Owner Building Plans

347 KB Posted

Attached to
ITB - Timberline Booster Pump Station Replacement
Solicitation number
2023-ITB-01
Issued by
Twiggs County, Georgia

About this file

This is an Owner Building Plans document related to the City of Young Harris, Georgia's Invitation to Bid for the Timberline Booster Pump Station Replacement project. The project encompasses the replacement of a water line and booster pump station for the Young Harris Water System. The scope includes installation of two Grundfos Hydro Multi-E CRE 10-10 60Hz booster pumps, replacement of approximately 2,540 linear feet of existing PVC water line with 6-inch diameter Class 305 PVC water line or 6-inch diameter Class 350 ductile iron pipe, and construction of a new single-story booster pump station building. Associated work includes site excavation and grading, on-site building construction, site concrete paving, asphalt access driveway, finish grading, erosion control, site stabilization, utility trenching, backfilling, waterline testing and decontamination, and replacement of all related valves, meters, curb stops, and appurtenances. Sealed bids were required to be submitted to City Hall at 50 Irene Berry Drive, Young Harris, Georgia 30582, by 3:00 P.M. local time on Friday, March 31st, 2023, at which time bids would be publicly opened and read.

Interested bidders could obtain copies of the Site Development Plans and related contract documents by contacting the City Engineer, Reid Dyer, at rdyer@husseygaybell.com. The document referenced serves as the Owner Building Plans for the booster pump station construction component of the project and would detail the specifications, design requirements, and technical parameters necessary for contractors to prepare accurate bids and execute the work.

Text of this file

Pump House

1. Attached sketch is for concept purposes only. All work shall conform to state and local building codes.

2. Main structure may be poured reinforced concrete or concrete block.

3. All wood framing shall be pressure treated lumber

4. All siding shall be “hardy” type material or equal.

5. Electrical

a. 2 - 20 amp GFI outlets as generally shown on sketch

b. 1 dedicated outlet as sufficient to power a 240VAC / 60Hz / 30A heater as generally shown on sketch.

c. 4 – EnviroLite T8 LED tube shop lights or equal as generally shown on sketch

6. Door: 5-0 commercial steel double door with deadbolt lock

7. Metal Roof

8. All soffits and eves shall be enclosed and properly ventilated.

9. All exterior surfaces excluding main door shall be painted.

OWNER'S BUILDING PLANS

Page:1February 16, 2023 Timberline Booster Pump ISO

Page:2February 16, 2023 Timberline Booster Pump Front

/4

1'-4"

Poured reinforced concrete wall or concrete block wall

5-0 commercial double steel door w/ deadbolt

All wood framing to be pressure treated

Page:3February 16, 2023 Timberline Booster Pump Side

24" overhang above door

6" overhang

2x6 pressure treated rafter

12"

2" metal roof

Page:4February 16, 2023 Timberline Booster Pump Electrical

240volt/30amp heater outlet

20 amp GFI outlet

Single pole light switch

20 amp GFI outlet

48" LED light bar

Double lamp flood w/ motion sensor

building notes
building sketch

Other files

File Type Posted
Scope of Work-Bid Requirements —
Pre-Bid Conference Agenda —
Award Information —
addendum No. 1 —
Invitation for Bids —
Pre-Bid Conf. Sign In Sheet —

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .