This cost estimate document pertains to the Oriole Beach Boat Ramp Improvements project in Santa Rosa County, Florida, with preliminary design prepared in May 2023. The project encompasses two construction scenarios: the OPC Boat Ramp with cast-in-place concrete construction and a more comprehensive Boat Ramp & Upland Site Improvements option. The first scenario includes mobilization, traffic control, demolition, erosion prevention, dewatering, vinyl sheet-pile seawall construction (189 linear feet), concrete bulkhead (188 linear feet), reinforced concrete ramp (321 square yards), curbing (118 linear feet), and site restoration. The second scenario incorporates all elements from the first option plus underground stormwater system installation, concrete pavement (3,145 square yards), pavement markings, signage, Type "D" curbing (42 linear feet), landscape and irrigation improvements, and additional site restoration. Santa Rosa County Board of County Commissioners issued solicitations for properly licensed and insured contractors with question deadlines of February 23, 2026, and March 13, 2026, with proposal submission deadlines of March 9, 2026, and March 23, 2026, respectively, via the county procurement portal with public opening via Teams.

The OPC Boat Ramp scenario carries a subtotal of $1,076,010 with a 20 percent contingency allocation of $215,202, resulting in a total project cost of $1,291,212. The comprehensive Boat Ramp & Upland Site Improvements scenario has a subtotal of $1,538,400 with a 20 percent contingency of $307,680, totaling $1,846,080. Unit pricing varies by construction component, ranging from $45 per linear foot for standard curbing to $1,500 per linear foot for seawall and bulkhead work, and $1,200 per square yard for reinforced concrete ramp construction. Santa Rosa County encourages participation from all business segments including small businesses, minority-owned businesses, women-owned businesses, and disadvantaged business enterprises, with the county reserving the right to waive irregularities, reject bids, and award based on determination of best county interest.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Table 1 Oriole Beach Boat Ramp May 26, 2023 Preliminary Design OPC Boat Ramp - Cast in Place

ItemDescriptionQuantityUnit PriceCost
1Mobilization/Demobilization1LS$ 20,000$ 20,000
2Maintenance of Traffic1LS$ 5,000$ 5,000
3Demolition1LS$ 30,000$ 30,000
4Prevention, Control, and Abatement of
Erosion and Water Pollution1LS$ 10,000$ 10,000
5Dewater1LS$ 50,000$ 50,000
6Vinvl Sheet-Pile Seawall189LF$ 1,500$ 283,500
7Concrete Bulkhead188LF$ 1,500$ 282,000
8Reinforced Concrete Ramp321SY$ 1,200$ 385,200
9Curb118LF$ 45$ 5,310
10Site Restoration0.5LS$ 10,000$ 5,000
Subtotal:$ 1,076,010
Contingency: 20%$ 215,202
Total Cost:$ 1,291,212
Boat Ramp & Upland Site Improvements
ItemDescriptionQuantityUnit PriceCost
1Mobilization/Demobilization1LS$ 20,000$ 20,000
2Maintenance of Traffic1LS$ 5,000$ 5,000
3Demolition1LS$ 30,000$ 30,000
4Prevention, Control, and Abatement of
Erosion and Water Pollution1LS$ 10,000$ 10,000
5Underground Stormwater System1LS$ 100,000$ 100,000
6Dewater1LS$ 50,000$ 50,000
7Vinyl Sheet-Pile Seawall189LF$ 1,500$ 283,500
8Concrete Bulkhead188LF$ 1,500$ 282,000
9Reinforced Concrete Ramp321SY$ 1,200$ 385,200
10Concrete Pavement3,145SY$ 100$ 314,500
11Pavement Markings1LS$ 10,000$ 10,000
11Signage1LS$ 1,000$ 1,000
12Curb118LF$ 45$ 5,310
13Type "D" Curb42LF$ 45$ 1,890
14Landscape and Irrigation1LS$ 30,000$ 30,000
15Site Restoration1LS$ 10,000$ 10,000
Subtotal:$ 1,538,400
Contingency: 20%$ 307,680
Total Cost:$ 1,846,080