BUILDING ELEMENTS DAMAGED DURING DEMOLITION. 14. CONTRACTOR SHALL PROTECT THE SITE AND THE REBUILDING FROM UN-AUTHORIZED ENTRY AT ALL TIMES.
AutoCAD SHX Text
1. REQUIRED EGRESS SHALL NOT BE IMPEDED DURING COURSE OF CONSTRUCTION 2. SECURITY AND FIRE SAFETY SHALL BE MAINTAINED DURING COURSE OF CONSTRUCTION WORK 3. WHERE STRUCTURAL WORK IS TO BE DONE, THE SAFETY OF OCCUPANTS SHALL BE MAINTAINED 4. DUST CREATED DURING THE COURSE OF CONSTRUCTION SHALL BE CONTAINED AND KEPT UNDER CONTROL 5. NOISE TO BE CONTROLLED DURING ALL WORKING HOURS 6. THE WORK SHALL BE SO PERFORMED, AND SUCH TEMPORARY FACILITIES AND UTILITIES FURNISHED, AS NOT TO INTERFERE WITH ACCESS TO ANY OCCUPIED PARTS OF THE EXISTING BUILDING AND SO AS TO CAUSE THE LEAST POSSIBLE INTERFERENCE WITH THE OPERATION OF THE BUILDING OF ESSENTIAL SERVICES THEREOF. THE CONTRACTOR SHALL WORK OUT A TIME SCHEDULE WITH THE OWNER AND OBTAIN WRITTEN APPROVAL OF THE OWNER TWO WEEKS IN ADVANCE OF WORK WHICH MAY OR WILL CAUSE INTERFERENCE. 7. WHEN INSTALLATION OF PARTIAL OR NEW SYSTEM SHALL BE PERFORMED ONLY AFTER WRITTEN NOTIFICATION OF ESTIMATED SHUTDOWN PERIOD HAS BEEN APPROVED BY OWNER. 8. THE CONTRACTOR SHALL PROVIDE ADEQUATE PROTECTION FOR ALL PARTS OF THE EXISTING BUILDING, ITS CONTENTS AND OCCUPANTS. 9. PROPER PROTECTION SHALL BE PROVIDED AROUND ALL AREAS IN WHICH DEMOLITION OR NEW WORK IS TO BE CARRIED SO AS TO PREVENT DIRT, OR DUST, FROM ENTERING ACTIVE PORTIONS OF THE BUILDING. PROTECTIVE MEASURES SHALL CONSIST OF DUST-TIGHT STUD AND PLYWOOD PARTITIONS. 10. ALL RUBBISH AND DEBRIS SHALL BE COLLECTED AND REMOVED FROM THE SITE BY THE CONTRACTOR.
AutoCAD SHX Text 1, COORDINATE A KICKOFF MEETING AT THE SITE TO REVIEW THE WORK CONTENT, DESIGN FOR THE WORK, DRAWING APPROVAL PROCESS, IF ANY, AND FINALIZE THE SCHEDULE FOR THE DESIGN AND PRODUCTION OF THE WORK. 2. COORDINATE AND ATTEND A PRE-CONSTRUCTION MEETING AND PERIODIC PROGRESS MEETINGS. COMPILE AND DISTRIBUTE THE MINUTES OF THOSE MEETINGS AND AN UPDATED CONSTRUCTION SCHEDULE FOLLOWING EACH OF THOSE MEETINGS. 3. PROJECT MANAGEMENT AND FULL-TIME CONSTRUCTION SUPERVISION SERVICES AT THE SITE DURING THE PRODUCTION OF THE WORK. 4. SEAL OF APPLICABLE SITE SUPPLY AND RETURN DIFFUSERS AD GRILLES TO MINIMIZE DUST CONTAMINATION OF DUCTWORK AND THE SURROUNDING AREA. 5. FURNISH AND INSTALL (i) TEMPORARY WALK-OFF MATS AT THE ENTRANCES TO THE SITE, AND (ii) A TEMPORARY NEGATIVE AIR UNIT FOR THE SITE WITH HEPA FILTRATION FOR GENERAL DUST CONTROL. 6. MAINTAIN THE SITE IN A REASONABLY CLEAN AND SAFE CONDITION IN COMPLIANCE WITH APPLICABLE OSHA REGULATIONS. 7. COMPLY WITH THE REASONABLE WRITTEN FIRE PREVENTION MEASURES AND OTHER WRITTEN GENERAL CONSTRUCTION RELATED RULES FURNISHED BY FACILITY AND THAT ARE IN EFFECT AT THE SITE. 8. THE WORK WILL BE PRODUCED DURING STANDARD WORK HOURS. 9. POWER AND OTHER UTILITIES SHUT DOWNS WILL OCCUR DURING STANDARD WORK HOURS AND WILL BE COORDINATED WITH A REPRESENTATIVE OF FACILITY ENGINEERING DEPARTMENT. 10. CLEAN THE SITE (BROOM CLEAN) ON A DAILY BASIS. AT THE COMPLETION OF THE WORK, REMOVE ALL TOOLS, EQUIPMENT, SURPLUS MATERIAL, AND TEMPORARY STRUCTURES. 11. FURNISH A DUMPSTER FOR WORK RUBBISH AND DEBRIS NEAR THE SITE IN AN AREA DESIGNATED BY FACILITY. 12. IF AREAS ADJOINING THE SITE ARE OCCUPIED DURING THE PRODUCTION OF THE WORK, COORDINATE THE WORK SO THAT THE USE AND OCCUPANCY OF THOSE AREAS WILL NOT BE UNREASONABLY IMPAIRED FOR EXTENDED PERIODS OF TIME. 13. COORDINATE THE DELIVERY AND STORAGE OF THE WORK MATERIALS WITH FACILITY. 14. THE WORK WILL COMPLY WITH APPLICABLE BUILDING CODES, RULES, AND REGULATIONS ENACTED BY THE STATE WHERE THE SITE IS LOCATED. 15. IF FINISHES (E.G., PLASTIC LAMINATE, FLOOR OR CEILING TILE, CARPET, CERAMIC TILE, PAINT, STAIN, ETC.) ARE INCLUDED IN T HE WORK, SAMPLES OF THOSE FINISH MATERIALS WILL BE FURNISHED TO VA MEDICAL CENTER FOR ITS SELECTION OF THE COLOR/PATTERN OF THOSE FINISHES.
