Enclosure_4_RTO_2_SOW.pdf

PDF 315 KB Posted

Attached to
Facilities Construction Engineering and Technical Services Federal contract opportunity
Solicitation number
NNG16557109R
Issued by
National Aeronautics and Space Administration Goddard Space Center

About this file

Enclosure 4

View the file

Other files for this federal contract opportunity

Other files attached to Facilities Construction Engineering and Technical Services, newest first.
File Type Posted
Amendment_7.pdf PDF
FaCETS_III_Final_RFP_NNG16557109R_Section_B-M.pdf PDF
Q_ _A.docx DOCX document
Appendix_6.pdf PDF
Appendix_3.pdf PDF
Amendment_4_doc.pdf PDF
ATTACHMENT_R_IDIQ_Fixed_Price_Rate_Matrix__Revised_9-27-16_(001).pdf PDF
Appendix_5.pdf PDF
ATTACHMENT_R_IDIQ_Fixed_Price_Rate_Matrix__Revised_9-20-16_(001).pdf PDF
Amendment_3.pdf PDF
FaCETS_III_Final_RFP_NNG16557109R_Section_B-M.pdf PDF
Amendment_2.pdf PDF
Amendment_1.pdf PDF
Appendix_2_-_FaCETS_III_A-E_Specifications_February_2016.pdf PDF
ATTACHMENT_P_OCI_Avoidance_Plan.pdf PDF
ATTACHMENT_L_IT_Security_ADL__JUL_2016_.pdf PDF
ENCLOSURE_3_RTO_1_SOW.pdf PDF
APPENDIX_5.pdf PDF
EXHIBIT_10_Past_Performance_Questionnaire_.pdf PDF
ATTACHMENT_G_MD35.pdf PDF
APPENDIX_4_BIM_SCOPE.pdf PDF
ATTACHMENT_R_IDIQ_Fixed_Price_Rate_Matrix__Revised_7-1-16_(003).pdf PDF
ATTACHMENT_B_Construction_Specifications.pdf PDF
Summary_of_Changes_Between_Draft_RFP_Documents_and_Final_RFP_Documents.pdf PDF
ATTACHMENT_E_Contract_Historical_Data_Attachment.pdf PDF
ATTACHMENT_O_PMC_Plan.pdf PDF
ATTACHMENT_H_MD58.pdf PDF
ATTACHMENT_K_DD_254.pdf PDF
APPENDIX_6.pdf PDF
ATTACHMENT_F_MD15.pdf PDF
APPENDIX_3_CADD_MANUAL.pdf PDF
Section_A_SF30.pdf PDF
ENCLOSURE_1_IT_Security_Management_Plan_Template.pdf PDF
FaCETS_III_Industry_Day_List_of_Attendees.xlsx XLSX spreadsheet
ATTACHMENT_O_PMC_Plan.pdf PDF
EXHIBIT_10_Past_Performance_Questionnaire_20160314.pdf PDF
ATTACHMENT_C_-_List_of_Installation-Accountable_Government_Property_February_2016.pdf PDF
Appendix_1_-_FMD_Standard_Reference_Document_Feb_2016.pdf PDF
ATTACHMENT_E_Contract_Historical_Data_Attachment.pdf PDF
ATTACHMENT_R_IDIQ_Fixed_Price_Rate_Matrix__Revised_7-1-16_(003).pdf PDF
ATTACHMENT_N_Small_Business_Sub_Plan.pdf PDF
ENCLOSURE_1_IT_Security_Management_Plan_Template.pdf PDF
ATTACHMENT_K_DD_254.pdf PDF
ATTACHMENT_Q_IT_Security_Mgt_Plan_COVER_PAGE.pdf PDF
ATTACHMENT_F_MD15.pdf PDF
ATTACHMENT_L_IT_Security_ADL__JUL_2016_.pdf PDF
APPENDIX_5.pdf PDF
FaCETS_III_DRFP_Section_A_SF_33.pdf PDF
APPENDIX_4_BIM_SCOPE.pdf PDF
Appendix_2_-_FaCETS_III_A-E_Specifications_February_2016.pdf PDF
Show all 50

Facilities Construction Engineering and Technical Services has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Facilities Management Division Scope of Work

