This is a Request for Proposal for a construction contract to replace air handling units at the Smithsonian Institution's National Museum of American History in Washington, DC. The project scope includes removing existing air handling units in four mechanical rooms on the fourth floor and replacing them to provide climate control for collection storage spaces on the fourth and fifth floors. Temporary cooling systems must be provided throughout construction. The contractor must submit load calculations and shop drawings for the temporary systems and purchase equipment to turn over to the Smithsonian. The period of performance is 570 calendar days from notice to proceed. Offerors must demonstrate minimum qualifications, and technical and cost proposals will be evaluated. The project magnitude is estimated over $10 million.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Replace ACU’s for Collection Storage on 4th and 5th Floors NMAH 14 Street & Constitution Ave NW, Washington, DC
2003112
Replace ACU’s for Collection Storage on 4 and 5 Floors NMAH 14th Street & Constitution Ave NW, Washington, DC
Construction Documents 12/21/22
12/21/22
ChanVC Typewriter Appendix 2
December 21, 2022 SF Project No. 2003112
Construction Documents Page 1 of 67
SUPPLEMENTARY CONDITIONS FOR CONSTRUCTION 010000
S P E C I F I C A T I O N S
TABLE OF CONTENTS
DIVISION 1 GENERAL REQUIREMENTS
010000 Supplementary Conditions for Construction
PROJECT SUMMARY AND INFORMATION
1. Project Information
2. Summary of Work
3. Contract Time for Completion
4. Schedule of Options for Bid/Proposal
5. Schedule of Unit Prices
6. Bidder/Offeror Examination of Site
7. Availability of Documents
SPECIAL PROJECT REQUIREMENTS
8. Units of Measure
9. Non-Public, Tenant and Secured Spaces
10. Museum Artifacts and Scientific Research Materials
11. Protection of Historic Properties
12. Commitment to Sustainability
13. Commissioning
CONTRACTOR USE OF PREMISES
14. Hours of Work, Workdays and Government Holidays
15. Conditions Affecting Contractor’s Work
16. Contractor Deliveries, Hauling and Access
17. Dress and Deportment
18. Contractor Parking
19. Eating, Drinking, Smoking and Illegal Substance Abuse
PROJECT COORDINATION
20. Coordination of Trades
21. Quality Control
Construction Documents Page 2 of 67
22. Permits, Licenses and Fees
23. Utility Service Interruptions and New Connections
24. Smithsonian-Furnished Items Installed by the Contractor
25. Salvage
26. Cutting, Patching and Matching Existing Work
PROTECTION OF THE SITE DURING CONSTRUCTION
27. Protection of the Site
28. Protection of Flora, Fauna and Central Computer Controller Irrigation
System
29. Debris Control and Daily Cleanup
30. Dust and Air Quality Control
31. Noise Control
32. Vermin, Pest and Rodent Control
33. Drilling, Welding andTorchCutting
TEMPORARY CONSTRUCTION FACILITIES
34. Contractor Field Offices, Trailers and Sheds
35. Staging, Storage and Work Areas
36. Sanitary Facilities
37. Temporary Utility Services and Extensions
38. Scaffolding and Platforms
39. Project Signs
MEETINGS
40. Preconstruction Meeting
41. Pre-Condition Survey of the Site
42. Project Meetings
SUBMISSIONS
43. Submittal Definitions
44. Submittals and Reviews
45. Criteria for Product Selection
46. Progress Photographs
47. Contractor Correspondence and Daily Reports
SAFETY, HEALTH AND FIRE PROTECTION
48. Jobsite Safety
Construction Documents Page 3 of 67
49. Toxic and Hazardous Substances
50. Personal Protective Equipment
51. Barriers, Barricades and Walkways
52. Existing Fire Protection Systems
SECURITY REQUIREMENTS
53. General Security Requirements
54. Identification Badges
55. Access and Property Control at the Museum Support Center
56. Security of Temporary Openings
57. Existing Building Alarm Systems
58. Security Guard Duty Charges
SCHEDULES AND PAYMENTS
59. Schedule of Values
60. Scheduling & Payments / Bar Chart
61. Scheduling & Payments / Critical Path Method
62. Assignment of Claims
PROJECT CLOSEOUT REQUIREMENTS
63. Project Closeout
64. Substantial Completion
65. Final Completion and Acceptance
Section 013250 Bim Requirements
Section 017823 Operations and Maintenance Data Requirements
Section 019100 Testing, Adjusting and Balancing for HVAC
Section 019113 Commissioning
DIVISION 2 EXISTING CONDITIONS
Section 028200 Asbestos Abatement
Section 028300 Work Activities Impacting Lead-Containing Materials
Construction Documents Page 4 of 67
DIVISION 7 THERMAL AND MOISTURE PROTECTION
Section 078413 Penetration Firestopping
DIVISION 8 OPENINGS
DIVISION 9 FINISHES
Section 092110 Gypsum Board Assemblies
Section 095100 Acoustical Ceilings
Section 099000 Painting and Coating
DIVISION 21 FIRE SUPPRESSION
Section 211313 Wet Pipe Sprinkler Systems
DIVISION 22 PLUMBING
Section 220000 Plumbing
DIVISION 23 HEATING, VENTILATING AND AIR CONDITIONING
Section 230000 General Provisions
Section 230500 Demolition and Removals
Section 230513 Motors and Starters
Section 230523 Piping, Valves and Fittings
Section 230548 Equipment Bases and Vibration Control
Section 230700 Insulation
Section 230923 Controls and Instrumentation
Section 232000 Plumbing Equipment
Section 232500 Specialties and Accessories
Section 233000 Ductwork and Air Outlets
Section 237000 Air Handling and Treatment
Construction Documents Page 5 of 67
Section 237323 Custom Air Handling Units
DIVISION 26 ELECTRICAL
Section 260000 General Provisions
Section 260050 Demolition and Removals
Section 260500 Basic Materials
Section 262416 Panelboards
DIVISION 28 ELECTRONIC SAFETY AND SECURITY