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building Number
Project Number
Drawing Number
Drawn
Dwg. ofRevisions: Date
CONSULTANTS: ARCHITECT:
Facilities
Management on e eig ht h inc h on e fo ot th re e inc he s = o ne fo ot
6"
6" on e an d on e ha lf i nc he s = o ne fo ot on e inc h on e fo ot
6" 6" th re e qu ar te rs in ch o ne fo ot on e ha lf i nc h on e fo ot th re e eig ht hs in ch o ne fo ot on e qu ar te r i nc h on e fo ot
VA FORM 08-6231, OCT 1978
1 2 3 4 5 6 87 9
F
E
D
C
B
A
97 8654321
Services
MG PROJECT #
GAMMA CAMERA RM 6503E/F
MANHATTAN, VAMC
MANHATTAN VA MEDICAL CENTER
423 EAST 23RD STREET
NEW YORK, NEW YORK 6
M.E.P. ENGINEER:M.E.P. ENGINEER:
777 SUNRISE HWY, STE 300
LYNBROOK, NY 11563
516 561 5922 WWW.BEPC.US
BECKER ENGINEERING, PC STCETIC HRA
M G NEW YORK
MICHAEL J. GADALETA, R.A. A.I.A. N.Y. LIC.: 17474 N.J. LIC.: 8935
11 BROADWAY, SUITE 860 NEW YORK, N.Y. 10004
212 674 8456 MGNEWYORKARCHITECTS.COM
LANDMARKS & PRESERVATION
DESIGN & PLANNING
ARCHITECTURE, HEALTH CARE,
LIFE SAFETY PLAN - 6TH FLOOR
02 22 2023 AMG 2
A-001.00
630-CSI-102
2019-63
A-001
N.T.S.
LIFE SAFETY PLAN - 6TH FLOOR
AREA OF WORK
Project Title
Date
Location
Checked
Building Number
Project Number
Drawing Number
Drawn
Dwg. ofRevisions: Date
CONSULTANTS: ARCHITECT:
Facilities
Management on e eig ht h inc h on e fo ot th re e inc he s = o ne fo ot
6"
6" on e an d on e ha lf i nc he s = o ne fo ot on e inc h on e fo ot
6" 6" th re e qu ar te rs in ch o ne fo ot on e ha lf i nc h on e fo ot th re e eig ht hs in ch o ne fo ot on e qu ar te r i nc h on e fo ot
VA FORM 08-6231, OCT 1978
1 2 3 4 5 6 87 9
F
E
D
C
B
A
97 8654321
Services
MG PROJECT #
GAMMA CAMERA RM 6503E/F
MANHATTAN, VAMC
MANHATTAN VA MEDICAL CENTER
423 EAST 23RD STREET
NEW YORK, NEW YORK 6
M.E.P. ENGINEER:M.E.P. ENGINEER:
777 SUNRISE HWY, STE 300
LYNBROOK, NY 11563
516 561 5922 WWW.BEPC.US
BECKER ENGINEERING, PC STCETIC HRA
M G NEW YORK
MICHAEL J. GADALETA, R.A. A.I.A. N.Y. LIC.: 17474 N.J. LIC.: 8935
11 BROADWAY, SUITE 860 NEW YORK, N.Y. 10004
212 674 8456 MGNEWYORKARCHITECTS.COM
LANDMARKS & PRESERVATION
DESIGN & PLANNING
ARCHITECTURE, HEALTH CARE,
INFECTION CONTROL PLAN
02 22 2023 AMG 3
A-002.00
630-CSI-102
2019-63
A-002
SCALE: 1/2" = 1'-0"
INFECTION CONTROL PLAN AT ROOM 6503E / 6503F
AutoCAD SHX Text
PROJECT AREA LIMIT
AutoCAD SHX Text
WALK-OFF MAT
AutoCAD SHX Text M
AutoCAD SHX Text NOTE: 1. PROVIDE TAPE AND PLASTIC SHEET PROTECTIONS AT ANY WALL OR DOOR PENETRATIONS IN ACTIVE CONSTRUCTION AREAS TO PREVENT CONTAMINATION OF ADJACENT OCCUPIED SPACES AT ALL TIMES. ALL CONSTRUCTION DOORS MUST BE PROVIDED WITH SELF-CLOSING DOOR HARDWARE DURING CONSTRUCTION PROCESS 2. BASED ON THE PROJECT SCHEDULE, OFF-HOUR CONSTRUCTION MAY BE REQUIRED. ANY WORK OCCURRING OFF-HOURS SHALL BE COORDINATED IN ADVANCE WITH THE VA. 3. CONTRACTOR SHALL PROVIDE HEPA EQUIPPED AIR FILTRATION UNITS TO MAINTAIN NEGATIVE PRESSURE AND TO EXHAUST THE WORK SITE DURING CONSTRUCTION. CONTRACTOR SHALL PROVIDE REINFORCED FLEXIBLE DUCT TO EXHAUST THE WORK SITE IN A MANNER WHICH IS SAFE AND APPROVED BY THE RESIDENT ENGINEER.