Facilities Management Division A-E Services – Formal Design

Date: 12/2/2015 Page 1 of 12

Work Request No.: Representative Task Order #2

Title: GSFC Bldg. 012, Near Earth Object Focal Plane Array Project Suite Renovation

Project Type: Formal Design

Attachments: None

Funding:

The escalated total Engineering Estimate for Construction (EEC), developed by the

Government, shall serve as the estimated construction price of this task order. The escalated total engineering estimate is the estimated cost escalated to the midpoint of construction, including management costs but not including any contingencies, engineering, or Government quality assurance costs. Per FAR 52-236-22, “Design Within

Funding Limitations”, the A-E Contractor shall provide a complete and biddable design that is within the funding limitations established in the Government’s EEC. The EEC for this task order is $305K.

General:

Satellite Servicing Capabilities Office (SSCO) needs a project management suite of approximately 1500 Square Feet (SF) constructed to the secret level to collaborate with an external partner on an emergent capability for launch in 2017. A future expansion of capability may require office expansion as a separate future phase.

The new suite will be improved over the existing mismatch of finishes, exposed pipes, surface mounted power strip and other features that date back to when the area was a lab.

The suite should be convenient to an existing secure conference room and will incorporate 780 SF of office space already assigned to SSCO in B12 Rooms E036, E034 and E032. Detailed requirements include:

Space Physical Requirements

Project Manager Office 1@ ~150 SF

Semi-private office for two management level external partners1@ ~ 150 SF

Secretary/project suite reception and work area 1 @ ~200 SF

Facilities Management Division A-E Services – Formal Design

Date: 12/2/2015 Page 2 of 12

Open office suite to accommodate 12 workstations for Project leads at GS-15 level ~825 SF

Space for Multi-Functional Device (MFD)

Closet space for office products storage ~ 10 SF

Adjacency Requirements

All office spaces are to be housed within same perimeter defined as secret level accessible by key card.

Project suite shall be adjacent to a secret level conference room or space capable of being upgraded to the required security. A follow-on phase is anticipated to upgrade an existing conference room to a Secure Compartmentalized Information

Facility (SCIF) level space.

Potential growth of project suit for future project(s). There are ongoing discussions involving the use of E008, E008A, E008B and E020.

Aesthetics

In order to make the space as appealing as possible to the undisclosed external partner the project scope will maximize clean, planar wall surfaces and enclose abutments and protrusions created by pipes, surface mounted raceways and LAN wire mold within reason. The carpeting, ceiling tiles, wall surface shall be uniform and consistently treated. The renovations are intended to eliminate the remaining vestiges of previous uses for lab space.

Security

Each primary entrance shall be outfitted with electronic Card Key access

Perimeter walls and ceilings adjacent to corridors and unrelated office space shall prevent transmission of conversational level speech. The development area is bordered by the corridor, the secured conference room, the mechanical room and an outside wall. The true likelihood of sound transmission outside the space is minimal. All occupants will share the same security level. Normal sound transmission class is acceptable.

Safe - Provided by customer

Gray phone/Secure Internet Protocol Routing (SIPR) net phone and connection

Facilities Management Division A-E Services – Formal Design

Date: 12/2/2015 Page 3 of 12

General Scope of Work:

The Contractor shall furnish all labor, and associated services necessary to perform the following in accordance with the Scope of Work and Figures and Sketches depicted below:

This purpose of this project is to expand the current SSCO office holdings of E036, E034 and E032, which will be augmented by E030 and E026 (also Code 400 space.) E032 and

E034 will be demolished and two new offices will be constructed more centrally to the whole development area. This will constitute phase one development. Sporadically applied existing acoustical wall panels not attached to walls slated for demolition will also be removed. Three-fourths of the existing ceiling grid and the entire existing acoustical ceiling tiles and finish flooring will be removed. Existing lights will be retained, augmented and redistributed. Concrete Masonry Unit (CMU) walls to remain shall be furred-out and given a layer of drywall. Surface mounted electrical receptacles and LAN shall be placed in new partitions and new box-outs around induction unit valves. Use power pole where necessary for LAN and electric in open workstation area.