Section 283111 Addressable Fire Alarm Systems
APPENDIX A: LIMITED HAZ MAT REPORT
END OF TABLE OF CONTENTS
December 21, 2022 OFEO Project No. 2003112
Construction Documents Page 6 of 67
SUPPLEMENTARY CONDITIONS FOR CONSTRUCTION 01000
DIVISION 1 - GENERAL REQUIREMENTS
SECTION 01000
SUPPLEMENTARY CONDITIONS FOR CONSTRUCTION
PROJECT SUMMARY AND INFORMATION
1. PROJECT INFORMATION
1.1. SF Project No. 2003112
Replace ACU’s for Collection Storage on 4th and 5th Floors
National Museum of American History
14th Street and Constitution Avenue, NW
Washington, D.C. 20001
1.2. Smithsonian Institution Contacts:
Contracting Officer (CO), address for Fed Ex and UPS delivery:
Smithsonian Institution
Office of Contracting
MRC 1200
2011 Crystal Drive
Arlington, VA 22202
Contracting Officer (CO), address for USPS delivery:
Smithsonian Institution
Office of Contracting
MRC 1200
P.O. Box 37012
Washington, DC 20013-7012
Contracting Officer's Technical Representative (COTR), address for Fed Ex and UPS, delivery:
Smithsonian Institution
Mr. Jamil Burnett
COTR – Construction Manager
Office of Planning, Design & Construction
600 Maryland Avenue, SW
Suite 5001
Washington, DC 20024
Contracting Officer's Technical Representative (COTR), address for USPS delivery:
Construction Documents Page 7 of 67
Smithsonian Institution
Attn: Mr. Jamil Burnett
OPDC Capital Gallery
MRC 511
PO Box 37012
Washington, DC 20013-7012
2. SUMMARY OF WORK
2.1. The Contractor shall furnish all supervision, labor, materials and equipment needed to Replace ACU’s for Collection Storage on 4th and 5th Floors
National Museum of American History, as set forth on the Drawings for SF Project No.
2003112, sheets l through 22 and in these specifications, both dated June 25, 2021.
2.2. The Work includes, but is not limited to: replacement of the air handling units also known as ACU’s in the mechanical rooms at the 4th floor serving collection storage spaces on the 4th and 5th floors. In this project, the existing air handling units to be removed are addressed as ACUs, the new units will be addressed as AHUs. ACU replacement project will occur within four mechanical equipment rooms and will be staged over a single construction period to allow temporary cooling and time for the relocation of collections if necessary. The intent of the replacement is to address consolidation of current systems, as well as future support of expanded research and conservation areas on the 4th and 5th floors. Intent of the equipment replacement is to meet conservation standards for climate control.
2.3 Temporary cooling shall be provided, to maintain temperature and humidity on the collection storage spaces throughout the construction period, in accordance with the locations and parameters set out in the Construction Documents. The Contractor shall submit shop drawings and calculations of the temporary systems for approval. All temporary equipment shall be purchased and turned over to SI upon decommissioning.
Intent of suggested phasing plan is to utilize temporary equipment for Phase 1 then move the same equipment into different positions for Phase 2. For this reason, only two mechanical rooms on the 4th floor can be shut down at one time. The phasing and logisics plan indicates that two rooms on the East or West wing would be sequenced together to take so that only (1) of the buildings (2) freight elevators could be dedicated to the construction effort. AE after discussion with SI and could be changed in consultation with COTR if the contractor recommends a different phasing/logistics plan.
Contractor to submit load calculations and shop drawings for temporary cooling systems.
2.4 The Contractor shall furnish and install rented or purchased rooftop air handling units to provide temporary temperature and humidity control for the 5th floor Collection
Storage spaces as shown on the Drawings. The rooftop air handling units will not have
Construction Documents Page 8 of 67 freeze protection. All work associated with replacement of air handling units serving the
5th floor collection storage spaces shall be completed during the period of April 15 through October 31. Outside of this time period, chilled water will not be available for the temporary rooftop units and the units shall not be in operation
3. CONTRACT TIME FOR COMPLETION
3.1. Work under this contract shall begin by the Contractor within ten (10) calendar days after the Notice to Proceed and shall be completed within the total contract time of approximately 570 calendar days. All work, including project closeout activities, shall be completed in every respect within the contract time.
The assumption above includes 150 day pre construction period to for the procurement of long lead items, followed by a 420 day construction period.
3.2. The start date and completion date shall be as stated in the Notice to Proceed issued by the Contracting Officer.
4. SCHEDULE OF OPTIONS FOR BID/PROPOSAL
4.1. The following is a brief statement of the Work identified for *bid/proposal options. The complete description of the Work is identified elsewhere in the drawings and specifications.
BASE BID/PROPOSAL:
DEDUCT ALTERNATE 1: Deduct AHU-4CW-17.
Deduct the Air Handler AHU -4CW-17 and all associated work within the Mechanical
Equipment Room 4000M4.
5. SCHEDULE OF UNIT PRICES
5.1. The unit prices in the following schedule shall be submitted as part of the *bid/ proposal. The Smithsonian reserves the right to accept or reject any or all unit prices.
