This document is a Contract Data Requirements List (CDRL) that outlines the data items required for a federal contract opportunity. The NSAM3 RFP is for the operation of the Naval Shipbuilding and Advanced Manufacturing Center of Excellence III (NSAM III) under the Navy Manufacturing Technology (ManTech) Program.
The key details are:
- The contract requires the submission of a Project Plan and Project Final Report on a recurring basis.
- The Project Plan must adhere to the current Navy ManTech template and be submitted per the FY planning cycle.
- The distribution statements for the Project Plan and Project Final Report vary, ranging from Distribution Statement A (approved for public release) to Distribution Statement D (DoD and DoD contractors only).
- The contract has a 60-month ordering period and the NAICS code is 541715 for Research and Development in the Physical, Engineering, and Life Sciences.
- The core mission of the NSAM COE is to identify, develop, and facilitate the deployment of advanced manufacturing technologies to U.S. shipyards and other industrial facilities to reduce the cost and time to build and sustain naval platforms.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services and Communications Directorate (0704-1088). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. Listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
C. CATEGORY:
TDP_____ TM ______ OTHER: R&D
D. SYSTEM/ITEM
TBD
E. CONTRACT/PR NO.
TBD
F. CONTRACTOR
TBD
1. DATA ITEM NO.
B001
2. TITLE OF DATA ITEM
Project Plan
3. SUBTITLE
COE Task Order 2
4. AUTHORITY (Data Acquisition Document No.)
DI-MISC-81612B
5. CONTRACT REFERENCE
Statement of Work
6. REQUIRING OFFICE
N00014
7. DD 250 REQ
* Block 16
9. DIST STATEMENT
REQUIRED
# Dist. D
10. FREQUENCY
Once
12. DATE OF FIRST SUBMISSION
** Block 16
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
8. APP CODE
N/A
11. AS OF DATE
13. DATE OF SUBSEQUENT
SUBMISSION
Once
| Draft |
| Final |
| Reg |
| Repro |
16. Remarks:
* Block 7: The contractor shall submit Project Plan in accordance with SOW and current Navy ManTech template under the ManTech Guidance documentation.
# Block 9: DISTRIBUTION STATEMENT D. Distribution authorized to the Department of Defense and U.S. DoD contractors only (Critical Technology) (date of determination). Other requests shall be referred to the Office of Naval Research, Code 332, COR noted in the contract.
** Blocks 11 and 12: The Project Plan for each planned project will be due in accordance to FY planning cycle in accordance to the ONR Navy ManTech Office.
Use of DI-MISC-81612B will be discussed with ONR program officer upon contract award to finalize content according to ManTech Guidance.
See Enclosure 1
15. TOTAL
G. PREPARED BY
Paul Huang
H. DATE
3/12/2024
I. APPROVED BY
Paul Huang
J. DATE
DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 1 of 6 Pages
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services and Communications Directorate (0704-1088). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. Listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
C. CATEGORY:
TDP_____ TM ______ OTHER: R&D
D. SYSTEM/ITEM
TBD
E. CONTRACT/PR NO.
TBD
F. CONTRACTOR
1. DATA ITEM NO.
B002
2. TITLE OF DATA ITEM
Project Plan
3. SUBTITLE
COE Task Order 2
4. AUTHORITY (Data Acquisition Document No.)
DI-MISC-81612B
5. CONTRACT REFERENCE
Statement of Work
6. REQUIRING OFFICE
N00014
7. DD 250 REQ
* Block 16
9. DIST STATEMENT
REQUIRED
# Dist. C
10. FREQUENCY
Once
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
b. COPIES
8. APP CODE
11. AS OF DATE
13. DATE OF SUBSEQUENT
SUBMISSION
Once
| Draft |
| Final |
| Reg |
| Repro |
16. Remarks:
* Block 7: The contractor shall submit Project Plan in accordance with SOW and current Navy ManTech template under the ManTech Guidance documentation.
# Block 9: DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government agencies and their contractors (Critical Technology) (date of determination). Other requests shall be referred to the Office of Naval Research, Code 332, COR noted in the contract.
** Blocks 11 and 12: The Project Plan for each planned project will be due in accordance to FY planning cycle in accordance to the ONR Navy ManTech Office.
Use of DI-MISC-81612B will be discussed with ONR program officer upon contract award to finalize content according to ManTech Guidance.
See Enclosure 1
15. TOTAL
G. PREPARED BY
H. DATE
I. APPROVED BY
Paul Huang
J. DATE
DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 2 of 6 Pages
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services and Communications Directorate (0704-1088). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. Listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
C. CATEGORY:
TDP_____ TM ______ OTHER: R&D
D. SYSTEM/ITEM
TBD
E. CONTRACT/PR NO.
TBD
F. CONTRACTOR
1. DATA ITEM NO.
B003
2. TITLE OF DATA ITEM
Project Plan
3. SUBTITLE
COE Task Order 2
4. AUTHORITY (Data Acquisition Document No.)
DI-MISC-81612B
5. CONTRACT REFERENCE
Statement of Work
6. REQUIRING OFFICE
N00014
7. DD 250 REQ
* Block 16
9. DIST STATEMENT
REQUIRED
# Dist. A
10. FREQUENCY
Once
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
b. COPIES
8. APP CODE
11. AS OF DATE
13. DATE OF SUBSEQUENT
SUBMISSION
Once
| Draft |
| Final |
| Reg |
| Repro |
16. Remarks:
* Block 7: The contractor shall submit Project Plan in accordance with SOW and current Navy ManTech template under the ManTech Guidance documentation.