AutoCAD SHX Text
LEGEND:
AutoCAD SHX Text
TEMPORARY PLASTIC DUST BARRIER
AutoCAD SHX Text
NUCLEAR ROOM 6503E
AutoCAD SHX Text C.H. +8'-11"
AutoCAD SHX Text
INJECTION ROOM 6503F
AutoCAD SHX Text C.H. +8'-11"
AutoCAD SHX Text
APPOINTMENT ROOM 6505A
AutoCAD SHX Text ±10'-2"
AutoCAD SHX Text ±10'-2"
AutoCAD SHX Text
FILM PROJECTION 6517
AutoCAD SHX Text
DEXA ROOM 6503D
AutoCAD SHX Text
CORRIDOR 6503
AutoCAD SHX Text
CORRIDOR 6522
AutoCAD SHX Text
CORRIDOR
AutoCAD SHX Text M
AutoCAD SHX Text SEAL EXIST. DOOR WITH HEAVY DUTY PLASTIC FOR AIR TIGHT SEAL. PROVIDE TEMPORARY DUST BARRIER DURING DOOR REMOVAL
AutoCAD SHX Text PROVIDE DUST MAT (BOTH SIDES) AND ZIPPERED DUST BARRIER FOR CONSTRUCTION DOOR. ALL CONSTRUCTION DOORS NOT SEALED TO BE PROVIDED WITH SELF-CLOSING HARDWARE AND STOREROOM LOCK FUNCTION DURING THE CONSTRUCTION PROCESS
AutoCAD SHX Text
EXIST. 30 MIN RATED SMOKE BARRIER
AutoCAD SHX Text PROVIDE TEMPORARY DUST PARTITION TO WORK AREA AND NEW 3'-0"x7'-0" CONSTRUCTION DOOR; 3-5/8" METAL STUD TIGHT TO UNDERSIDE OF EXISTING CEILING, TAPE AND SPACKLE ONE SIDE.
AutoCAD SHX Text M
AutoCAD SHX Text
TEMPORARY CONSTRUCTION WALL
AutoCAD SHX Text
EXISTING MED GAS
AutoCAD SHX Text
EXISTING MED GAS
AutoCAD SHX Text
PROVIDE NEGATIVE PRESSURE MONITOR AT NEW CONSTRUCTION DOOR - SEE NOTE 3
AutoCAD SHX Text EXISTING SMOKE BARRIER WALL TO REMAIN SEALED AT ALL TIMES. DAILY CHECKS MUST BE CONDUCTED AND ANY UNSEALED PENETRATIONS MUST BE FIRE STOPPED
AutoCAD SHX Text N.I.C.
AutoCAD SHX Text N.I.C.
AutoCAD SHX Text 5'-0"
AutoCAD SHX Text 5'-0"
AutoCAD SHX Text CONTRACTOR TO INSTALL 1-HR RATED CEILING BETWEEN TEMPORARY PARTITION AND AREA OF WORK
AutoCAD SHX Text
TYPE
AutoCAD SHX Text "A"
AutoCAD SHX Text
INFECTION CONTROL RISK ASSESSMENT
AutoCAD SHX Text
MIXED OF PRECAUTIONS FOR CONSTRUCTION & RENOVATION
AutoCAD SHX Text
TYPE
AutoCAD SHX Text "B"
AutoCAD SHX Text
TYPE
AutoCAD SHX Text "C"
AutoCAD SHX Text
TYPE
AutoCAD SHX Text "D"
AutoCAD SHX Text
GROUP 1:
AutoCAD SHX Text
LOW RISK
AutoCAD SHX Text
PATIENT RISK GROUP
AutoCAD SHX Text
GROUP 2:
AutoCAD SHX Text
MEDIUM RISK
AutoCAD SHX Text
GROUP 3:
AutoCAD SHX Text
HIGH RISK
AutoCAD SHX Text
GROUP 4:
AutoCAD SHX Text
HIGHEST RISK
AutoCAD SHX Text
PATIENT RISK
AutoCAD SHX Text
GROUP
AutoCAD SHX Text
CONSTRUCTION PROJECT TYPE
AutoCAD SHX Text
LOW RISK GROUP
AutoCAD SHX Text
TYPE "A"
AutoCAD SHX Text
MEDIUM RISK GROUP
AutoCAD SHX Text
HIGH RISK GROUP
AutoCAD SHX Text
HIGHEST RISK GROUP
AutoCAD SHX Text I
AutoCAD SHX Text I
AutoCAD SHX Text I
AutoCAD SHX Text
II
AutoCAD SHX Text
TYPE "B"
AutoCAD SHX Text
II
AutoCAD SHX Text
II
AutoCAD SHX Text
II
AutoCAD SHX Text
III / IV
AutoCAD SHX Text
TYPE "C"
AutoCAD SHX Text
II
AutoCAD SHX Text
III
AutoCAD SHX Text
III / IV
AutoCAD SHX Text
III / IV
AutoCAD SHX Text
TYPE "D"
AutoCAD SHX Text
III / IV
AutoCAD SHX Text
IV
AutoCAD SHX Text
IV
AutoCAD SHX Text
IV
AutoCAD SHX Text
%%UNOTE:
AutoCAD SHX Text
CLASS
AutoCAD SHX Text "I"
AutoCAD SHX Text
DESCRIPTION OF REQUIRED INFECTION CONTROL PRECAUTIONS BY CLASS
AutoCAD SHX Text
CLASS "II"
AutoCAD SHX Text
DURING CONSTRUCTION PROJECT
AutoCAD SHX Text
UPON COMPLETION OF PROJECT
AutoCAD SHX Text
CLASS
AutoCAD SHX Text
"III"
AutoCAD SHX Text
CLASS
AutoCAD SHX Text
"IV"
AutoCAD SHX Text
%%UNOTE:
AutoCAD SHX Text
* EMERGENCY ROOM * POST ANESTHESIA CARE UN. * LABOR AND DELIVERY * PEDIATRICS * ADMISSION / DISCHARGE * LABORATORIES (SPECIMEN) * AMBULATORY SURGERY * PHARMACY * RECOVERY ROOM * SURGICAL UNITS * INPATIENT UNITS (NOT OTHERWISE SPECIFIED) AT ALL AEHN LOCATIONS.
