On-Call As-Needed Pump Repair & Replacement Services

This is an Invitation to Bid (ITB #26-013-ITB) issued by the Kenton County Airport Board (KCAB) for on-call pump repair and replacement services at Cincinnati/Northern Kentucky International Airport (CVG). The solicitation seeks a contractor to provide repair or replacement services for pumps ranging from 3 hp to 150 hp used in the airport's environmental systems, including storm water and spent aircraft deicing fluid conveyance. Services include pump teardown and written reports, pickup and delivery of pumps, confined space entry work as needed, and on-site or classroom training for KCAB personnel covering mechanical components, electrical systems, troubleshooting, and pump dynamics. The contractor must demonstrate a minimum of five years of hands-on experience with Flygt and/or Ebara pumps, maintain OSHA-compliant safety programs including confined space entry and lockout/tagout plans, and possess the capability to source OEM-approved parts and perform field work with portable lifting equipment. Questions must be submitted by 11:59 pm on March 24, 2026, with answers posted by 11:59 pm on March 26, 2026. Sealed bids are due by 2:00 pm Eastern Time on April 2, 2026, submitted electronically through KCAB's OpenGov procurement portal. The contract term is two years with the option for three additional one-year renewal terms at prices not to exceed five percent increases or the Consumer Price Index, whichever is less. Anticipated contract implementation is May 1, 2026.

Pricing must be firm fixed for two years and all-inclusive, with bidders required to provide hourly rates for service during normal working hours (7:00 am to 5:00 pm, Monday through Friday), hourly rates for service outside normal working hours, hourly rates for confined space work during normal hours, flat rates for pump pickup and delivery, a percentage markup for contractor-supplied parts and equipment, and hourly and daily rates for training services. The contractor must maintain a written safety program with documented evidence, provide a Certificate of Insurance meeting ITB requirements, and identify any exceptions to the contract terms with full justification. Contractor personnel must obtain airport badges at a cost of $44 per badge, with additional fees for lost badges ($100 for the first loss, $200 for the second, and $300 for the third with Airport Security Coordinator approval). KCAB will apply Kentucky resident preference in accordance with state law and reserves the right to waive informalities, reject any or all bids, make multiple awards, and alter specifications and service frequencies as needed. Bids must remain valid for a minimum of 120 days from the closing date, and KCAB is not liable for any costs incurred by bidders in proposal preparation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

By participating in this solicitation, you, on behalf of the Vendor, understand and agree that all plans, drawings, maps, specifications, documents, or similar information included in this solicitation (“Protected Information”) may only be used by Vendor for the purpose of this solicitation and no other purpose. Without the written permission of KCAB, Vendor must not reproduce, copy, duplicate, or disclose the Protected Information by any means, except to employees and agents who have a “need to know” for the purpose of this solicitation. All employees and agents of Vendor are bound by these provisions, and Vendor shall inform those employees and agents of these terms. If Protected Information becomes available to third parties Vendor is responsible for third party compliance with these terms. Vendor shall indemnify and hold KCAB harmless from any liabilities or damages resulting from the unauthorized use or disclosure of Protected Information.

All Protected Information in any form remains the sole property of KCAB. At the request of KCAB Vendor agrees to immediately return Protected Information to KCAB. All Protected Information in any form must be destroyed upon completion of the purpose above. KCAB has all rights and remedies available by law and equity to enforce these provisions, specifically including injunctive relief to prevent unauthorized use of the Protected Information.

INVITATION TO BID

26-013-ITB

ON-CALL AS-NEEDED PUMP REPAIR & REPLACEMENT

SERVICES

ATTENTION: This is not an order. Read all instructions, terms, and conditions carefully.

IMPORTANT: Proposals must be received no later than 2:00 pm Eastern Time (ET) on

Thursday, April 2, 2026.