Install new carpet and acoustical ceiling tiles throughout.

Structural – Existing structural framing supports required demolition and reconfiguration of the area. Interior walls are not load bearing.

Architectural – Finish previously unfinished walls using materials and techniques to preserve the maximum amount useable space. Select materials and finishes from standard palette that evoke an upscale environment that one might expect to find in private industry. Where practical however, re-use and integrate significant expanses of walls, ceiling grid or floor finishes (carpet) that are in good condition and match to finish out areas of the project requiring demolition and reconfiguration. To maximum practical extent, conceal mechanical, plumbing and electrical features behind framed wall/ceiling constructions. Minimize spatial protrusions and abutments. Make use of existing alcoves to satisfy requirements for storage, and office conveniences like counters and cabinets.

Mechanical – The new occupancy will be roughly equivalent to the existing occupancy.

The ratio of enclosed office space to open work space will also be nearly equal.

Therefore, reconfigure existing ducts, supplies and returns to provide for the old location

Facilities Management Division A-E Services – Formal Design

Date: 12/2/2015 Page 4 of 12 of private offices to the new locations. Conceal all central air distribution features above the ceiling. Re-use and balance excess capacity from induction units where new offices enclose less space than previously conditioned by induction units. Induction units in the remaining open workstation area is assumed to provide adequate fresh air for occupancy.

Electrical – Conceal all new outlets within new wall cavities and where practical within an existing wall. Remove any existing surface run wire mold and outlets. Run new wire mold only where concealed by proposed workstation arrangement. Wire open office workspace light switches on circuit(s) independent of private offices. Re-use existing circuits to maximum extent possible. Provide standard office power, plus standard MFD receptacle.

Demolition Scope of Work:

Civil - None

Structural - None

Architectural

1. Room E026

a. Demo carpet and tile to substrate and vinyl cove base [abate Asbestos

Containing Material) ACM]

b. Demo ceiling grid angle along east wall

c. Demo east metal panel wall (abate ACM)

2. Room E030

a. Demo carpet and tile to substrate and vinyl cove base (abate ACM)

b. Demo ceiling grid and acoustical tile

c. Demo lights and salvage to Gov’t.

d. Demo east wall consisting of metal panel and CMU

e. Demo door and frame

3. Room E032 and E034

a. Demo carpet and tile to substrate and vinyl cove base (abate ACM)

b. Demo ceiling grid and acoustical tile

c. Demo lights retain for re-use

d. Demo east and south metal panel walls

e. Demo door and frame at E034 only

Facilities Management Division A-E Services – Formal Design

Date: 12/2/2015 Page 5 of 12

4. Room E036

a. Demo carpet and tile to substrate and vinyl cove base (abate ACM)

b. Demo ceiling grid and acoustical tile

c. Demo lights retain for re-use

d. Demo door and frame

e. Demo acoustical wall tiles glued to east wall and south wall (Option-

Retain and complete acoustical treatment as base for new drywall. Issue:

acoustical separation may be beneficial adjacent to mechanical room.)

Mechanical –see new work

Electrical/Telecom

1. Room E026

a. Demo light switch and blank off switch box

b. Demo east wall electrical receptacles and conduit back to nearest junction box

c. Demo LAN boxes; coil wire with box above ceiling

2. Room E030

a. Demo light switch and blank off switch box

b. Demo east wall electrical receptacles and conduit back to nearest junction box

c. Demo LAN boxes; coil wire with box above ceiling

3. Room E032 and E034

a. Demo light switch and blank off switch box (E034 only)

b. Demo east wall electrical receptacles and conduit back to nearest junction box

c. Demo LAN boxes; coil wire with box above ceiling

4. Room E036

a. Demo light switch and blank off switch box

b. Demo east wall electrical receptacles and conduit back to nearest junction box

c. Demo LAN boxes; coil wire with box above ceiling

Facilities Management Division A-E Services – Formal Design

Date: 12/2/2015 Page 6 of 12

d. Demo surface mounted electrical raceway and outlets along south wall

New Scope of Work:

Civil –No Work

Structural – No Work

Architectural

1. Room E026

a. Install new acoustical ceiling tile in existing grid

b. Install new 2’x 2’ carpet tile and vinyl cove base

c. Install new Metal Stud/Drywall (MS/DW) partition at corridor wall

2. Combined Open Rooms E030, E032, E034, E036

a. Far east wall with hat channel and install one layer 5/8” Gypsum Wall

Board (GWB) (Option- complete acoustical treatment on lower wall of same thickness as acoustical tile on upper half of wall and cover east wall with one layer of drywall.)

b. Frame columns and induction unit valves along south wall from floor to 6” above ceiling level; finish with GWB.

c. Box frame around pipes and plumbing that extend below finish ceiling level

d. Install new acoustical ceiling grid starting at remaining Room E026 grid to east wall

e. Install new MS/DW partitions for two new 150 SF offices

f. Install new MS/DW partitions at corridor alcove to create new closet

g. Install two new 3 x 7 wood doors with hardware at new offices and new closet

h. Paint all new and existing wall surfaces, doors, frames, and induction units.

i. Re-install removed fluorescent light fixtures plus additional matching fixtures in new ceiling area.

j. Install sound attenuation Batt insulation 1 foot on each side of new office partitions and above ceiling in space adjacent to corridor.

Facilities Management Division A-E Services – Formal Design

Date: 12/2/2015 Page 7 of 12

k. Optional- Install custom casework cabinet with counter top in existing alcove (This can also be handled by a furniture solution which the customer can fund using R&D funds.)

Mechanical

1. Combined Open Rooms E030, E032, E034, E036

a. Extend duct work as required to reposition supply air diffusers that served rooms E032, E034 and E036 to align with new ceiling grid; do same for return air grills

b. Install new ducted return air grill in new Partner office

c. Reposition return air grill in new Project Manager office

2. Relocate existing thermostats as required for open space arrangement

3. Rebalance 12-AC-5 and induction unit flows as required for new occupancy

Electrical

1. Install 13 new quad electrical outlets in new open workstation area to support 13 workstations (four may incorporated with new office partitions; the remainder shall be provide via power pole installation

2. Install new outlet to support standard MFD in new alcove

3. Install new GFI duplex receptacle at counter top level in alcove to be outfitted with furniture cabinet.

4. Install approximately 16 re-used recessed fluorescent light fixtures. Install one surface mounted 2 x 4, two-tube fluorescent fixture above

Fire Protection

1. Install one exit sign

2. Install two new fire alarm strobes

3. Upgrade and adjust sprinkler head locations to align with new ceiling grid. Add up to two as needed for appropriate coverage.

Other

1. Provide conduit from primary entrance to nearest low voltage circuit for electronic key card reader.

2. Provide new key card reader and outfit existing door for new electric strike

(Existing door may require replacement—not addressed under Architectural new

Facilities Management Division A-E Services – Formal Design

Date: 12/2/2015 Page 8 of 12 work) If required, remove existing door, side leaf and frame; replace frame with steel knock-down door frame and steel door for 3-0 x 7-0 nominal steel

3. Provide new project signage for entrance door and new room number placard.

4. Provide metal shelving standards, brackets and shelves for interior of new storage closet.

Outages:

Outage(s) required: HVAC 12-AC-5, Isolated Power

Building/spaces affected by the outage: Most E-wing spaces on 00X level E001 through

E036

NOTE: All work shall be accomplished in accordance with GSFC FaCETS III

Construction and Architect-Engineer specifications.

Figures and Sketches:

Existing Room Configuration Proposed Room Configuration

Facilities Management Division A-E Services – Formal Design

Date: 12/2/2015 Page 9 of 12

Conceptual Furnishings and Build-outs

Demolition- Partitions, Doors and Frames

Facilities Management Division A-E Services – Formal Design

Date: 12/2/2015 Page 10 of 12

Demolition – Flooring, Carpet, Ceilings

Demolition- Lighting, Electric, Telecom

Facilities Management Division A-E Services – Formal Design

Date: 12/2/2015 Page 11 of 12

New Work – Walls and Partitions

New Work – Sprinklers and Mechanical Devices

Facilities Management Division A-E Services – Formal Design

Date: 12/2/2015 Page 12 of 12

New Work – Ceiling Grid

New Work – Lighting, Electrical, and LAN