5.2. The Contractor agrees that, in the event that the Contractor is directed by the
Smithsonian to increase or decrease the quantities of work required by the contract documents on items listed below, the contract amount shall be adjusted based on the following unit prices.
Construction Documents Page 9 of 67
5.3. Unit prices shall include the furnishing of all materials, labor, equipment and services necessary for or incidental to the execution of the work specified. Unit prices shall include all direct and indirect costs, overhead, taxes, insurance and profit.
5.4. These unit prices shall be binding upon the Contractor for the duration of the project. No escalation or other variation shall be allowed.
5.5. If requested by the Smithsonian, the Contractor shall provide material, equipment and personnel to verify or determine changes in quantities. Contractor measurements and calculations shall be subject to verification by the COTR.
5.6. Schedule of Required Unit Prices:
ITEM Price ($) Per Unit
6. *BIDDER/OFFEROR EXAMINATION OF SITE
6.1. Every effort has been made to indicate all work necessary to complete the project as identified. All *bidders/offerors shall carefully examine the premises during the
*bid/offer period and satisfy themselves as to the extent, nature and location of the work, general and local conditions, particularly those bearing on transportation, disposal, handling and storage of materials, availability of labor, water, electric power, access routes, uncertainties of the weather, type of equipment and facilities needed for the successful execution of the Work.
6.2. Before the bid/offer opening date, bidders/offerors may view the project site on an appointment basis. Any comments, information or discussion during the site visit shall not modify the contract documents. Bidders/offerors shall make an appointment to view the site by contacting:
Mr. Jamil Burnett
COTR – Construction Manager
Smithsonian Institution
OPDC Capital Gallery
MRC 511
PO Box 37012
Washington, DC 20013-7012
Construction Documents Page 10 of 67
6.3. Pre-Bid/Pre-Proposal Conference and Site Visit. Before the bid/proposal opening date, a scheduled pre-bid/pre-proposal conference and site visit will be announced by the
Contracting Officer. The purpose of the scheduled meeting is to provide an opportunity for all bidders/offerors to review the project site. Any comments, information or discussion during the site visit shall not modify the contract documents.
6.4. This project is in a public area and requires no special arrangements to visit the site between the hours of 10:00AM and 5:30PM.
6.5 This project requires special arrangements for access to a non-public area. Access to the site may be restricted at times other than during the scheduled visit.
7. AVAILABILITY OF DOCUMENTS
7.1. The bidder/offeror may obtain a thumb drive with electronic versions of the drawings and specifications from:
Office of Planning, Design and Construction
600 Maryland Avenue, SW
Suite 5001
Washington, DC 20024
The solicitation documents are available, at no cost to the bidder/offeror, from the
Contracting Officer.
SPECIAL PROJECT REQUIREMENTS
8. UNITS OF MEASURE
8.1. All fabrication and installation shall be performed in accordance with the units of measure given in the Contract Documents.
8.2. All Contractor and subcontractor personnel working on the site shall possess and use metric measuring equipment for all work shown in metric units. Conversion of dimensions shown on contract drawings to English units for use of non-metric measuring equipment is prohibited.
Construction Documents Page 11 of 67
9. NON-PUBLIC, TENANT AND SECURED SPACES
9.1. Certain tenant spaces, non-public spaces, utility and equipment rooms and other areas related to or used for purposes of storage, conservation, research, curation of museum collection and artifacts or for scientific research may have restricted access.
9.2. The Contractor shall identify to the COTR as soon as possible, but no less than two (2) working days in advance, any occupied areas that the Contractor must access that are located outside the limits of the project site. The Contractor shall identify in writing:
9.2.1. Restricted areas to be accessed.
9.2.2. Specific reason for needing access.
9.2.3. Nature of the work to be performed.
9.2.4. Date(s) and hours needed to complete construction work activity.
10. MUSEUM ARTIFACTS AND SCIENTIFIC RESEARCH MATERIALS
10.1. The handling of museum artifacts or scientific research experiments by the
Contractor is strictly prohibited without written consent of the Smithsonian. The existing museum artifacts and research related materials may be moved only by authorized
Smithsonian museum curatorial personnel. An offender of this clause may be subject to arrest or removal from the premises and project by Smithsonian security officers.
10.2. If temporary relocation of artifacts or research experiments is necessary, the
Contractor shall give notice to the COTR at least five (5) working days in advance of the time relocation is needed.
10.3. Humidity/Temperature Controlled Spaces: The Contractor shall take care to minimize fluctuations in air conditions and quality, particularly in areas containing artifacts and storage collections and laboratories and scientific research experiments.
Humidity and temperature-controlled areas require consistency of utility operation.
11. PROTECTION OF HISTORIC PROPERTIES
11.1. The project site is located in a designated National Historic Landmark property and requires special attention to the quality of materials selected for installation and workmanship efforts to satisfactorily preserve and restore historic elements and finishes of an historic landmark structure.
Construction Documents Page 12 of 67
11.2. Upon request of the COTR, the Contractor shall submit evidence of technical competence in restoration work for National Historic Landmark structures, including subcontractor resumes, references and photographs or previous similar work.
11.3. Without exception, all original building fabric of the NMAH Building is designated historic.
12. COMMITMENT TO SUSTAINABILITY
12.1. The Smithsonian Institution is a trust instrumentality of the United States
(recognized as a tax-exempt organization under Section 501(c)(3) of the Internal Revenue
Code) and although not an Executive Branch of the U.S. Government, is committed to planning, designing, constructing, maintaining and operating its owned and leased buildings and facilities consistent with Federal environmental and energy management requirements, as listed in the Smithsonian OFEO Codes, Standards and Guidelines document, dated Feb 15, 2012, to the maximum extent practical.