BID INVITATION# 26-013-ITB

DATE ISSUED: March 12, 2026

Table Of Contents

1. NOTICE TO BIDDERS

1.1. NOTICE TO BIDDERS

2. GENERAL INFORMATION & BID INSTRUCTIONS

2.1. SCHEDULE OF EVENTS

2.2. AUTHORITY TO RELEASE

2.3. BACKGROUND

2.4. SUBMISSION OF BIDS

2.5. BID QUESTIONS

2.6. ADDENDA

2.7. SCOPE OF SERVICES

2.8. KENTUCKY OPEN RECORDS ACT

2.9. ACCEPTANCE PERIOD

2.10. AWARD

2.11. PERFORMANCE AND PAYMENT

2.12. BADGES AND KEYS

2.13. RECORDS/FINANCIALS

2.14. GRATUITIES AND KICKBACKS

2.15. NON-COLLUSIVE VENDOR CERTIFICATION

2.16. BID CONDITIONS AND PROVISIONS

3. PRICING PROPOSAL

3.1. PRICING PROPOSAL

4. VENDOR QUESTIONNAIRE

4.1. VENDOR QUESTIONNAIRE

4.2. ATTACHMENTS

Attachments:

A - 26-013-ITB Pump & Pump Station Photos - Attachment A

C - 26-013-ITB On-Call Pump Repairs - Sample Agreement - Attachment C

D - 26-013-ITB On-Call As-Needed Pump Repair & Replacement Services - Ad

1. NOTICE TO BIDDERS

1.1. NOTICE TO BIDDERS

Pursuant to the provisions of KRS 424.260, the Kenton County Airport Board (“KCAB”) will receive bids for On-Call As-Needed Pump Repair & Replacement Services at the Cincinnati/Northern

Kentucky Int’l Airport (“CVG”). Bids will be received no later than Thursday, April 2, 2026, at 2:00 pm.

No bids will be accepted after that time unless such date or time is extended pursuant to an addendum issued by KCAB.

KCAB reserves the right to waive any informality or irregularity in any proposal or bid guaranty, to reject any or all proposals, to award or refrain from awarding a contract for the work, and to negotiate with the apparent qualified responsible proposer to such extent as may be beneficial to KCAB.

Preference for Kentucky resident bidders will be applied in accordance with Kentucky law.

KCAB in accordance with the provisions of Title VI of the Civil Rights Act of 1964 (78 Stat. 252, 42

U.S.C. §§ 2000d to 2000d-4) and the Regulations, hereby notifies all bidders that it will affirmatively ensure that any contract entered into pursuant to this advertisement, disadvantaged business enterprises will be afforded full and fair opportunity to submit bids in response to this invitation and will not be discriminated against on the grounds of race, color, or national origin in consideration for an award.

Further information and copies of the Invitation to Bid (ITB) may be downloaded from our website www.cvgairport.com/bids - KCAB's e-Procurement Portal.

KENTON COUNTY AIRPORT BOARD

Lawrence J. Krauter, Chief Executive Officer

CINCINNATI/NORTHERN KENTUCKY INTERNATIONAL AIRPORT

Hebron, KY 41048 https://www.cvgairport.com/bids

2. GENERAL INFORMATION & BID INSTRUCTIONS

2.1. SCHEDULE OF EVENTS

Release Project Date: March 12, 2026

Deadline For Questions To Be

Submitted:

March 24, 2026, 11:59pm

Answers To Questions Issued: March 26, 2026, 11:59pm

Proposals Due: April 2, 2026, 2:00pm

Anticipated Contract Implementation: May 1, 2026

KCAB reserves the right to modify or alter the schedule of events to such extent as may be beneficial to KCAB.

2.2. AUTHORITY TO RELEASE

KCAB is the sole entity with the authority to issue and/or distribute any solicitation documents and/or related information. All solicitation documents obtained from any source other than KCAB may be incomplete or incorrect. KCAB assumes no responsibility for any error, omission or misinterpretation resulting from the reliance or use of any Solicitation Documents not issued and distributed by KCAB.

