NPS-Housing_--_Specs___1.pdf

PDF 14 MB Posted

Attached to
Multiple Award Task Order Contract for design-build
Solicitation number
140P2025R0030
Issued by

About this file

This document appears to be a set of specifications for the National Park Service's Multiple Award Task Order Contract for design-build of National Park employee housing.

The key details are: this is a pre-solicitation for a Multiple Award Task Order Contract for design-build of National Park employee housing, with a Solicitation Number of 140P2025R0030. The contracting agency is the Department of the Interior National Park Service National Office. The specifications provided cover various requirements for the housing design and construction. No further details are given on the pricing terms, set-asides, incumbents, or award dates in this document. This appears to be a technical specifications document rather than a full solicitation package.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

<Park - PMIS number> 00 01 07 - 1

SEALS PAGE

DOCUMENT 00 01 07 - SEALS PAGE

1.1 DESIGN PROFESSIONALS OF RECORD

A. Architect:

1. <Insert name>.

2. <Insert license #>.

3. Responsible for Divisions 01-33 Sections except where indicated as prepared by other design professionals of record.

B. Civil Engineer:

1. <Insert name>.

2. <Insert license #>.

3. Responsible for <Insert list of Sections>.

C. Landscape Architect:

1. <Insert name>.

2. <Insert license #>.

3. Responsible for <Insert list of Sections>.

D. Structural Engineer:

1. <Insert name>.

2. <Insert license #>.

3. Responsible for <Insert list of Sections>.

E. Fire-Protection Engineer:

1. <Insert name>.

2. <Insert license #>.

3. Responsible for <Insert list of Sections>.

F. Plumbing Engineer:

1. <Insert name>.

2. <Insert license #>.

3. Responsible for <Insert list of Sections>.

G. HVAC Engineer:

1. <Insert name>.

2. <Insert license #>.

3. Responsible for <Insert list of Sections>.

H. Electrical Engineer:

1. <Insert name>.

<Park - PMIS number> 00 01 07 - 2

SEALS PAGE

2. <Insert license #>.

3. Responsible for <Insert list of Sections>.

END OF DOCUMENT 00 01 07

Updated October 2020

[100% DRAFT – DD SPECIFICATIONS]

FOR

[WASO HOUSING PROTOTYPE UPDATE]

[INSERT PARK NAME]

[PMIS NO. ######]

Month ##, 202#

This 100% DRAFT Specification book is only for the building, with the specific project A/E adding in for all sitework related specifications

This DRAFT specification book includes BASELINE AND OPTIONS within all specification sections for the project team to use as needed for the final design. The specifications referenced as BASELINE are the initial recommended specifications for the projects. However, depending on site specific requirements each project can adjust the BASELINE or substitute for the OPTIONS as needed. Project will need to track those OPTION items used and be prepared to justify if overall project exceeds the budget.

Once all project applicable specifications are identified A/E must remove all unused specifications and remove all references to BASELINE & OPTIONS in the final 100% CD Specifications.

A/E is responsible to review, revise, and add to this DRAFT specification book as needed in all systems related to the specific project in developing the final project 100% CD Specifications. This includes all site and building specific requirements including but not limited to code requirements, NPS requirements, design requirements, sustainability requirements, structural requirements, MEP requirements, all sitework, etc. If the A/E does not understand their responsibility to the building and site-specific requirements prior to submitting their fee proposal they must notify to NPS in writing for clarity for understanding. NPS Housing Prototypes have no responsibility in providing any additional information other than plans and specifications provided.

<Park - PMIS number> TABLE OF CONTENTS - 1

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 10 00 Summary of Work 01 26 01 Contract Modification Procedures 01 27 00 Definition of Contract Line Items 01 31 00 Project Management and Coordination 01 32 16 Construction Schedule 01 32 33 Photographic Documentation 01 33 23 Submittal Procedures 01 35 13.22 Archeological Protection 01 35 23 Safety Requirements 01 35 25 Explosives 01 35 91 Historic Preservation Treatment Procedures 01 40 00 Quality Requirements 01 42 00 Reference Standards 01 50 00 Temporary Facilities and Controls 01 57 19.11 Indoor Air Quality Management 01 57 19.12 Noise and Acoustics Management 01 57 23 Temporary Storm Water Pollution Prevention 01 67 00 Product Requirements 01 73 29 Cutting and Patching 01 73 40 Execution 01 74 19 Construction Waste Management and Disposal 01 77 00 Closeout Procedures 01 78 23 Operation and Maintenance Data 01 79 00 Demonstration and Training 01 81 13 Sustainable Design Requirements for Non-LEED Projects 01 91 14 Total Building Commissioning