AutoCAD SHX Text
* ANY AREA CARING FOR IMMUNOCOMPROMISED PATIENT * ANESTHESIA AND PUMP AREA * CENTRAL EQUIPMENT / STERILE SUPPLY * CARDIAC CATH LAB & ANGIOGRAPHY AREA * INTERVENTIONAL RADIOLOGY * SPD * CRITICAL CARE & INTENSIVE CARE UNITS * MEDICAL UNIT * NEGATIVE PRESSURE ISOLATION ROOMS * RADIOLOGY/ ONCOLOGY(INPATIENT / OUTP.) * OPERATING ROOMS INCL. LABOR & DELIV. * TRANSPLANT - INPATIENT / OUTPATIENT * DIALYSIS * PHARMACY ADMIXTURE * NEWBORN NURSERIES, INCLUDING NICU
AutoCAD SHX Text IT IS THE GENERAL CONTRACTOR RESPONSIBILITY TO PROVIDE THE FOLLOWING INFECTION CONTROL PRECAUTIONS DEPENDING UPON THE AREA CLASS DESIGNATION
AutoCAD SHX Text INFECTION CONTROL APPROVAL WILL BE REQUIRED WHEN THE CONSTRUCTION ACTIVITY AND RISK LEVEL INDICATE THAT [CLASS "III"] OR [CLASS "IV"] CONTROL PROCEDURES ARE NECESSARY
AutoCAD SHX Text 1 - EXECUTE WORK BY METHODS TO MINIMIZE RAISING DUST FROM CONSTRUCTION OPERATIONS. 2 - IMMEDIATELY REPLACE A CEILING TILE DISPLACED FOR VISUAL INSPECTION.
AutoCAD SHX Text 1 - PROVIDE ACTIVE MEANS TO PREVENT AIRBORNE DUST FROM DISPERSING INTO ATMOSPHERE. 2 - WATER MIST WORK SURFACES TO CONTROL DUST WHILE CUTTING 3 - SEAL UNUSED DOORS WITH DUCT TAPE 4 - BLOCK OFF AND SEAL AIR VENTS 5 - PLACE DUST MAT AT ENTRANCE AND EXIT OF WORK AREA 6 - REMOVE OR ISOLATE HVAC SYSTEM IN AREAS WHERE WORK IS BEING PERFORMED
AutoCAD SHX Text 1 - REMOVE OR ISOLATE HVAC SYSTEM IN AREA WHERE WORK IS BEING DONE TO PREVENT CONTAMINATION OF DUCT SYSTEM 2 - COMPLETE ALL CRITICAL BARRIERS I.E. SHEETROCK, PLYWOOD, PLASTIC, TO SEAL AREA FROM NON-WORK AREA OR IMPLEMENT CONTROL CUBE METHOD (CART WITH PLASTIC COVERING AND SEALED CONNECTION TO WORK SITE WITH HEPA VACUUM FOR VACUUMING PRIOR TO EXIT) BEFORE CONSTRUCTION BEGINS. 3 - MAINTAIN NEGATIVE AIR PRESSURE WITHIN WORK SITE UTILIZING HEPA EQUIPPED AIR FILTRATIONS UNITS. 4 - CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT IN TIGHTLY COVERED CONTAINERS. COVER TRANSPORT RECEPTACLES OR CARTS. TAPE COVERING UNLESS SOLID LID.
AutoCAD SHX Text 1 - ISOLATE HVAC SYSTEM IN AREA WHERE WORK IS BEING DONE TO PREVENT CONTAMINATION OF DUCT SYSTEM. 2 - COMPLETE ALL CRITICAL BARRIERS I.E. SHEETROCK, PLYWOOD, PLASTIC, TO SEAL AREA FROM NON-WORK AREA OR IMPLEMENT CONTROL CUBE METHOD (CART WITH PLASTIC COVERING AND SEALED CONNECTION TO WORK SITE WITH HEPA VACUUM FOR VACUUMING PRIOR TO EXIT) BEFORE CONSTRUCTION BEGINS. 3 - MAINTAIN NEGATIVE AIR PRESSURE WITHIN WORK SITE UTILIZING HEPA EQUIPPED AIR FILTRATIONS UNITS. 4 - SEAL HOLES, PIPES, CONDUITS, AND PUNCTURES APPROPRIATELY. 5 - CONSTRUCTION ANTEROOM AND REQUIRE ALL PERSONNEL TO PASS THROUGH THIS ROOM SO THEY CAN BE VACUUMED USING A HEPA VACUUM CLEANER BEFORE LEAVING WORK SITE OR THEY CAN WEAR CLOTHES OR PAPER COVERALLS THAT ARE REMOVED EACH TIME THEY LEAVE THE WORK SITE. 6 - ALL PERSONNEL ENTERING WORK SITE ARE REQUIRED TO WEAR SHOE COVERS. SHOE COVERS MUST BE CHANGED EACH TIME THE WORKER EXITS THE WORK AREA. 7 - DO NOT REMOVE BARRIERS FROM WORK AREA UNTIL COMPLETED PROJECT IS INSPECTED BY THE OWNER'S SAFETY DEPARTMENT AND INFECTION CONTROL DEPARTMENT AND THOROUGHLY CLEANED BY THE OWNER'S ENVIRONMENTAL SERVICES DEPARTMENT.
AutoCAD SHX Text 1 - WIPE WORK SURFACES WITH DISINFECTANT 2 - CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT IN TIGHTLY COVERED CONTAINERS. 3 - WET MOP AND/ OR VACUUM WITH HEPA FILTER. 4 - REMOVE ISOLATION OF HVAC SYSTEM IN AREAS WHERE WORK IS BEING PERFORMED.
AutoCAD SHX Text 1 - DO NOT REMOVE BARRIERS FROM WORK AREA UNTIL COMPLETED PROJECT IS INSPECTED BY THE OWNER'S SAFETY DEPARTMENT AND INFECTION CONTROL DEPARTMENT AND THOROUGHLY CLEANED BY THE OWNER'S ENVIRONMENTAL SERVICES DEPARTMENT. 2 - REMOVE BARRIER MATERIALS CAREFULLY TO MINIMIZE SPREADING OF DIRT AND DEBRIS ASSOCIATED WITH CONSTRUCTION. 3 - VACUUM WORK AREA WITH HEPA FILTERED VACUUMS. 4 - WET MOP AREA WITH DISINFECTANT. 5 - REMOVE ISOLATION OF HVAC SYSTEM IN AREAS WHERE WORK IS BEING PERFORMED.