All solicitation documents are posted on KCAB’s e-procurement portal at: https://procurement.opengov.com/portal/cvgairport

2.3. BACKGROUND

The Environmental Operations Department operates and maintains the environmental systems at

CVG. As part of the environmental system, there are numerous pumpstations designed to convey glycol laden stormwater captured from storm drains on the pavement and drains in the grassy islands to a Stormwater Treatment Plant (“SWTP”). In addition to glycol laden stormwater, Spent Aircraft

Deicing Fluid ("SADF") from aircraft deicing activities are also captured at deice pads. The SADF that is captured on the deice pads are conveyed to storage tanks prior to being sent to the SWTP. From time to time, the pumps need to be repaired or replaced due to failure of internal components. The pump stations mentioned above utilize various sizes and models pumps. Most of the pumps in the environmental system are Flygt pumps, however, Environmental Operations does use a few Ebara pumps. The pumps range in size from 3 hp up to 150 hp.

2.4. SUBMISSION OF BIDS

Responses to this ITB must be submitted electronically through KCAB’s online bidding system which can be accessed at https://procurement.opengov.com/portal/cvgairport. Select the project titled On-

Call As-Needed Pump Repair & Replacement Services (Invitation #26-013-ITB) and follow the instructions for submittal. The completed and signed bid (together with all required attachments) must be transmitted and received through OpenGov no later than Thursday, April 2, 2026 at 2:00 pm Eastern

Time (ET). Bidders should allow for sufficient time to upload and transmit all required information.

https://nam12.safelinks.protection.outlook.com/?url=https%3A%2F%2Fprocurement.opengov.com%2Fportal%2Fcvgairport&data=05%7C02%7Clpurcell%40cvgairport.com%7C915de49180aa4be8bfc808dd4c6e70bc%7Ce88b51b645364ffaa129350653cdad28%7C0%7C0%7C638750759399244215%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=dfJmJP4%2FJyNShw%2F66qqftK7bU4WctyXlBbuJWjH7szY%3D&reserved=0 https://procurement.opengov.com/portal/cvgairport

Proposer is solely responsible to ensure its submission is transmitted prior to the due date and time.

KCAB will not accept submissions after the due date and time and is not responsible for any error in transmission including but not limited to power outage, internet connectivity, unauthorized access, etc.

2.5. BID QUESTIONS

KCAB is not bound by, and bidders may not request or rely on any oral interpretation or clarification of this RFP. Therefore any questions regarding this ITB are encouraged and must be submitted electronically using the Question and Answer tab of this ITB on KCAB’s online bidding system, which can be accessed at https://procurement.opengov.com/portal/cvgairport.

Questions received on or before the Deadline to Submit Questions in the Schedule of Events will be posted on the Question and Answer tab of this ITB on the bidding system per the Schedule of

Events. Answers to questions from any bidder will be available to all proposers.

All communications regarding this solicitation must only be through the Questions and

Answers section of the ITB or through the Contract and Procurement Administration

Department. No communication is to be directed to any other KCAB personnel unless otherwise instructed by the Contract and Procurement Administration Department. Failure to comply may result in the disqualification of proposer’s submittal.

2.6. ADDENDA

In the event it becomes necessary to revise, change, modify or cancel this ITB or to provide additional information, addenda will be issued to all recipients of this ITB.

2.7. SCOPE OF SERVICES

2.7.1. Scope of Services

KCAB is soliciting bids for a contractor to provide on-call pump repair services for the pumps that are utilized in the environmental systems at CVG. SADF is captured at various deice pads and conveyed to storage tanks via various pump stations. Storm drains convey SADF not captured at the deice pads to various storm pump stations and then convey the contaminated water directly to the SWTP. There are times when the pumps need to be repaired or replaced due to failure of internal components. The SWTP pump stations utilize various sizes and models of Flygt and Ebara pumps. These pumps range in size from 3 hp up to 150 hp. Photos of the pumps and pump stations are attached as Attachment A.