DIVISION 02 - EXISTING CONDITIONS

<Insert Sections for Site-Specific work>

DIVISION 03 - CONCRETE

03 30 00 Cast-in-Place Concrete ............................................................................................(BASELINE)

DIVISION 04 - MASONRY

04 22 00 Concrete Unit Masonry ............................................................................................... (OPTION)

DIVISION 05 - METALS

05 51 13 Metal Pan Stairs .......................................................................................................... (OPTION) 05 52 16 Premanufactured Aluminum Railings .....................................................................(BASELINE)

<Park - PMIS number> TABLE OF CONTENTS - 2

DIVISION 06 - WOOD, PLASTIC AND COMPOSITES

06 10 00 Rough Carpentry .....................................................................................................(BASELINE) 06 12 00 Structural Insulated Panels (SIP) ................................................................................ (OPTION) 06 13 00 Heavy Timber Construction ....................................................................................(BASELINE) 06 15 33 Wood Patio Decking ........................................................................ (BASELINE & OPTIONS) 06 16 00 Sheathing .................................................................................................................(BASELINE) 06 17 45 Wood Trusses and Joists .................................................................. (BASELINE & OPTIONS) 06 40 23 Interior Architectural Woodwork ...........................................................................(BASELINE) 06 43 13 Premanufactured Wood Stairs ................................................................................(BASELINE)

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 05 43 Cladding Support Systems ........................................................................................... (OPTION) 07 11 00 Dampproofing .........................................................................................................(BASELINE) 07 17 00 Bentonite Waterproofing ........................................................................................(BASELINE) 07 19 00 Water Repellents .....................................................................................................(BASELINE) 07 21 00 Thermal Insulation ..................................................................................................(BASELINE) 07 25 00 Weather Barriers .............................................................................. (BASELINE & OPTIONS) 07 31 13 Asphalt Shingles ......................................................................................................(BASELINE) 07 31 29 Wood Shingles and Shakes ......................................................................................... (OPTION) 07 41 11 Formed Metal Roof Panels ......................................................................................... (OPTION) 07 41 13 Standing-Seam Metal Roof Panels ............................................................................. (OPTION) 07 46 00 Siding and Soffits ............................................................................. (BASELINE & OPTIONS) 07 46 24 Wood Shingle and Shake Siding ................................................................................. (OPTION) 07 53 23 Ethylene-Propylene-Diene-Monomer (EPDM) Roofing ............................................ (OPTION) 07 62 00 Sheet Metal Flashing and Trim ...............................................................................(BASELINE) 07 71 00 Roof Specialties ........................................................................................................... (OPTION) 07 72 00 Roof Accessories .....................................................................................................(BASELINE) 07 72 53 Snow Guards ............................................................................................................... (OPTION) 07 92 00 Joint Sealants ...........................................................................................................(BASELINE)

DIVISION 08 - OPENINGS

08 05 11 Performance Requirements for Openings .................................................................. (OPTION) 08 14 00 Wood Doors ..................................................................................... (BASELINE & OPTIONS) 08 31 13 Access Doors and Frames .......................................................................................(BASELINE) 08 36 13 Sectional Doors ........................................................................................................... (OPTION) 08 50 00 Windows ........................................................................................... (BASELINE & OPTIONS) 08 51 23 Steel Windows ............................................................................................................. (OPTION) 08 62 23 Tubular Skylights ........................................................................................................ (OPTION) 08 71 00 Door Hardware ........................................................................................................(BASELINE) 08 80 00 Glazing ....................................................................................................................(BASELINE) 08 91 19 Fixed Louvers ..........................................................................................................(BASELINE)

DIVISION 09 - FINISHES

09 05 61 Common Work Results for Flooring Preparation ..................................................(BASELINE) 09 24 00 Cement Plastering - Stucco .......................................................................................... (OPTION)

