Orlando_Executive_Airport_(ORL)_Runway_7-25_Rehabilitation_and_Related_Work_(BP-00050)_(Addendum_#1_Revision).pdf

PDF 418 KB Posted

Attached to
Orlando Executive Airport (ORL) Runway 7-25 Rehabilitation and Related Work (BP-00050)
Solicitation number
25-597-IFB
Issued by
Orange County, Orlando City, Florida

About this file

This is an Invitation for Bids (IFB) issued by the Greater Orlando Aviation Authority for the Runway 7-25 Rehabilitation and Related Work at Orlando Executive Airport (Project BP-00050). The project involves comprehensive runway rehabilitation, including milling and overlaying the runway, blast pads, and connecting taxiways within the safety area. Specific scope elements include pavement geometric modifications, safety area improvements to meet FAA standards, and rehabilitation of the existing runway lighting system, markings, and signage. The bid includes multiple schedules (Schedule A, Schedule B, and Add Alternatives No. 1-3) with detailed line items covering activities such as mobilization, cold milling at various depths, joint and crack repair, asphalt surface course installation, pavement marking, electrical work, lighting modifications, and sodding.

The solicitation is structured as a federal version construction bid, with electronic submissions required through the OpenGov Procurement Platform. Bidders must complete a vendor questionnaire, provide bid security, and ensure consistent unit pricing across schedules. The project includes several allowances, including a $200,000 drainage pipe rehabilitation allowance, a $25,000 FAA flight inspection allowance, and a $30,000 airfield lighting control system modification allowance. The bid documents specify detailed technical specifications for each line item, with quantities ranging from single lump sum items to thousands of square yards or linear feet of various construction and rehabilitation activities. Bidders are required to follow strict submission guidelines, including creating a free account on the procurement platform and submitting all documents electronically.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INVITATION FOR BIDS

(FEDERAL VERSION - CONSTRUCTION)

25-597-IFB

ORLANDO EXECUTIVE AIRPORT (ORL)

RUNWAY 7-25 REHABILITATION AND

RELATED WORK (BP-00050)

TABLE OF CONTENTS

1. Introduction

2. Instructions to Bidders

3. Vendor Questionnaire

4. Pricing Table

ATTACHMENTS

A - ORL_BP-00050_IFB_SPECS

B - ORL_BP-00050_IFB_PLANS

C - ORL_BP-00050_IFB_SIGNED AND SEALED TOPOGRAPHIC SURVEY

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

GREATER ORLANDO AVIATION AUTHORITY

Orlando Executive Airport (ORL) Runway 7-25 Rehabilitation and Related Work (BP- 00050)

1. Introduction

1.1. Summary

This project provides the rehabilitation of Runway 7-25 at the Orlando Executive

Airport. The scope of work includes the milling and overlaying of the runway, blast pads, and connecting taxiways within the safety area of the runway. It includes pavement geometric modifications and safety area improvements to meet FAA standards. It will also include rehabilitating the existing runway lighting system, markings, and signage.

Please see the Attachments section for the Division 00, Procurement and

Contracting Requirements (including Bid Documents, Bid Forms), drawings and specifications.

https://procurement.opengov.com/portal/goaa/projects/157577/document?section=1432843

2. Instructions to Bidders

2.1. Important Instructions for Electronic Submittal

The Greater Orlando Aviation Authority is ONLY accepting electronic submissions.

Vendor shall create a FREE account with OpenGov Procurement by signing up at https://procurement.opengov.com/signup. Once you have completed account registration, browse back to this page, click on "Draft Response", and follow the instructions to submit the electronic bid.

2.2. Solicitation Information / Instructions

a. Sealed electronic responses will be received for this Solicitation through the

Greater Orlando Aviation Authority e-Procurement Platform located at https://procurement.opengov.com/portal/goaa. Once you have completed the free account registration, browse back to this page, click on "Draft Response", and follow the instructions to submit the electronic response. By way of the

Platform, Respondents will be locked and digitally encrypted until the submission deadline passes.

b. All Responses must be received by the Aviation Authority as noted in the

Timeline. All Responses timely received will be listed with the name of the

Respondent during the Virtual Opening. The e-Procurement Platform will not allow for late submittals.

c. The time/date stamp clock located in the electronic submittal Platform shall serve as the official authority to determine lateness of any response.

d. The Aviation Authority shall not be responsible for delays caused by any occurrence. This shall include any delay as a result of a technology issue. Any late response shall not be accepted.

e. Responses submitted by hard copy, e-mail, or fax shall not be accepted.