The Successful Bidder (“Contractor”) must be able to provide the following services:

1) Repair or replacement of pumps on an as needed basis.

• Every attempt will be made to have the pump removed from the pump station, but there may be times when the pump must be removed by the Contractor.

• Confined space entry will be required if entry into the pump station is needed to remove the pump(s) from the pit.

• Pickup and delivery of the pumps is the responsibility of the Contractor.

• A written teardown report is required as part of the repair/replacement process.

• Repair or replacement may not proceed until the tear down report and written estimate is provided to the

KCAB Contract Manager responsible for the management of these pumps.

https://procurement.opengov.com/portal/cvgairport

2) Provide on-site and/or classroom training for KCAB personnel on the operation, maintenance, troubleshooting of pumps at CVG. Training may include:

• Mechanical Components:

o Seal types o Bearings and lubrication o Impeller types and trimming o Wear ring inspection

• Electrical Components o Motor winding o Megger testing o Troubleshooting high amp draw o Phase Imbalance o VFD Impacts on motors

• Troubleshooting o Overheating o Seal Failure o Clogging o Excessive Vibration o Short Cycling

• Hands-On Component o Live tear-down demonstration o Seal replacement demonstration o Proper reinstallation techniques

• Pump Dynamics o Pump Flow Curve o Best Efficiency Point o Troubleshooting o VFD Impact

2.7.2. Minimum Qualifications

Manufacturer Experience

• Contractor must have a minimum of 5 years of hands-on experience with Flygt and/or Ebara pumps

Safety & Regulatory Compliance

• Contractor must maintain a written safety program compliant with OSHA and applicable regulations o Provide a copy of its safety manual upon award of contract.

o Provide a copy of its confined space entry plan and permit upon award of a contract.

o Provide a copy of its Control of Hazardous Energy plan (Lock-out/Tagout).

o Provide training records for their employees who may be conducting work on CVG AA property.

Parts & Technical Capability

• Contractor must have the ability to:

o Quickly source OEM or OEM-approved replacement parts.

o Interpret manufacturer manuals, tolerances and performance curves.

o Perform repairs in accordance with manufacturer specifications.

Field Capabilities:

• Contractor must be able to provide the following field work:

o Remove and reinstall pump using its own portable lifting equipment as needed.

o Provide its own equipment and tools to access the lift stations to remove pumps as needed.

2.8. KENTUCKY OPEN RECORDS ACT

Each bidder must specifically identify any portion of its bid which it deems confidential, or which contains proprietary information, patents, copyrights or trade secrets. Bidder should provide justification of what material should not be disclosed, upon request, by KCAB to a third party. All documents received by

KCAB are subject to general inspection under the provisions of Kentucky Revised Statutes Chapter

61.870 et seq, the “Kentucky Open Records Act”, subject to very narrow exceptions. These statutes may require disclosure of documents a bidder deems confidential. KCAB may otherwise use or disclose the data submitted by each bidder for any purpose, unless such data is so identified as confidential or proprietary by the bidder. The bidder's opinion of proprietary information is not binding upon KCAB.

2.9. ACCEPTANCE PERIOD

Bids in response to this ITB must indicate it is valid for a period no less than one hundred twenty (120) days from the closing date.

2.10. AWARD

1. KCAB intends to award a contract or contracts resulting from this solicitation to the responsible bidder(s) whose bid represents the best value after evaluation.

2. KCAB reserves the right to waive any informality or irregularity in any bid guaranty, to reject any or all bids, to award or refrain from awarding a contract for the work, and to negotiate with the apparent qualified responsible bidder to such extent as may be beneficial to KCAB.

3. KCAB intends to evaluate bids and may award a contract without discussions with bidders.

Therefore, the bidder's initial bid should contain the bidder's best terms from a cost or price and technical standpoint.