12.2. DELETED
13. COMMISSIONING
13.1 The Smithsonian requires Fundamental Commissioning (as defined by the LEED
NC and CI rating systems) of all eligible design and construction projects, even if the project is not eligible to pursue LEED certification. The Smithsonian additionally requires Enhanced Commissioning (as defined by the LEED NC and CI rating systems) for larger projects and projects pursuing LEED certification, based on the size and complexity of the project
13.2 DELETED
CONTRACTOR USE OF PREMISES
14. HOURS OF WORK, WORKDAYS AND GOVERNMENT HOLIDAYS
14.1. Contractor shall perform work under this contract during the normal workdays of
Monday through Friday, and the normal work hours of 6:00 AM to 3:00 PM.
Quiet work shall be performed, under this contract, during the normal workdays of
Monday through Friday, except Smithsonian holidays as specified herein and the normal work hours. Noise generation and hot work can occur during normal work hours at the specific approval of the SI COTR. Debris hauling will only be permitted during nighttime hours. See Section 16.5 below.
Construction Documents Page 13 of 67
14.2. NOT USED
14.3. For each occasion the Contractor intends to work on Saturdays, Sundays or
Smithsonian holidays or during hours other than those indicated above, the Contractor shall obtain written permission from the COTR, at least three (3) working days in advance.
14.4. The Contractor shall reimburse the Smithsonian Institution for security and inspection services provided by the Smithsonian when the Contractor chooses to work outside the normal workdays and hours, as identified herein. However, the Contractor will not be charged for SI overtime security and inspection services, if in the opinion of the COTR, the work cannot be done during the normal workdays and hours due to requirements of the Smithsonian.
14.5. Smithsonian Holidays: For holidays that fall on Saturday, the Smithsonian
Holiday is observed on the previous Friday. For holidays that fall on Sunday, the
Smithsonian holiday is observed on the following Monday. The Smithsonian Holidays are listed below.
New Year's Day January 1
Martin Luther King Jr.'s Birthday January, third Monday
George Washington's Birthday February, third Monday
Memorial Day May, last Monday
Junteenth June 19
Independence Day July 4
Labor Day September, first Monday
Columbus Day October, second Monday
Veterans' Day November 11
Thanksgiving Day November, fourth Thursday
Christmas Day December 25
15. CONDITIONS AFFECTING CONTRACTOR'S WORK
15.1. Existing Occupied Spaces: The premises will be occupied during the performance of the Work. The Contractor shall schedule work activities to minimize interruption of occupants and occupied spaces. Efforts will be made to temporarily move employees and contents out of specific areas under construction, as needed, during the times requested by the Contractor. However, the needs of the Smithsonian Institution take precedence and free access for the Contractor cannot always be guaranteed. The
Contractor may work in NMAH only in the presence of authorized Smithsonian staff or guard personnel. Areas that will remain occupied include the Collections Storage spaces, Construction Documents Page 14 of 67 perimeter office areas, staff circulation corridors, and public circulation corridors on
Lower Level, and Levels 1, 2, and 3.
15.2. Relocation of Existing Occupants: Contractor's requests for the Smithsonian to temporarily relocate existing occupants or for Contractor's access to secured areas shall be made to the COTR as far in advance as possible, but no less than three working days in advance of the need for relocation.
15.3. Space for Contractor Use: The space available for Contractor's use is limited to areas indicated on the Contract Drawings as the project site. Space allocation and availability are subject to change, at the discretion of the Smithsonian, to meet the needs of all parties requiring access and space within the building and the surrounding areas.
16. CONTRACTOR DELIVERIES, HAULING AND ACCESS
16.1. The Contractor's materials and equipment shall be delivered, received and handled by the Contractor's personnel.
16.2. Access to the building for on- and off-loading of all material, structures and equipment shall be through the Lower Level Loading dock and will be limited to nightime and morning 5:30 pm to 10:00 am. All access must be coordinated with the
COTR.
16.3. The Contractor may use either of the two freight elevators for movement of material, structures and equipment within acceptable loading limits.
16.4. The transportation of hazardous materials or hazardous waste into or out of the building shall be limited to the following routes and freight elevators approved by the
COTR. All hazardous materials shall be transported through the building in secondary containment and properly secured to transport carts to prevent breakage or spills.
Further direction on the transportation of asbestos containing or lead containing waste materials is provided in Specification Sections 13280 and 13285 respectively.
16.5 All Debris hauling through the NMAH interior spaces shall occur during the nighttime hours 5:30pm – 5:30am.
16.6 Contractor to coordinate with COTR for site office needs and determine if there is a suitable location within the building footprint.
17. DRESS AND DEPORTMENT
17.1. Contractors' personnel shall be fully and appropriately clothed at all times and shall conduct themselves in a manner appropriate to a public place. The COTR may
Construction Documents Page 15 of 67 require removal of any individual from the premises and project for unacceptable dress, demeanor or disruptive conduct, if the Contractor superintendent fails to correct conditions in violation of this paragraph.
18. CONTRACTOR PARKING
18.1. The Contractor should contact the COTR to make arrangements to obtain an SI parking permit and make arrangements at least three (3) working days before the start of any work on the site. SI cannot reserve specific parking spaces for Contractors.
18.2. SI parking permits may be picked up at the following location between the hours of 8:00 AM and 5:00 PM, Monday through Friday, except government holidays.