Responses submitted outside of the designated electronic submission Platform shall be rejected as non-responsive regardless of where and when they were received.

f. Respondents shall not be allowed to modify their responses after the opening time and date.

g. Respondents shall submit one Response only. Prime Respondents who also participate in other responses as subcontractors will not be considered.

h. Each Respondent shall complete the Vendor Questionnaire. Please respond to each item individually, as applicable.

https://procurement.opengov.com/signup https://procurement.opengov.com/portal/goaa

i. Unless otherwise directed, all uploaded files must be in PDF format. Do not upload zip files.

j. Once the deadline for receipt of Responses has occurred, no Response may be altered without written approval from the Aviation Authority.

2.3. Submitting Questions and Review of Solicitation

a. Respondents shall submit all inquiries regarding this Solicitation via the e-

Procurement Platform, located at https://procurement.opengov.com/portal/goaa

. Please note the deadline for submitting inquiries. All answers to inquiries will be posted on the Aviation Authority e-Procurement Platform. Respondents may also click “Follow” on this Solicitation to receive an email notification when answers are posted. It is the responsibility of the Respondent to check the website for answers to inquiries.

b. The purpose of any Pre-bid Conference is to review and discuss the solicitation

(and any addenda) as published. Attendance is non-mandatory, but highly encouraged. Respondents are expected to be familiar with the Solicitation

Documents.

c. Questions will be answered through the e-Procurement Platform.

d. If the Aviation Authority determines that it is necessary to change the dates or times prior to the due date, the change will be announced and posted on the e-

Procurement Platform

e. All prospective Respondents shall thoroughly examine and become familiar with the Solicitation package and carefully note the items which must be submitted with the Solicitation as detailed in Section: Vendor Questionnaire.

f. Submission of a Response shall constitute an acknowledgment that the

Respondent has read and understands the Solicitation Documents. The failure or neglect of a Respondent to receive or examine any Solicitation Document shall in no way relieve it from any obligations under its Response or the Contract. No claim for additional compensation will be allowed which is based upon a lack of knowledge or understanding of any of the Contract Documents or the scope of work.

2.4. Communications; Questions Regarding Specifications or Solicitation

Process

a. Any official communication from a Respondent during the Solicitation process should be submitted to the Aviation Authority via the e-Procurement Platform, https://procurement.opengov.com/portal/goaa . A copy of the Administration

Policies (Sections 180.01 and 180.03) are available on the Aviation Authority website.

b. In accordance with the above-referenced policies, any communication directly or indirectly to seek to encourage any specific result in connection with an Aviation

Authority selecting process, including but not limited to, written communications, any and all forms of electronic communications or messaging, including social media, oral communications either in person or by telephone, initiated by a

Respondent or through a lobbyist, agent or third person, to any Aviation

Authority staff and/or Committee/Board member who is a member of any committee constituted for the purposes of ranking Solicitations, making recommendations or making an award, is prohibited from the time that the

Solicitation is released to the time that the award is made.

c. All firms are hereby placed on notice that the Aviation Authority Board and staff shall not be contacted about this solicitation. Firms and their agents shall not contact members of the Aviation Authority staff and/or Committee/Board member (with the exception of designated Procurement Agent and the Small

Business Development Department). An appropriate official or employee of the

Aviation Authority may initiate communication with a Respondent in order to obtain information or clarification needed to develop a proper and accurate evaluation. Any official communication from a Respondent during the solicitation process should be submitted via the e-Procurement Platform as directed during the solicitation process. Failure to adhere to these requirements may result in

Board action to disqualify your firm from consideration of award.

d. Requests for interpretation, clarification or correction of this solicitation, documents, forms or other material in the solicitation should be made in writing via the e-Procurement Platform during the Question-and-Answer period.

Questions or issues raised at the Pre-Bid Conference or during the Question-and-

Answer period, which, in the Aviation Authority's discretion, necessitate changes to the solicitation documents, will be issued via an Addendum at the conclusion of the question period, and will be made available through the e-Procurement

Platform. It is the responsibility of each Respondent to ensure that it has received and reviewed any and all such responses and addenda.

2.5. Appeals

Any Bidder who is adversely affected by a decision or intended decision concerning this competitive solicitation or contract award and who wants to appeal such specifications, decision, or intended decision shall file an appeal within five (5) business days of the date of any decision or intended decision of the Construction Committee and in compliance with the Aviation Authority’s Policy 110.04, Appeal Process. Failure to file an appeal in accordance with the Aviation Authority’s Policy 110.04, shall constitute a waiver of the appeal process.

