P09 SOW Replace Roof of emergency generator on Bldg 39- Final.docx

DOCX document 40 KB Posted

Attached to
Z1DZ--502-23-392 Replace Roof on Emergency Generator Building 39
Solicitation number
36C25626R0020
Issued by

About this file

This is a Statement of Work (SOW) for Project 502-23-392, detailing the replacement of approximately 566 square feet of roof on Building 39 at the Alexandria VA Health Care System in Pineville, Louisiana. The primary scope involves removing the deteriorated bituminous felt roof down to deck level and installing a new 80 mil Thermoplastic Polyolefin (TPO) membrane. Work includes treating rusted deck areas (up to 200 square feet), extending non-compliant curbs with steel framing, installing new trim and gutters, and using a crane to remove and reinstall the vent hood. Additional work encompasses removing and replacing two layers of drywall ceiling, lighting, and ceiling-mounted electrical devices, with interior drying over a 60-day period using contractor-provided fans. The contractor must apply a fire-rated coating system (3M fire dam coat basis of design) to achieve a two-hour fire rating, install energy-efficient LED lights, and address mold remediation and lead-based paint identified on exterior surfaces. The work must comply with ICRA Standard I for exterior projects and applicable interior abatement practices.

The total period of performance is 150 calendar days, divided into a 30-day pre-construction phase and a 120-day construction phase, both requiring separate Notices to Proceed. Critical requirements include conducting a mandatory site survey before mobilization to verify utilities and identify conflicts, with findings submitted as Submittal #1 for approval. All work must occur between 8:00 a.m. and 4:30 p.m. CST, Monday through Friday, excluding federal holidays, and the contractor must maintain the building as water-tight and keep the standby-mode generator protected and operational throughout construction. The contractor is responsible for all labor, tools, materials, equipment, supervision, site preparation, demolition, debris removal (with contractor-provided dumpsters), and obtaining access badges for all personnel. Key deliverables include a submittal log, site survey report, and all required submittals approved by the Architect/Engineer and VA Contracting Officer's Representative. All personnel must have proper certifications, with the superintendent requiring OSHA 30 certification, and the contractor must provide monthly payment applications with work approved by the Project Engineer or COR before payment authorization.

View the file

Other files

File Type Posted
S05 RFIs 502-23-392 Replace Roof on Emerg. Adment 0004.docx DOCX document
36C25626R0020 0004.docx DOCX document
Wage Determination LA20250051 01-15-2026.pdf PDF
36C25626R0020 0003.docx DOCX document
36C25626R0020 0002.docx DOCX document
S05 RFIs 502-23-392 Replace Roof on Emerg. Generator Bldg. 39.docx DOCX document
S04 Site Visit 03-02-2026 Sign in sheet-Final.pdf PDF
36C25626R0020 0001.docx DOCX document
EXHIBIT C.docx DOCX document
P09 502-23-392 Drawings.pdf PDF
EXHIBIT D.docx DOCX document
EXHIBIT B.docx DOCX document
EXHIBIT E.docx DOCX document
EXHIBIT A.docx DOCX document
36C25626R0020.docx DOCX document
P09 502-23-392 Pineville Generator Roof - Specifications updated 01-02-26.pdf PDF
P07 Wage Determination LA20250051 01-15-2026.pdf PDF
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scope of Work

Project No. 502-23-392 Pineville Bldg 39 Generator Roof Replacment Alexandria VA Health Care System, Pineville, LA

Scope:

The primary scope of the project is to replace approximately 566 square feet of the existing roof of building 39 with a new 80 mil Thermoplastic Polyolefin (TPO) Membrane type. The current roof component of bituminous felt that has deteriorated will be completely removed to the deck level. The current curbs and all roofing components will be removed. The current curb is not code compliant. The contractor will extend the curb with additional steel framing to received the hood as indicated in the drawings. All new roofing systems will be installed with the use of construction drawings and specifications. The rusted (up to 200 sf) part of the deck will be treated and prepared according to the recommendation of AE to receive new roofing component and TPO.