SI Parking Office - NASM Room P706A
National Air & Space Museum
6th Street and Independence Avenue, S.W.
Washington, DC 20560
Telephone No.: (202) 633-3900
18.3. The assigned space can only be used by the company vehicle. The vehicle must be clearly marked with company name and/or logo. The permit shall be displayed on the vehicle dashboard on the driver's side. Vehicles not in compliance with this clause are subject to ticketing and towing. Costs associated with parking violations shall be the sole responsibility of the Contractor.
18.4. Parking permits will indicate an expiration date for a maximum three (3)-month period or for the last date of the contract time, whichever is earlier. Upon permit expiration, the Contractor shall be responsible for returning the expired permit to the SI
Parking Office or renewing it. SI parking permits remain the property of the Smithsonian
Institution.
18.5. Arrangements for Contractor's parking are the sole responsibility of the
Contractor. Parking may not be available at the project site.
19. EATING, DRINKING, SMOKING AND ILLEGAL SUBSTANCE ABUSE
19.1. Eating and drinking in Smithsonian buildings or leased space will be allowed only in designated areas. Offenders may be subject to removal from the premises and project should the Contractor's Superintendent fail to correct conditions, which, in the opinion of the COTR, violate this clause.
Construction Documents Page 16 of 67
19.2. The consumption of alcoholic beverages by the Contractor's personnel is prohibited in all Smithsonian buildings or leased space.
19.3. Smoking or carrying lighted tobacco products is prohibited in all Smithsonian buildings or leased space, in exhibition and public spaces, in areas where hazardous materials are stored or handled and in areas undergoing construction, renovation or repair. Acceptable areas for smoking are outside of the building at least 25 feet from any opening, operable window or air intake vent and as designated by the Smithsonian
Building Manager.
19.4. The possession, sale and/or use of narcotics or other illegal substances or firearms by Contractor employees are strictly prohibited in all Smithsonian facilities and leased space. Contractor employees are strictly prohibited from working on the project under the influence of alcohol and/or illegal substances. Contractor employees in violation of any of the above prohibitions will be removed from the project.
PROJECT COORDINATION
20. COORDINATION OF TRADES
20.1. The Contractor shall coordinate work of different trades so that interference between mechanical, electrical, architectural and structural work, including existing services, shall be avoided.
20.2. DELETED
20.3 Where work by separate entities requires off-site fabrication of products and accurate interfacing of materials to produce the required results, the Contractor shall prepare coordination drawings to indicate how work shown on separate shop drawings will be interfaced, intermeshed and sequenced for installation. Coordination drawings shall be submitted in accordance with the requirements of the "Submissions" section.
20.3.1. Work installed prior to approval of coordination drawings shall be at the
Contractor's risk. Subsequent relocations required to avoid interferences shall be made without additional expense to the Smithsonian. If an interference develops, the COTR will decide which work shall be relocated, regardless of which was installed first.
20.4. Installation of equipment and systems shall allow the maximum practical space for operation, repair, removal and testing, within the limits indicated on the Contract
Documents. Pipes, conduit, ducts and other system components shall be installed as
Construction Documents Page 17 of 67 close as possible to ceiling slabs, walls and columns to minimize space used while accommodating function and maintenance.
21. QUALITY CONTROL
21.1. The Contractor shall provide for quality control, inspections, testing and re-testing as necessary for all work, including that of Subcontractors, to assure compliance with the contract documents.
21.2. Contractor Quality Control (CQC) System: The Contractor shall provide a quality control organization and system to perform quality control, inspections, testing and re-testing as necessary for any item of work, including that of Subcontractors, to assure compliance with the contract documents.
21.3. CQC Representative Designation and Authority:The Contractor shall provide a
CQC Representative, supplemented as necessary by additional personnel, who shall be on the jobsite at all times during progress, with complete authority to take any action necessary to ensure compliance with the contract documents. The CQC Representative shall be appointed by a letter addressed to him/her and signed by an officer of the firm and shall not be the same individual as, or be subordinate to, the job superintendent or project manager.
21.4. CQC Plan Requirements:The Contractor shall submit for review/approvala CQC
Plan within thirty (30) calendar days after Contract Award to the COTR for approval.
The Plan shall detail the procedures, instruction and reports to be used to assure compliance with the contract documents. As a minimum, the Plan shall include the following:
21.4.1. Designation of the CQC Representative: Identify the person and list duties, responsibilities and authority.
21.4.2. Organization Chart: Show CQC staff and its relationship with other staff members and Subcontractors.
21.4.3. Personnel Matrix: For each specification section, identify who is the authorized submittal reviewer, who will inspect the work, what testing laboratory or person will perform on-site testing, who will perform factory inspections and testing and who will certify the documentation.
21.4.4. Responsibility and Authority: State the responsibility and authority for each individual in the CQC system.
Construction Documents Page 18 of 67
21.4.5. Personnel Qualifications: Provide resumes and descriptions of prior experience on similar work.
21.4.6. Inspection Procedures and Schedule:Identify the inspection and testing procedures and scheduled dates as reflected on the CPM project schedule, organized by technical specification section.
21.4.7. Submittal Review Procedures and Schedule: Provide submittal log in accordance with the Submissions section. For each specification section, identify the name(s) of person(s) authorized to review and sign submittals for compliance.
21.4.8. CQC Documentation: Identify the procedures for documenting quality control operations, inspection and testing. Provide samples of each type of required documentation - all forms, logs, reports, etc. Include a testing log listing all tests and inspections required by the contract documents and stating the action to be taken by the Contractor and/or the Smithsonian.
