2003112 NMAH Rpl ACUs Collection Storage 4th and 5th Bid Sch.xlsx
XLSX spreadsheet 18 KB Posted
- Solicitation number
- 33330223RF0010026
- Issued by
-
Smithsonian Institution
About this file
This solicitation seeks offers to replace air handling units for collection storage spaces on the fourth and fifth floors of the National Museum of American History. The project includes removing existing air handling units known as ACUs in four mechanical equipment rooms and replacing them with new AHUs. Temporary cooling systems must be provided throughout construction to maintain temperature and humidity conditions for collections. A phased approach is recommended to allow continuous operation of two freight elevators, with either the east or west wings addressed together. Offers are due by April 15, 2024 for completion of fifth floor work between that date and October 31, 2024, as chilled water will be unavailable outside that window. The fixed price construction contract is estimated over $10 million with a performance period of 570 calendar days from notice to proceed.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Blank bid summary
| Title : | NMAH Replace ACU's Collection Storage 4th & 5th | Prepared by : |
| Facility : | NMAH | Date : |
| Project Number : | 2003112 | Company: |
| Base Bid | ||||
| BASE BID: All work associated with replacing AHU's on the the & 5th floor at NMAH as described the specifications and drawings both dated December 21, 2022. | ||||
| Description | Material | Labor | Equipment | Total |
| Div. 1 General Conditions | $ - 0 | $ - 0 | $ - 0 | |
| Div. 2 Existing Conditions | $ - 0 | $ - 0 | $ - 0 | |
| HAZMAT | $ - 0 | $ - 0 | $ - 0 | |
| Div. 3 Concrete | $ - 0 | $ - 0 | $ - 0 | |
| Div. 4 Masonry | $ - 0 | $ - 0 | $ - 0 | |
| Div. 5 Metals | $ - 0 | $ - 0 | $ - 0 | |
| Div. 6 Wood, Plastics and Composites | $ - 0 | $ - 0 | $ - 0 | |
| Div. 7 Thermal and Moisture Prot. | $ - 0 | $ - 0 | $ - 0 | |
| Div. 8 Openings | $ - 0 | $ - 0 | $ - 0 | |
| Div. 9 Finishes | $ - 0 | $ - 0 | $ - 0 | |
| Div. 10 Specialties | $ - 0 | $ - 0 | $ - 0 | |
| Div. 11. Equipment | $ - 0 | $ - 0 | $ - 0 | |
| Div. 12 Furnishings | $ - 0 | $ - 0 | $ - 0 | |
| Div. 13 Special Construction | $ - 0 | $ - 0 | $ - 0 | |
| Div. 14 Conveying Systems | $ - 0 | $ - 0 | $ - 0 | |
| Div. 21 Fire Suppression | $ - 0 | $ - 0 | $ - 0 | |
| Div. 22 Plumbing | $ - 0 | $ - 0 | $ - 0 | |
| Div. 23 HVAC | $ - 0 | $ - 0 | $ - 0 | |
| Div. 26 Electrical | $ - 0 | $ - 0 | $ - 0 | |
| Div. 27 Communications | $ - 0 | $ - 0 | $ - 0 | |
| Div. 28 Electronic Safety & Security | $ - 0 | $ - 0 | $ - 0 | |
| Div. 31. Earthwork | $ - 0 | $ - 0 | $ - 0 | |
| Div. 32 Exterior Improvements | $ - 0 | $ - 0 | $ - 0 | |
| Div. 33 Utilities | $ - 0 | $ - 0 | $ - 0 |
BASE BID SUBTOTAL
| Overhead and Profit |
| Performance Bond |
Total
| BASE BIDTotal | ||||
| DEDUCT Alternate / Option | ||||
| DEDUCTIVE Alternate/Option: All work associated with AHU 4 CS 17 amd work in mechanicl equipment room 4000M4 at NMAH as described the specifications and drawings both dated December 21, 2022. | ||||
| Description | Material | Labor | Equipment | Total |
| Div. 1 General Conditions | $ - 0 | $ - 0 | $ - 0 | |
| Div. 2 Existing Conditions | $ - 0 | $ - 0 | $ - 0 | |
| HAZMAT | $ - 0 | $ - 0 | $ - 0 | |
| Div. 3 Concrete | $ - 0 | $ - 0 | $ - 0 | |
| Div. 4 Masonry | $ - 0 | $ - 0 | $ - 0 | |
| Div. 5 Metals | $ - 0 | $ - 0 | $ - 0 | |
| Div. 6 Wood, Plastics and Composites | $ - 0 | $ - 0 | $ - 0 | |
| Div. 7 Thermal and Moisture Prot. | $ - 0 | $ - 0 | $ - 0 | |
| Div. 8 Openings | $ - 0 | $ - 0 | $ - 0 | |
| Div. 9 Finishes | $ - 0 | $ - 0 | $ - 0 | |
| Div. 10 Specialties | $ - 0 | $ - 0 | $ - 0 | |
| Div. 11. Equipment | $ - 0 | $ - 0 | $ - 0 | |
| Div. 12 Furnishings | $ - 0 | $ - 0 | $ - 0 | |
| Div. 13 Special Construction | $ - 0 | $ - 0 | $ - 0 | |
| Div. 14 Conveying Systems | $ - 0 | $ - 0 | $ - 0 | |
| Div. 21 Fire Suppression | $ - 0 | $ - 0 | $ - 0 | |
| Div. 22 Plumbing | $ - 0 | $ - 0 | $ - 0 | |
| Div. 23 HVAC | $ - 0 | $ - 0 | $ - 0 | |
| Div. 26 Electrical | $ - 0 | $ - 0 | $ - 0 | |
| Div. 27 Communications | $ - 0 | $ - 0 | $ - 0 | |
| Div. 28 Electronic Safety & Security | $ - 0 | $ - 0 | $ - 0 | |
| Div. 31. Earthwork | $ - 0 | $ - 0 | $ - 0 | |
| Div. 32 Exterior Improvements | $ - 0 | $ - 0 | $ - 0 | |
| Div. 33 Utilities | $ - 0 | $ - 0 | $ - 0 |
BASE BID SUBTOTAL
| Overhead and Profit |
| Performance Bond |
DEDUCTIVE Total:
B-&P
Sheet1
File details come from the government source that posted it. Updated .