During the material sample collection, it was discovered that some of the roof deck insulation is saturated with moisture-100%. Though no pinholes were noted in the test area, the rust was extensive. The design has accounted for rust treatment; however, if pinholes are discovered, partial deck replacement may be required.

The roof work will also include careful installation of trim and gutters. A crane will be needed to perform work to remove the vent hood prior to roof replacement and reinstall.

The two layers of drywall ceiling, lighting and ceiling mounted electrical devices will be removed and replaced with new. The interior wall shall be thoroughly cleaned and allowed to dry over a 60 day period using fans provided by the contractor. The contractor shall test to ensure the surfaces are dried out based on recommendation of the paint manufacturer. The deck, the joists, and roofing members shall be coated to achive a two hour fire rating. Paint shall be applied to achive uniformity. A Basis of Design 3M fire dam coat will be applied over any void areas, taping off each section for a clean looking hard edge finish.

The new lights to be installed shall be energy-efficient LED lights.. Other existing devices shall be installed in accordance with code compliance.

Both construction drawing and specifications should be used together. The contractor will provide an insulation shop drawing before commencement of the roofing work. If the construction drawings conflict with the specifications, please bring to the attention of the COR and CO. The specifications superceed the Construction drawings.

The project is exterior in nature and shall meet ICRA Standard I. Any interior abatement will adhere to those abatement practices.

The contractor will ensure proper protection of the generating system housed in building 39 from construction debris and ensure that the building is water tight throughout the construction period. The generator should never be flooded during the construction period.

The generator will be in a standby mode for operation throughout the construction period. The contractor will give unrestricted access to the VA staff and also allow the VA to operate the generator as required. This includes regulary scheduled maintenance during the construction period.

If the generator will not be in an operable status, this shall be communicated no less than two weeks in advance and this shall be coordinated with COR for minimum disruptions to the facility operations. Schedule this for outside normal hours of operation (Monday-Friday, 8AM-4:30PM, excluding Federal Holidays).

Objective:

1. To ensure all requirements of contract drawings and specifications are met and completed by the completion date provided in contract documents.

2. To ensure that all construction activities are performed in such a manner as to ensure safe and correct operation and in compliance with applicable local, state and federal regulations and contract drawings and specifications.

3. Mold remediation will be necessary in several areas as water infiltration has been occurring for some time.

4. Lead has been identified on the exterior paint of the buildings at our facility.

Tasks:

Furnish all labor, tools, materials, equipment, and supervision necessary for the work to replace the existing Alexandria VAHCS Building 39 Roof as detailed in the Drawings and Specifications for this project.

The work for this project includes, but is not limited to the following improvements:

Contractor shall completely prepare site for operations, including demolition and removal of existing roof, and other associated equipment, including dumpsters. Use of any VA dumpsters for debris removal is strictly prohibited. Furnish labor and materials and perform work to provide new roof and associated components.

Special Condition:

Prior to mobilization and commencement of any construction, the contractor shall conduct a mandatory thorough survey and investigation of all the work sites for the Replace Bldg. 39 Roof Project. This survey and investigation shall include verifying all utilities and equipment impacted by the roof replacement project, which includes but is not limited to existing generator. Verify all components, materials, utilities, the depth, size and material and any structures that may conflict with the proposed construction. The contractor shall be responsible for choosing the process He/She deems necessary to employ that will provide the most accurate data of the existing conditions at these sites. Once this information is obtained, the contractor shall prepare a report listing all discrepancies, conflicts and remedies to all conflicts. This report shall be submitted as Submittal #1. The Resident Engineer/COR will review for technical feasibility. Once approved, the Contracting Officer will request a formal proposal for the corrective work. Approval of this cost proposal will be required prior to the commencement of any corrective construction.

All conditions requiring further repair, that are discovered during demolition, shall be reported to the COR within 24 hours in a documented report with photos. e.g. Any unforeseen circumstances on stripping of the roof should be brought to the COR attention within 24 hours of discovery. Also, any other conditions falling under the description of unforeseen conditions.