21.5. CQC Staffing Requirements:The following listing of minimum staff requirements in no way relieves the Contractor of meeting the basic requirements of the Contractor
Quality Control System for this project. The Contractor shall ensure an adequate staff to meet the CQC requirements at all times during construction. When necessary for a proper CQC organization, the Contractor shall provide additional staff at no cost to the
Smithsonian.
21.5.1. CQC Representative:The CQC Representative shall be a graduate engineer or architect with a minimum of seven (7) years of construction experience on projects similar to this one, including three (3) years experience in
Quality Control.
21.5.2. Alternate CQC Representative:The Contractor shall designate an alternate person to act for the CQC Representative in case the CQC
Representative is absent from the construction site. The alternate may not act for the CQC Representative for a period longer than fourteen (14)consecutive calendar days without written approval by the COTR.
21.5.3. CQC Submittals Assistant:The Contractor shall assign an assistant, to work until submittals are 95% complete, whose sole duty shall be to assist the
CQC Representative in maintaining files and logs for submittals.
21.5.4. CQC Specialized Supplemental Personnel:The Contractor shall provide, as a minimum, a different person in each of the areas listed below to assist and report to the CQC Representative. Supplemental personnel shall be responsible
Construction Documents Page 19 of 67 for ensuring that the construction complies with the contract documents in their areas of responsibility. They shall be on the jobsite during all installation and testing in their areas of responsibility and shall be responsible for performing inspections and witnessing testing as required by the contract documents.
Mechanical
Electrical
21.6. CQC Inspection Requirements:As a minimum, the inspection procedures shall include the following:
21.6.1. Preparatory Inspection: Preparatory inspection shall be performed before beginning work and before beginning each segment of work. Preparatory inspection shall include a review of the contract requirements, complete review of shop drawings and other submittals for conformance with contract documents, confirmation that all required testing will be provided, physical examination of all materials and equipment for conformance with approved shop drawings and submittals and verification that all required preliminary work has been completed.
21.6.2. Initial Inspection:Initial inspection shall be performed as soon as a representative segment of the particular item of work has been accomplished.
Initial inspection shall include checking of all dimensions, careful inspection of workmanship, performance of required testing, performance of corrective actions as necessary and approval or rejection of the initial segment of the work.
21.6.3. Follow-up Inspections:Follow-up inspections shall be performed daily or more frequently, as necessary, and shall include continued testing and examinations to assure continued compliance with the contract requirements.
21.6.4. Special Inspection and Documentation:In addition to the above inspection requirements, certain Special Inspection and Documentation requirements may be contained within the technical specification sections. Each
Special Inspection shall be performed and documented as required and documentation shall be submitted as soon as possible after performance unless otherwise indicated.
21.6.5. Factory Inspection by the Contractor:The Contractor shall arrange and perform all factory inspections specifically required in the technical specifications sections.
Construction Documents Page 20 of 67
21.6.6. Non-Compliance Check-Off List: The CQC Representative shall maintain a check-off list of work that does not comply with the contract, stating specifically what is non-complying, the date the faulty work was originally discovered and the date the work was corrected. The CQC Representative shall not allow the Contractor to add to or build upon non-complying work unless, in the opinion of the COTR, correction can be made without disturbing the continuing work. The CQC Representative shall submit a copy of the check-off list to the COTR on a monthly basis. Items corrected on the day they are discovered do not need to be included on the submitted list.
21.6.7. Completion and Inspection of Work:The CQC Representative shall sign the written request for Substantial Completion Inspection (discussed in the Project
Closeout Requirements section).
21.7. Testing Requirements:Except as specifically stated otherwise, the Contractor shall be responsible for all field sampling and in-place testing required by the contract documents.
21.7.1. Independent Testing Laboratory: The Contractor shall provide an independent, commercial testing laboratory to perform all sampling and testing services required, unless otherwise specified. The testing services shall be on- or off-site as required. Submit complete documentation of all tests performed in connection with the construction contract.
21.7.2. Smithsonian Acceptance of Laboratories: Except for factory tests, all field sampling and testing normally performed by commercial laboratories shall be performed by an independent commercial laboratory employed by the
Contractor and accepted by the COTR. The Contractor shall submit the following information to the COTR for approval:
21.7.2.1. Name, registration number and engineering discipline of the
Registered Professional Engineer in charge of the laboratory.
21.7.2.2. Affidavit of compliance and certification that the laboratory performs work in accordance with requirements as stated in the contract documents.
21.7.2.3. A list of testing equipment proposed for each test procedure including latest calibration data.
Construction Documents Page 21 of 67
21.7.2.4. A copy of the latest Laboratory Inspection Report by an independent agency with laboratory certification that deficiencies (if any) have been corrected.
21.7.2.5. Names and qualifications of persons actually performing testing and sampling. Changes in personnel shall be approved by the
COTR prior to performance of work under this contract.
21.7.3. Factory Tests: Unless otherwise specified, the Contractor shall arrange for factory tests when they are required under the Contract. Certified copies of test reports showing that the materials to be incorporated into the work conform to the contract documents will be acceptable, provided they are performed by the manufacturer or by agencies or laboratories acceptable to the COTR.
21.7.4. Test Results: Test results shall cite the contract requirements, the test or analytical procedures used, the actual results and include a statement that the item tested or analyzed conforms or fails to conform to specification requirements.
The cover sheet for each report shall be conspicuously stamped in large red letters
"CONFORMS" or "DOES NOT CONFORM" to the specification requirements, as the case may be. All test reports shall be signed by a testing laboratory representative authorized to sign certified test reports. The Contractor shall arrange for immediate and direct delivery of the signed reports, certifications and other documentation to the COTR.
