NSAM3 RFP Sec J Attachment 28 Review Form Instructions - Portfolio Review.pptx
PPTX presentation 2 MB Posted
- Attached to
- Manufacturing Technology (ManTech) Naval Shipbuilding and Advanced Manufacturing 3 (NSAM 3)
- Solicitation number
- N0001424R0002
About this file
This document appears to be instructions for completing an Annual Portfolio Review Form for the Navy Manufacturing Technology (ManTech) Program's Naval Shipbuilding and Advanced Manufacturing 3 (NSAM 3) initiative. The instructions provide guidance on how to properly complete the review form, including definitions for the green, yellow, and red ratings to be used for the implementation risk assessment. Completed forms are to be emailed to the designated POC.
The related federal contract opportunity is a Request for Proposal (RFP) for research and development services to operate the NSAM III Center of Excellence under the Navy ManTech Program. The core mission is to identify, develop, and facilitate deployment of advanced manufacturing technologies to U.S. shipyards and other industrial facilities to reduce the cost and time to build and sustain naval platforms. Key technology focus areas include design for producibility, digital manufacturing, automation, and supply chain improvements. This is a single award IDIQ cost plus fixed fee contract with a 60-month ordering period.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Navy ManTech Program Annual Portfolio Review
Instructions to Complete Review Forms
Jan 2023
DISTRIBUTION A. Approved for public release. Distribution is Unlimited. Approved 1 March 2017
Annual Portfolio Review Form
Add as much input as possible, particularly the Comments column. Charts provided should clearly address the column headers and key questions.
Use the drop-down menu to rate green, yellow, or red per next slide Complete with your information
Annual Portfolio Review Form Use the below definitions to provide a green, yellow, or red rating in columns E, F, and G.
These definitions are also located in the review form.
The three categories are part of the ManTech implementation risk assessment.
If a red rating is given two reviews in a row, a risk mitigation plan must be developed.
Completed Forms At the end of the review, email completed forms to Gabriel Puente Lay at gabriel.r.puentelay.ctr@us.navy.mil image4.png image2.png image5.png image6.png image7.png image1.png image3.jpeg