<Park - PMIS number> TABLE OF CONTENTS - 3

09 29 00 Gypsum Board ........................................................................................................(BASELINE) 09 30 13 Ceramic Tiling ............................................................................................................. (OPTION) 09 65 13 Resilient Base and Accessories ...............................................................................(BASELINE) 09 65 16 Resilient Sheet Flooring ..........................................................................................(BASELINE) 09 65 19 Resilient Tile Flooring ................................................................................................ (OPTION) 09 68 13 Tile Carpeting .............................................................................................................. (OPTION) 09 68 16 Sheet Carpeting ........................................................................................................(BASELINE) 09 91 00 Painting ....................................................................................................................(BASELINE) 09 96 00 High-Performance Coatings ...................................................................................(BASELINE)

DIVISION 10 - SPECIALTIES

10 14 19 Dimensional Letter Signage ....................................................................................(BASELINE) 10 26 00 Wall and Door Protection .......................................................................................(BASELINE) 10 28 00 Toilet and Bath Accessories ....................................................................................(BASELINE) 10 28 21 Prefabricated Shower Enclosures ................................................................................ (OPTION) 10 44 16 Fire Extinguishers ...................................................................................................(BASELINE) 10 57 23 Closet and Utility Shelving ......................................................................................... (OPTION)

DIVISION 11 - EQUIPMENT

11 30 13 Residential Appliances .......................................................................... (NOT IN CONTRACT)

DIVISION 12 - FURNISHINGS

12 21 13 Horizontal Louver Blinds ..................................................................... (NOT IN CONTRACT) 12 32 13 Manufactured Wood-Veneer-Faced Casework ......................................................(BASELINE) 12 36 23 Plastic-Laminate-Clad Countertops ........................................................................(BASELINE)

DIVISION 21 - FIRE SUPPRESSION

21 05 00 Common Work Results for Fire Suppression ............................................................ (OPTION) 21 05 01 Common Work Results for Hybrid Metal-CPVC Fire Suppression .................... (BASELINE) 21 13 01 Hybrid Metal-CPVC Fire Suppression Sprinkler Systems ............................... (BASELINE)

DIVISION 22 - PLUMBING

22 05 19 Plumbing Devices ...................................................................................................(BASELINE) 22 05 23 General-Duty Valves for Plumbing Piping ............................................................(BASELINE) 22 05 29 Hangers and Supports for Plumbing Piping and Equipment .................................(BASELINE) 22 05 48 Vibration and Seismic Controls for Plumbing Piping and Equipment ..................(BASELINE) 22 05 53 Identification for Plumbing Piping and Equipment ...............................................(BASELINE) 22 05 93 Testing, Adjusting, and Balancing for Plumbing ...................................................(BASELINE) 22 07 00 Plumbing Insulation ................................................................................................(BASELINE) 22 10 00 Plumbing Piping ................................................................................. (BASELINE & OPTION) 22 30 00 Plumbing Equipment .......................................................................... (BASELINE & OPTION) 22 40 00 Plumbing Fixtures ............................................................................................. (BASELINE)

<Park - PMIS number> TABLE OF CONTENTS - 4

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING

23 05 53 Identification for HVAC Piping, Ductwork and Equipment .................................(BASELINE) 23 07 00 HVAC Insulation ....................................................................................................(BASELINE) 23 09 33 Electric and Electronic Control System for HVAC ...............................................(BASELINE) 23 11 23 Facility Fuel - Natural Gas Piping and Systems ................................ (BASELINE & OPTION) 23 21 13 HVAC Piping .............................................................................................................. (OPTION) 23 31 00 HVAC Ducts and Casings ................................................................. (BASELINE & OPTION) 23 33 00 Air Duct Accessories ...............................................................................................(BASELINE) 23 34 00 HVAC Fans ........................................................................................ (BASELINE & OPTION) 23 37 00 Air Outlets and Inlets ..............................................................................................(BASELINE) 23 51 00 Breechings, Chimneys and Stacks ..........................................................................(BASELINE) 23 55 00 Fuel Fired Heaters .............................................................................. (BASELINE & OPTION) 23 63 13 Air Cooled Refrigerant Condensers ............................................................................ (OPTION) 23 81 26 Small Split System and Unitary HVAC Equipment .............................................. (OPTION) 23 81 43 Air Source Heat Pumps ............................................................................................... (OPTION) 23 82 00 Terminal Heat Transfer Equipment ........................................................................(BASELINE) 23 82 16 Air Coils ...................................................................................................................... (OPTION) 23 84 00 Humidity Control Equipment ................................................................................. (OPTION)