4. KCAB reserves the right to make an award on any item for a quantity less than the quantity offered, at the unit cost or prices offered.

5. KCAB reserves the right to make multiple awards if, after considering the bids submitted, it is in KCAB’s best interest to do so.

6. The successful bidder will be required to enter into a contract substantially in the form of the contract included under the ATTACHMENTS Tab and incorporated by reference. All proposers are required to note any exception(s) to the Invitation to Bid or the attached contract and are required to specifically state the exception(s) and the reason(s) for the exception(s). No exceptions will be recognized to the Government

Clauses section of the proposed contract. If no exceptions to the contract are included in the bidder's response, the bidder is expected to execute the contract in the form set forth herein. Final acceptance of a bid and contract is contingent upon reaching a mutually satisfactory agreement regarding noted exceptions. If an acceptable and timely agreement is not reached, KCAB reserves the right to disqualify the bidder and to reevaluate the remaining bids. KCAB reserves the right to refuse to negotiate with a successful bidder on any item not specifically excepted in its submittal.

7. KCAB will have the right, at its sole election, to alter the specifications and/or frequencies of services required and tailor the contract price to said change (increase or decrease).

8. The initial term of the agreement will be for two (2) years. KCAB, in its sole discretion, may renew the agreement for three (3) additional one-year terms upon mutually agreeable terms. Renewal terms may be exercised individually or combined in multi-year terms. Renewal pricing for these services after the first year may not exceed the prices for the prior year plus 5 percent (5%) or the then current year over year increase in the

Consumer Price Index (CPI-U), whichever is less. Renewal price for the services will be negotiated and mutually acceptable to both parties. All price increases must be substantiated through showing proof of price increase documentation for this industry.

2.11. PERFORMANCE AND PAYMENT

The successful bidder shall issue an invoice on a monthly basis for work performed along with supporting data. KCAB will pay submitted invoices on a net 30 basis subject to the terms of the attached agreement.

2.12. BADGES AND KEYS

1. Contractor shall badge a sufficient number of employees to satisfactorily complete its obligations under this contract regardless of circumstances. This will require a background check made through a fingerprint process. When determining the number of employees to https://procurement.opengov.com/portal/cvgairport/projects/240071/document?section=2287644 badge, Contractor must consider absent employees due to illness, vacation, employment termination, or other reasons, emergency/on call situations, and supervisors who need access for inspection/supervision visits.

2. Contractor is responsible for the cost of badging. The current fee for identification badges is

$44.00 per badge for the badge, security threat assessment, and for fingerprinting.

3. Contractor shall return all badges upon expiration or termination of the contract whichever is earlier. Additionally, Contractor shall immediately return an employee’s badge when that employee is no longer employed by Contractor. Contractor shall pay $100.00 per badge for each badge not returned within ninety (90) days from the date the Contractor is required to return the badge(s).

4. Contractor is responsible for all keys or badges issued to Contractor’s employees. Such keys or badges may not be duplicated. Contractor shall return any or all keys or access cards to KCAB when requested by KCAB. If the loss of keys or access cards requires changing the combination of locks or changing other access equipment, the cost of such labor and material may be charged to Contractor at the discretion of KCAB. Replacement of lost or damaged keys or badges will be provided at Contractor’s expense. Any fines or civil penalties assessed to KCAB caused by Contractor negligence is the responsibility of Contractor.

5. Badge replacement is at the sole discretion of KCAB. A $100.00 fee will be assessed per lost badge. In the event a Contractor’s employee loses a second badge, the Contractor shall pay

$200.00. If a third badge is lost, the badge will only be renewed with permission of the Airport

Security Coordinator and the Contractor shall pay $300.00.