The intent to award to a Bidder, if any, will be posted on the Aviation Authority’s e-procurement platform website, and will remain posted for a period of five business days: excluding weekends, federal holidays, and Aviation Authority’s holidays. Failure to file an appeal in accordance with the above stated policy shall constitute a waiver of the appeal process.

2.6. Nondiscrimination Legal Notices

a. The Aviation Authority does not discriminate upon the basis of any individual’s disability status. Anyone requiring reasonable accommodations as provided for in the Americans with Disabilities Act or Section 86.26, Florida Statutes, should contact the ADA Coordinator at 407-825-7105 as soon as possible, or at least one full business day prior to any scheduled meeting.

b. In accordance with Section 287.05701, Florida Statutes, the Aviation Authority may not request documentation of or consider a Respondent social, political, or ideological interests when determining if the Respondent is responsible.

2.7. Reservation of Rights

a. The Aviation Authority reserves the right, in its sole discretion, to waive any informalities or irregularities of a Response, except that (i) the Aviation Authority will not waive the requirement that a Response, complete in all material respects, be received by the Aviation Authority by the time and date specified in the Timeline for the receipt thereof, and (ii) the Aviation Authority will not consider any Response which does not conform in all material respects to the terms of this solicitation including a commitment to execute the Contract by the

Respondent, if applicable.

b. The Aviation Authority reserves the right to solicit from available sources relevant information concerning a Respondent’s past performance and may consider such information in its evaluation and selection of Respondents.

c. The Aviation Authority reserves the right to request clarification of information submitted in any Response, to require additional information from any

Respondent, or, in the Aviation Authority's sole discretion, to reject any or all

Respondents for any reason and to re-advertise or not to re-advertise the project.

d. The Aviation Authority reserves the right to reject responses containing any additional terms or conditions not specifically requested in the original special conditions and/or the terms and conditions.

e. The Aviation Authority reserves the right to cancel an award to a Respondent for any reason via written notice.

f. As the best interest of the Aviation Authority may require, the right is reserved to make award(s) by individual items, group of items, all or none, or a combination thereof; or to reject any and all responses. Respondents are cautioned to make no assumptions unless their Response has been determined as meeting the Minimum Requirements and being responsive and responsible. All awards made as a result of this solicitation shall be made in accordance with the applicable policies of the Aviation Authority.

g. The Aviation Authority reserves the right to reject any and all Solicitation, and to re-advertise or elect not to proceed with the services for any reason.

h. The Aviation Authority shall have the right, but not the obligation, to award all or any portion of the services. The extent and scope of the Services, along with the fees for such services, will be subject to final approval by the Aviation Authority.

i. The Aviation Authority reserves its right to award any or all of the advertised services subject to the availability of funding.

j. The terms Bidder, Proposer and Respondent are used interchangeably throughout this Solicitation. The terms Proposal, Response, Bid and Statement of

Qualifications are used interchangeably throughout this Solicitation.

k. Labeling information as “proprietary” or “confidential” or any other designation of restricted use shall not protect information from release if required or deemed appropriate by the Aviation Authority under applicable policies, open meeting laws, or public records laws, see Chapters 119 and 286, Florida Statutes. All materials or documents submitted in response to this Solicitation will become the property of the Aviation Authority. By submitting a Response, Respondents specifically waive all claims against the Aviation Authority related to the disclosure of public records.

2.8. Code of Ethics and Business Conduct Policy

a. The Aviation Authority has adopted a Code of Ethics and Business Conduct Policy

(Section 204.01) which addresses the obligation of the Aviation Authority’s Board members and employees to follow the Florida Statutes in reference to these issues. This includes, but is not limited to, the obligations of the Aviation

Authority’s Board members and employees with respect to having an interest in business entities, outside employment, gratuities, divulgence of information, unauthorized compensation and acceptance of gifts. Please be aware that any violation of this policy by a Respondent and/or any attempt to influence an

Aviation Authority Board member or employee to violate the policy is sufficient cause for the denial of the right of the Respondent to Respond on any Contract or sell any materials, supplies, equipment, or services to the Aviation Authority for a period of time that is determined by the Chief Executive Officer. A copy of this policy is available upon request from the Chief Administrative Officer.