Any of damage to the building orchestrated by construction activity or any damage to the generator even when it is a small magnitude shall be reported to the COR, with a documented report including photos, an explanation of what happened and why, within 24 hours of occurrence. This shall be for the purpose of updating plans, schedules, and material orders activating contingency plan as may deem necessary.

The building will remain in full operation during construction, the generator will remain in standby mode and the building will remain completely water tight during construction to the maximum extent practical.

Delivery:

All personnel in the contractor’s services shall have certified or proper training on the tasks they perform. Superintendent must provide OSHA 30 certification.

The Project Engineer or COR shall be informed by the contractor of the following situations/events in writing:

· The anticipated start date of any contract work.

· As soon as it is known that the work will take longer than expected.

· As soon as it is known that a possible change order will have to happen.

· To provide a written plan for corrective action for any work that cannot be completely within contract specified time.

· Inform COR if contractor needs to stay outside of normal operating hours.

· Contractor Payment Application shall be provided at the beginning of each month for the previous month work that has been completed.

All work shall be completed in accordance with contract drawings and specifications.

All required contract works completed shall be approved and accepted by Project Engineer or COR prior to accepting and approving contractor application for payment.

Security and General Requirements:

All on-site work should be completed between the hours of 8am and 4:30pm CST, Monday through Friday excluding federal holidays unless otherwise listed in the tasks section or other working hours are approved by the COR.

Contractor shall obtain an access badge from the VA Police Department while performing work on-site for their self, their employees and all subcontractors under their authority.

Security and privacy requirements vary depending on the equipment to be serviced and the service being performed. Contractor personnel may be required to complete any or all of the following but not limited to:

· Online training.

· Read, sign, and comply with ‘Contractor Rules of Behavior’.

· Submit to finger printing and background investigation.

· Provide network security information as requested for any equipment used in the VA facilities.

· The extent of these requirements shall be determined by Project Engineer or COR using current facility Information Technology and Privacy rules in cooperation with experts in those departments.

Parking shall be limited to established concrete or improved rock parking lots, Project Engineer or COR will advise which parking lots to use. Contractors and personnel are not allowed on the grass area unless specifically authorized by the Project Engineer. U.S. District Court Violation Notices shall be issued for parking violations.

The contractor and all employees shall comply with all applicable Alexandria VA Health Care System fire, safety, and traffic regulations.

The contractor is to field verify existing conditions.

All work is to be performed within all ASME, OSHA, EPA, VA, and Federal, State and local codes and regulations.

Proper Lock-out/Tag-out procedures shall be used when appropriate.

No roadway, drainage ditch, pedestrian walkway, or any other service, utility, or access to any of the above is to be blocked or rendered unusable for any length of time during this project unless previously approved by the Project Engineer.

All work, materials, storage of materials and equipment, repair procedures and unforeseen problems or circumstances are to be coordinated with the Project Engineer.

Work on this project shall not begin until authorized by the Contracting Officer.

The title Project Engineer or COR shall refer to the Contracting Officer’s Representative.

Work to be conducted on a Fully Operational VA Hospital Campus, in and around Mental Health and Long Term Care facilities. Tools and equipment shall be kept under close watch to prevent patient injury.

Place of Performance:

· Work shall be performed, with issuance of Notice to Proceed by the CO, at the Alexandria VA Health Care System, Pineville, LA, or in the immediate vicinity as required by this Scope of Work.

· Equipment or Government property may be removed from the facilities with prior permission from Project Engineer or COR and the Department Director.

Period of Performance – 150 days

The construction portion of this project will consist of two separate periods, each of which must be preceded by a NTP issued by contracting.

1. Pre-construction period – 30 Days – Contractor to provide the following deliverables before the end of this period:

a. Submittal log of all submittals to be approved during the course of the project.

b. Site survey of pre-existing conditions as described in paragraph titled “special conditions”.

c. All submittals which are to be approved by the AE and VA COR.

2. Construction period – All contractually required work and tests must be successfully completed within 120 calendar days of issuance of Notice to Proceed for construction.

ISO Requirements:

· The C&A requirements do not apply, therefore a Security Accreditation Package is not required.

Smoking, vaping, and tobacco dipping are not allowed at this facility.