6. If necessary, KCAB will provide initial supply of keys after receipt of a $500.00 deposit from

Contractor. In the event Contractor loses or duplicates a key(s), KCAB will charge the cost of rekeying the lock(s) of the corresponding area against the $500.00 deposit. Contractor shall be responsible for the full cost of rekeying if Contractor loses or duplicates a key. Any funds remaining of this $500.00 deposit upon termination of the contract will be returned to contractor upon KCAB’s receipt of all keys.

2.13. RECORDS/FINANCIALS

In submitting bids on any item to be purchased by KCAB, the bidder hereby agrees to make available any and all records, books of account, correspondence, or other information reasonably necessary to enable KCAB or its designated agents to investigate the responsibility of the bidder in terms of its financial status, capacity to produce, sources of supply, performance record in the business or industry, and any other matter reasonably related to the proposer’s probable ability to perform adequately under a contract if it is awarded to the bidder.

2.14. GRATUITIES AND KICKBACKS

It is a breach of ethical standards for any person to offer, give, or agree to give any employee or former employee, or for any employee or former employee to solicit, demand, accept, or agree to accept from another person, a gratuity or an offer of employment in connection with any decision, approval, disapproval, recommendation, preparation of any part of a program requirement or a purchase request, influencing the content of any specification or procurement standard, rendering of advice, investigation, auditing, or in any other advisory capacity in any proceeding of application, request for ruling, determination, claim or controversy, or other particular matter, pertaining to any program requirement or a contract or subcontract, or to any solicitation or proposal therefore.

It is a breach of ethical standards for any payment, gratuity, or offer of employment to be made by or on behalf of a subcontractor under a contract to the prime vendor or higher tier subcontractor or any person associated therewith, as an inducement for the award of a subcontract or order.

In the event that any gratuities or kickbacks are offered or tendered to any KCAB employee, the proposal shall be disqualified and shall not be reinstated.

2.15. NON-COLLUSIVE VENDOR CERTIFICATION

By the submission of this proposal, the proposer certifies that:

1. The proposal has been arrived at by the proposer independently and has been submitted without collusion with any other vendor.

2. The contents of the proposal have not been communicated by the proposer, or, to its best knowledge and belief, by any of its employees or agents, to any person not an employee or agent of the proposer or its surety on any bond furnished herewith and will not be communicated to any such person prior to the official opening of the proposal.

3. No proposer may submit more than one proposal for this purchase. It shall be the responsibility of each proposer to obtain the prior written permission of KCAB before proposal opening in every situation in which the proposer, due to corporate association or other affiliation, may be found to be impermissibly associated with another vendor. Failure to observe this requirement could result in all such affiliated proposals being rejected.

2.16. BID CONDITIONS AND PROVISIONS

The terms and conditions of this Invitation to Bid (ITB) include all general and special conditions as enumerated herein.

All participating bidders agree to comply with all of the conditions, requirements and instructions of this

ITB as stated or implied herein. Any alteration, erasure or interlineation by the bidder in this bid constitutes cause for rejection by KCAB. Should KCAB omit anything from this ITB which is necessary to a clear understanding of the work, or should it appear that various instructions are in conflict, then the bidder shall notify the Contract and Procurement Administration Department prior to the deadline for question submissions as per the time and date shown in the Schedule of Events.

Typographical errors in entering quotations on this bid may result in the disqualification of this bid.

All bidders are required to complete all information requested in this bid. Failure to do so may result in the disqualification of bid.

Unit price for each item must be shown for the unit of measurement indicated. In case of error in extension of prices, the unit price governs.

Each bidder shall fully acquaint and familiarize themselves with the conditions as they exist and the character of the operations to be carried on under the proposed contract and make such investigations as the bidder may see fit so that the bidder shall fully understand the facilities, physical conditions and restrictions associated with the services.

The successful bidder shall comply with all of the specifications, terms and conditions of this ITB.

KCAB is not liable for any costs incurred by bidder in the preparation of bids or for any work performed in connection therein.