DIVISION 26 - ELECTRICAL

26 00 00 Electrical Basic Requirements 26 05 09 Equipment Wiring ...................................................................................................(BASELINE) 26 05 19 Low-Voltage Electrical Power Conductors and Cables .................... (BASELINE & OPTION) 26 05 26 Grounding and Bonding for Electrical Systems .....................................................(BASELINE) 26 05 33 Raceways ..................................................................................................................... (OPTION) 26 05 34 Boxes .................................................................................................. (BASELINE & OPTION) 26 05 53 Identification for Electrical Systems ......................................................................(BASELINE) 26 08 05 Electrical Acceptance Testing..................................................................................(BASELINE) 26 09 00 Contactors and Control Devices ................................................................................. (OPTION) 26 24 16 Panelboards .............................................................................................................(BASELINE) 26 24 18 Residential Type Multi-Meter Center .....................................................................(BASELINE) 26 27 26 Wiring Devices ........................................................................................................(BASELINE) 26 28 16 Enclosed Switches and Circuit Breakers .................................................................(BASELINE) 26 41 13 Lightening Protection for Structures ........................................................................... (OPTION) 26 43 00 Surge Protection Devices ............................................................................................ (OPTION) 26 51 00 Lighting ............................................................................................................. (BASELINE)

DIVISION 27 - COMMUNICATIONS

27 05 28 Pathways for Communication Systems ....................................................................... (OPTION) 27 10 01 Backbone and Horizontal Communication ............................................................(BASELINE)

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 31 00 Fire Detection and Alarm ........................................................................................(BASELINE)

<Park - PMIS number> TABLE OF CONTENTS - 5

DIVISION 31 - EARTHWORK

<Insert Sections for Site-Specific work>

DIVISION 32 - EXTERIOR IMPROVEMENTS

<Insert Sections for Site-Specific work>

DIVISION 33 - UTILITIES

<Insert Sections for Site-Specific work>

END OF TABLE OF CONTENTS

This Page Intentionally Blank

<Insert Park and PMIS number> 01 11 00 - 1

091015 SUMMARY OF WORK

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Work covered by the Contract Documents.

2. Work phases.

3. Work under other contracts.

4. Government Furnished Materials.

5. Contractor use of premises.

6. Public use of site.

7. Occupancy requirements for buildings.

8. Work Restrictions.

9. Special Construction Requirements.

10. Soils Investigation Report.

11. Additional Reports.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: <Insert Project location (Park, area in park, city, and state). Describe the project location in enough detail that the Contractor can visit the site.>

B. The Work consists of the following:

1. The Work includes <Insert a brief description of the project. Do not merely repeat the title>.

2. Project is designed to comply with a Certification Level according to the U.S. Green Building Council's Leadership in Energy & Environmental Design (LEED) Rating System, as specified in Division 01 Section "Sustainable Design Requirements."

C. Project will be constructed under a single prime contract.

1.3 WORK PHASES

A. The Work shall be conducted in <Insert number> phases in the following order, with each phase substantially complete before beginning the next phase:

1. Phase <Insert designation>: <Briefly describe work of this phase> Work of this phase shall be substantially complete and ready for occupancy within <Insert number of days> after [the Notice to Proceed] [commencement of construction of this phase].

2. Phase <Insert designation>: The remaining Work shall be substantially complete and ready for occupancy at time of Substantial Completion.

<Insert Park and PMIS number> 01 11 00 - 2

1.4 WORK UNDER OTHER CONTRACTS

A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate the Work of this Contract with work performed under separate contracts.

B. Preceding Work: Government [has awarded] [will award] separate contract(s) for the following construction operations at Project site. Those operations are scheduled to be substantially complete before work under this Contract begins.

1. <Insert name of the Contract>: A separate contract [has been] [will be] awarded to <Insert name of separate Contractor> [to] [for] <Insert a brief description of work performed under separate contract>.