2.9. Public Meetings/Public Records

a. Please be aware that all meetings of the Aviation Authority’s Board are duly noticed public meetings and all documents submitted to the Aviation Authority as a part of or in connection with a Solicitation will constitute public records under

Florida law regardless of any person’s claim that proprietary or trade secret information is contained therein. Public meetings are posted on the Aviation

Authority's website: https://flymco.com/airport-business/sunshine-meetings/

b. Attendance by all interested Parties is encouraged.

https://flymco.com/airport-business/sunshine-meetings/

3. Vendor Questionnaire

3.1. Confirmation of Addenda*

Please confirm that your Bid includes all Addenda that have been posted for this solicitation.

☐ Please confirm

*Response required

3.2. Fully Executed Bid with all forms and documents (without pricing)*

Please Upload your COMPLETE response, including any and all required forms listed in the solicitation and the corresponding attachments.

(Do not upload pricing information in this document. Instead, complete the

Pricing Table.)

*Response required

3.3. Separate Pricing Table*

Confirm that no pricing is included in the above document and that pricing has been submitted on the Opengov pricing table.

*Response required

3.4. Requirement for Consistent Unit Prices*

Respondent confirms it understands that its pricing table may be rejected as non-responsive if the unit rates for the same work in the Schedule B and all alternates are not identical. See Addendum No. 1.

☐ Please confirm

*Response required

3.5. Bid Security

Please upload a copy of the fully executed bid security and deliver the original to the address in the instructions.

4. Pricing Table

BP-00050 ORL RUNWAY 7-25 REHABILITATION & RELATED WORK - BID

SCHEDULE A

Line

Item

Spec Description Unit of

Measure

Quantity Unit Cost Total

A1 C-105-

Mobilization (10% Maximum) LS 1

A2 C-100-

Contractor's Quality Control

Program

LS 1

A3 C-102-

Temporary Air and Water

Pollution, Soil Erosion, and

Siltation Control

LS 1

A4 C-106-

Safety, Security, and

Maintenance of Airport

Operations

LS 1

A5 C-104-

Construction Survey LS 1

A6 P-101-

Cold Milling, 0.5" Nominal

Depth

SY 2,850

A7 P-101-

Cold Milling, 4" Nominal

Depth

SY 125,000

A8 P-101-

Cold Milling, 2" Nominal

Depth

SY 1,850

A9-1 P-101-

Joint and Crack Repair, Greater than 1.5 Inches in

Width

LF 2,500

A9-2 P-101-

Joint and Crack Repair, 1.5

Inches or Less in Width

LF 12,500

A10 P-101-

Full-Depth Pavement

Demolition

SY 4,150

Line

Item

Spec Description Unit of

Measure

Quantity Unit Cost Total

A11 P-152-

Unclassified Excavation CY 1,000

A12 P-152-

Off-Site Borrow Excavation CY 7,200

A13 P-152-

Stripping SY 32,700

A14 P-401-

Asphalt Surface Course, 4"

Nominal Depth

TON 28,500

A15 P-401-

Asphalt Surface Course, 2"

Nominal Depth

TON 250

A16 P-603-

Emulsified Asphalt Tack Coat GAL 24,100

A17 P-620-

Pavement Marking, Temporary, Without

Reflective Media

SF 236,800

A18 P-620-

Pavement Marking, Permanent, Without

Reflective Media

SF 40,600

A19 P-620-

Pavement Marking, Permanent, With Type III

Reflective Media

SF 130,500

A20 P-620-

Pavement Marking Removal SF 1,350

A21 P-621-

Runway Sawcut Grooving SY 96,000

A22 T-904-

Sodding SY 37,000

Item

Spec Description Unit of

Measure

Quantity Unit Cost Total

A23 SP-

104-1

Temporary Power &

Temporary Airfield

Lighting/Signage/Navigational

Facilities

LS 1

A24 SP-

105-1

Electrical Demolition LS 1

A25 SP-

111-1

Short

Circuit/Coordination/Device

Evaluation/Arc Flash Analysis

EA 1

A26 L-107-

L-806(L), Style 1B, Size 1, LED Internally Lighted Wind

Cone, with L-810(L)