AutoCAD SHX Text 1 - REMOVE BARRIER MATERIAL CAREFULLY TO MINIMIZE SPREADING OF DIRT AND DEBRIS ASSOCIATED WITH CONSTRUCTION. 2 - CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT IN TIGHTLY COVERED CONTAINERS. 3 - COVER TRANSPORT RECEPTACLES OR CARTS. TAPE COVERING UNLESS SOLID LID. 4 - VACUUM WORK AREA WITH HEPA FILTERED VACUUMS. 5 - WET MOP AREA WITH DISINFECTANT. 6 - REMOVE ISOLATION OF HVAC SYSTEM IN AREAS WHERE WORK IS BEING PERFORMED.
AutoCAD SHX Text INSPECTION AND NON-INVASIVE ACTIVITIES (INCLUDED, BUT IS NOT LIMITED TO): * REMOVAL OF CEILING TILES FOR VISUAL INSPECTION LIMITED TO 1 TILE PER 50 SQUARE FEET. * PAINTING (BUT NOT SANDING) * WALL COVERING, ELECTRICAL TRIM WORK, MINOR PLUMBING, AND ACTIVITIES WHICH DO NOT GENERATE DUST OR REQUIRE CUTTING OF WALLS OR ACCESS TO CEILING OTHER THAN FOR VISUAL INSPECTION.
AutoCAD SHX Text SMALL SCALE, SHORT DURATION ACTIVITIES WHICH CREATE MINIMAL DUST (INCLUDED, BUT IS NOT LIMITED TO): * INSTALLATION OF TELEPHONE AND COMPUTER CABLING * ACCESS TO CHASE SPACES * CUTTING OF WALLS OR CEILING WHERE DUST MIGRATION CAN BE CONTROLLED
AutoCAD SHX Text WORK THAT GENERATES A MODERATE TO HIGH LEVEL OF DUST OR REQUIRES DEMOLITION OR REMOVAL OF ANY FIXED BUILDING COMPONENTS OR ASSEMBLIES (INCLUDED, BUT IS NOT LIMITED TO): * SANDING OF WALLS FOR PAINTING OR WALL COVERING * REMOVAL OF FLOOR COVERINGS, CEILING TILES AND CASEWORK. * NEW WALL CONSTRUCTION * MINOR DUCT WORK OR ELECTRICAL WORK ABOVE CEILING * MAJOR CABLING ACTIVITIES * ANY ACTIVITY THAT CANNOT BE COMPLETED WITHIN A SINGLE WORK SHIFT
AutoCAD SHX Text MAJOR DEMOLITION AND CONSTRUCTION PROJECTS (INCLUDED, BUT IS NOT LIMITED TO): * ACTIVITIES WHICH REQUIRE CONSECUTIVE WORK SHIFTS * REQUIRES HEAVY DEMOLITION OR REMOVAL OF A COMPLETE CABLING SYSTEM * NEW CONSTRUCTION
AutoCAD SHX Text
* CARDIOLOGY * ECHOCARDIOGRAPHY * ENDOSCOPY - GI * NUCLEAR MEDICINE * PHYSICAL THERAPY * RADIOLOGY / MRI * RESPIRATORY THERAPY * RESPIRATORY CARE (EXCLUDED BRONCHOSCOPY AREA * CAFETERIA * KITCHEN * OUTPATIENT AREAS- CLINICS AND OFFICES (EXCEPTION: TRANSPLANT AND ONCOLOGY)
AutoCAD SHX Text
* OFFICE AREA OFFICE AREA * STORAGE AREA STORAGE AREA * MECHANICAL MECHANICAL SPACES * PUBLIC PUBLIC CORRIDOR
%%USIXTH FLOOR ROOMS 6503D / 6503E / 6503F
CENTRAK CENTRAK
XRAY IN USE
CENTRAK
AP
APT
XRAY IN USE
CENTRAK
T
AP
AP
T
CENTRAK
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building Number
Project Number
Drawing Number
Drawn
Dwg. ofRevisions: Date
CONSULTANTS: ARCHITECT:
Facilities
Management on e eig ht h inc h on e fo ot th re e inc he s = o ne fo ot
6"
6" on e an d on e ha lf i nc he s = o ne fo ot on e inc h on e fo ot
6" 6" th re e qu ar te rs in ch o ne fo ot on e ha lf i nc h on e fo ot th re e eig ht hs in ch o ne fo ot on e qu ar te r i nc h on e fo ot
VA FORM 08-6231, OCT 1978
1 2 3 4 5 6 87 9
F
E
D
C
B
A
97 8654321
Services
MG PROJECT #
GAMMA CAMERA RM 6503E/F
MANHATTAN, VAMC
MANHATTAN VA MEDICAL CENTER
423 EAST 23RD STREET
NEW YORK, NEW YORK 6
M.E.P. ENGINEER:M.E.P. ENGINEER:
777 SUNRISE HWY, STE 300
LYNBROOK, NY 11563
516 561 5922 WWW.BEPC.US
BECKER ENGINEERING, PC STCETIC HRA
M G NEW YORK
MICHAEL J. GADALETA, R.A. A.I.A. N.Y. LIC.: 17474 N.J. LIC.: 8935
11 BROADWAY, SUITE 860 NEW YORK, N.Y. 10004
212 674 8456 MGNEWYORKARCHITECTS.COM
LANDMARKS & PRESERVATION
DESIGN & PLANNING
ARCHITECTURE, HEALTH CARE,
EXISTING PLANS AT ROOMS 6503E & 6503F
02 22 2023 AMG 4
A-100.00
630-CSI-102
2019-63
A-100
SCALE: 1/2" = 1'-0"
ROOM 6503E / 6503F EXISTING PLAN
A-100
SCALE: 1/2" = 1'-0"
ROOM 6503E / 6503F EXISTING R.C.P.