3. PRICING PROPOSAL

3.1. PRICING PROPOSAL

Pricing must be all-inclusive, firm fixed for 2 years, and delivered to the address specified inclusive of all transportation charges FOB Cincinnati/Northern Kentucky International Airport.

Bids must be submitted electronically using the Line Items tab on KCAB’s electronic bidding system.

Submittals must be confirmed by a duly authorized official of the bidding company.

MAIN BID

Line Item Description Quantity Unit of

Measure Unit Cost Total

1 Hourly rate for service during normal working hours (7:00 a.m. to

5:00 p.m., Monday through Friday).

1 HR

2 Hourly rate for service outside normal working hours.

1 HR

3 Hourly rate for confined space service work during normal working hours (7:00 a.m. to 5:00 p.m., Monday through Friday).

1 HR

4 Flat Rate for Pickup of Pump(s) 1 EA

5 Flat Rate for Delivery of Pump(s) 1 EA

6 Percentage markup for parts and/or equipment supplied by

Contractor.

1 PCT

7 Hourly rate for training during normal working hours (7:00a.m. to

5:00p.m) Monday through Friday.

1 HR

Line Item Description Quantity Unit of

Measure Unit Cost Total

8 Daily rate for training during normal working hours (7:00a.m. to

5:00p.m) Monday through Friday.

1 Daily

TOTAL

4. VENDOR QUESTIONNAIRE

4.1. VENDOR QUESTIONNAIRE

Each bid must include the following written information:

1. Minimum Qualifications*

Provide documentation of the following:

A. Minimum experience required with Flygt and/or Ebara pumps.

B. Technical capabilities.

C. Equipment and tool list for any required field work.

*Response required

2. Safety Qualifications*

Please download the below Safety Forms - Attachment B, complete as well as provide the additional information required, and upload. Also provide proof of Safety Program which should include:

a, Evidence of a Safety Manual

b. Confined space entry plan and permit

c. Control of Hazardous Energy Plan

d. Training records for employees

• 26-013-ITB_On-Call_Pump_Rep...

*Response required

3. Warranty Documentation*

Provide warranty documentation for parts and labor.

*Response required

4. Certificate of Insurance*

Provide a copy of your Certificate of Insurance that meets the requirements of this ITB and attached sample agreement.

*Response required https://government-project.s3.us-west-2.amazonaws.com/240071/cab6c4c8-74f9-488f-b140-2fcf6083d7a7_26-013-ITB_On-Call_Pump_Repairs_-_Proposal_Safety_Forms_-_Attachment_B.pdf

5. Exceptions*

State in writing all exceptions to this RFP or sample agreement attached as Attachment

C. Exceptions should list referencing page and paragraph numbers. If no exceptions are taken, the proposal must include a statement that the bidder takes “No Exceptions”.

*Response required

6. Resident & Non Resident Status Forms*

Please download the below documents, complete, and upload.

• Resident_&_Non_Resident_Sta...

*Response required

7. Confirmation*

By submitting a bid, the bidder consents to its use and acceptance of electronic signatures to execute any awarded contract and associated agreements. Bidder agrees to be bound by electronic signatures to the same legal effect and extent as if manually signed. KCAB expects the successful bidder will execute any awarded contract using KCAB’s electronic signature service unless the bidder includes an exception with its proposal signifying its desire to sign manually. Included with the bid, bidders must identify the following information regarding the person with full authority to legally bind proposer and sign agreements on its behalf:

A. Full Name;

B. Position Title; and

C. Email Address.

Please provide this information in the next questions.