Obstruction Light

EA 1

A27 L-108-

1/C L-824-Type C Unshielded

#8 AWG 5 KV Stranded

Copper Cable (Black

Insulation), Installed in Duct or Conduit

LF 30,000

A28 L-108-

1/C L-824-Type C Unshielded

#8 AWG 5 KV Stranded

Copper Cable (Red

Insulation), Installed in Duct or Conduit

LF 25,000

A29 L-108-

1/C #2 AWG Solid Copper

Counterpoise Cable, Installed over Duct or Conduit

LF 22,000

A30 L-108-

3/4" Diameter by 10.00' Long

Copper Clad Steel Sectional

Ground Rod

EA 770

Item

Spec Description Unit of

Measure

Quantity Unit Cost Total

A31 L-109-

Airfield Lighting Control

System Modifications:

Contractor

LS 1

A32 L-109-

Airfield Electrical Vault

Modifications

LS 1

A33 L-109-

4 KW L-829 Constant Current

Regulator - 5 Step - 208V

EA 1

A34 L-109-

10 KW L-829 Constant

Current Regulator - 5 Step -

208V

EA 1

A35 L-110-

1 Way 2" Schedule 40 PVC

Direct Earth Buried Duct

LF 16,000

A36 L-110-

1 Way 2" Schedule 80 PVC

Directional Bored Duct

LF 3,000

A37 L-110-

2 Way 2" Schedule 40 PVC

Direct Earth Buried Duct

LF 1,600

A38 L-110-

2 Way 2" Schedule 80 PVC

Directional Bored Duct

LF 350

A39 L-110-

4 Way 4" Schedule 40 PVC

Direct Earth Buried Duct

LF 30

A40 L-110-

4 Way 4" Schedule 80 PVC

Directional Bored Duct

LF 120

A41 L-110-

1 Way 4" Split Duct LF 50

A42 L-110-

Base Can Drain Well EA 16

A43 L-115-

L-867D Junction Can (T) EA 8

Item

Spec Description Unit of

Measure

Quantity Unit Cost Total

A44 L-115-

Junction Can Plaza – Two L-

867D Cans

EA 7

A45 L-115-

Junction Can Plaza – Four L-

867E Cans

EA 2

A46 L-125-

L-850C(L) Bidirectional, Clear/Clear, LED, Runway

Edge Light (A)

EA 3

A47 L-125-

L-850C(L) Bidirectional, Clear/Yellow, LED, Runway

Edge Light (A)

EA 7

A48 L-125-

L-858(L) Sign –

Single/Double Face, LED, Size

2 - 1 Module

EA 4

A49 L-125-

L-858(L) Sign –

Single/Double Face, LED, Size

2 - 2 Module

EA 13

A50 L-125-

L-858(L) Sign –

Single/Double Face, LED, Size

2 - 3 Module

EA 15

A51 L-125-

L-858B(L) Runway Distance

Remaining Sign, LED, Size 4

EA 5

A52 L-125-

L-861T(L) Omnidirectional, Blue, LED, Taxiway Edge

Light (T)

EA 16

A53 L-125-

L-862(L) Bidirectional, Clear/Clear, LED, Runway

Edge Light (T)

EA 17

Item

Spec Description Unit of

Measure

Quantity Unit Cost Total

A54 L-125-

L-862(L) Bidirectional, Clear/Yellow, LED, Runway

Edge Light (T)

EA 33

A55 L-125-

L-862E(L) Bidirectional, Green/Red, LED, Runway

Threshold Light (T)

EA 3

A56 L-125-

L-862E(L) Bidirectional, Green/Red, LED, Runway

Threshold Light (A)

EA 13

A57 L-125-

L-862E(L) Unidirectional, Red/Obscured, LED, Runway

Threshold Light (T)

EA 6

A58 L-125-

L-867B, 1/2" Galvanized

Steel Blank Cover (NE)

EA 13

A59 L-125-

L-868B, 3/4" Galvanized

Steel Blank Cover (E)