AutoCAD SHX Text
NUCLEAR ROOM 6503E
AutoCAD SHX Text C.H. +9'-0"
AutoCAD SHX Text
INJECTION ROOM 6503F
AutoCAD SHX Text C.H. +9'-0"
AutoCAD SHX Text
APPOINTMENT ROOM 6505A
AutoCAD SHX Text
EXISTING MED GAS
AutoCAD SHX Text
CORRIDOR
AutoCAD SHX Text ±10'-2"
AutoCAD SHX Text ±10'-2"
AutoCAD SHX Text
FILM PROJECTION 6517
AutoCAD SHX Text
DEXA ROOM 6503D
AutoCAD SHX Text
EXISTING ELECTRICAL CONDUIT
AutoCAD SHX Text C.H. +9'-0"
AutoCAD SHX Text C.H. +8'-0"
AutoCAD SHX Text C.H. +8'-0"
AutoCAD SHX Text
EXISTING 30 MIN-RATED SMOKE BARRIER
AutoCAD SHX Text
EXISTING MED GAS
AutoCAD SHX Text N.I.C.
AutoCAD SHX Text N.I.C.
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text
EXISTING XRAY IN USE SIGN
AutoCAD SHX Text
EXISTING XRAY IN USE SIGN
AutoCAD SHX Text
EXISTING ELECTRICAL CONDUIT
AutoCAD SHX Text
EXISTING MEDICAL AIR, OXYGEN, AND VACUUM
AutoCAD SHX Text
EXISTING SYSTEM MAIN DISCONNECT PANEL
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text N.I.C.
AutoCAD SHX Text N.I.C.
AutoCAD SHX Text
SINGLE POLE LIGHT SWITCH
AutoCAD SHX Text
TELEPHONE AND DATA OUTLET
AutoCAD SHX Text
DUPLEX RECEPTACLE
AutoCAD SHX Text
CEILING DIFFUSER
AutoCAD SHX Text
SPRINKLER HEAD
AutoCAD SHX Text
THERMOSTAT
AutoCAD SHX Text
LIGHT FIXTURE
AutoCAD SHX Text
CIRCUIT BREAKER PANEL
AutoCAD SHX Text
ELECTRICAL LEGEND
AutoCAD SHX Text
CEILING MTD CENTRAK SYSTEM
S
FD
Approved: Project Director
Project Title
Date
Location
Checked
Building Number
Project Number
Drawing Number
Drawn
Dwg. ofRevisions: Date
CONSULTANTS: ARCHITECT:
Facilities
Management on e eig ht h inc h on e fo ot th re e inc he s = o ne fo ot
6"
6" on e an d on e ha lf i nc he s = o ne fo ot on e inc h on e fo ot
6" 6" th re e qu ar te rs in ch o ne fo ot on e ha lf i nc h on e fo ot th re e eig ht hs in ch o ne fo ot on e qu ar te r i nc h on e fo ot
VA FORM 08-6231, OCT 1978
1 2 3 4 5 6 87 9
F
E
D
C
B
A
97 8654321
Services
MG PROJECT #
GAMMA CAMERA RM 6503E/F
MANHATTAN, VAMC
MANHATTAN VA MEDICAL CENTER
423 EAST 23RD STREET
NEW YORK, NEW YORK 6
M.E.P. ENGINEER:M.E.P. ENGINEER:
777 SUNRISE HWY, STE 300
LYNBROOK, NY 11563
516 561 5922 WWW.BEPC.US
BECKER ENGINEERING, PC STCETIC HRA
M G NEW YORK
MICHAEL J. GADALETA, R.A. A.I.A. N.Y. LIC.: 17474 N.J. LIC.: 8935
11 BROADWAY, SUITE 860 NEW YORK, N.Y. 10004
212 674 8456 MGNEWYORKARCHITECTS.COM
LANDMARKS & PRESERVATION
DESIGN & PLANNING
ARCHITECTURE, HEALTH CARE,
DEMO PLAN AT ROOMS 6503E & 6503F
02 22 2023 AMG 5
A-101.00
630-CSI-102
2019-63
A-101
SCALE: 1/2" = 1'-0"
ROOM 6503E / 6503F DEMO PLAN
AutoCAD SHX Text CONTRACTOR TO INSPECT ALL AREAS OF ROOM UPON COMPLETION OF DEMOLITION. ALL AREAS OF MISSING FIRE PROTECTION, FLOOR SLAB, OR WALL PENETRATIONS TO BE BROUGHT TO THE ATTENTION OF THE VA
AutoCAD SHX Text CONTRACTOR SHALL PROVIDE HEPA EQUIPPED AIR FILTRATION UNITS TO MAINTAIN NEGATIVE PRESSURE AND TO EXHAUST THE WORK SITE DURING CONSTRUCTION. CONTRACTOR SHALL PROVIDE REINFORCED FLEXIBLE DUCT TO EXHAUST THE WORK SITE IN A MANNER WHICH IS SAFE AND APPROVED BY THE RESIDENT ENGINEER.
AutoCAD SHX Text NO CHOPPING OR CHIPPING OF THE CONCRETE SLAB WILL BE PERMITTED; CORE DRILL ONLY. CONTRACTOR TO X-RAY FLOOR SLAB PRIOR TO ANY SLAB PENETRATION OR CORE DRILLING
AutoCAD SHX Text
APPOINTMENT ROOM 6505A
AutoCAD SHX Text
EXISTING MED GAS TO REMAIN
AutoCAD SHX Text ±10'-2"
AutoCAD SHX Text ±10'-2"
AutoCAD SHX Text
FILM PROJECTION 6517
AutoCAD SHX Text
CORRIDOR 6522
AutoCAD SHX Text
DEXA ROOM 6503D
AutoCAD SHX Text
NUCLEAR ROOM 6503E
AutoCAD SHX Text C.H. +9'-0"
AutoCAD SHX Text
INJECTION ROOM 6503F
AutoCAD SHX Text C.H. +8'-11"
AutoCAD SHX Text EXIST. DIAGNOSTIC EQUIPMENT TO BE REMOVED AS DIRECTED BY THE VA. REMOVE EXISTING SLAB-EMBEDDED FLOOR ANCHORS AS REQUIRED.