C. Concurrent Work: Government [has awarded] [will award] separate contract(s) for the following construction operations at Project site. Those operations will be conducted simultaneously with work under this Contract.

1. <Insert name of the Contract>: A separate contract [has been] [will be] awarded to <Insert name of separate Contractor> [to] [for] <Insert a brief description of work performed under separate contract>.

D. Future Work: Government [has awarded] [will award] separate contract(s) for the following additional work to be performed at site after Substantial Completion. Completion of that work will depend on successful completion of preparatory work under this Contract.

1. <Insert name of the Contract>: A separate contract [has been] [will be] awarded to <Insert name of separate Contractor> [to] [for] <Insert a brief description of work performed under separate contract>.

1.5 GOVERNMENT-FURNISHED MATERIALS

A. Government will furnish products indicated.

1. Government will arrange and pay for delivery of Government-furnished items according to Contractor's Construction Schedule.

2. After delivery, Government will inspect delivered items for damage. Contractor shall be present for and assist in Government's inspection.

3. If Government-furnished items are damaged, defective, or missing, Government will arrange for replacement.

4. Contractor is responsible for receiving, unloading, and handling Government-furnished items at Project site.

5. Contractor is responsible for protecting Government-furnished items from damage during storage and handling, including damage from exposure to the elements.

6. If Government-furnished items are damaged as a result of Contractor's operations, Contractor shall repair or replace them.

7. Contractor shall install and otherwise incorporate Government-furnished items into the Work.

B. Government-Furnished Products:

<Insert Park and PMIS number> 01 11 00 - 3

1. <Insert description, in separate subparagraphs, for each Government-furnished product.>

1.6 CONTRACTOR USE OF SITE

A. General: Contractor shall have full use of the site for construction operations during the construction period. Contractor's use of the site is limited only by the Government's right to perform work or to retain other contractors on portions of Project.

B. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to [work in areas] [areas within the Contract limits] indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Confine constructions operations to <Insert description of areas where work is permitted>.

2. Limit site disturbance, including earthwork and clearing of vegetation, to 40 feet beyond building perimeter; 10 feet beyond surface walkways, patios, surface parking, and utilities less than 12 inches in diameter; 15 feet beyond primary roadway curbs and main utility branch trenches; and 25 feet beyond constructed areas with permeable surfaces (such as pervious paving areas, storm water detention facilities, and fields) that require additional staging areas in order to limit compaction in the constructed area.

C. Storage of Materials: Confine storage of materials to <Insert description of areas where materials may be stored>.

D. Preservation of Natural Features:

1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

2. Provide temporary barriers to protect existing trees and plants and root zones.

3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with

Contracting Officer and remove agreed-on roots and branches that interfere with construction.

4. Do not fasten ropes, cables, or guys to existing trees.

5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

E. Driveways and Entrances: Keep driveways <list other areas if applicable> and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

F. Construction Camp: Establishment of a camp within the park will not be permitted.

G. Construction Camp: Establishment of a camp will be permitted in <Insert description of area where construction camp is permitted>. Provide utilities as specified in Division 1 Section “Temporary Facilities and Controls”. Keep camp neat and clean and return site to previous condition

<Insert Park and PMIS number> 01 11 00 - 4 at completion of work. These requirements also apply to all Contractors’ employees who may, with prior approval, establish their own camping facilities.

H. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.

1.7 PUBLIC USE OF SITE

A. The [building] [road] will be closed to the public during construction.

B. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public.

[Building] [Road] closures will be permitted, when required, upon specific approval of Contracting Officer for a maximum of <Insert maximum time period allowed for closures>.

1.8 OCCUPANCY REQUIRMENTS FOR BUILIDINGS

A. Existing Buildings

1. Full Government Occupancy: Government will occupy buildings that will be under construction during the entire contract period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.

a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO.

b. Maintain existing building in a weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period.

2. Partial Government Occupancy: Government will occupy the premises during entire construction period, with the exception of areas under construction. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government’s operations.

Maintain existing exits, unless otherwise indicated.

a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the Contracting Officer (CO).