EA 10

A60 L-125-

Field Lightning Arrestor

Assembly

EA 25

A61 SP-

154-1

L-880(L) PAPI Style B - 4 Box

- 2 Lamps/Optical Box

System - New Complete with

Baffles

EA 1

A62 SP-

155-1

L-849I(L) Runway End

Identifier Light

EA 2

A63 SP-

156-1

6 Strand OSP Multi Mode

Fiber Optic Cable

LF 600

A64 SP-

156-2

FAA Rated Underground

Splice Enclosure

EA 2

Item

Spec Description Unit of

Measure

Quantity Unit Cost Total

A65 D-701-

Drainage Pipe Rehabilitation

Allowance

ALLOW 1 $200,000.00

A66 SP-

111-2

FAA Flight Inspection ALLOW 1 $25,000.00

A67 L-109-

Airfield Lighting Control

System Modifications: Vendor

ALLOW 1 $30,000.00

TOTAL

BP-00050 ORL RUNWAY 7-25 REHABILITATION & RELATED WORK - BID

SCHEDULE B - BASE BID

Line

Item

Description Quantity Spec Unit of

Measure

Unit Cost Total

B1 Mobilization (10% Maximum) 1 C-105-

LS

B2 Contractor's Quality Control

Program

1 C-100-

LS

B3 Temporary Air and Water

Pollution, Soil Erosion, and

Siltation Control

1 C-102-

LS

B4 Safety, Security, and

Maintenance of Airport

Operations

1 C-106-

LS

B5 Construction Survey 1 C-104-

LS

B6 Cold Milling, 4" Nominal

Depth

23,000 P-101-

SY

Item

Description Quantity Spec Unit of

Measure

Unit Cost Total

B7 Cold Milling, 2" Nominal

Depth

215 P-101-

SY

B8-1 Joint and Crack Repair, Greater than 1.5 Inches in

Width

500 P-101-

LF

B8-2 Joint and Crack Repair, 1.5

Inches or Less in Width

3,000 P-101-

LF

B9 Stripping 4,920 P-152-

SY

B10 Asphalt Surface Course, 4"

Nominal Depth

5,200 P-401-

TON

B11 Asphalt Surface Course, 2"

Nominal Depth

30 P-401-

TON

B12 Emulsified Asphalt Tack Coat 4,500 P-603-

GAL

B13 Pavement Marking, Temporary, Without

Reflective Media

60,000 P-620-

SF

B14 Pavement Marking, Permanent, Without

Reflective Media

10,500 P-620-

SF

B15 Pavement Marking, Permanent, With Type III

Reflective Media

38,500 P-620-

SF

B16 Runway Sawcut Grooving 17,000 P-621-

SY

B17 Sodding 4,950 T-904-

SY

Item

Description Quantity Spec Unit of

Measure

Unit Cost Total

B18 Temporary Power &

Temporary Airfield

Lighting/Signage/Navigational

Facilities

1 SP-

104-1

LS

B19 Electrical Demolition 1 SP-

105-1

LS

B20 Short

Circuit/Coordination/Device

Evaluation/Arc Flash Analysis

1 SP-

111-1

EA

B21 L-806(L), Style 1B, Size 1, LED Internally Lighted Wind

Cone, with L-810(L)

Obstruction Light

1 L-107-

EA

B22 1/C L-824-Type C Unshielded

#8 AWG 5 KV Stranded

Copper Cable (Black

Insulation), Installed in Duct or Conduit

30,000 L-108-

LF

B23 1/C L-824-Type C Unshielded

#8 AWG 5 KV Stranded

Copper Cable (Red

Insulation), Installed in Duct or Conduit

25,000 L-108-

LF

B24 1/C #2 AWG Solid Copper

Counterpoise Cable, Installed over Duct or Conduit

22,000 L-108-

LF

B25 3/4" Diameter by 10.00' Long

Copper Clad Steel Sectional

Ground Rod

770 L-108-

EA

Item

Description Quantity Spec Unit of

Measure

Unit Cost Total

B26 Airfield Lighting Control

System Modifications:

Contractor

1 L-109-

LS

B27 Airfield Electrical Vault

Modifications

1 L-109-

LS

B28 4 KW L-829 Constant Current

Regulator - 5 Step - 208V

1 L-109-

EA

B29 10 KW L-829 Constant

Current Regulator - 5 Step -

208V

1 L-109-

EA

B30 1 Way 2" Schedule 40 PVC

Direct Earth Buried Duct

16,000 L-110-

LF

B31 1 Way 2" Schedule 80 PVC

Directional Bored Duct

3,000 L-110-

LF

B32 2 Way 2" Schedule 40 PVC

Direct Earth Buried Duct

1,600 L-110-

LF

B33 2 Way 2" Schedule 80 PVC

Directional Bored Duct

350 L-110-

LF

B34 4 Way 4" Schedule 40 PVC

Direct Earth Buried Duct

30 L-110-

LF

B35 4 Way 4" Schedule 80 PVC

Directional Bored Duct

120 L-110-

LF

B36 1 Way 4" Split Duct 50 L-110-

LF

B37 Base Can Drain Well 16 L-110-

EA

B38 L-867D Junction Can (T) 8 L-115-

Item

Description Quantity Spec Unit of

Measure

Unit Cost Total

B39 Junction Can Plaza – Two L-

867D Cans

7 L-115-

EA

B40 Junction Can Plaza – Four L-

867E Cans

2 L-115-

EA

B41 L-850C(L) Bidirectional, Clear/Clear, LED, Runway

Edge Light (A)