AutoCAD SHX Text
REMOVE EXIST. SLAB-EMBEDDED FLOOR ANCHORS
AutoCAD SHX Text EXIST. VCT FLOOR AND BASE TO BE REMOVED. PREP FLOOR IN ACCORDANCE WITH PRE- INSTALLATION MANUAL SPECS
AutoCAD SHX Text EXIST. NON-LOAD BEARING PARTITION TO BE REMOVED. PATCH WALL AS REQUIRED. RETURN WALL-MOUNTED CASEWORK TO VA
AutoCAD SHX Text
EXISTING FLOOR RAIL TO BE REMOVED
AutoCAD SHX Text
EXIST DOOR AND FRAME TO BE REMOVED
AutoCAD SHX Text
EXISTING SINK TO BE REMOVED. CAP PLUMBING AT SOURCE
AutoCAD SHX Text
REMOVE EXIST. STORAGE CABINET AND RETURN TO VA
AutoCAD SHX Text UPON REMOVAL OF EXIST. EQUIPMENT, BASE PLATES, ANCHORS, FILL ALL REMAINING DEPRESSIONS WITH SELF-LEVELING CEMENTITIOUS NDERLAYMENT (ARDEX K15 OR EQUAL)
AutoCAD SHX Text EXIST. COUNTERTOP, BASE AND WALL CABINETS, AND STORAGE TO BE REMOVED AND RETURNED TO VA
AutoCAD SHX Text
EXISTING SINK TO REMAIN
AutoCAD SHX Text
EXIST. DOOR AND FRAME TO BE REMOVED.
AutoCAD SHX Text EXIST. NON-LOAD BEARING PARTITION TO BE REMOVED. PATCH WALL AS REQUIRED. RETURN WALL-MOUNTED CASEWORK AND IMAGING TO VA
AutoCAD SHX Text
EXISTING SINK TO BE REMOVED. CAP PLUMBING BEHIND NEW GYP BD.
AutoCAD SHX Text
EXIST. DOOR AND FRAME TO BE REMOVED
AutoCAD SHX Text PROVIDE OPENING IN EXIST. CORRIDOR WALL FOR NEW 3'-0"x7'-0" DOOR AND FRAME
AutoCAD SHX Text ENLARGE OPENING IN EXIST. CORRIDOR WALL FOR NEW 6'-0" WIDE DOUBLE-DOOR AND NEW FRAME
AutoCAD SHX Text
ALL FURNISHING TO BE RETURNED TO THE VA
AutoCAD SHX Text
ALL DEXA EQUIPMENT TO BE REMOVED BY VA
AutoCAD SHX Text
EXISTING MED GAS TO REMAIN
AutoCAD SHX Text
EXISTING LEAD LINED GYP BD. CORRIDOR WALL TO REMAIN
AutoCAD SHX Text PROVIDE TEMPORARY DUST PARTITION TO WORK AREA AND NEW 3'-0"x7'-0" CONSTRUCTION DOOR; 3-5/8" METAL STUD TIGHT TO UNDERSIDE OF EXISTING CEILING, TAPE AND SPACKLE ONE SIDE.
AutoCAD SHX Text N.I.C.
AutoCAD SHX Text N.I.C.
AutoCAD SHX Text M
AutoCAD SHX Text M
AutoCAD SHX Text
CORRIDOR 6503
AutoCAD SHX Text 5'-0"
AutoCAD SHX Text 5'-0"
AutoCAD SHX Text EXISTING GYP BD. TO BE REMOVED AT ROOM SIDE (TYP.) TO PROVIDE NEW LEAD LINED WALL SEE PROPOSED PLAN
AutoCAD SHX Text
EXISTING LEAD LINED GYP BD. CORRIDOR WALL TO REMAIN
AutoCAD SHX Text
LEGEND:
AutoCAD SHX Text
WALK-OFF MAT
AutoCAD SHX Text M
AutoCAD SHX Text
TEMPORARY PLASTIC DUST BARRIER SEAL
AutoCAD SHX Text
EXISTING TO BE REMOVED
AutoCAD SHX Text
EXISTING WALL TO REMAIN
EXISTING 30 MIN RATED SMOKE BARRIER TO REMAIN UNDISTURBED
CENTRAK CENTRAK
CENTRAK
AP
APT
CENTRAK
T
AP
AP
T
CENTRAK
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building Number
Project Number
Drawing Number
Drawn
Dwg. ofRevisions: Date
CONSULTANTS: ARCHITECT:
Facilities
Management on e eig ht h inc h on e fo ot th re e inc he s = o ne fo ot
6"
6" on e an d on e ha lf i nc he s = o ne fo ot on e inc h on e fo ot
6" 6" th re e qu ar te rs in ch o ne fo ot on e ha lf i nc h on e fo ot th re e eig ht hs in ch o ne fo ot on e qu ar te r i nc h on e fo ot
VA FORM 08-6231, OCT 1978
1 2 3 4 5 6 87 9
F
E
D
C
B
A
97 8654321
Services
MG PROJECT #
GAMMA CAMERA RM 6503E/F
MANHATTAN, VAMC
MANHATTAN VA MEDICAL CENTER
423 EAST 23RD STREET
NEW YORK, NEW YORK 6
M.E.P. ENGINEER:M.E.P. ENGINEER:
777 SUNRISE HWY, STE 300
LYNBROOK, NY 11563
516 561 5922 WWW.BEPC.US
BECKER ENGINEERING, PC STCETIC HRA
M G NEW YORK
MICHAEL J. GADALETA, R.A. A.I.A. N.Y. LIC.: 17474 N.J. LIC.: 8935
11 BROADWAY, SUITE 860 NEW YORK, N.Y. 10004
212 674 8456 MGNEWYORKARCHITECTS.COM
LANDMARKS & PRESERVATION
DESIGN & PLANNING
ARCHITECTURE, HEALTH CARE,
DEMO R.C.P AT ROOMS 6503E & 6503F
02 22 2023 AMG 6
A-102.00
630-CSI-102
2019-63
A-102
SCALE: 1/2" = 1'-0"
ROOM 6503E / 6503F DEMO R.C.P.