21.8. Documentation: The CQC shall prepare or assist with the preparation of the following documents:
21.8.1. Daily Reports: The Contractor's Daily Report, as discussed in the section Contractor Correspondence and Daily Reports, shall be signed by the
CQC Representative as well as the Superintendent. The CQC Representative's signature certifies that, to the best of his or her knowledge, the report is complete and correct and that all materials, equipment and work described on the report are in compliance with the contract plans and specifications, except as noted otherwise.
21.8.2. Special Inspection and Documentation: Reports of Special Inspections shall be signed by both the CQC Representative and the CQC Specialized
Supplemental Person who witnessed the test or inspection certifying compliance with the specific contract requirement.
21.8.3. As-Builts: The CQC Representative shall ensure that all requirements for as-built record drawings and specifications are met. The CQC Representative
Construction Documents Page 22 of 67 or Specialized Supplemental Personnel assigned to inspect that particular portion of work shall initial each as-built drawing or technical specification section to certify its accuracy prior to submission in accordance with the Project Close-Out
Requirements section.
22. PERMITS, LICENSES & FEES
22.1. The Contractor shall obtain and pay for all applicable permits and licenses required by regulating agencies, including but not limited to: permits for pedestrian and road markings, construction fences, sidewalk cuts, utility company connections, elevator certificates, waste containers, etc.
22.2. The Contractor shall pay all duties, fees, taxes and other charges and give all notices necessary and incidental to the due and lawful execution of the work.
22.3. The Contractor shall keep the Smithsonian indemnified against all penalties and liability for breach of provisions of any national, provincial, district or city statute, ordinance or law and the regulations and by-laws of any local or other duly constituted authority, which may be applicable to the Work and with such rules and regulations of public bodies and companies.
22.4. NOT USED
22.5. Accessibility for Physically-Disabled Persons: The Contractor's shall provide temporary constructions at the site as necessary to maintain access for physically disabled persons. All provisions for temporary access shall be subject to the approval of the
22.6. NOT USED
23. UTILITY SERVICE INTERRUPTIONS AND NEW CONNECTIONS
23.1. Any planned interruption in utility service must be approved by and coordinated through the COTR. The Contractor shall submit a written request as far in advance of scheduled interruption as possible, but no less than two (2) full working days in advance.
The Contractor shall make the necessary temporary provisions to supply continuous electrical power, HVAC space conditioning and security as required during periods when service is interrupted.
23.2. The Contractor's work efforts to restore service shall be continuous until the interrupted utility is back in service.
Construction Documents Page 23 of 67
23.3. The electrical power for NMAH may not be interrupted during public attendance
10a-5pm Monday – Sunday or during special events.
23.4. A fire watch shall be provided for the time periods when fire suppression and detection systems are out of service.
24. SMITHSONIAN-FURNISHED ITEMS INSTALLED BY THE CONTRACTOR
24.1. The following items shall be furnished by the Smithsonian for installation by the
Contractor as part of this contract:
ITEM DELIVERY LOCATION
NOT USED
24.2. Required delivery dates for all Smithsonian furnished items shall be included in the Contractor's Project Schedule, as discussed in the Schedules and Payments section.
Any items requiring delivery within the first sixty (60) days of the project or prior to submission of the Project Schedule shall be identified at the Preconstruction Meeting.
24.3. The COTR will notify the Contractor of scheduled delivery dates no less than two
(2) full working days in advance of delivery. The Contractor shall accept delivery of the items on scheduled dates or be responsible for any damage and/or expenses resulting from his failure to take delivery. Promptly upon delivery, the Contractor shall contact the
COTR and they shall jointly inspect the material or equipment for possible shortage or damage. If a shortage or damage is found, the Contractor and the COTR shall submit a report to the Contracting Officer.
24.4. The Contractor shall be responsible for proper storage and protection of items delivered, including all expenses incidental thereto.
24.5. For each item, the Contractor shall receive, sign for receipt, provide additional transportation as necessary, uncrate, assemble, locate in place and provide complete installation including all connections necessary for operation or use. Installation and connection shall be in accordance with manufacturer's specifications as well as contract documents, including all labor and material required.
25. SALVAGE
25.1. The Smithsonian Institution assumes no responsibility for salvage value or any loss or damage to materials or structures on the site for which the Contractor may have reflected a salvage value in his or her *proposal or bid.
Construction Documents Page 24 of 67
25.2. Except as specifically stated in the contract documents, construction materials, equipment or other items that are to be removed and neither re-used under this contract nor reserved as property of the Smithsonian Institution shall become the property of the
Contractor and shall be removed from the premises by the Contractor.
25.3. The following items shall remain the property of the Smithsonian and the
Contractor shall deliver the items to the locations specified or as otherwise directed by the COTR, at no additional cost to the Smithsonian.
ITEM DELIVERY LOCATION
TBD
26. CUTTING, PATCHING AND MATCHING EXISTING WORK
26.1. Existing work shall be cut, drilled, altered, removed or temporarily removed and replaced as necessary for performance of work under the contract. Work that is replaced shall match similar existing work. Structural members shall not be cut or altered, except where noted on drawings, without authorization of the COTR. Work to remain in place, which is damaged or defaced during this contract shall be restored to match the conditions existing at the time of award of the contract, at no additional cost to the
Smithsonian.
26.2. Conditions exposed by removal of existing work that do not match new finishes or align with new work shall be called to the COTR's immediate attention. Necessary corrective work directed by the COTR will be subject to adjustment provisions as stated in the General Conditions of the contract.