3 L-125-

EA

B42 L-850C(L) Bidirectional, Clear/Yellow, LED, Runway

Edge Light (A)

7 L-125-

EA

B43 L-858(L) Sign –

Single/Double Face, LED, Size

2 - 1 Module

4 L-125-

EA

B44 L-858(L) Sign –

Single/Double Face, LED, Size

2 - 2 Module

13 L-125-

EA

B45 L-858(L) Sign –

Single/Double Face, LED, Size

2 - 3 Module

15 L-125-

EA

B46 L-858B(L) Runway Distance

Remaining Sign, LED, Size 4

5 L-125-

EA

B47 L-861T(L) Omnidirectional, Blue, LED, Taxiway Edge

Light (T)

16 L-125-

EA

B48 L-862(L) Bidirectional, Clear/Clear, LED, Runway

Edge Light (T)

17 L-125-

Item

Description Quantity Spec Unit of

Measure

Unit Cost Total

B49 L-862(L) Bidirectional, Clear/Yellow, LED, Runway

Edge Light (T)

33 L-125-

EA

B50 L-862E(L) Bidirectional, Green/Red, LED, Runway

Threshold Light (T)

3 L-125-

EA

B51 L-862E(L) Bidirectional, Green/Red, LED, Runway

Threshold Light (A)

13 L-125-

EA

B52 L-862E(L) Unidirectional, Red/Obscured, LED, Runway

Threshold Light (T)

6 L-125-

EA

B53 L-867B, 1/2" Galvanized

Steel Blank Cover (NE)

13 L-125-

EA

B54 L-868B, 3/4" Galvanized

Steel Blank Cover (E)

10 L-125-

EA

B55 Field Lightning Arrestor

Assembly

25 L-125-

EA

B56 L-880(L) PAPI Style B - 4 Box

- 2 Lamps/Optical Box

System - New Complete with

Baffles

1 SP-

154-1

EA

B57 L-849I(L) Runway End

Identifier Light

2 SP-

155-1

EA

B58 6 Strand OSP Multi Mode

Fiber Optic Cable

600 SP-

156-1

LF

B59 FAA Rated Underground

Splice Enclosure

2 SP-

156-2

Item

Description Quantity Spec Unit of

Measure

Unit Cost Total

B60 Drainage Pipe Rehabilitation

Allowance

1 D-701-

ALLOW $200,000.00

B61 FAA Flight Inspection 1 SP-

111-2

ALLOW $25,000.00

B62 Airfield Lighting Control

System Modifications: Vendor

1 L-109-

ALLOW $30,000.00

SCHEDULE B - ADD ALTERNATIVE NO. 1

Line Item Description Quantity Spec Unit of

Measure

Unit Cost Total

B63 Mobilization (10%

Maximum)

1 C-105-1 LS

B64 Contractor's

Quality Control

Program

1 C-100-1 LS

B65 Temporary Air and

Water Pollution, Soil Erosion, and

Siltation Control

1 C-102-1 LS

B66 Safety, Security, and Maintenance of Airport

Operations

1 C-106-1 LS

B67 Construction

Survey

1 C-104-1 LS

Line Item Description Quantity Spec Unit of

Measure

Unit Cost Total

B68 Cold Milling, 4"

Nominal Depth

20,200 P-101-2 SY

B69 Cold Milling, 2"

Nominal Depth

250 P-101-3 SY

B70-1 Joint and Crack

Repair, Greater than 1.5 Inches in

Width

500 P-101-4 LF

B70-2 Joint and Crack

Repair, 1.5 Inches or Less in Width

2,500 P-101-4 LF

B71 Full-Depth

Pavement

Demolition

4,150 P-101-5 SY

B72 Unclassified

Excavation

800 P-152-1 CY

B73 Off-Site Borrow

Excavation

500 P-152-2 CY

B74 Stripping 12,500 P-152-3 SY

B75 Asphalt Surface

Course, 4"

Nominal Depth

4,700 P-401-1 TON

B76 Asphalt Surface

Course, 2"