☐ Please confirm

*Response required

8. Provide the following:*

Proposers must identify the following information regarding the person with full authority to legally bind proposer and sign agreements on its behalf:

A. Full Name;

B. Position Title; and

C. Email Address.

*Response required https://government-project.s3.us-west-2.amazonaws.com/134681/b1d14070-0fed-42ee-ab6f-9e9b9302c53f_Resident_%26_Non_Resident_Status_Forms.pdf?X-Amz-Algorithm=AWS4-HMAC-SHA256&X-Amz-Content-Sha256=UNSIGNED-PAYLOAD&X-Amz-Credential=ASIA47RIURE4FKUKEVEE%2F20260312%2Fus-west-2%2Fs3%2Faws4_request&X-Amz-Date=20260312T120004Z&X-Amz-Expires=72000&X-Amz-Security-Token=IQoJb3JpZ2luX2VjEKv%2F%2F%2F%2F%2F%2F%2F%2F%2F%2FwEaCXVzLXdlc3QtMiJIMEYCIQCKHYBkFczTjgcPPp4hrx3eXs%2FI4w2uULyuAAc93KQczgIhAKCVN2nPJHaVk4aYsdwg7MP%2FpHdjH%2F4HHkTaHi83qhl3KowFCHQQAhoMODkyMzY0Njg3NjcyIgzRhOJkeb5cKI60bcoq6QQ85C87oRmikR75m9lcwZtMevPOLpiFyeo9tODH9e9F5FWm9RmjDmwwFtT%2FZ%2FsbXtawQl70i7tMPsNLddOFdm48dVx7fVKRW1b8uCQERPsfwJMAqyU4anmbIEPvSlFLADeTbMuYT6OXoaCzxbe5naPpbuWcjLut2NslsVn9GdRF1wEnY4iW%2BLHn0yXs9dKI3j1I9X0rffjcA501xc8wSyUX4dsGK6x863cgF43z27WOlCOlEcu%2F0eeFRjQd9i1kenCMuXfkPxKVTg6qgHRJIkEcJsQrkWBCQ%2Bqk20Nc4%2FUk%2B2I0SDR2%2BODs0rgEZa2Ek%2Bi8wRPwXypROsZ4A%2BjocmHX6eqtF7%2BxbSjqI95fojn8fEE1wXz3SXWL8GWyYZCKpgWE4yko6HLGeTAbbtWDW4xY%2Fbz3qFUV%2BI72wlnloUXY5QYUrHE20Tuver8vwW1rim9NWmcQkTvYt1NPXAWbMm0rcFYZPHDm72dPuEl%2BbuCKQ%2Fk7559Tsu80Fjlgut5p1eMN5%2FqBg%2BEMEySzQ%2B202qqQqU9u35bRDAXebHv%2BoYYHnmpbqojCfJ9oJE5DWB%2BsE9DxMgPqDI9CfR1Yd1UYbGFR7hWTUyBn7VK6Il2mNsCvHDYqnxsMVOtJaklbSlZ07QM6mivGMjGCEoSy6oAeHxqYoSV6JUrcccrJCzsomydMDRRG5DKB8VlJuHDYaA02R8hgya69Yq7whbyLU1A1MbKT%2BEsEujjPaTmqhIEdIky8K5zBpND8aLExylXf3uAcPilAeev8u0ZJw1jzgp4oh%2BTACV1NGFTN4ADv3lvX9Hr%2B8pUdgSkwyrUJ8jDUtsrNBjqYAVhyZAy%2B5XanQJ61L3zGqJmukVZ1kIUGRWlMOFBZ9uE8rh2qV455%2F3xHF2oPNiz0QUkxWZaCageKvojXgg3vJlL3PofaHWIV7MNVcz3i9iPP5mpGJ6O8g%2BBfC%2FOQYS1nJXWgDs%2F9skjTH6t6igVU2rdH25qERgSlUyN%2BS67mpeyudiLprPcD34Sju%2FHLA7OP9NcQS2zTB5l4&X-Amz-Signature=46fa6e8c757f6a8f0cb295b813af2ca77283167d5ed68792e076f9172ceba770&X-Amz-SignedHeaders=host&response-content-disposition=attachment%3B%20filename%3D%22Resident_%2526_Non_Resident_Status_Forms.pdf%22&x-id=GetObject

File details come from the government source that posted it. Updated .