PROTECTION OF THE SITE DURING CONSTRUCTION
27. PROTECTION OF THE SITE
27.1. The Contractor shall provide adequate protection for all parts of the building, including interior and exterior surfaces, its occupants and contents and grounds wherever work under this contract is performed.
27.2. Plan for Protection of the Site:The Contractor shall submit a plan for protection of the site to the COTR for approval based on the Logistics Plans included in the
Construction Documents. As a minimum, the Plan shall describe:
27.2.1. Proposed method, location and construction of temporary enclosures.
Construction Documents Page 25 of 67
27.2.2. Routes of access and egress, including those for people with disabilities.
27.2.3. Location and maintenance of emergency exits.
27.2.4. Methods of protection of existing surfaces and occupants.
27.2.5. Means of connection of temporary enclosures/surfaces to existing historic materials.
27.3. NOT USED
27.4. During construction, temporary enclosures shall be constructed to prevent unauthorized access or egress. Dust and fume barriers shall be constructed, as needed or as determined by the COTR, to seal and isolate the work area from the remainder of the interior areas while the work is in progress. Wood used for protection of the site shall be pressure-impregnated, fire-retardant. All plastic sheeting shall be fire retardant 6-mil polyethylene. Submit product data to the COTR for review and approval.
27.5. The Contractor shall submit information describing the proposed construction of temporary enclosures and methods of installation to the COTR for approval. Any connections to existing structures must be accomplished in such a way as to minimize disturbance of existing surfaces.
28. PROTECTION OF FLORA,FAUNA AND CENTRAL COMPUTER
CONTROLLER IRRIGATION SYSTEM
29. DEBRIS CONTROL AND DAILY CLEANUP
29.1. The Contractor shall regularly clean up the work areas and shall, at all times, maintain the project in as neat and orderly a manner as is consistent with normal operations. Debris resulting from construction operations shall be removed from the site daily by the Contractor. The Contractor shall keep all access, haul routes and site areas free of dirt, debris and other materials resulting from construction activities.
29.2. Under no circumstances shall any rubbish or waste be dropped or thrown from one level of scaffolding to another or within or outside the building. Rubbish may be lowered by way of chutes, taken down on hoists or lowered in receptacles.
29.3. Trash receptacles: The Contractor shall provide enclosed trash receptacle(s) in quantity and size necessary to meet project needs, located as approved by the COTR.
Construction Documents Page 26 of 67
29.4. DELETED
30. DUST AND AIR QUALITY CONTROL
30.1. The Contractor will execute the Work by methods that minimize dust, vapors and gases raised by construction operations. The Contractor will utilize engineering controls and work practices to prevent airborne dust, vapors, gases and objectionable odors from dispersing into the atmosphere and from being drawn into existing air-intake louvers, ductwork and adjacent elevator shafts. A work plan of methods and means for this section shall be submitted to the COTR for review and approval.
30.2. Dust barriers shall be erected, where necessary, to protect adjacent areas from dust infiltration as required by the COTR. Dust barriers shall be rigid and visually opaque and shall seal the work area by affixing to the structure on all sides (i.e. ceiling, walls and floor). Wood used for dust barriers shall be pressure-impregnated, fire-retardant treated lumber. All plastic sheeting shall be fire-retardant 6-mil polyethylene.
Submit product data for review and approval to the COTR.
30.3. Means of connection of dust barriers to existing structures shall not damage the building fabric. Details of barriers shall be submitted for approval to the COTR.
30.4. No open fires or burning of trash are permitted.
31. NOISE CONTROL
31.1. The Contractor shall comply with the regulations of the District of Columbia and
OSHA Standards 1926.52 and 1910.95 and all other regulations relative to safety noise control.
31.2. Activities that generate excessive noise or vibration and interrupt museum functions or create public disturbances may be required to be performed during off-hours at the discretion of the COTR.
31.3. The Contractor shall provide sound attenuation to maintain acoustic level below
75 dBA at a distance of 15 m or below 75 dBA in occupied staff areas if less than 15 m away from noise source.
32. VERMIN, PEST AND RODENT CONTROL
32.1. The Contractor shall develop an Integrated Pest Management (IPM) plan and provide regularly scheduled inspection services by a licensed Pest Management
Professional to manage and, when possible, to eliminate insects, rodents, birds, arachnids
Construction Documents Page 27 of 67 and other miscellaneous pests invading the project site or premises for the duration of the project. In general, preventative pesticide applications are prohibited. Preventative pesticide applications may be made when there is a surveillance-based indication of pest infestation. Such applications shall be made on a case-by-case basis and only upon written approval of the COTR prior to such application.The IPM plan must address all the specific IPM requirements listed in the Leadership for Energy and Environmental
Design (LEEDTM) Existing Buildings: Operations & Maintenance Indoor Environmental
Quality (IEQ) Credit for Green Cleaning: Indoor Integrated Pest Management, including preferred use of nonchemical methods, the use of least toxic pesticides as identified by
San Francisco Tier 3 Low Hazard pesticides (SF Pesticide Hazard Screening List), the definition of emergency conditions (defined as a threat to landscape, building integrity or human occupancy after non-chemical methods have been exhausted) and universal notification (advance notice of not less than 72 hours under normal conditions and 24 hours in emergencies before a pesticide, other than a least toxic pesticide, is applied in a building or on surrounding grounds that the building management maintains). Any outdoor IPM plan must also be integrated with any indoor IPM plan for the building, as appropriate.
32.2. Throughout the term of this contract, all Contractor personnel providing on site pest control service must maintain…