Nominal Depth

50 P-401-2 TON

B77 Emulsified Asphalt

Tack Coat

4,000 P-603-1 GAL

Measure

Unit Cost Total

B78 Pavement

Marking, Temporary, Without Reflective

Media

25,000 P-620-1 SF

B79 Pavement

Marking, Permanent, Without Reflective

Media

8,000 P-620-2 SF

B80 Pavement

Marking, Permanent, With

Type III Reflective

Media

15,500 P-620-3 SF

B81 Pavement Marking

Removal

850 P-620-4 SF

B82 Runway Sawcut

Grooving

15,500 P-621-1 SY

B83 Sodding 16,500 T-904-1 SY

SCHEDULE B - ADD ALTERNATIVE NO. 2

Line Item Description Quantity Spec Unit of

Measure

Unit Cost Total

B84 Mobilization (10%

Maximum)

1 C-105-1 LS

Measure

Unit Cost Total

B85 Contractor's

Quality Control

Program

1 C-100-1 LS

B86 Temporary Air and

Water Pollution, Soil Erosion, and

Siltation Control

1 C-102-1 LS

B87 Safety, Security, and Maintenance of Airport

Operations

1 C-106-1 LS

B88 Construction

Survey

1 C-104-1 LS

B89 Cold Milling, 0.5"

Nominal Depth

2,850 P-101-1 SY

B90 Cold Milling, 4"

Nominal Depth

41,150 P-101-2 SY

B91 Cold Milling, 2"

Nominal Depth

800 P-101-3 SY

B92-1 Joint Crack Repair, Greater than 1.5

Inches in Width

750 P-101-4 LF

B92-2 Joint and Crack

Repair, 1.5 Inches or Less in Width

3,500 P-101-4 LF

B93 Unclassified

Excavation

200 P-152-1 CY

B94 Off-Site Borrow

Excavation

6,700 P-152-2 CY

Measure

Unit Cost Total

B95 Stripping 11,500 P-152-3 SY

B96 Asphalt Surface

Course, 4"

Nominal Depth

9,600 P-401-1 TON

B97 Asphalt Surface

Course, 2"

Nominal Depth

125 P-401-2 TON

B98 Emulsified Asphalt

Tack Coat

8,200 P-603-1 GAL

B99 Pavement

Marking, Temporary, Without Reflective

Media

40,000 P-620-1 SF

B100 Pavement

Marking, Permanent, Without Reflective

Media

10,500 P-620-2 SF

B101 Pavement

Marking, Permanent, With

Type III Reflective

Media

23,000 P-620-3 SF

B102 Pavement Marking

Removal

300 P-620-4 SF

B103 Runway Sawcut

Grooving

31,200 P-621-1 SY

B104 Sodding 11,500 T-904-1 SY

Measure

Unit Cost Total

SCHEDULE B - ADD ALTERNATIVE NO. 3

Line Item Description Quantity Spec Unit of

Measure

Unit Cost Total

B105 Mobilization (10%

Maximum)

1 C-105-1 LS

B106 Contractor's

Quality Control

Program

1 C-100-1 LS

B107 Temporary Air and

Water Pollution, Soil Erosion, and

Siltation Control

1 C-102-1 LS

B108 Safety, Security, and Maintenance of Airport

Operations

1 C-106-1 LS

B109 Construction

Survey

1 C-104-1 LS

B110 Cold Milling, 4"

Nominal Depth

41,150 P-101-2 SY

B111 Cold Milling, 2"

Nominal Depth

650 P-101-3 SY

B112-1 Joint and Crack

Repair, Greater than 1.5 Inches in

Width

750 P-104-4 LF

Measure

Unit Cost Total

B112-2 Joint and Crack

Repair, 1.5 Inches or Less in Width

3,500 P-104-4 LF

B113 Stripping 4,200 P-152-3 SY

B114 Asphalt Surface

Course, 4"

Nominal Depth

9,100 P-401-1 TON

B115 Asphalt Surface

Course, 2"

Nominal Depth

100 P-401-2 TON

B116 Emulsified Asphalt

Tack Coat

8,000 P-603-1 GAL

B117 Pavement

Marking, Temporary, Without Reflective

Media

90,000 P-620-1 SF

B118 Pavement

Marking, Permanent, Without Reflective

Media

14,000 P-620-2 SF

B119 Pavement

Marking, Permanent, With

Type III Reflective

Media

54,000 P-620-3 SF

B120 Pavement Marking

Removal

250 P-620-4 SF

Measure

Unit Cost Total

B121 Runway Sawcut

Grooving

30,000 P-620-1 SY

B122 Sodding 4,200 T-904-1 SY

File details come from the government source that posted it. Updated .