B. New Buildings

1. Government Occupancy of Completed Areas of Construction: Government reserves the right to occupy and to place and install equipment in completed areas of building, provided

<Insert Park and PMIS number> 01 11 00 - 5 such occupancy does not interfere with completion of the Work. Such placement of equipment and partial occupancy shall not constitute acceptance of the entire project.

a. Contracting Officer will prepare a Beneficial Occupancy letter for each specific portion of the Work to be occupied before Government occupancy.

b. Obtain a Certificate of Occupancy from the NPS before Government occupancy.

c. Before partial Government occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed.

On occupancy, Government will operate and maintain mechanical and electrical systems serving occupied portions of building.

d. On occupancy, Government will assume responsibility for maintenance and custodial service for occupied portions of building.

1.9 CONDUCT OF OPERATIONS

A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.

B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Submit requests [24 hours] [48 hours] <Insert number> in advance of the work to the Contracting Officer for approval.

C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

1.10 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be generally performed during normal business working hours of <Insert time> a.m. to <Insert time> p.m., Monday through Friday, except when otherwise indicated.

1. Weekend Hours: <Insert restrictions on times permitted for weekend work.>

2. Early Morning Hours: <Insert restrictions or references to regulations by agency(ies) with jurisdiction for restrictions on noisy work.>

3. Hours for [Core Drilling] <Insert noisy activity>: <Insert Government’s restrictions.>

B. Existing Utilities

1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.

2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

<Insert Park and PMIS number> 01 11 00 - 6

1. Notify Contracting Officer not less than [two] <Insert number> days in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without Contracting Officer’s written permission.

3. Hours for Utility Shutdowns: <Insert Government’s restrictions when outages are allowed and the maximum length of time for the outage.>

D. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes.

1.11 SPECIAL CONSTRUCTION REQUIREMENTS

A. Project Website: A project website administered by the NPS will be used for purposes of managing communication and documents during the construction stage.

1. See Section 01 31 00 “Project Management and Coordination” for requirements on using the Project Website.

B. <Insert special requirements like limited access due to seasonal shutdown, park activities, limited access periods, government furnished permit requirements, etc.>

1.12 SOILS INVESTIGATION REPORT

A. A soils investigation report entitled <Insert title, date> has been prepared by<Insert author>.

B. A copy of the report is available to all plan holders with this package.

C. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.

1.13 ADDITIONAL REPORTS

A. A report entitled <Insert title, date> has been prepared by<Insert author>.

B. A copy of the report is available to all plan holders with this package.

C. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 11 00

XXXX - 111111 01 26 01 - 1

031414 CONTRACT MODIFICATION PROCEDURES

SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. The work of this section consists of administrative and procedural requirements for contract modifications.

1.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):

1. Rent

2. Utilities

3. Furnishings

4. Office equipment

5. Executive and management staff not exclusively assigned to the project

6. Support, accounting, and administrative staff

7. Preparation of cost proposals, estimating, and schedule analyses connected with

Modifications

8. Estimating and preconstruction services

9. Mortgage costs

10. Real estate and corporate taxes

11. Automobile maintenance and travel costs for home office personnel

12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.

13. Depreciation of equipment and other assets

14. Home office supplies (paper, staples, etc.)

15. Legal services

16. Accounting and data processing

17. Professional fees/registration

B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:

1. Project Manager, Assistant Project Manager

2. Superintendent, Assistant Superintendent

3. Quality Control, Safety Officer, Environmental Manager, etc.

4. Engineers

5. Travel, lodging, and per diem (as established by Federal Travel Regulations)

XXXX - 111111 01 26 01 - 2

6. Scheduling

7. Field Office Trailers and associated temporary utilities

8. Field office supplies

a. Mailing and couriers

b. Reproduction costs

c. Storage

d. Phones

e. Computers

f. Copiers

9. Personal vehicles i.e. Superintendent Pickup trucks

C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:

1. Hoisting

2. Material handling

3. Temporary fencing

4. Port-a-lets

5. Trash removal, dumpsters

6. Barricades

7. Small tools

8. Safety supplies

9. Scaffolding

10. Daily cleaning

11. Traffic control

12. Temporary signage

13. Temporary heating and power

D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: This is the hourly rate paid directly to the worker

b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:

1) Social Security

2) Medicare

3) Workers Compensation– Policy and company calculation to be made available.

4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.

5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.

XXXX - 111111 01 26 01 - 3

6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.

c. Fringe Benefits: Various non-wage compensations provided to employees such as:

1) Health Care Insurance Premiums

2) Cell Phone

3) Clothing

4) 401K and Pensions

5) Vehicle allowances

6) Gas allowance

7) Life insurance premiums

8) Disability insurance

9) Other Fringe Benefits required under an enforceable collective bargaining agreement

E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.

F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.

G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.

H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS

A. General:

1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.

2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement.

Contractor may utilize the government provided Contractor Estimate Form, or their http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank http://www.nps.gov/dscw/publicforms.htm#ct

XXXX - 111111 01 26 01 - 4

own form, provided that it contains the same information and level of detail as the Gov’t provided form.

3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.

Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.

4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.

5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

B. Labor:

1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.

Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. The labor cost for foremen shall only be costs for related work required for the modification.

C. Materials:

1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.

2. No markup shall be applied to any material provided by the NPS.

D. Equipment:

1. Equipment used for the project must be appropriately sized for the work being performed.

2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.

3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region)

b. Construction Blue Book

XXXX - 111111 01 26 01 - 5

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals.

Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.

6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.

8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

E. Establishment and Application of Overhead and Profit Percentages:

Utilize the Profit Calculator to generate the allowable maximum rate for Profit on self-performed work.

Insert the result below where indicated by the red X.XX%. Work collaboratively with the COR to produce the draft Profit Calculator for Design Development (DD) submission. Denver Service Center Contracting Services division will approve the final number. Submit completed Profit Calculator with the DD submission.

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.

Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:

Overhead………………10% Profit………………X.XX%

2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.

http://www.nps.gov/dscw/publicforms.htm#dt

XXXX - 111111 01 26 01 - 6

4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.

5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

PART 2 - PRODUCTS

PART 3 - EXECUTION

END OF SECTION 012601

<Insert Park and PMIS number> 01 27 00 - 1

082714 DEFINITION OF CONTRACT LINE ITEMS

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS

PART 1 - GENERAL

1.1 SUMMARY

A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.

B. If no contract line item exists for a portion of the work, include the costs in a related item.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS

A. Contract Line Item No.[0001] <Insert item number, continue with sequential numbering> <Insert item title>.

1. This item consists of <Insert item description>.

2. Measurement for payment will be <Insert description of method or conditions affecting measurement.>

3. Payment will be made at the contract [price per <Insert units >] [lump sum price].

B. Contract Line Item No. [000X] <Insert item number, continue with sequential numbering>Option [A] <Insert letter designation, continue with sequential letters> <Insert Option title>.

1. This item consists of <Insert item description>.

2. Measurement for payment will be <Insert description of method or conditions affecting measurement.>

3. Payment will be made at the contract [price per ]<Insert units >[lump sum price].

C. Option [A] <Insert letter designation, continue with sequential letters> <Insert Option title>.

1. Contract Line Item No. [0001] <Insert item number, continue with sequential numbering>:

a. This item consists of <Insert item description>.

b. Measurement for payment: <Insert description of method or conditions affecting measurement.>

c. Payment will be made at the contract [price per ]<Insert units >[lump sum price].

2. Contract Line Item No. [0002] <Insert item number, continue with sequential numbering>:

<Insert Park and PMIS number> 01 27 00 - 2

082714 DEFINITION OF CONTRACT LINE ITEMS

a. This item consists of <Insert item description>.

b. Measurement for payment: <Insert description of method or conditions affecting measurement.>

c. Payment will be made at the contract [price per ]<Insert units >[lump sum price].

3. Contract Line Item No. [0003] <Insert item number, continue with sequential numbering>:

a. This item consists of <Insert item description>.

b. Measurement for payment: <Insert description of method or conditions affecting measurement.>

c. Payment will be made at the contract [price per ]<Insert units >[lump sum price].

END OF SECTION 01 27 00

<Insert Park and PMIS number> 01 31 00 - 1

091015 PROJECT MANAGEMENT AND COORDINATION

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Definitions

2. Construction Coordination.

3. Submittals

4. Coordination Drawings.

5. Requests for Information (RFIs).

6. NPS/DSC SharePoint Project Website.

7. Project meetings.

8. Environmental Coordination.

9. Permits

B. Related Requirements:

1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.

2. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering…

This is the start of the file's text. The full file is on GovTribe.