# Block 9: DISTRIBUTION STATEMENT A. Approved for public release: distribution unlimited.
** Blocks 11 and 12: The Project Plan for each planned project will be due in accordance to FY planning cycle in accordance to the ONR Navy ManTech Office.
Use of DI-MISC-81612B will be discussed with ONR program officer upon contract award to finalize content according to ManTech Guidance.
See Enclosure 1
15. TOTAL
G. PREPARED BY
H. DATE
I. APPROVED BY
Paul Huang
J. DATE
DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 3 of 6 Pages
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services and Communications Directorate (0704-1088). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. Listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
C. CATEGORY:
TDP_____ TM ______ OTHER: R&D
D. SYSTEM/ITEM
TBD
E. CONTRACT/PR NO.
TBD
F. CONTRACTOR
1. DATA ITEM NO.
B004
2. TITLE OF DATA ITEM
Project Final Report
3. SUBTITLE
COE Task Order 2
4. AUTHORITY (Data Acquisition Document No.)
DI-MISC-81612B
5. CONTRACT REFERENCE
Statement of Work
6. REQUIRING OFFICE
N00014
7. DD 250 REQ
* Block 16
9. DIST STATEMENT
REQUIRED
# Dist. D
10. FREQUENCY
quarterly
12. DATE OF FIRST SUBMISSION
See Block 16
14. DISTRIBUTION
b. COPIES
8. APP CODE
11. AS OF DATE
13. DATE OF SUBSEQUENT
SUBMISSION
Once
| Draft |
| Final |
| Reg |
| Repro |
16. Remarks:
* Block 7: The contractor shall submit Final Project Report in accordance with SOW and current Navy ManTech template under the ManTech Guidance documentation.
# Block 9: DISTRIBUTION STATEMENT D. Distribution authorized to the Department of Defense and U.S. DoD contractors only (Critical Technology) (date of determination). Other requests shall be referred to the Office of Naval Research, Code 332, COR noted in the contract.
** Blocks 11 and 12: The Project Plan for each planned project will be due in accordance to FY planning cycle in accordance to the ONR Navy ManTech Office.
Use of DI-MISC-81612B will be discussed with ONR program officer upon contract award to finalize content according to ManTech Guidance.
See Enclosure 1
15. TOTAL
G. PREPARED BY
H. DATE
I. APPROVED BY
Paul Huang
J. DATE
DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 4 of 6 Pages
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services and Communications Directorate (0704-1088). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. Listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
C. CATEGORY:
TDP_____ TM ______ OTHER: R&D
D. SYSTEM/ITEM
TBD
E. CONTRACT/PR NO.
TBD
F. CONTRACTOR
1. DATA ITEM NO.
B005
2. TITLE OF DATA ITEM
Project Final Report
3. SUBTITLE
COE Task Order 2
4. AUTHORITY (Data Acquisition Document No.)
DI-MISC-81612B
5. CONTRACT REFERENCE
Statement of Work
6. REQUIRING OFFICE
N00014
7. DD 250 REQ
* Block 16
9. DIST STATEMENT
REQUIRED
# Dist. C
10. FREQUENCY
quarterly
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
b. COPIES
8. APP CODE
11. AS OF DATE
13. DATE OF SUBSEQUENT
SUBMISSION
Once
| Draft |
| Final |
| Reg |
| Repro |
16. Remarks:
* Block 7: The contractor shall submit Final Project Report in accordance with SOW and current Navy ManTech template under the ManTech Guidance documentation.
# Block 9: DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government agencies and their contractors (Critical Technology) (date of determination). Other requests shall be referred to the Office of Naval Research, Code 332, COR noted in the contract.
** Blocks 11 and 12: The Project Plan for each planned project will be due in accordance to FY planning cycle in accordance to the ONR Navy ManTech Office.
Use of DI-MISC-81612B will be discussed with ONR program officer upon contract award to finalize content according to ManTech Guidance.
See Enclosure 1
15. TOTAL
G. PREPARED BY
H. DATE
I. APPROVED BY
Paul Huang
J. DATE
DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 5 of 6 Pages
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services and Communications Directorate (0704-1088). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. Listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
C. CATEGORY:
TDP_____ TM ______ OTHER: R&D
D. SYSTEM/ITEM
TBD
E. CONTRACT/PR NO.
TBD
F. CONTRACTOR
1. DATA ITEM NO.
B006
2. TITLE OF DATA ITEM
Project Final Report
3. SUBTITLE
COE Task Order 2
4. AUTHORITY (Data Acquisition Document No.)
DI-MISC-81612B
5. CONTRACT REFERENCE
Statement of Work
6. REQUIRING OFFICE
N00014
7. DD 250 REQ
* Block 16
9. DIST STATEMENT
REQUIRED
# Dist. A
10. FREQUENCY
quarterly
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
b. COPIES
8. APP CODE
11. AS OF DATE
13. DATE OF SUBSEQUENT
SUBMISSION
Once
| Draft |
| Final |
| Reg |
| Repro |
16. Remarks:
* Block 7: The contractor shall submit Final Project Report in accordance with SOW and current Navy ManTech template under the ManTech Guidance documentation.
# Block 9: DISTRIBUTION STATEMENT A. Approved for public release: distribution unlimited.
** Blocks 11 and 12: The Project Plan for each planned project will be due in accordance to FY planning cycle in accordance to the ONR Navy ManTech Office.
Use of DI-MISC-81612B will be discussed with ONR program officer upon contract award to finalize content according to ManTech Guidance.
See Enclosure 1
15. TOTAL
G. PREPARED BY
H. DATE
I. APPROVED BY
Paul Huang
J. DATE
DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 6 of 6 Pages