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text REMOVE THE EXISTING DIAGNOSTIC IMAGING SYSTEM'S MAIN DISCONNECT PANEL. REMOVE THE EXISTING CONDUCTORS BACK TO PANEL AP-L6BC IN ELECTRICAL CLOSET 6543 ALL EXISTING ELECTRICAL DEVICES AT THIS WALL TO BE REMOVED AND RETURNED BACK TO PANEL
AutoCAD SHX Text
EXISTING XRAY IN USE SIGN TO BE REMOVED AND RETURNED TO THE VA
AutoCAD SHX Text S
AutoCAD SHX Text EXISTING MEDICAL AIR, OXYGEN, AND VACUUM TO BE REMOVED. REMOVE ELECTRICAL DEVICES BACK TO SOURCE
AutoCAD SHX Text
REMOVE ANY ABANDONED SURFACE- MTD OR EXPOSED ELECTRICAL CONDUITS. V.I.F.
AutoCAD SHX Text EXISTING 2'x2' LIGHTS AND DOWNLIGHTS AND ASSOCIATED WIRING TO BE REMOVED THROUGHOUT BACK TO FIRST JUNCTION BOX (TYP.) RESECURE EXISTING ELECTRICAL JUNCTION BOXES
AutoCAD SHX Text EXISTING SPRINKLER HEADS TO BE REMOVED THROUGHOUT AND REPLACED WITH NEW TO ALIGN WITH NEW CEILING GRID AS REQ'D (TYP.)
AutoCAD SHX Text
EXISTING XRAY IN USE SIGN TO BE REMAIN
AutoCAD SHX Text EXIST. CEILING MTD CENTRAK MONITORING SYSTEM TO BE REMOVED AND STORED FOR RE-INSTALLATION. COORDINATE WITH HOSPITAL STAFF (TYP.)
AutoCAD SHX Text
EXISTING CEILING GRID AND TILES TO BE REMOVED
AutoCAD SHX Text
EXISTING DIFFUSERS AND DUCTWORK ABOVE TO BE REMOVED. SEE MECHANICAL DRAWINGS
AutoCAD SHX Text EXISTING CEILING DIFFUSERS AND DUCTWORK ABOVE TO BE REMOVED. SEE MECHANICAL DRAWINGS.
AutoCAD SHX Text EXISTING 2x4 LIGHTS TO BE REMOVED
AutoCAD SHX Text
EXISTING SPRINKLER HEADS TO REMOVED AND REPLACED WITH NEW. SEE PROPOSED PLAN
AutoCAD SHX Text
EXISTING CEILING GRID AND TILES TO BE REMOVED
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text
EXISTING RETURN GRILLE TO BE REMOVED AND REPLACED IN NEW ROOM. SEE PROPOSED PLAN
AutoCAD SHX Text EXISTING CEILING DIFFUSERS TO BE REPLACED. SEAL TO MINIMIZE CONTAMINATION AND DUST CONTAINMENT
AutoCAD SHX Text N.I.C.
AutoCAD SHX Text N.I.C.
AutoCAD SHX Text CONTRACTOR TO INSTALL 1-HR RATED CEILING BETWEEN TEMPORARY PARTITION AND AREA OF WORK
AutoCAD SHX Text
EXISTING ELECTRICAL DEVICES AND OUTLETS TO REMAIN UNLESS OTHERWISE NOTED
AutoCAD SHX Text
SINGLE POLE LIGHT SWITCH
AutoCAD SHX Text
TELEPHONE AND DATA OUTLET
AutoCAD SHX Text
DUPLEX RECEPTACLE
AutoCAD SHX Text
CEILING DIFFUSER
AutoCAD SHX Text
SPRINKLER HEAD
AutoCAD SHX Text
THERMOSTAT
AutoCAD SHX Text
LIGHT FIXTURE
AutoCAD SHX Text
CIRCUIT BREAKER PANEL
AutoCAD SHX Text
ELECTRICAL LEGEND
AutoCAD SHX Text
CEILING MTD CENTRAK SYSTEM
S
A-202A-201
A-201
A-202
A-200
A-200
FD
A-200
ITEM DESCRIPTION
(GE SUPPLIED / CONTRACTOR INSTALLED)
CT GANTRY BASEPLATE
NM GANTRY BASEPLATE
TABLE ANCHOR PLATE
COLLIMATOR EXCHANGE PLATE
SWING PLATE
3 5/8" METAL RUNNER
SECURED TO SLAB
PROVIDE 1 LAYER OF 5/8" LEAD
LINED (1/16") GYP. BD. BOTH SIDES
FROM FLOOR TO HEIGHT OF 7'
3 5/8" METAL STUDS
@ 16" O.C.
SOUND ATTENUATION BATT.
1 HR FIRE RATING
ANSI/UL 263 DESIGN NO. U465
43-44 STC SOUND TRANS.
SCALE: 1" = 1'-0"
ACOUSTICAL
CEILING TILE
EXISTING CONCRETE SLAB
NEW METAL STUD WALL
3 5/8" METAL RUNNER
SECURED TO SLAB
3 5/8" METAL STUDS
@ 16" O.C.
SOUND ATTENUATION BATT.
1 HR FIRE RATING
ANSI/UL 263 DESIGN NO. U465
43-44 STC SOUND TRANS.
SCALE: 1" = 1'-0"
PROVIDE 1 LAYER OF
5/8" GYP. BD. BOTH SIDES
ACOUSTICAL
CEILING TILE
EXISTING CONCRETE SLAB
NEW LEAD LINED WALL
3 5/8" METAL RUNNER SECURED TO
SLAB
PROVIDE 1 LAYER OF 5/8" LEAD
LINED (1/16") GYP. BD. AT NUCLEAR
ROOM SIDE FROM FLOOR TO
HEIGHT OF 7'
3 5/8"…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .