Draft Request for Proposal (RFP) NNG17611358R, Questions and Answers #74-86
View the file
Other files
Show 40 more
Latest 50 of 67 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question # RFP Section RFP
Requirement/Statement/Topic Question Issue/Rationale for Question/Proposed Solution Answer
74 L.15 (b) (2) para
Attachment C Section 6
"In Section 6, provide Position Qualification for all Prime Offeror proposed direct labor categories specified in Section 1 and each individual Subcontractor Direct Labor Category included in Section 5."
"6. POSITION QUALIFICATIONS
(For All Prime and Subcontractor Direct Labor Categories):
NOTE: TO BE PROPOSED (TBP)
– A Position Qualification shall be proposed for each individual Prime Direct Labor Category included in Section 1 and each individual Subcontractor Direct Labor Category included in Section 5"
Will the Government please provide direction and guidance in Section L Staffing Plan on what should be included in a written Position Qualifications? The following guidance was included in the earlier FRFP:
"Offerors shall provide written position qualifications for the specific labor categories proposed for this requirement.
Offerors shall address the minimum requirements in the position qualifications, to include the necessary experience, summary of duties and responsibilities, specific requirements/licensing, minimum education and minimum experience required for the position. All position qualifications will be incorporated into the resultant contract in Attachment C, Section 6."
There is no requirement for Position Qualifications in Mission Suitability Management SF B? Without guidance from MS Staffing Plan there are no requirements on what should be included in a Position Qual.
In Provision L.14 (b)(2), paragraph 2, the Government will add the following language, "Offerors shall provide written position qualifications for the specific labor categories proposed for this requirement. Offerors shall address the minimum requirements in the position qualifications, to include the necessary experience, summary of duties and responsibilities, specific requirements/licensing, minimum education and minimum experience required for the position. All position qualifications will be incorporated into the resultant contract in Attachment C, Section 6."
75 Draft SOW N/A Will the government be releasing additional referenced documents in the eLibrary (e.g.
GPR-8830.1A, GPR-1410.2, etc.)?
Will the Government provide electronic links to or copies of the compliance documents referenced throughout the SOW to assist offeror's in determining necessary scope or level of effort associated with SOW support requirements?
Provide copies or links to documents referenced in the
SOW.
The Government will provide GPR- 8830.1A and GPR 1410.2 in the bidder’s library.
If additional documents referenced in the SOW are not accessible, Offerors are encouraged to identify those specific documents to the Government.
Requirement/Statement/Topic Question Issue/Rationale for Question/Proposed Solution Answer
76 Section L, L.14 (c), Subfactor C
N/A Subfactor C(a)(7) states, " NOTE: FOR
PURPOSES OF THE SMALL BUSINESS
SUBCONTRACTING PLAN, THE PROPOSED
GOALS SHALL BE STATED AS A PERCENT OF
TOTAL SUBCONTRACTS, NOT
AS A PERCENT OF THE IDIQ MAXIMUM
ORDERING VALUE, REFER TO THE BELOW
EXAMPLE".
The note makes previous and later instructions in this section unclear as it states goals should be based on "percent of total subcontract, not as a percent of the IDIQ Maximum Ordering Value" when all other instructions and the example also state goals will be expressed as a percent of the IDIQ Maximum Ordering Value.
Clarification The Government will correct the note to read "stated as a percent of total subcontracts, and as a percent of the total IDIQ Maximum Ordering Value…" in the Final RFP.
77 Att. A; SOW 4.0; N/A Is the contractor responsible for the operations and maintenance of the Range Operations Management Systems (ROMS) architecture (e.g. IT Security, system upgrades, license management, etc)?
If answer to above is yes, please provide details on the complete system architecture to include specific applications, application modules, and purpose / usage.
The Government will provide system details in the bidder's library
78 Att. A; SOW 4.0; N/A Will the government provide a User Handbook for ROMS or any other guide?
The Government will provide system details in the bidder's library
Requirement/Statement/Topic Question Issue/Rationale for Question/Proposed Solution Answer
79 N/A N/A Given the extensive nature of equipment obsolescence, it would be beneficial to non-incumbents to have the ability to examine firsthand the equipment to be operated and maintained under the performance of this contract. We respectfully request the government to host an Open House / Industry Day including an inspection and assessment of the facilities and systems to be operated and maintained under the Range Operations Contract.
The Government will host a site visit on August 28, 2017.
80 Att. M N/A When will the government release Attachment M – Contract Historical Data?
The Contract Historical Data requirement did not exist on the preceding contract and is therefore unavailable for this acquisition. The contract Attachment M refers to the Contract Historical Data to be generated under ROC II in accordance with clause C.1 GSFC 52.211-91 SCOPE
OF WORK (FEB 2016)
81 SOW 4.1 Operations Directive With the successful launch of Antares on October 17. 2016 it is assumed that new procedures and protocols were enforced and integrated into existing documents, including the OD. Could the Government provide the approved OD for the most recent Antares mission and other recent projects?
Provide recently approved (Year 2015 or later) OD for the Antares and other projects in the Bidder’s Library.
The Government will provide additional Antares documentation in the bidder's library.
Requirement/Statement/Topic Question Issue/Rationale for Question/Proposed Solution Answer
82 RTO 1, RTO 2,
RTO 3
Preventative Maintenance Instructions (PMI) for sustainment and maintenance activities
In order to effectively size the support requirements for sustainment and maintenance activities of the Range, a complete list of all PMIs including descriptions and frequency is required.
Could the Government provide a listing and breakout of all Preventive Maintenance Instructions specific to each part of the range required for all contract equipment both software and hardware associated with the RTOs?
All PMIs be added to the Bidder’s Library including the frequency of activities. If Government can provide volume, it will allow for more competitive solutions.
The Government will provide preventative maintenance instructions in the bidder's library.
83 SOW 4 ROMS ROMS is an integral part of the Range, yet very little information is provided on its design, architecture, interfaces and current issues. Will the Government provide design documents, architecture documents, interface documents, open issues and other information?
Provide design documents, interface documents, architecture documents and other pertinent documents in the bidders library
The Government will provide system details in the bidder's library.
84 SOW 3.1.1 and 3.1.2
Weekly and Monthly Reporting for maintenance activities.
In order to effectively size the amount of maintenance and sustaining engineering support on ROC II, can the Government provide weekly reports for the last 6 months and monthly status reports up to the last 2 years of the current ROC contract?
Provide the last 6 months of weekly reports and up to 2 years of monthly reports that provide information on sustaining and maintenance activities in the Bidder’s Library.
The Government will provide preventative maintenance instructions in the bidder's library.
85 Non-proposed Costs
Material Plug To minimize varying assumptions and pricing, would the government consider providing plug numbers for RTO # 3 materials and travel?
The Government will provide a material and travel plug number for RTO3 in the final RFP
86 Exhibit 2
The Government has not provided a separate set of lines for fringe benefits. Is it permissible for an Offeror to add a column to address Fringe and distinguish those costs from Overhead in the exhibit?
The RFP instructions for Exhibit 2 refer to "Indirect Costs" which include Fringe Benefits. The Offeror is permitted to add lines in Exhibit 2 to capture "Indirect Costs."